Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

LITIGATION

PROPORTIONATE I propose to discuss, with but obviously are not limited to,
LIABILITY IN particular although not sole claims arising out of or relating
reference to construction to building and construction work
CONSTRUCTION litigation, the scheme of where those claims fall within
LITIGATION proportionate liability established the definition of an apportionable
Justice Robert McDougall in New South Wales by Part 4 of claim.
the Civil Liability Act 2002 (CL
Supreme Court of NSW For some seven years prior to the
Act). I shall not deal, except in commencement of Part 4, there
so far as it is necessary to do so, had been in force in New South
with the scheme of proportionate Wales a more limited regime of
liability established under proportionate liability in ‘building
Commonwealth law pursuant to actions’, established by s 109ZJ
the CLERP 9 legislative package,1 of the Environmental Planning
including (by way of example) and Assessment Act 1979. By
the proportionate liability regime s 109ZI, a ‘building action’ was
established for claims under s 52 defined to mean ‘an action
of the Trade Practices Act 1974 by (including a counter–claim) for
Part VIA of that Act.2 loss or damage arising out of or
After dealing briefly with the concerning defective building
background to proportionate work’; and ‘building work’ was
liability ‘reform’,3 I shall look defined in an inclusive fashion
at the structure and operation that did nothing to limit the
of Part 4 and then consider its ordinary meaning of those words.
application, and problems that The scheme of proportionate
may arise from its application, in liability established by s 109ZJ
a number of different scenarios, was repealed by Schedule 4.2
including some that might be to the Civil Liability Amendment
expected typically to arise in (Personal Responsibility)
construction litigation. Act 2002, with effect from 1
December 2004,6 the date of
BACKGROUND commencement of Part 4 of the
Under New South Wales law, CL Act.
proportionate liability is dealt with
by Pt 4 of the CL Act. Part 4 was The background to the
inserted into the Act by the Civil introduction of proportionate
Liability Amendment (Personal liability has been comprehensively
Responsibility) Act 2002, but was described by Professor Barbara
not proclaimed to commence McDonald in her article
in that form. It was amended by ‘Proportionate Liability in
the Civil Liability Amendment Australia: The Devil in the Detail’.7
Act 2003 and, so amended, I will not state, by repeating or
commenced on 1 December seeking to summarise, what
2004.4 Professor McDonald said; but
it is interesting to set what she
The proportionate liability regime says against the somewhat
established by Part 4 applies to rosier comments of the Attorney
civil liability arising before, as General for New South Wales,
well as after, the commencement the Hon Bob Debus MP, in his
of Part 4, but does not apply to article ‘Tort Law Reform in New
proceedings commenced before South Wales: State and Federal
that commencement.5 Interactions’.8
In terms, the proportionate
liability regime established THE LEGISLATIVE SCHEME
In this section, I look at the
by Part 4 applies to all
key features of the legislative
‘apportionable claims’ as defined
scheme in New South Wales, and
in s 34—I shall return to this.
advert to some problems that it
Apportionable claims include,
24 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #110 SEPTEMBER/OCTOBER 2006
raises. Those problems are of (4) For the purposes of this Part it general law applicable to the
a general nature, and are not does not matter that a concurrent subject matter in dispute.’ Thus,
unique to (or even likely to afflict wrongdoer is insolvent, is being his Honour said, the effect of
disproportionately) construction wound up or has ceased to exist the submission was to give the
litigation. or died. arbitrator power to award interest
conformably with s 94 of the
The operation of Part 4 is …
Supreme Court Act 1970 (NSW)
triggered by two key concepts. The section raises a number (which section, his Honour said,
First, as I have indicated, there of issues. One arises from the altered ‘the antecedent principle
must be an ‘apportionable references, in paras (a) and (b), of law regulating the payment
claim’. Second, there must be to a claim made ‘in an action for of interest on monies included
‘concurrent wrongdoers’. damages’: specifically, the word in judgments between the date
Those expressions are defined, ‘action’. Does the word ‘action’ when the cause of action arose
and some aspects of their signify that the proportionate and the date when the judgment
practical operation clarified, in s liability regime applies only in takes effect’).
34 of the CL Act: proceedings in a court? Or does
Stephen J said at 235 ‘that
it extend to arbitral proceedings?
34 Application of Part arbitrators must determine
If the former—i.e. if there is no
(1) This Part applies to the disputes according to the law
proportionate liability regime for
following claims (‘apportionable of the land’ (with irrelevant
claims advanced through and
claims’): exceptions relating to such
decided by arbitration—what is
things as equitable relief).
(a) a claim for economic loss or the underlying policy justification?
This, his Honour said, led to
damage to property in an action On the face of things, the former
the conclusion, supported
for damages (whether in contract, would represent an extraordinary
by authorities to which he
tort or otherwise) arising from a outcome, and one liable to
referred, ‘that, subject to such
failure to take reasonable care, increase the flow of work to
qualifications as relevant statute
but not including any claim arbitrators. I suggest that a
law may require, an arbitrator
arising out of personal injury; purposive construction of the
may award interest where interest
phrase ‘in an action for damages’
(b) a claim for economic loss would have been recoverable had
would apply it to any kind of
or damage to property in an the matter been determined in a
‘proceeding’ whereby a claim for
action for damages under the court of law.’
damages can be vindicated.
Fair Trading Act 1987 for a Of course, the particular problem
contravention of section 42 of that Some support for this approach
has been resolved by s 32 of the
Act. may be obtained from the
Commercial Arbitration Act 1984.
decision of the High Court
(1A) For the purposes of this Part, But the general principle—that
of Australia in Government
there is a single apportionable arbitrators decide disputes
Insurance Office of NSW v
claim in proceedings in respect of according to law—is capable of
Atkinson–Leighton Joint Venture.9
the same loss or damage even if application to the circumstances
In that case, it was held, among
the claim for the loss or damage created by the proportionate
other things, that an arbitrator
is based on more than one cause liability regime. If that is to be
had power to award interest
of action (whether or not of the taken as altering ‘the antecedent
on the amount of the award.
same or a different kind). principle of law regulating’ the
The basis for this holding was
doctrine of joint and several
(2) In this Part, a ‘concurrent that interest would have been
liability, then it should be taken
wrongdoer’, in relation to a claim, recoverable in a court and the
to be part of the general law
is a person who is one of two parties by their submission
applying, among other things,
or more persons whose acts or had, by implication, given the
to the conduct of arbitrations,
omissions (or act or omission) arbitrator authority to determine
and the awards of arbitrators, in
caused, independently of each all differences between them
appropriate cases.
other or jointly, the damage or according to law. Mason J (with
loss that is the subject of the whom Murphy J agreed) said at Arbitrations are, of course, a
claim. 247 that a reference to arbitration creature of contract (although
of ‘all differences arising out of’ a now with significant legislative
(3) For the purposes of this Part,
policy of insurance ‘contemplates support). In the ordinary way,
apportionable claims are limited
that all such differences shall the arbitrator has jurisdiction
to those claims specified in
be arbitrated in the light of the in accordance with the terms of
subsection (1).

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #110 SEPTEMBER/OCTOBER 2006 25


... the plaintiff should seek the submission: that is to say, accordance with any applicable
to identify all concurrent jurisdiction between the parties proportionate liability regime.
to the submission in respect
wrongdoers and to join It is important to note that an
of disputes that fall within the
them all in the one action, apportionable claim includes
ambit of the submission. If what
so that they can fight out one brought in contract, where
I have said is correct, and the the economic loss or damage to
among themselves the proportionate liability regime property is alleged to arise from
amounts of their several extends to disputes that are to a failure to take reasonable care.
liabilities to the plaintiff. be resolved by arbitration, then a Thus, in many cases it will be the
proportionate liability issue may plaintiff’s formulation of the claim
be raised by one of the parties that determines whether or not a
to the contract—typically, by defendant is entitled to the benefit
the respondent. It may then be of the proportionate liability
open to the arbitrator to find that regime. However, even where it is
the respondent is liable for X not apparent from the plaintiff’s
percent of the loss and damage pleading10 that the claim is one to
sustained by the claimant. But in which the proportionate liability
the ordinary way, unless the other regime might attach, it would
concurrent wrongdoers consent be open to a defendant to plead
to be joined in the arbitration, the an entitlement to proportionate
claimant will be left to pursue limitation of liability, and the
its remedies against them in material facts from which that
the courts. Unlike a plaintiff in entitlement is said to arise.
ordinary litigation, a claimant
in an arbitration cannot join all Because of the wide definition
alleged concurrent wrongdoers of the noun ‘damages’ in s 3 of
to whom the respondent points the Act (‘includes any form of
as having some responsibility monetary compensation …’), the
for the claimant’s loss or proportionate liability regime
damage. Thus, the risk of established by Part 4 is not
multiplicity of proceedings, limited to claims for damages
and the consequential risk of at law or in equity; it would
inconsistent decisions, is likely to extend, for example, to claims for
be multiplied. equitable compensation or claims
of a restitutionary nature where
Another consequence of the those claims otherwise satisfy the
contractual nature of arbitrations requirements of s 34.
is that it would be open to the
parties to the contract in which Section 34A denies the benefit
the submission is found to agree, of apportionment to some
pursuant to s 3A(2) of the CL concurrent wrongdoers (including
Act, for some regime other than those who intend to cause the
that of proportionate liability loss or damage, and those who
established by the CL Act to apply cause it by fraudulent means).
to their relationship. Section 35 sets out the regime
Similar jurisdictional problems whereby proportionate liability
may arise where disputes are, is imposed. By sub s 1(a),
or may be, referred to specialist the liability of a concurrent
tribunals such as (in New South wrongdoer defendant must reflect
Wales) the Consumer, Trading a proportion of the damage or
and Tenancy Tribunal. To the loss that is ‘just having regard
extent that the decisions of such to the extent of the defendant’s
tribunals are intended to reflect, responsibility for the damage
or follow, the law of the land, or loss’. By para (b), the court
then presumably they would be cannot give judgment against
required, in appropriate cases, that defendant for more than that
to make determinations in amount.

26 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #110 SEPTEMBER/OCTOBER 2006


Section 35(2) deals with have regard to the comparative which might be thought to be
proceedings that involve responsibility of a concurrent substantial, of the case already
both apportionable and non wrongdoer who is not a party, run) but with the risk that the
apportionable claims. They are then logically it would do defendant against whom that case
to be separated and dealt with so by seeking to determine, is run will be able to minimise
distinctly: the former under Pt for the purpose of excluding the extent of its responsibility.
4 and the latter under whatever from the amount of damages The consequence might be that
legal rules are applicable to it. otherwise payable by concurrent the plaintiff, although it has sued
wrongdoers who are parties, the all concurrent wrongdoers, does
Section 35(3)(a) requires that the
amount of damages that reflects not recover the full amount of its
plaintiff’s responsibility (if any) for
the extent of that non party’s loss, even though there can be no
the damage or loss in question
responsibility. In other words, doubt that, between them, those
(arising from the plaintiff’s
the court is required to assess wrongdoers caused the whole of
contributory negligence) is to
the non party’s contribution to that loss.
be excluded before apportioning
the overall damage applying the
responsibility as between The answer appears to be that the
formula set out in s 35(1)(a). But
defendants. Paragraph (b) entitles plaintiff should seek to identify
it is to carry out that task without
the court to have regard to the all concurrent wrongdoers
hearing from the non party,
responsibility of concurrent and to join them all in the one
and in circumstances where
wrongdoers who are not parties to action, so that they can fight out
the defendants have a very real
the proceedings. It thus appears among themselves the amounts
interest in fixing that non party
that, in an appropriate case, the of their several liabilities to the
with as much of the responsibility
plaintiff’s contributory negligence plaintiff. Undoubtedly, that is
as possible. Whilst the plaintiff
must be taken into account under what parliament intended should
has a competing interest, in
s 35(3)(a) even though the plaintiff happen. But the plaintiff may not
seeking to fix the defendants
brings its claim in contract: Astley always be aware of the identity of
with as much responsibility as
v Austrust Limited.11 all concurrent wrongdoers.
possible (which will minimise
Section 35(3)(b) marks a the responsibility of the non Section 35A seeks to mitigate
significant distinction between party), the plaintiff may lack the this situation. It imposes on a
the regime in force in New South information or resources available defendant a duty to inform the
Wales (and, for that matter, under to the defendants. Regardless, the plaintiff of the identity of other
Commonwealth legislation) court will be unlikely to have the persons that the defendant on
compared to that in force in benefit of hearing from the non reasonable grounds believes may
Victoria.12 party. be a concurrent wrongdoer in
relation to the plaintiff’s claim,
Another peculiarity of s 35(3) There are at least two and to inform the plaintiff of the
is the shift in language from immediately obvious circumstances that give rise to
‘defendants’ in the opening consequences. The first is that that belief. However, the only
words to the word ‘party’ in the court’s orders may tend to sanction for breach of this duty
para (b). Responsibility can understate the responsibility of is that of costs. Particularly
be apportioned only among the concurrent wrongdoers who where circumstances of common
defendants. Regard may be had are defendants, compared to the insurance arise, it may well be
to the comparative responsibility responsibility that might have in the interests of a defendant
of parties to the proceedings (eg, been allocated had all concurrent (or its insurer) to hold back for
cross defendants) who are not wrongdoers been defendants. as long as possible information
defendants: ‘defendant’ includes This will diminish the amount concerning the identity of
a cross–defendant,13 even though of damages recoverable by the concurrent wrongdoers, so as to
the cross–defendant is not at plaintiff in the action. The second put the plaintiff in the position
issue with the plaintiff. Since the is that the non party will not where it must elect either to
court can allocate responsibility be bound by the assessment, abandon a trial date so as to join
to parties who are not defendants, in proceedings to which it was the non party or take its chances
it would seem that they would not a party, of its responsibility. on the apportionment, at trial, of
be thereby estopped, in later If, therefore, the plaintiff sues responsibility to that non party.
proceedings at the suit of the that non party in subsequent
plaintiff, from disputing the proceedings, the plaintiff will be It may be that this situation could
liability so fixed. required to run the entirety of be dealt with by rules of court or a
its case (involving duplication, practice note aimed at preventing
Section 35(3)(b) gives rise to a
problem. If the court decides to
AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #110 SEPTEMBER/OCTOBER 2006 27
a defendant from relying on the Where a subsequent action is claim and concurrent wrongdoers
comparative responsibility of a brought, the plaintiff cannot in respect of that claim. In the
concurrent wrongdoer who is recover from any ‘new’ defendant ordinary way, it would not be
not a party where the defendant more than its apportionable in the interests of a plaintiff
has breached its duty under s responsibility for the loss or having a non apportionable
35A(1)(b) to notify the plaintiff damage; and in any event cannot claim against one deep pocketed
‘as soon as practicable’ of the recover, overall, an amount that defendant to plead material facts
relevant matters in relation to would result in the plaintiff’s that might show the existence
that non party. There would receiving more than the amount of an apportionable claim and
remain a question, whether the of the damage or loss actually concurrent wrongdoers. A clear
express terms of s 35A could be, sustained by it. example is a plaintiff having a
as it were, reinforced (and, more claim against a contractor for
Section 38 empowers the court
relevantly, perhaps restricted) breach of an express contractual
to give leave for non party
in this way;14 and, in any event, warranty to hand over the works
concurrent wrongdoers to be
the efficacy of any such rule of by the time limited for practical
joined in proceedings concerning
court or practice note in relation completion (as extended from
an apportionable claim (thus
to a defendant’s right under time to time) free of defects.
dealing, at least to an extent, with
Commonwealth legislation may A claim in respect of defective
the situation that would arise if a
be questionable. However, the works (and/or for late delivery)
defendant to existing proceedings
discretionary nature of the power could be brought for breach of
complies with its duty under s
have regard to the comparative that promise. In terms, it would
35A(1)(b)). However, a person
responsibility of non–parties (in not be an apportionable claim.
who was a party to any previously
New South Wales, s 35(3)(b): ‘may concluded proceedings in respect However, the defendant might
have regard to’) may solve this of that claim cannot be joined wish to allege that its breach
problem. under s 38. of contract was the result of
The scheme of which s 35(3)(b) negligence: negligently failing
forms part is supplemented by s PROPORTIONATE LIABILITY to manage and undertake the
36 and, in particular, by ss 37 and AND CONSTRUCTION works, and negligently failing to
38. LITIGATION use reasonable care and skill in
I have already adverted to some and about their execution. This
Section 36 provides protection
difficulties with the proportionate gives rise to two problems:
to defendants against whom
liability legislation in New South
judgment has been given as a (1) Who ‘owns’ the litigation?
Wales. In this section, I shall
concurrent wrongdoer in relation
look at some applications of (2) Where does the onus of proof
to an apportionable claim. They
the legislation to scenarios that lie?
cannot be required to contribute
commonly occur in construction As to the first question: it is
to damages or contribution
litigation. I shall also look at hard to see why the application
recovered from other wrongdoers
some difficulties that, whilst not of the statutory regime (which,
(whether in the same proceedings
necessarily unique to construction after all, was introduced to serve
or not) and cannot be required to
litigation, may nonetheless be the interests of prospective
indemnify any such wrongdoer.
raised frequently in the context of defendants and their insurers)
Section 37 expressly permits that litigation. should be governed by the
the bringing of subsequent
Onus of Proof ingenuity of those who plead
actions against concurrent
This is a particular problem in plaintiffs’ causes of action.
wrongdoers who were not parties
New South Wales and those Put in less emotive language:
to a previous action.15 Where the
other jurisdictions that empower the question should fall to be
identity of such a concurrent
the court to take into account, answered by considerations of
wrongdoer was known to, and
in assessing the responsibility substance rather than form.
not disclosed by, a defendant
in the earlier proceedings, of defendants, the proportionate As to the second question:
this might be thought to be a responsibility of non parties.16 a plaintiff is not entitled to
less than satisfactory solution: But it is also a problem of more judgment against a defendant
particularly having regard to the general application. for more than the amount that
public interests that are served by The application of the CL Act the court ‘considers’ to reflect
preventing multiplicity of litigation depends, as I have said, on there that proportion of the damage
in respect of the same ‘cause’. being both an apportionable or loss for which the defendant
is responsible: s 35(1). Where a
28 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #110 SEPTEMBER/OCTOBER 2006
plaintiff sues one defendant only, wrongdoing of others would need Einstein J addressed the onus of
then it is likely to be clear, at least to plead the defence (as did the proof issue in Nemeth at paras
by implication, that the plaintiff third defendant in Ferdinand [17] and following.22 Having
is asserting that the defendant Nemeth v Prynew Pty Ltd).19 On referred at para [17] to the article
sued is responsible for the whole this basis, a single defendant of Professor McDonald, to which
of the loss or damage.17 But what sued in respect of what on the I have referred above, his Honour
is the position where the plaintiff plaintiff’s pleading is not an said at para [19] that ‘the position
sues several alleged concurrent apportionable claim might be is made quite clear by the terms
wrongdoers? Is the plaintiff entitled to plead material facts of sections 35 and 35A of the
obliged to plead, and prove, the showing that it is in substance Civil Liability Act’. His Honour
proportionate responsibility of a material claim, and showing did not state explicitly what it
each? Or is it a matter for the the existence of concurrent was that was made ‘quite clear’.
defendants to raise? wrongdoers; and would bear the By inference, I think, his Honour
onus of proving those material was suggesting that a defendant
Perhaps the plaintiff can sue in
facts (and, one might think, rightly could, but need not, raise a
the alternative, pleading that the
so). proportionate liability defence, but
first defendant, alternatively the
that the onus of proof lay upon it if
second defendant, alternatively In each case, the onus would
it did. This I think follows from his
the third defendant, is wholly follow the allegation; and the
Honour’s discussion at paras [20]
responsible for its loss and person making the allegation
to [22] of the limited legislative
damage. But there may be real would be required to plead (and
sanctions imposed on defendants
practical (and indeed legal) ultimately to prove) material facts
who do not comply with their duty
problems in this approach. in support of the allegation.
of disclosure.
In Platt v Nutt,18 Kirby P at 238 However, the legislation is not
referred to ‘the general rule which entirely clear on this point. Plaintiff Unaware of
obtains in our courts, namely that Thus, although (as I have said) Identities of Those
those who assert must prove’. His it imposes on defendants an Responsible
Honour said that this principle obligation to identify to the Where the plaintiff either knows,
‘applies throughout the law’. I plaintiff others whom the or is likely to know, the identity of
do not think that the force of his defendant believes on reasonable all those who have (or may have)
Honour’s observations on this grounds may be concurrent contributed to its loss, it has the
point is diminished by his dissent wrongdoers,20 it does not impose choice to sue some or all of those
in the result. on them any obligation to plead that it believes to be responsible.
or prove the contribution of those If it chooses to sue some only, one
On that basis, a plaintiff that
concurrent wrongdoers to the could say that the consequences
sought to attribute proportionate
overall loss and damage. (including recovering less than
responsibility to various
defendants (eschewing the Professor McDonald has the full amount of its loss, or
device of alternative attributions discussed this problem in the being forced to the expense and
of total liability) would be article to which I have already delay of further proceedings) are
required to plead, with adequate referred (‘Proportionate Liability of its own making.
particularisation, the material in Australia: The Devil in the But in some cases, the plaintiff
facts supporting the proposed Detail’)21. She points out that in may not know who may be
allocation. Where the court found some cases the defendant will responsible. Take, for example,
that a defendant’s contribution be in a better position than the the situation of a plaintiff whose
was less than that asserted by plaintiff to identify concurrent land and premises are damaged
the plaintiff, there would be no wrongdoers. That circumstance— by adjacent works. The plaintiff
difficulty; but query whether this likely to be of very common may know the name of the builder
would be so if the court found application indeed in construction carrying out those works (or
that a particular defendant’s litigation—provides a sound policy the principal for whom those
responsibility was greater than basis, in addition to the ‘general works are carried out). But it
that alleged by the plaintiff. rule’ identified by Kirby P, for may not know precisely who was
allocating the onus of proof to responsible for all aspects of the
Application of the principle
defendants where they wish to works which led to the damage.
enunciated by Kirby P would
avail themselves of the benefits
mean that a defendant that In those circumstances, the
offered by the legislation.
wished to limit its liability by plaintiff may sue those who
reliance on the concurrent it knows, or thinks, to be

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #110 SEPTEMBER/OCTOBER 2006 29


responsible. But what is it to believed to be concurrent (under a retainer imposing on the
do if those who are sued do not wrongdoers. His Honour noted at architect, among other things, an
comply with their obligations para [25] that interrogatories were obligation to inspect construction
under s 35A(1)? How, then, is the generally to be directed to facts, work carried out and to require
plaintiff to ascertain the names of not to state of mind. However, he the rectification of defects); and
potential defendants? said at para [28], s 61 of the Civil the supervisor (retained under a
Procedure Act23 could be used contract obliging it to certify the
Einstein J confronted just this
to permit the grant of leave to value of progress payments, so as
situation in Nemeth. The nature of
administer such interrogatories. to entitle the builder to payment,
the proceedings was summarised
His Honour said that this was and oblige the principal to pay).
succinctly in paras [1] and [2] of
‘perfectly consistent’ with the
his Honour’s reasons: In the ordinary case, the
case management requirements defective workmanship will
[1] The plaintiff claims damages of Part 6 of the Civil Procedure be the responsibility of the
arising from the subsidence Act, and that it ‘especially builder or its subcontractors.
of premises at 46 Mona Road, caters for efficiency in terms of The damage recoverable would
Darling Point. At the time of the the disposal of the business of be, with some qualifications,
subsidence the first and second the court’ (presumably, in the the cost of rectification.24 The
defendants were apparently particular case). damages recoverable against the
developing the adjoining lot, 44
At para [30], his Honour noted architect might be the same, or
Mona Road.
that nothing would prevent the (if it be different) the value of the
[2] Claims are made that the third defendant from relying on lost opportunity to require the
subsidence was caused by a new information which might builder to rectify. The damages
breach of duty of care owed by emerge as to a further concurrent against the supervisor might
the first and second defendants, wrongdoer; but said in para [31] be the amount of progress
a breach of duty of care owed by that the court could impose a claims overpaid by failing to take
the third defendant and breaches continued obligation on that into account the cost of defect
of statutory duty by the first, defendant to update what it had rectification. But, overall (and in
second and/or third defendants. said in answer to interrogatories broad outline) the total damages
Claims are also made in nuisance if it became aware of the identity recoverable would not in the
against the first, second and third of other possible concurrent ordinary case exceed the cost of
defendants. wrongdoers. As his Honour noted: rectification.
A number of issues arose for This is the same obligation as On ordinary common law
consideration in the context of the continuing obligation to give principles of causation, it may
case management. The only discovery. readily be seen that each of
relevant one related to the third the builder, the architect and
It is likely that, as parties and
defendant’s proposed amendment the supervisor have some
practitioners become used to the
of its defence, claiming a liability to the principal. But
proportionate liability regime, the
limitation of liability under s under the proportionate liability
courts will need to be careful to
35 of the Civil Liability Act. The regime, the court would be
ensure that case management
plaintiff opposed the grant of required to assess the individual
procedures enable the real issues
leave on the basis, as explained contributions of each. In a case
to be exposed in a way that does
by Einstein J at para [15] ‘that as a of defective workmanship, the
not threaten ambush and that
condition of obtaining such leave, builder—who (by itself or through
minimises the risk of multiplicity
the third defendant should be those for whom it is responsible)
of proceedings in relation to the
required to identify the particular negligently carries out the works
same event of loss.
person or persons whom the so as to hand over a defective
third defendant has reasonable One Defendant is Wholly building requiring rectification—
grounds to believe may be the Responsible may be thought to be responsible
concurrent wrongdoer in relation Consider a case where a plaintiff for 100% of the loss suffered.
to the claim’. (principal) sues to recover A finding that one defendant is
Einstein J gave the third damages in respect of defective responsible for 100% of the loss
defendant leave to amend; but, as workmanship. The claim is might be thought to suggest
a condition, required it to answer one for economic loss. Those that there is no percentage
interrogatories administered by responsible might include the responsibility (or no proportionate
the plaintiff as to the identity of builder (under a contract with responsibility) to allocate to any
those whom the third defendant the principal); the architect other defendant. If this is the
30 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #110 SEPTEMBER/OCTOBER 2006
correct outcome of the application having regard to the extent of ... as parties and
of s 35(1) of the Civil Liability their respective responsibilities practitioners become used
Act, the negligent architect and for the damage or loss. What
to the proportionate liability
the negligent supervisor would does ‘responsibility’ mean in this
escape scot free. Alternatively, if context? regime, the courts will
the proportionate responsibilities need to be careful to ensure
The builder’s primary
of the architect and the supervisor responsibility is its contractual
that case management
are considered before that of the obligation to deliver a completed procedures enable the real
builder, and each is fixed with issues to be exposed in a
building (or whatever) in
some percentage of responsibility, accordance with the relevant way that does not threaten
the result may be that the plans and specifications and ambush and that minimises
builder, who in the real world other requirements, and free the risk of multiplicity of
should be regarded as liable for of defective workmanship.25
the whole of the loss, has its That responsibility will usually
proceedings in relation to
liability diminished by operation arise under express contractual the same event of loss.
of the statutory scheme. Section provisions; otherwise, it will
35(3) seems to make clear what be implied on well understood
is in any event implicit in the principles.26 It is a basic principle
scheme: that the court’s task is to of the law that people should
apportion responsibility between honour their contracts; that idea
defendants. That must mean an ‘forms part of our idea of what is
apportionment of the total (100%), just’.27
not an apportionment that yields
a greater amount (in excess of Did the legislature intend to
100%) of the total amount of override this general policy
damages. of the law? Or is the builder’s
contractual responsibility
Conflict Between Tortious something to be taken into
and Contractual Liability account in assessing what is ‘just
In the facts just referred to, it having regard to the extent of the
is likely that responsibility for [builder’s] responsibility for the
defective workmanship will damage or loss’?
be attributed to the builder
Perhaps the answer may be
pursuant to the contract between
found in s 39(a) of the CL Act,
the builder and the principal.
whereby nothing in Part 4 is to
However, in the usual case,
prevent ‘a person from being
the underlying or primary
held vicariously liable for a
responsibility may be attributed to
proportion of any apportionable
the subcontractor who performed
claim for which another person
the negligent work, under a
is liable’. That may reinforce an
contract with the builder.
approach which suggests that,
If the pleaded case against the when considering questions of
builder demonstrates that there allocation of responsibility, the
is an apportionable claim then, court may well take into account
notwithstanding that the builder the primary contractual obligation
may be sued in contract, the and the responsibilities, of a
proportionate liability regime vicarious nature, embodied in it.
will be engaged. In those
This suggests that questions
circumstances, the builder
of the application of the
may seek to limit its liability by
proportionate liability regime may
pointing to the responsibility of
well depend upon a close analysis
the subcontractor.
of the pleaded claim. If this is
If the court finds that the so, then those advancing claims
subcontractor is a concurrent pursuant to a contract might be
wrongdoer with the builder then it well advised to plead them very
is to give damages against them carefully, and to restrict them to

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #110 SEPTEMBER/OCTOBER 2006 31


the contract. In particular, they they think may be liable as plaintiff will commence further
might be well advised to avoid cross–defendants, so as to claim proceedings against those ‘found’
the currently fashionable practice contribution or indemnity. Two in the earlier proceedings to have
of alleging all possible causes things may be said about this. some responsibility.30 The result,
of action including in contract, First, where defendants do so, it as I have already indicated, will
negligence and under the Trade is at their risk as to costs, not the be further litigation in which
Practices Act or equivalent plaintiff’s (except in the case of much if not all of that which
regime.28 an order that the plaintiff meet has already been heard and
those costs).29 The second is resolved will need to be reheard.
Proliferation of Parties … that it is not uncommon, at least Firstly, this means that the same
Typically, in construction in New South Wales, for those court may be required to hear
litigation, there may be many who have been sued to make what is substantially the same
entities that are, or may be said to common cause with those who dispute several times over, but
be, liable for damage suffered by might have been sued, taking the against different defendants.
a plaintiff. The previous example view that this is the best way to Secondly, it is likely to mean that
was very simple. In more complex defeat the plaintiff’s claim. The the defendants in the second
cases, both external professionals proportionate liability regime, and later proceedings will ask
(including the various engineering by encouraging proliferation of for a judge other than the one
professionals engaged for defendants (on the assumption who heard the first or earlier
different aspects of the design that a plaintiff, having been proceedings, upon the obvious
and construction process) and notified of the identity of potential basis of apprehension of bias.
various subcontractors may all be concurrent wrongdoers, will seek
thought to have some part of the Presumably, we will need either
to join them as defendants) may
overall responsibility. Hitherto, a more Construction List judges (in
in fact make it more difficult for a
plaintiff was able to pick its victim jurisdictions such as the Supreme
defendant successfully to resist
and to proceed, in an attempt to Court of New South Wales, where
a claim. It may be doubted that
keep the proceedings as simple there is a specialist Technology
the legislature had this possible
as possible, and to obtain a and Construction List) or more
consequence in mind.
resolution of its claim with the judges who are willing, or if not
minimum expense of time and I do however acknowledge willing at least available, to be
money, against that victim only. that one likely result of the co–opted (‘drafted’ might be a
But under the new regime, a proportionate liability regime will better word) into hearing building
plaintiff will be forced to consider be a reduction in the number of cases.
very seriously who may be liable, cross–claims. Again, it does not appear that
and the result will be proliferation There is no evidence that the the legislature or the executive
of defendants. Even if the plaintiff legislature or the executive have have made plans to cope with the
does not pursue this task made any plans to meet the likely increased demand on court
vigorously, it may be expected likely significant increase in court resources.
that defendants will do so, with and related resources that will
the same result. be required to deal with these Impact on Prospects of
Thus, resolution of the dispute problems. Settlement
It may be wondered whether the
is likely to require resolution of a … or Multiplicity of proportionate liability regime, and
very large number of subordinate
disputes, each with its own Proceedings its propensity for proliferation
The alternative is that the plaintiff of parties or multiplicity of
peculiarities and complexities.
will seek to keep the proceedings proceedings, will facilitate
This is likely to lead to a very
as simple as possible, and to settlement of disputes. On the
substantial increase in demands
take its chances on recovering one hand, the regime may be
on court (or referee or arbitrator)
all, or the great part, of its thought to provide defendants
time and very substantial
damages against those whom with further opportunities to limit
increases in costs.
it has chosen to sue. If the or pass off to others their liability.
It may be said that the risk plaintiff is not successful in this On the other, complex multiparty
of proliferation of parties is endeavour (ie, if those whom disputes, involving numerous
exaggerated, because in many it has chosen to sue succeed cross–claims for contribution,
cases under the ‘old’ regime, in deflecting a substantial part have proved to be susceptible to
defendants that are sued will of the responsibility onto non alternative dispute resolution in
in any event join others who parties), then it is likely that the the past, and it may be that the

32 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #110 SEPTEMBER/OCTOBER 2006


new regime will not produce any be imposed on the negligent extent (if any) that the statement
different outcome. party’. This is required to be is against his or her interest.
considered both: whether, ‘in an
However, there remains the (4) For the purpose of determining
exceptional case’, negligence
situation where a party may the scope of liability, the court
that cannot be shown to be a
wish to extricate itself from is to consider (amongst other
necessary condition of the harm
proceedings either by making relevant things) whether or not
should nonetheless be accepted
an offer of compromise under and why responsibility for the
as establishing factual causation
the relevant rules or by making harm should be imposed on the
(s 5D(2)); and, as I have indicated,
a ‘Calderbank’ offer. Some of negligent party.’
in considering the scope of
the problems in this connection
were articulated, in the context liability once causation is found. Pleading Issues
I have adverted to one particular
of the Building Act, by Tim I set out the section in all its
issue already and will not repeat
de Uray, ‘Building Act 1993 glory:
what I have said.
(Vic), s 131—Application and 5D General principles
Effect’.31 It may be that the Further, in considering pleadings,
courts of Victoria have some (1) A determination that it will be necessary to have
experience of the application negligence caused particular regard to the onus of proof and,
of the proportionate liability harm comprises the following at least in New South Wales, to
regime to those mechanisms. elements: the requirements of s 5D of the
There is not so far as I know any (a) that the negligence was CL Act.
consideration of the problem in a necessary condition of the It will be observed that the form
New South Wales under s 109ZJ occurrence of the harm (‘factual of defence propounded in Nemeth
of the Environmental Planning causation’), and simply sought an order that the
and Assessment Act (which may
(b) that it is appropriate for the relevant defendant’s liability be
reflect the fact that many litigants
scope of the negligent person’s ‘limited to such other proportion
appeared to be either unaware
liability to extend to the harm so [of the plaintiff’s loss and damage]
of the section and its effect or
caused (‘scope of liability’). as the Court determines is just
unwilling to poke a stick into the and equitable, having regard to
viper’s nest). (2) In determining in an the extent of [that defendant’s]
exceptional case, in accordance liability for any damage’.
Causation with established principles,
It will be seen that the concept To my mind, a defence in those
whether negligence that cannot
of causation lies at the heart of terms should not be permitted.
be established as a necessary
the proportionate liability regime: If pleaded, it should be struck
condition of the occurrence of
see the definition of ‘concurrent out; and if sought to be raised
harm should be accepted as
wrongdoer’ in s 34(2) of the CL by amendment, leave to amend
establishing factual causation,
Act, set out above. should be refused. That is so even
the court is to consider (amongst
In New South Wales, the concept other relevant things) whether or having regard to the more liberal
of causation is addressed by s not and why responsibility for the rules that attend proceedings
5D of the CL Act. Two elements harm should be imposed on the entered in the Technology and
are involved: factual causation negligent party. Construction List.
and scope of liability. The former If a defendant wishes to take
(3) If it is relevant to the
requires a conclusion ‘that the advantage of the statutory regime
determination of factual causation
negligence was a necessary for limitation of its liability, it
to determine what the person
condition of the occurrence of should plead, and particularise
who suffered harm would have
the harm’. The latter involves the adequately, the material facts.
done if the negligent person had
conclusion ‘that it is appropriate To my mind, that would require
not been negligent:
for the scope of the negligent the defendant to identify the
person’s liability to extend to the (a) the matter is to be determined other persons whom it believes
harm so caused’. subjectively in the light of all to be concurrent wrongdoers,
relevant circumstances, subject to and to set out the material facts
In determining causation
paragraph (b), and that, it says, show that they are
according to those elements,
and in determining the scope of (b) any statement made by the concurrent wrongdoers. In other
liability, the court is required to person after suffering the harm words, I think, a proper pleading
address ‘whether or not and why about what he or she would have should address the issues raised
responsibility for the harm should done is inadmissible except to the by s 35(1)(b) of the Act: identifying

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #110 SEPTEMBER/OCTOBER 2006 33


the alleged concurrent wrongdoer better, of something that is faulty: that subsection may be put to one
and the circumstances that may see, for example, The Oxford side for present purposes.
make that person a concurrent English Dictionary (online version 13. CL Act s 35(5)
wrongdoer. In substance, the at http://dictionary.oed.com).
defendant should plead with the (That dictionary’s citations include 14. Such a practice note, or rule
same degree of precision and what might be thought to be an of court, might be justified in
particularity as it would do under apt quotation from ‘Florio’ by New South Wales by ss 56 and 57
the old regime if it were bringing the obscure 19th century writer, of the Civil Procedure Act 2005.
a cross–claim against that alleged Hannah More, (Dramas, 1827): Those sections provide as follows:
concurrent wrongdoer. ‘He said when any change was 56 Overriding purpose (cf SCR
brewing, Reform was a fine name Part 1, rule 3)
Case Management for ruin’.)
As I have said, courts will (1) The overriding purpose of this
need to ensure that their case 4. See Proclamation 2004 No 754, Act and of rules of court, in their
management procedures are 24 November 2004 application to civil proceedings,
adapted to ensure that cases 5. See CL Act Schedule 1, cls 6(1), is to facilitate the just, quick
where proportionate liability is 13 and cheap resolution of the real
an issue are managed efficiently, issues in the proceedings.
so as (among other things) 6. See Proclamation 2004 No 755,
dated 24 November 2004 (2) The court must seek to give
to eliminate multiplicity of
effect to the overriding purpose
proceedings. However, and again 7. (2005) 26 Aust Bar Rev 29 at when it exercises any power
as I have indicated, there may 30–33. Reference may also be given to it by this Act or by rules
be some tension between such made to her article ‘Reforms of court and when it interprets
case management procedures to Liability in the Construction any provision of this Act or of any
which, typically, might impose on Industry’ (1994) 3 Torts Law such rule.
defendants who do not comply Journal 285.
with their obligations under (3) A party to civil proceedings is
8. (2002) UNSWLJ Vol 25(3) at 825
s 35A(1) (in a timeous way) a under a duty to assist the court
sanction more severe than costs 9. (1981) 146 CLR 206 to further the overriding purpose
and the terms of the legislation. and, to that effect, to participate
10. Or equivalent. In New South
in the processes of the court and
One topic that will require Wales, for cases brought in
to comply with directions and
particular attention is that the Commercial List or the
orders of the court.
of pleading and particulars, Technology and Construction
where a defendant relies on List, there are no pleadings. (4) A solicitor or barrister must
limitation of its liability to its See Practice Note. Parties are not, by his or her conduct, cause
proportionate share. That required to file ‘statements’ and his or her client to be put in
raises the more fundamental ‘responses’ appropriate to the breach of the duty identified in
question of onus of proof. I nature of the claim or cross– subsection (3).
now turn to those questions claim being asserted. Those (5) The court may take into
dealing with the latter first. documents are not pleadings; account any failure to comply with
they are required to eschew subsection (3) or (4) in exercising
formality; but they are required
REFERENCES a discretion with respect to costs.
to enable the true issues to be
1. Corporate Law Economic exposed. (Whether or not they 57 Objects of case management
Reform Program (Audit Reform achieve this is a matter on which (1) For the purpose of furthering
and Corporate Disclosure) Act minds may differ.) In this paper, the overriding purpose referred
2004 I will use the common and well to in section 56 (1), proceedings
understood term ‘pleadings’ in any court are to be managed
2. Equivalent regimes are to include any form of quasi having regard to the following
established under the pleading whereby a claim or a objects:
Corporations Act (s 1041L) and defence is propounded before a
the ASIC Act 2001 (s 12GP) for (a) the just determination of the
court or arbitral tribunal.
claims under the provisions of proceedings,
those Acts that are analogous to 11. (1999) 197 CLR 1
(b) the efficient disposal of the
s 52. 12. Wrongs Act 1958 (Vic), s business of the court,
3. The noun ‘reform’ connotes the 24AI(3): the exceptions set out in
amendment, or change for the
34 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #110 SEPTEMBER/OCTOBER 2006
(c) the efficient use of available 23. Which reads: (f) it may direct the party to pay
judicial and administrative Division 2 Powers of court to give the whole or part of the costs of
resources, directions another party;
(d) the timely disposal of the 61 Directions as to practice and (g) it may make such other order
proceedings, and all other procedure generally (cf SCR Part or give such other direction as it
proceedings in the court, at a 23, rule 4; Act No 9 1973, section considers appropriate.
cost affordable by the respective 68A) (4) Subsection (3) does not limit
parties.
(1) The court may, by order, give any other power the court may
(2) This Act and any rules of such directions as it thinks fit have to take action of the kind
court are to be so construed and (whether or not inconsistent with referred to in that subsection or
applied, and the practice and rules of court) for the speedy to take any other action that the
procedure of the courts are to be determination of the real issues court is empowered to take in
so regulated, as best to ensure between the parties to the relation to a failure to comply with
the attainment of the objects proceedings. a direction given by the court’.
referred to in subsection (1).’
(2) In particular, the court may, by 24. Bellgrove v Eldridge (1954) 90
See also r 2.1 of the Uniform Civil order, do any one or more of the CLR 613
Procedure Rules 2005: following: 25. That contractual responsibility
Part 2 – Case management (a) it may direct any party to will ordinarily extend to the whole
generally proceedings to take specified of the defects.
2.1 Directions and orders steps in relation to the 26. BP Refinery (Westernport) Pty
proceedings; Limited v President, Councillors
(cf SCR Part 26, rule 1)
(b) it may direct the parties to and Ratepayers of the Shire of
The court may, at any time and proceedings as to the time within Hastings (1977) 180 CLR 266
from time to time, give such which specified steps in the 27. Baltic Shipping Company
directions and make such proceedings must be completed; v Dillon (1991) 22 NSWLR 1, 9
orders for the conduct of any
(c) it may give such other (Gleeson CJ). The decision was
proceedings as appear convenient
directions with respect to the reversed in the High Court (1993)
(whether or not inconsistent
conduct of proceedings as it 176 CLR 344, but nothing said in
with these rules or any other
considers appropriate; the High Court casts doubt on
rules of court) for the just,
this statement of fundamental
quick and cheap disposal of the (3) If a party to whom such a principle.
proceedings. direction has been given fails to
comply with the direction, the 28. These suggestions are
15. In the case of joint tortfeasors,
court may, by order, do any one or not made entirely without self
this abolishes the principle
more of the following: interest.
known as the rule in Brinsmead v
Harrison (1872) LR 7 CP 547 (a) it may dismiss the 29. As to which, see eg Edginton
proceedings, whether generally, v Clark [1964] 1 QB 367; Thomas
16. CL Act s 35(3)(b)
in relation to a particular cause of v The Times Book Co Ltd [1966] 1
17. There will be exceptional action or in relation to the whole WLR 911
cases, particularly where, having or part of a particular claim; 30. I have italicised the word
sued one defendant or group of
(b) it may strike out or limit any ‘found’ to emphasise that the non
defendants, and recovered part
claim made by a plaintiff; parties will not be bound by any
only of its loss, a plaintiff decides
such finding.
to sue other alleged concurrent (c) it may strike out any defence
wrongdoers for the balance of its filed by a defendant, and give 31. (2003) 19 BCL 162 at 171–173
loss. judgment accordingly;
This is a revised version of
18. (1998) 12 NSWLR 231 (d) it may strike out or amend a paper Justice McDougall
19. [2005] NSWSC 1296 any document filed by the party, presented to the Building Dispute
either in whole or in part; Practitioners’ Society, Melbourne,
20. CL Act, s 35A(1)
(e) it may strike out, disallow or on 10 July 2006. His Honour
21. See footnote 7 above. reject any evidence that the party acknowledges the contribution of
22. I deal with this decision in has adduced or seeks to adduce; his tipstaff, Anne Egan Wagstaff.
more detail in the following
section.
AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #110 SEPTEMBER/OCTOBER 2006 35

You might also like