Professional Documents
Culture Documents
Index:: Project Overview - Project Tasks - Given Data
Index:: Project Overview - Project Tasks - Given Data
1) Project Overview .
2) Project Tasks .
3) Given Data .
3.1 Table 1 | Loads and Moments .
3.2 Figure 1 | Soil Profile .
4) Soil Properties .
4.1 Table 2 | Soil Properties .
5) Eccentricity Calculations .
5.1.1 Table 3 | Eccentricity Calculations .
6) Foundation design .
6.1 Shallow foundation
6.1.1 Calculation Sample for Shallow Foundations (Square Sections) .
6.1.2 Calculation Sample for Shallow Foundations (Rectangular Sections) .
6.1.2.1 Figure 2 | C3’ Column .
6.1.3 Shallow foundation results .
6.1.3.1 Table 4 | Shallow Foundations Dimensions Results .
6.1.3.2 Table 5| Concrete Volume Calculations .
6.2 Pile Foundations .
6.2.1 Calculation Sample for Bored Piles .
6.2.2 Calculation Sample for Driven Piles .
6.2.3 Pile foundation results .
6.2.3.1 Table 6 | Pile Foundations Results .
7) Comparing.
7.1.1.1 Comparing Between shallow foundation and group piles .
7.1.1.2 Comparing Between Driven piles and bored piles “Both Group piles”
.
8) Differential settlement .
9) Drawing .
1
1 | Project Overview
In this project, it is required to design a foundation system for a
multistory building of area 568.327 m2, the calculations of the bearing
capacity would l
1) Shallow Foundations.
2) Piles Foundations.
2
2 | Project Tasks
1) Justification for the foundation type choice.
2) Justification of the design parameters choice.
3) Consideration for the serviceability limit state design (Settlement and
Differential Settlement).
4) Suitable alternative design if needed.
3 | Given Data
3
4 | Soil Properties
Based on field-testing, the following properties have been resulted:
5 | Eccentricity Calculations:
Calculation of total applied load and eccentricities were calculated as
follows:
6 | Foundations Design
In this section, the following types of foundations will be designed:
1) Shallow foundations.
2) Pile Foundations (Board and Driven).
All mathematical Calculations have been done Using (Wolfram Mathematica
8.0 and Microsoft Excel), and the following shows a sample calculation for
each foundation type.
4
1) Shallow foundations :
q allowable :
0.025842576
Q 6e (
18574 1+
B ) (1)
q all =qmax =
BL B (
1+ B = ) B
2
qultimate :
q ult=¿c N c s c d c ic +q N q s q d q i q+0.5 γB N γ s γ d γ i γ ¿
Parameters :
B'=B - 2e= B - 0.008614192
∅
K p = tan 2 45+ ( 2
=1 )
B 0.2B'
Sc =1+0.2 K p = 1+
L B
Sq =S γ =1
D 1.
d c =1+0.2 √ K p =1+
B B−0.0086
d q =d γ =1
i c =i q=1
i γ =0
1 0.2 (B-0.0086)
q ult = 81.86 + 782.6 (1 + )(1 + ) (2)
B-0.0086 B
qult
=3
qmax
5
1. 0.2( B -0.0086)
(81.86+782.61(1+ )(1+ )) B2
B -0.0086 B
=3
0.0258
18574(1 + )
B
∴B = 6.9558 m ≅ 7 m
Column 3’
This calculation has been done for
edge columns C3’ to prevent outer
border crossing as shown in Figure
(2).
All exterior foundations have been
moved 1.5 m inside the borders.
By changing the length “L” of the foundation and fixing the
eccentricity to 1.5 m to find the optimum B=5.5 m.
The required length is 14m.
Figure 2 | C3’ Column
Data from sections (1 , 2) :
Cu = 152.25 kPa Pu = 11824 kN e = 1.5101 m
Considering L = 14 m
q allowable :
9.0606
5912(1+ )
Q 6e 6e B
qall = qmax = (BL
1+ )B
B
= ( q/ ( B ×14 ) ) (1+ ) =
B 7B
q ultimate :
q ult = c N c sc dc i c +q Nq s q dq i q +0.5γB Nγ sγ d γ i γ
6
Parameters :
∅
(
K p = tan 2 45+
2 )
=1
0.2 B'
Sc =1+ =1+0.014(-3.0202+B)
14
Sq = Sγ =1
0.2(5) 1.
dc=1+ = 1+
B' B−3.0202
d q =d γ =1
i c =i q=1
1.
q ult= 81.8 +782.6(1+ )(1+0.014(B-3.0202))
B -3.0202
qult
=3
qmax
1.
7(81.86 +782.61(1+ )(1+0.014(-3.0202+ B ))) B
-3.0202+ B
=3
9.061
5912(1+ )
B
By Solving this equation for B :
B →-77.02 , B → -4.22 , B→ 3.463 , B →5.502
So B = 5.5 m
7
c) Shallow foundation results :
After using a factor of safety of 3, and solving for B, the follows resulted :
And By using the values of approximated B & L, and solving for F.S ,
and calculating concrete volume :
2) Pile Foundations :
Instead of using a single pile for each column, group piles
have been designed for the whole structure to minimize the
number of piles used and the depth of them.
8
Two types of Piles were designed:
1) Bored Piles.
2) Driven Piles.
Nc = 9
α = 1 for soft clay .
Number of Piles : = 89
Rows = Columns = 9
Diameter = 1.5 m
Qb = Cu Nc Ab
2
Qb=Cu ×9 × (3.141592/ 4 ) d =2421.58
Qs = α Cu As
Qs=Cu ×3.141592 ×d × L=717.5048 L
Qult/Qall = 2.5
0.000113 (2421.579+717.504 L) = 2.5
9
Solving for L , L = 27.38 m
Nc = 9
0.5
Cu
α= ( )
σ eff
Number of Piles : = 89
Rows = Columns = 9
Diameter = 1.5 m
spacing=(141.1815−( n× d ))/(n) = 14.18 m
n(n−1)+ n(n−1) d
eff =1−( )( tan −1 [ ]) = 0.88
90× n ×n spacing
Qb = Cu Nc Ab
2
Qb=Cu ×9 × (3.141592/ 4 ) d =2421.58
0.5
1
78.38(2421.57 +8853.536 L( ) )
81.75 +3.28 L
10
Qall=691984
Qult/Qall = 2.5
0.5
1
(
0.00011328 2421.579 +8853.536 L ( 81.75 + 3.28 L ) )=2.5
Solving for L , L = 29.7 m
7 | Comparing
1) Comparing Between shallow foundation and group piles :
In assumption of 0.5 m thickness of the footing, there is no basis for
comparison, massive success for the shallow upon the pile system.
11
Generally, Soft clay soil can maintain the stability of the foundation just by
bearing capacity, there’s no need for extra capacity which could be resisted
by the side surfaces of the group piles.
2) Comparing Between Driven piles and bored piles “Both Group piles”:
From the resulted data, it can be seen that the amount of Concrete used in
Bored piles are much lower than those by Driven at the same conditions of
pile diameter and number of piles, on the other hand there’s no need for
excavation in the driven piles, on both cases machines and workman are
important factors, accurate comprehensive analysis should be taken either
economically or technically to balance between the two pile systems if one
of them has to be used.
There isn’t any available information about other economic factors affecting
neither the project nor the site conditions.
8 | Settlement
Differential settlement:
Due to the relatively close values of the factor of safety, stresses of the
foundations differ by a small range of 349 to 390 kN/m2 for all foundations,
eventually that would result relatively close values of differential
settlements due to consolidation, although all the values would be high
because the clay is likely to be consolidated especially when a large height
of clay stratum is available.
9 | Drawings
- Drawing 1 : Top Plan View (Attachment 1).
12
- Drawing 2 : Foundations (Attachment 2)
13