Professional Documents
Culture Documents
Cementing Manual 2020
Cementing Manual 2020
CEMENTING
MANUAL
CEMENTING MANUAL
First edition
April 1991
Second edition
January 2020
Published by
Pradip Kumar Mishra
ED-HOI, IDT
Institute of Drilling Technology
Oil and Natural Gas Corporation Ltd
Kaulagarh Road, Dehradun-248195
Uttarakhand, India
Updated by
Bhaskar De, CGM (D)
Dr. Kishori Lal, GM (Chem.)
Pramod Kumar, Chief Chemist
Parvinder Singh, SE (Cementing)
Lokender Singh, SE (Cementing)
Prashant Faujdar, EE (Cementing)
Abhinav Hazra, Sr. Chemist
Preface
A need was felt to update the manual as advance techniques have been
developed for better cementation. Efforts have been made to include major
aspects of cementation to have an integrated approach to this vital operation
of well completion in line with updated SOP.
I hope that this manual will not only enhance the knowledge but also go a long
way in planning and execution of good cementation jobs and reducing
unwarranted NPT. Cementing best practices have been known for more than
60 years, and these practices have to be used by everyone to protect the
environment and community and increase productivity of wells.
P K Mishra
ED-HOI, IDT
Contents
S. No. Chapter Page
Introduction 1-5
Annexure-1 180-191
sdfgghv bbnbnn
Introduction
An oil well is a boring in the earth that is designed to bring hydrocarbon to the surface. To
extract hydrocarbon well is drilled to the target depth in stages in telescopic manner to separate
different formations. After the hole is drilled, sections of steel pipe (casing), slightly smaller in
diameter than the borehole, are placed in the hole. Cement may be placed between the outside
of the casing and the borehole known as the annulus. The casing and cementation provides
structural integrity to the newly drilled wellbore, in addition to isolating potentially dangerous
high pressure zones from each other and from the surface.
With these zones safely isolated and the formation protected by the casing, the well can be
drilled deeper (into potentially more-unstable and violent formations) with a smaller bit, and
also cased with a smaller size casing. Modern wells often have two to five sets of subsequently
smaller hole sizes drilled inside one another, each cemented with casing.
Cementing History
A serious problem in drilling wells right from the beginning was water seeping from behind
casing and entering a well via the casing shoe. The casing shoe had some ability to shut off
water, but drillers were nevertheless forced to be creative. A common solution was to wrap
various seeds in heavy canvas or leather around the bottom joint of the casing and wait for
them to swell, and in the best outcome they provided a barrier.
Casing
pipe
Open
Hole
Seeds after
swell make
barrier near
shoe
The idea of using cement to create a seal between casing and formation was first tried in Russia
by a certain Romanovsky in 1859 in a water well. In the US, the idea can be attributed to John R.
Hill with his 1871 patent “Improved Mode of Closing the Water Courses Encountered in Drilling
Oil Wells.” The patent describes putting cement into a borehole, setting a casing, then waiting
for the cement to set, and eventually, as the patent explains, “The drill cuts out the cement from
1
Cementing Manual
sdfgghv bbnbnn
Introduction
the bore of the well but leaves the water courses closed with said cement.” Experimenting in
this fashion, Wallace Hardison and Lyman Stewart of Hardison & Stewart Oil Company were the
first drillers to put cement in a well in Pico, California, in 1883. The quality of the cement
obviously wasn’t that good because water soon began entering the well.
By the late 19th century, a new type of cement was coming on the market. Portland cement
was invented and named by John Aspdin, a bricklayer and inventor from Leeds, England. For
some years he had been experimenting with various cement formulations, and in 1824 his
efforts were crowned by a British patent entitled “An Improvement in the Mode of Producing an
Artificial Stone,” in which he coined the term portland cement. He named it thus because the
produced solid resembled a limestone quarried on the Isle of Portland on the south coast of
England.
Unlike earlier cements, portland cement was made by burning a blend of limestone and clay,
and crucially, it could harden in an underwater environment.
William Aspdin Son of Joseph Aspdin is regarded as the inventor of "modern" Portland cement
due to his developments in the 1843s.
By 1890, Hardison and Stewart cofounded an oil
company called the Union Oil Company of California,
later to be renamed Unocal, and in 1903 decided to try
the new portland cement. Frank F. Hill, a director of
production for Union Oil, was the first to use the new
cement.
Frustrated with leakage from unconsolidated sands in a
well in the Lompoc region of California, Hill dumped 20
sacks of portland cement mixed with water into the Wallace Libby Lyman Stewart
hole. He then raised the casing 30 feet, capped the top Hardison
and lowered the string back to the bottom. Air
pressure forced most of the cement up the outside of the casing into the annulus. Hill still had to
drill out the cement inside the casing, but the ruse worked. Later, he tried pumping cement
down some tubing with a packer near the bottom. That eliminated most of the re-drilling of
cement set inside the casing, and thus began the era of modern cement jobs.
2
Cementing Manual
sdfgghv bbnbnn
Introduction
Nevertheless, cementing was still seen as a costly procedure. In 1910, Almond A. Perkins, who
owned The Perkins Oil Well
Cementing Company, made the key
breakthrough. In the Perkins
method, portland cement was mixed
with water to form a slurry. A plug
was then inserted into the casing
and pushed downhole in front of the
slurry. Behind the slurry came
another plug, this time pushed down
by water.
The first plug expelling the mud up
the annulus between the casing and
the formation, while the second did
exactly the same with the cement.
The first plugs used by Perkins were
cast-iron with belting discs, with the
addition of a leather cup on top of
the second plug. Perkins’s two-plug
cementing method eliminated the
need for re-drilling cement that had
set in the borehole. Erle Palmer
Halliburton, joined Perkins Oil Well
Cementing Company in 1918 as a
truck driver. Later on in 1924, he
made his own company called
Halliburton Oil Well Cementing
Company.
3
Cementing Manual
sdfgghv bbnbnn
Introduction
Objective of Cementing:
Cementing is a common term used for the process of placing cement slurry, usually formed by
mixing cementing material with water; into the annulus between outside of casing and the wall
of wellbore. Placement is usually done by pumping. Cementing of oil well casing annuli is
universally practiced for a number of reasons, depending on wellbore requirements. Following
are major objectives:
Another type of cementing operation is usually remedial or secondary cementing. The most
common remedial operation is known as squeeze cementing. In this process, a column of
cement is forced under pressure against the formation (open hole) into channels behind casing
or into perforation channels.
The process of cementing has gone through little changes over the years but vast changes have
taken place in cementing technology and its management. The cementing of a well is not
considered in isolation, because the quality of the well available for cementation is as important
as the technology of cementing. And knowledge of various inputs for cementing a well is
essential for job planning, material selection, execution and job evaluation. An attempt has been
made in this manual to cover most of the basic factors involved in cementing of the well and
updating the information.
4
Cementing Manual
sdfgghv bbnbnn
Introduction
The cementing of casing is one of the most critical operations during drilling and completion of
an oil well. The preparation of the hole, the assembly of the surface and subsurface equipment;
rigging up and running casing are all preliminary to the important stage, which is the period
between the running of the last few joints and the final displacement of the cement slurry.
During this critical period, the success or failure of the entire operation is likely to be
determined.
5
Cementing Manual
sdfgghv bbnbnn
CHAPTER 1
Crystalline Phases
Compound Chemical Formula Standard
Designation
(i) Tri-Calcium Aluminate 3CaO.Al2O3 C3A
(ii) Tri-Calcium Silicate 3CaO.SiO2 C3S
(iii) Di-Calcium Silicate 2CaO.SiO2 C2S
(iv) Tetra-Calcium Alumino ferrite 4CaO. Al2O3.Fe2O3 C4AF
The properties of cement are essentially the properties of these four phases. The percentage of
formation of these compounds, however, depends upon a number of factors e.g. quality of raw-
materials used, temperature in the kiln, retention time in the kiln, rate of quenching of the
clinker, particle size after the grinding, and the percentage of gypsum added.
In addition to above four compounds minor concentrations of sodium and potassium sulphate,
magnesium oxide and free lime are also present. The properties of four major components and
their effect on cement is summarized below:
6
Cementing Manual
sdfgghv bbnbnn
7
Cementing Manual
sdfgghv bbnbnn
Time – Days
Fig-1.1: Compressive strength development with time of different components of Portland
cement.
8
Cementing Manual
sdfgghv bbnbnn
9
Cementing Manual
sdfgghv bbnbnn
10
Cementing Manual
sdfgghv bbnbnn
solution that alter their reactivity. A typical schematic thermogram of Portland cement
hydration is shown in Fig.1.4.
C3A and gypsum within cement interact with water and hydration process starts.
Formation of inhibiting layer of first phase products precipitated at the C3S surface acts as a
barrier that inhibits the migration of water to the unhydrated surface. As a result, the initial
fast hydration of C3S slows and is followed by a period in which the reaction barely
progresses. Precipitation of Calcium Sulphoaluminates (ettringite) slows down further
hydration of C3A. Toward the end of this dormant period, the initial C-S-H layer becomes
more permeable, and the hydration rate accelerates again.
Development of fibrils of ettringite, eventually interlinking cement grains.
Strength is obtained principally from the reaction of C3S and C2S (β-form), forming Calcium
Silicate Hydrate (C-S-H).
C-S-H formed, polymerises from dimeric to pentamer and octamer with passing of time.
Hydration of β –C2S takes place rapidly at elevated temperatures.
11
Cementing Manual
sdfgghv bbnbnn
Temp 110°C
3CaO.SiO2 + H2O 1 ½CaO.SiO2.2 ½ H2O + Ca(OH)2
CSH Gel
Temp 110°C
1 ½CaO.SiO2.2 ½ H2O + Ca(OH)2
CSH Gel
2CaO.SiO2 + H2O
2CaO.SiO2.1 ¼ H2O
α-C2SH
Temp 110°C
12
Cementing Manual
sdfgghv bbnbnn
13
Cementing Manual
sdfgghv bbnbnn
14
Cementing Manual
sdfgghv bbnbnn
CHAPTER 2
Cement Additives
Cement slurries can be tailored for specific well requirements by using various cement additives.
These can be dry blended with cement or dispersed/dissolved in mixing water at the job site.
The major cement additive classificalions are:
Accelerators
Retarders
Light-weight materials
Heavy-weight materials
Dispersants
Fluid loss additives
Lost circulation malerials
Specialty materials
2.1 Accelerators
Accelerators are used in cementing shallow and low temperature wells to shorten the setting
time of cement slurry and to promote rapid early strength development. Various commonly
used accelerators are described below. In addition, cements with dispersant and reduced water
also have short thickening times.
Advantages:
Accelerates thickening time and strength development, reducing WOC time.
No extra water requirement.
Increases heat of hydration of cement to aid temperature surveys.
Economical
Limitations:
Concentrations above 6.0% may cause flash setting of cement slurry.
Detrimental to fluid loss additives.
Hygroscopic, difficult to handle.
Slurries treated with CMHEC (Diacel LWL) should not be accelerated with calcium chloride,
instead sodium silicate should be used.
Advantages:
Accelerates thickening time and strength development, reducing WOC time when used
in concentrations 3-10% (BWOW)
15
Cementing Manual
sdfgghv bbnbnn
Cement Additives
Fig. 2.1: Effect of salt on thickening time and strength of API Class "G' cement.
8000 ft API Casing Test.
Limitations:
Does not produce degree of acceleration as achieved with calcium chloride, however
may be used when CaCl2 is not available.
Limitations:
Concentrations above 7% deteriorate fluid loss control.
More expensive than other accelerators.
Highly corrosive, can cause skin burns, irritation.
Amount used %
Accelerator How used
BWOC
Calcium Chloride 2-4 Dry or with water
Sodium Chloride 1.5-5 Dry or with water
Semihydrate form of gypsum 20-100 Dry only
Sodium Silicate Na2SiO3 1-75 Dry or with water
Cement with Dispersants and reduced water 0.5-1.0 Dry or with water
16
Cementing Manual
sdfgghv bbnbnn
Cement Additives
2.2 Retarders
Retarders are the chemicals used to delay cement setting in order to allow enough time for
slurry placement. Besides retardation, most retarders affect cement slurry viscosity to some
extent.
Additives with high water ratios require additional retarder to achieve a desirable thickening
time because (i) materials with large surface areas, which generally have high water
requirements will adsorb part of the retarder, leaving less to retard the cement, and (ii)
additional water dilutes the retarder and reduces its effectiveness.
Retarders function either through surface adsorption (e.g. organic retarders), or the formation
of certain precipitates at the surface (e.g. sugars), thereby making cement particles
impermeable to the extent that hydration does not take place at an appreciable rate.
The chemicals commonly used as retarders are as follows.
2.2.1 Lignin Retarders
Lignin retarders-calcium lignosulphonate and calcium sodium lignosulphonates are used over a
range of 0.1 to 1.5% BWOC, where static bottom hole temperature range from 260°F to 290°F.
Lignin based retarders blended with organic acids can be used in high temperature wells (BHST
300°F and above). Lignosulfonate retarders perform best with low-C3A cements.
2.2.2 Carboxy Methyl Hydroxy Ethyl Cellulose (CMHEC)
Cellulose polymers are polysaccharides derived from wood or other plants. They are stable in
the alkaline environment of cement slurries. Set retardation occurs when the polymer adsorbs
onto the hydrated cement surfaces. The active sites for adsorption are the ethylene-oxide links
and carboxyl groups. Cellulose based CMHEC is a highly effective retarder in concentration
range of 0.1 to 1.5% BWOC and temperature upto 120°C.
Advantage:
Besides retardation, it offers good fluid loss control.
Limilations:
High viscosity when used above 0.7%, concentration greater than 0. 7% requires extra
water or dispersant to reduce slurry viscosity.
Degrades at high temperature.
17
Cementing Manual
sdfgghv bbnbnn
Cement Additives
poor retarders of the aluminate (C3A) and aluminoferrite (C4AF) phases, but they strongly retard
the silicate phases (C3S and C2S). Adding a borate salt to the retarder formulation solves this
problem.
2.2.5 Others
Sodium chloride (20% BWOW), and polyhydroxy organic acid blended with borax (upto
temperature 260°C).
18
Cementing Manual
sdfgghv bbnbnn
Cement Additives
accelerators. Thus, it is particularly suitable for low-temperature applications, for which short
waiting-on-cement times are difficult to obtain. Crosslinked polyvinyl alcohol (PVA) can also be
used in combination with polyvinylpyrrolidone (PVP). Cement slurries prepared with this
additive combination show excellent gas-tight properties. Such additives can be used in
combination with microcement and other chemicals for squeeze cementing during which a high
degree of fluid-loss control is often required.
Poly saccharides consisting of galactose, fructose and mannose units can be used as fluid loss
control additives with suitable dosage.
Fig 2.3: CMHEC molecular structure and illustration of degree of substitution (DS) and
molecular substitution (MS)
Advantages:
Minimises formation damage from slurry filtrate.
Prevents lost circulation and stuck pipe by minimising cement dehydration in the
annulus.
Minimises gas channeling.
Prevents changes in slurry rheology.
Decrease free water of cement slurries.
Limilations:
19
Cementing Manual
sdfgghv bbnbnn
Cement Additives
Cellulosic fluid-loss additives are effective water viscosifiers; as a result, they can
increase the difficulty of slurry mixing and ultimately cause undesirable cement-slurry
viscosification.
At temperatures less than about 150°F [65°C], cellulosic fluid-loss additives are efficient
retarders; thus, care must be taken to avoid slurry over-retardation.
Advantages:
Reduce slurry viscosity.
Reduce the yield point (consistency index) and allows slurry in turbulent flow at lower
pump rates.
Allows heavier slurries with less water and less weighing materials.
Helps in fluid loss control.
20
Cementing Manual
sdfgghv bbnbnn
Cement Additives
Limitations:
Excessive amount causes severe settling.
Increases viscosity when used with high concentration of salt.
Slurry setting is retarded, particularly at low temperatures.
Destroys thixotropic properties.
Factors affecting the response of cement to Additive:
1. Cement fineness: As the particle size decreases, no of adsorption sites gets increases. Hence
consumption of dispersants increases with fineness of cement.
2. C3A content: C3A is much more reactive than C4AF, especially at early hydration times. Thus,
the amount of dispersant required to obtain a given level of dispersion increases with the
C3A content.
3. Nature and amount of soluble alkali Sulphates: The alkali sulfates are very soluble and
readily go into solution when the cement powder is added to water. The solubility and
dissolution rates of the calcium sulfates are much lower (plaster >gypsum > anhydrite) and
can be altered by the presence of organic compounds.
Cement-dispersant efficiency is low when anhydrite is the principal calcium-sulfate phase.
Dispersant is more effective with cements that contain gypsum as the principal calcium-
sulfate phase, rather than plaster or anhydrite.
4. Cement Ageing: carbonation and prehydration of anhydrous cement causes increase in free
water and thickening time (see attached graph in Fig No-2.5).
5. Mixing energy and mixing method, Mix-water temperature, Water-to-cement ratio etc.
Fig No2.5:- Effect of ageing of cement sample on slurry properties (Studied in IDT)
21
Cementing Manual
sdfgghv bbnbnn
Cement Additives
(iii) Ultra light weight systems: Where extremely low density materials are used to create
exceptionally, light weight slurries e.g. nitrogen or air (foam slurry), high strength
microsphere.
Advantages:
Light weight slurries upto 1.38 specific gravity is possible.
Compatible with all additives.
Economical.
Provides some fluid loss control and free water separation.
Limitations:
Low compressive strength and increase in cement permeability.
At temperatures above 220°F, can promote strength retrogression.
Advantages:
Does not increase the viscosity of slurry like bentonite, when used in high percentages.
Slurry of specific gravity from 1.32 to 1.60 can be formulated.
Limitations:
Low compressive strength.
Much more expensive than bentonite.
(c) Metasilicate:
Anhydrous sodium metasilicate is a useful light weight filler slurry additive, used in
concentration of 1% to 3% BWOC.
Advantages:
Very light weight, high yield slurries possible.
Early compressive strength.
Economical considering the high yield.
Reduces free water content.
22
Cementing Manual
sdfgghv bbnbnn
Cement Additives
Limitations:
Low final compressive strengths.
Limited temperature range upto 150°F BHCT.
Not compatible with most slurry additives.
Cannot be used with salt concentration above 5%.
High permeability.
(a) Haematite:
An iron ore (Fe2O3), chemically inert and requires little additional water. It can produce slurry of
specific gravity 2.6
Advantages:
It has no effect on compressive strength and pumping time.
Ideal loading material for wells, except H2S gas wells.
(b) Ilmenite:
An inert material (Iron Titanium Oxide) sp. gr. 4.45-4.6.
Advantages:
No effect on compressive strength and pumping time.
No additional water required.
Slurry of sp. gr. more than 2.3 can be achieved.
Disadvantages:
Sometimes radioactivity is observed.
(c) Barytes:
A common weighing additive used in oil/gas wells.
Advantages:
Slurry sp. gr. of 2.2 can be achieved.
It has large water requirement (20% by weight) which effects compressive strength and
pumping time.
It is recommended for H2S wells.
23
Cementing Manual
sdfgghv bbnbnn
Cement Additives
TABLE 2.1
Extender Additives and Their Performance Features
24
Cementing Manual
sdfgghv bbnbnn
Cement Additives
25
Cementing Manual
sdfgghv bbnbnn
CHAPTER 3
Successful cementations depend heavily on the good cementing job design, designer's
knowledge of fluids, materials and procedures to be used in given well conditions and on the
strict adherence of the field units to the proposed cementing programme.
26
Cementing Manual
sdfgghv bbnbnn
27
Cementing Manual
sdfgghv bbnbnn
Table No- 3.2: API Temperature table (BHCT) for Casing and Liner primary cementing job
Table No- 3.3: API Temperature table (BHCT) for squeeze job
28
Cementing Manual
sdfgghv bbnbnn
blade wear, batch size, and mixing time. Usually, 600 mL of slurry are prepared. The mixer is
operated at 4,000 rpm for 15 sec (during which all of the cement solids should be added to the
mix water), followed by 35 sec at 12,000 rpm. Cement slurries are very abrasive; therefore,
careful monitoring of the mixer blade condition is essential. With this method, dry materials are
uniformly blended with the cement before addition to the mixing fluid (mix water plus any liquid
additives). If liquid additives are present, they should be thoroughly dispersed in the mix water
before the cement is added. In certain cases, the order of liquid-additive addition to the mix
water may be critical. Such special mixing procedures and mixing times should be documented.
If the slurry is going to be batch mixed during the cementing operation, it should be transferred
to a consistometer and stirred in a manner consistent with the expected wellsite conditions of
time and temperature. The slurry mixing procedure specified by the API is not suitable for
ultralow-density systems containing microspheres or nitrogen as extenders. Hollow
microspheres are easily broken under high shear; consequently, the mixer is typically operated
at or below 4,000 rpm. A typical mixing procedure for slurries containing microspheres involves
adding the solids to the mix fluid within 30 sec at 4,000 rpm, followed by an additional 300 sec
of mixing at 4,000 rpm.
29
Cementing Manual
sdfgghv bbnbnn
For large vertical holes, the focus is on density hierarchy. For highly deviated holes, the viscosity
ratio becomes the major requirement. A spacer combining high density and viscosity, together
with pipe rotation/reciprocation, remains the ultimate solution to clean and transport solids. An
operational procedure for determining slurry density is found in API RP 10B.
To some extent specific gravity of slurry can be adjusted by varying water-cement ratio. The
minimum quantity of water is adjusted to ensure its consistency less than 30 Bc and maximum
quantity of water is adjusted to keep the water separation of cement slurry less than 1.4%. By
keeping these two limitations in view, the water-cement ratio can be adjusted to achieve
cement slurries of sp. Gr. Between 1.8-1.9.
Bentonite when using as an extender, the way it reacts additional water is required. Bentonite
can be mixed in two ways. It can be directly mixed with cement (dry-blended) and later the
blend is mixed with mix water or it can be mixed in mix water (pre-hydrated) and later cement is
added in the mixed fluid. Table 3.4 represents a typical data of bentonite type extenders.
It should be kept in mind the following parameters:
1. 1% BWOC pre-hydrated bentonite = 4% BWOC Dry Blend bentonite,
2. The lower the bentonite extended cement slurry density is, cement compressive
strength will be poor.
3. The addition of bentonite to cement slurry requires additional mix water. A rule of
thumb is for each 1 % bentonite additional 5.3 % of water is required.
TABLE 3.4: Comparison of Prehydrated and Dry Blended Bentonite Slurry Properties
Percentage Percentage Dry- Fresh Slurry Density
prehydrated blended water/cement
Prehydrated Dry blended
Bentonite Bentonite Ratio
0 0 44 -- 1.90
0.5 2 54 1.78 1.78
1.0 4 64 1.69 1.70
1.5 6 74 1.62 1.64
2.0 8 84 1.57 1.59
2.5 10 94 1.52 1.55
3.0 12 102 1.49 1.51
4.0 16 124 1.43 1.47
5.0 18 144 1.38 1.42
Ref.: Dowell-Schlumberger Cementing Technology.
Chemical silicate based extender in the presence of water, react with lime in the cement or with
the calcium chloride to form a gel. It is this gel structure which allows the use of large quantities
of water without excessive free water separation, thereby, reducing specific gravity of slurry.
This is totally a distinct process from that exhibited by extenders like bentonite, which absorb
water themselves. Chemical extenders are used in relatively small amounts (0.1-3.0% BWOC).
These are ideal for sea water, also.
However, the premixing of silicates extenders in fresh water must be preceded by the addition
of calcium chloride. Table 3.5 represents a typical data of silicate type extenders.
30
Cementing Manual
sdfgghv bbnbnn
31
Cementing Manual
sdfgghv bbnbnn
The consistency of the slurry is measured in Bearden units (Bc), a dimensionless quantity with
no direct conversion factor to more common units of viscosity, such as Pa-s or poise. The end of
a thickening-time test occurs when the cement slurry reaches a consistency of 100 Bc; however,
30 Bc is generally considered to be the maximum pumpable consistency. Figure 3.4 shows the
output from a typical thickening-time test. Thickening time consistency profiles often begin with
a flat, low-consistency period that lasts a few hours. Then, as the slurry begins to set, the
consistency rises with an ever-increasing slope until 100 Bc is attained. The time at which the
consistency begins to increase is called the point of departure.
Thickening time of cement slurry should be sufficient. It should enable the operator to mix and
place the slurry to the predetermined depth safely. Some margin of safety is also included so as
to cover up the time of break down while pumping slurry. However, excess thickening time
should be avoided as excessive thickening time causes:
32
Cementing Manual
sdfgghv bbnbnn
3.4.3 Rheology
Rheology of cement slurry governs.
Mud displacement in the annulus.
Frictional pressure drop in the annulus and ultimately ECD.
Hydraulic horse power required to place the cement.
Rheology of cement slurry is governed by power law model which states:
Shear stress = k' (Shear rate} n’
Where n' = Flow behavior index
k' = Consistency index
A laboratory test is performed by using Fann Viscometer and plotting the corresponding reading
at various rpm on log-log paper,Slope of curve determines n' while intercept of shear stress is
value of k' in lb-sec/ft2.
From the values of n' and k' various flow equations are calculated to design cement slurry. For
turbulent flow the value of NR, Reynolds Number, is substituted by 3000, while for plug flow NR,
is 100.
33
Cementing Manual
sdfgghv bbnbnn
Depending upon the casing size and hole size including wash outs, slurry is designed for
turbulent flow or plug flow. Wells with low annular clearance turbulent flow is desirable for
good mud displacement. While, in wells with high annular clearance plug flow pattern provides
efficient displacement.
By adding dispersants to cement slurry, turbulent flow can be induced at lower annular
velocities. However, while using dispersants care should be taken so that excess of additive is
not used because this can result in an undesirable relationship between the viscosity of mud and
cement, resulting in channeling. For good mud removal, the cement gel strength should exceed
the mud gel strength by at least 20 lb/100 sq.ft. Excess of turbulence inducers also increase the
thickening time, causes settling of cement particles, excessive free water separation and reduce
the strength of the set cement.
Fluid-loss tests measure the slurry dehydration during and immediately following a cement job.
API RP 10B offers operational test procedures for determining the fluid-loss rate. After
conditioning at simulated wellbore conditions, the test slurry is placed in a heated cell and
subjected to 1,000 psi [6.9 MPa] of differential pressure. The filtrate loss is measured across a
34
Cementing Manual
sdfgghv bbnbnn
The test is performed either in a static heated filter press cell or in a stirred fluid-loss cell, shown
in Fig. 3.5. Whatever the equipment—static filter press or stirred fluid loss—the actual filtration
test always takes place with slurry in a static state. Before the filtration test, slurry conditioning
may be performed in a pressurized consistometer, in a stirred fluid-loss cell, or, if the
temperature is less than 194°F [90°C], in an atmospheric consistometer.
Filtration loss controlling agents are generally high molecular weight compounds blended with
cement slurry dispersants. Combination of these two components is very effective in controlling
filtration loss.
35
Cementing Manual
sdfgghv bbnbnn
water pockets in the annulus leading to the formation of micro channels in the set cement. This
separation can impair zonal isolation, particularly in a highly deviated wellbore.
The free-fluid test measures this separation tendency in the laboratory, using a graduated
cylinder as a simulated wellbore. The procedure permits slurry conditioning at elevated
temperatures and pressures. The duration of the test is 2 hr, measured from the moment the
slurry is poured into the graduated cylinder, shown in Fig. 3.6. For temperatures less than 176°F
[80°C], the graduated tube is placed in a preheated water bath. For higher temperatures, the
graduated tube is placed in a curing chamber. The test procedure is documented in API RP 10B.
Normally all the fluid loss reducing agents reduce the water separation of the cement slurries,
sometimes, the treatment of 1-2% bentonite is also given to reduce the water separation of the
cement slurry.
Immediately after mixing, the slurry is poured into the slurry container of an atmospheric or
pressurized consistometer for preconditioning. The container temperature must be initially
ambient to avoid thermally shocking temperature-sensitive additives. The slurry is then heated
to the test temperature and stirred for a period of 20 min. If preconditioning was performed in a
pressurized consistometer at an elevated temperature and pressure, the slurry must be cooled
as quickly as possible to 190°F [88°C] before the slurry container is opened.
36
Cementing Manual
sdfgghv bbnbnn
37
Cementing Manual
sdfgghv bbnbnn
decreasing the length of the cement column above the top of the flow zone, increasing the open
hole size or decreasing the casing size.
The CGSP is the time period starting when laboratory measurements indicate the slurry has
developed CSGS and ending when they show it has developed 500 lbf/100 ft2. If insufficient
information is available to confidently calculate the CSGS, a value of 100 lbf/ft2 can be
substituted as the starting point for determining the CGSP.
When flow potential is deemed severe, the cement slurry should be designed with the CGSP
minimized to the extent possible. A CGSP of 45 minutes or less (measured at the temperature of
the potential flow zone) has proven effective but for less severe flow potentials a longer period
is acceptable.
The Results Graph is comprises variable indicators and status indicator. During a test, the XY
Graph displays the temperature, pressure, SGS, and consistency that compose the test results.
38
Cementing Manual
sdfgghv bbnbnn
C3A phase of cement has highest heat of hydration viz, 207 cal/gm. To control heat of hydration,
obviously the cement with low C3A content should be used. Also Pozzolan and silica are used as
additives to reduce the heat of hydration of cement slurries.
39
Cementing Manual
sdfgghv bbnbnn
Of the various ways of introducing expansion, chemically compensated cements generally show
the best expansive properties from 5 percent to saturation, also exhibit expansion but to a
lesser degree. Cement containing 5 to 10% of the semi-hydrate form of gypsum also exhibit
expansion. Expansion characteristics of class 'H' cement containing gypsum or sodium chloride
are compared in Table 3.6.
TABLE 3.6
Linear Expansion (percent) with Sodium Chloride and Gypsum
40
Cementing Manual
sdfgghv bbnbnn
ΔV= 0.358(Lf-Li)
where
Li = initial distance measurement between pins (mm)
Lf = final distance measurement between pins (mm)
ΔV = dimensional change of the cement sample (%).
The cylindrical sleeve test is also an open-system bulk-expansion measurement with free access
to water. As shown in Fig. 3.11, three sets of pins are mounted on the outside of the sleeve,
each located on opposite sides of the slit and secured with a spring. The sleeve is closed when
the slurry is first introduced, and a zero reading of the distance between the three sets of pins is
taken with a micrometer. If the set cement expands during the curing period, the diameter of
the sleeve increases and the longitudinal slit opens. After the mold is removed from the curing
chamber, the distances between the pins are measured again, and the amount of expansion is
calculated according to the following equation.
41
Cementing Manual
sdfgghv bbnbnn
ΔV=*ri+L/ri X{L2/L1-1}]
where
L1 = average distance between the pins when the sleeve is empty
L2 = average distance between the pins when the sleeve is expanded
ri = inside radius of sleeve
ri + L = plus the length of the pin.
3.5.6 Durability
It is desirable that the cement stone behind the casing should retain its integrity for years even
in corrosive water. Hydrates of C3A in the set cementstone are known to react with sulphates
present in the formation waters to give a voluminous compound C3A.3CaSO4.31H2O (Calcium
Sulphoaluminate) which eventually damages the set cementstone. For these reasons, the
formations known for their sulphate waters are to be cemented with high sulphate resistant
cements having C3A content below 3% i.e. Class 'G' HSR type cement.
3.5.7 Resilience
Sometimes synthetic nylon fibers, latex and bentonite are added to improve the shatter
resistance and resilience of the set cement stone which in certain conditions may be prone to
damage by the vibrations produced by drilling or fracturing operations.
3.6 Preflushes
Preflushes are categorized into
1. Chemical washes & Surfactants.
2. Spacers
3.6.1 Chemical Washes- Washes are thin, usually water based fluids containing surfactants &
mud thinners, designed to thin and disperse the mud so that it can be efficiently removed from
the hole. Eg- Sodium Acid Pyrophosphate (SAPP)
42
Cementing Manual
sdfgghv bbnbnn
3.6.2 Spacers- Spacers are preflushes with carefully designed densities and rheological
properties. Spacers are more complicated chemically than washes. Below is a description of the
most common ingredients.
a. Viscosifiers are necessary to suspend the weighting agent(s) and control the rheological
properties. They can be subdivided into two classes, water soluble polymers and clays.
Polyacrylamides
Guar and guar derivatives
Cellulose derivatives (carboxymethylcellulose, hydroxyethylcellulose,
hydroxymethylcellulose, and hydroxypropylcellulose)
Various biopolymers like
Scleroglucan
Welan gum.
Diutan gum.
Nonpyruvylated xanthan gum.
Clays, such as bentonite, attapulgite, kaolinite, and sepiolite
Bentonite and sepiolite are often used in combination with biopolymers
b. Dispersants enhance the compatibility of the spacer with WBMs and cement slurries
and disperse the weighting agent in the spacer. The most common dispersant is
polynaphthalene sulfonate.
c. Fluid-loss control agents are usually water-soluble polymers. Sometimes the same
polymer functions as both a viscosifier and fluid-loss control agent
d. Weighting agent(s) are used to obtain the desired spacer density—silica flour, fly ash,
calcium carbonate, barite, hematite, ilmenite, and manganese tetra-oxide.
e. Surfactants increase the compatibility of spacers with OBMs and leave the casing
water-wet.
Because of their relatively high viscosity, spacers are most often flowing in the laminar flow
regime during mud displacement. However, their composition can be optimized to decrease
their viscosity without compromising stability, allowing turbulent-flow placement. The rheology
of spacer depends on many factors, including the concentration of viscosifying polymer and
weighting agent, temperature, and the base-fluid composition (fresh water, seawater, or
concentrated salt solution).
Cementing in oil and synthetic muds requires the use of specially designed spacer fluids to
prevent mixing of the cement and oil or synthetic mud. Some of the properties that are required
are
These spacers are designed to be compatible with both the cement and the mud while
providing other necessary functions for cementing.
Spacers also need to contain surfactants that will return the oil- or synthetic-wet
surfaces back to a water-wet condition so that an effective cement bond can be
achieved. Water-wetting the casing and borehole will lead to proper bonding of the
cement.
The formulation of spacers varies widely. The formulation used is dependent on the personal
preference of whoever is specifying or designing the spacer and cement job. However, there is
one philosophy or technique common to all spacer design — the fluid being displaced should be
as thin as possible, while the displacing fluid should be as thick as possible. This approach
43
Cementing Manual
sdfgghv bbnbnn
promotes thinning of the fluid in the hole so that it does not channel, improves filter-cake
removal and generates a “piston-type” action of the displacing fluid, forcing the displaced
displaced fluid out of the hole in the most efficient manner.
To achieve these goals, different pills are used, each designed to perform a specific function. In
short, viscous spacers separate incompatible fluids, and chemical washes clean the pipe walls.
From there, various combinations are possible, depending on the well requirements.
Once the mud has been conditioned, the following fluid sequences are recommended.
■ For a WBM: viscous spacer is alone sufficient with desired properties as listed above
■ For an OBM: Base oil →→Sacrificial water based mud →→Viscous spacer including surfactant
44
Cementing Manual
sdfgghv bbnbnn
CHAPTER 4
Rheology and Engineered Cementing Programme
4.0 What is Rheology?
Rheology is the study of the flow & deformation of fluids and behavior/ response of internal
attractive forces (Viscosity) with flow rate. It describes the relationship between the flow rate
(shear rate) and the pressure (shear stress) that causes movement. It enables one to deter-
mine the flow regime needed for optimum cement slurry placement and to calculate value for
friction pressure within the pipe and annulus.
2. Turbulent Flow:
When fluid particles swirls within pipe in a rolling motion and any particle can move
anywhere inside flow area transferring momentum with each other, flow is called turbulent
flow. In turbulent flow there is a chaotic and tumbling movement of flu id particles but the
flow front is flat (Fig no-4.1) with the result that very little intermingling of cement and mud
can take place at the interface. As compared to laminar flow, turbulent flow need more
discharge rate through same pipe.
45
Cementing Manual
sdfgghv bbnbnn
In between laminar and turbulent flow, flow regime exhibits transition phase.
The viscosity of a fluid is the ratio of the shear stress (τ) to the shear rate ( , The symbol for
viscosity is µ.
46
Cementing Manual
sdfgghv bbnbnn
In non-Newtonian fluids, slope of the line either increases (Shear Thickening fluids) or decreases
(Shear thinning fluids) with rate. There are three basic rheological model exits for non-
Newtonian fluids viz. Bingham Plastic Model, Power Law Model and Hurschel Bulkley Model
(Modified to Generalized Hurschel Bulkley Model). Characteristics and other details of these
fluids are given in table no-4.1.
ϒ ϒ
ϒ
47
Cementing Manual
sdfgghv bbnbnn
The instrument which is used in field or laboratory for finding rheological parameters is
Rotational Viscometer Meter' (Fig no 4.3) and is designed to operate at different rotational
speeds (Generally 600, 300, 200, 100, 6 and 3 rpm). For this instrument the shear stress (in
pounds per square foot) may be expressed as follows:
Factor of 1.066 may vary, depending on the combination of rotor and BOB.
2
(Shear stress (dyne/cm ) = k1 X k2 X Ɵ
Where,
K1 = Torsion spring constant (unitless)
-2
K2 = Shear stress constant for effective bob surface (cm )
Ɵ = Dial reading
K1 and k2 may vary, depending on the combination of rotor and BOB.
-2
For R1B1 configuration, k2 = 0.01323 cm
For torsion spring assembly F1, k1 = 386
Hence Shear Stress = 0.01323 * 386 * Ɵ
2
= 5.1067 Ɵ dyne/cm
2
= 0.51067 Ɵ N/m (Pa)
2
= 1.066 Ɵ lbf/100ft )
The shear rate is a function of the speed of rotation and the dimensions of the rotor and BOB.
For the standard instrument:
48
Cementing Manual
sdfgghv bbnbnn
and
where
Rb = radius of inner cylinder (bob), m (1.7247 cm);
Rc = radius of outer cylinder (cup), m; (1.8415 cm)
κ = ratio of radius of inner cylinder to outer cylinder and
Ω0 = angular velocity of outer cylinder.)
Pv-Plastic Viscocity & Yp-Yield Point are Fluid characteristics of Bingham Plastic Model where by
conventional calculations Pv and Yp can be calculated as;
(Plastic Viscosity(Pv)
= (Ʈ2 – Ʈ1) / (ϒ 2 - ϒ 1)
= 5.11* (Ɵ 2 – Ɵ 1) / 1.703 (Ω2 - Ω1) poise
=3 (Ɵ 2 – Ɵ 1) / (Ω2 - Ω1) poise
2 -1
= 300 (Ɵ 2 – Ɵ 1) / (Ω2 - Ω1) Centi poise (1 poise=1 Dyne/(cm .sec )= 100 cP)
=300 (Ɵ 2 – Ɵ 1) / (600 – 300) Centi poise (Considering Ɵ 2 = 600 & Ɵ 1=300 RPM)
Pv= (Ɵ 2 – Ɵ 1) Centi poise)
Example 1: Calculate Pv & Yp of the following mud system, whose fann Viscometer dial reading
are given as follows:
RPM (Ω) 3 6 30 60 100 200 300 600
Dial Reading (Ɵ) 10 19 -- -- 53 72 80 116
49
Cementing Manual
sdfgghv bbnbnn
Many times Pv/ Yp calculation by conventional method does not match with results evaluated
by cementing software. Therefore for more accurate Pv/ Yp calculation, Linest method may be
adopted by excluding 3 & 6 RPM readings. Linest method (By using MS excel) with this
procedure give more accurate values as compared to convenetional method (See a comparison
of convenetional and Linest method wrt software evaluated values at table No-4.2
Next to Bingham model, is power fluidic model, but here n (flow behaviour index) & k
(consistency Index) are the index for rheology, therefore the general manual procedure to
calculate n & k on graph paper is explained hereunder:
1. Calculate shear stress (τ) & Shear rate (ϒ) from Rotational viscometer dial
readings as
τ = 1.065* Dial Reading
ϒ = 1.7023*RPM
3. n= (300 rpm Log (τ) - 100 rpm Log (τ))/ (300 rpm Log (ϒ) - 100 rpm Log (ϒ)).
4. Now divide stress (τ) values by 100. Let the new value is stress (τ1)
5. K = τ1/ 511^n.
50
Cementing Manual
sdfgghv bbnbnn
Note:
Interpretation for k value on log graph paper must be carried out carefully.
Due to chances of slip factor affecting the end result, leave the readings of 3 & 6 rpm.
51
Cementing Manual
sdfgghv bbnbnn
52
Cementing Manual
sdfgghv bbnbnn
Fig No-4.5: Shear Stress /Shear Rate graph & software evaluated frictional
hierarchy for exp-1
Exp-1 is showing a properly designed fluid systems for a well, but sometimes it is not possible to
design the fluids as in exp-1 where fluids are having proper rheology from start of flow rate to
maximum limit (fig no 4.5 may be considered as ideal case). Therefore in this case if higher
discharge rate is limited to formation strength, cementer may plan with lower displacement rate
also.
Example-2: Rotational viscometer data at BHCT for a set of fluid system is given
here below.
RPM 3 6 30 60 100 200 300 600
Mud 8 11 -- -- 31 43 55 89
Spacer 18 23 -- -- 52 69 81 118
C/ Slurry 3 5 21 28 56 101 146 --
53
Cementing Manual
sdfgghv bbnbnn
Fig No-4.6: Shear Stress /Shear Rate graph & software evaluated frictional
hierarchy for exp-2
In exp-2 (fig no 4.6), for maintaining 20% higher rheological hierarchy criteria, minimum
discharge rate should be planned for more than 1.37 m3/min.
Example-3: Rotational viscometer data at BHCT for a set of fluid system is given
here below.
RPM 3 6 30 60 100 200 300 600
Mud 5 7 9 11 12 31 46 73
Spacer 10 12 18 22 28 34 40 --
C/ Slurry 5 7 24 40 59 95 134 --
54
Cementing Manual
sdfgghv bbnbnn
However, for better mud displacement efficiency and good cementation job, following criteria
should be followed:
I. Density hierarchy: Displacing fluid should be at least 10% heavier than the fluid it is
displacing.
II. Friction pressure hierarchy: Friction pressure of the displacing fluid should be greater by
at least 20% than the fluid it is displacing. This prevents by-passing of the fluid being
displaced.
III. Minimum pressure gradient: Each displacing fluid should be able to break the gel
strength of the fluid it is directly displacing to prevent leaving any gelled, un-displaced
layer in all side of annulus.
IV. Velocity profile: velocity of the displacing fluid in wider side should not exceed the
velocity of the fluid being displaced in narrow side of the same annulus in order to
effectively remove mud from narrow side of the annulus.
The formula for calculating the velocity of slurry in the annulus is as follows:
V2-n’ =
Where;
V = Velocity of skurry (ft/sec)
NRe = Reynold’s number (dimensionless)
n’ = Flow behaviour index (dimensionless)
k’ = Consistency index (lb-secn’/ft2)
De = Equivalent diameter (dia. Of hole – outer dia. of casing) (inches)
ρ = Slurry density (ppg)
With given discharge rate, pipe and annular velocity can be calculated which can be used to
further calculate Reynold number. Another important expression involved in the
hydraulic of non-Newtonian fluids is the relationship between Reynolds number and Fanning
Friction Factor (f), is as follows:
f = 0.00454 + 0.645(NRe)0.7 ... (For turbulent flow for Slurries containing bentonite)
f =16/NRe (For pipe flow) and f =24/NRe (For annular flow) ... (For Plug and Laminar flow)
55
Cementing Manual
sdfgghv bbnbnn
f (Fanning friction factor) and NRe can also be obtained from graph given ahead. Determination
of f (Fanning friction factor) is useful for calculating friction pressure drop.
As shown in graph for n’=1, minimum Reynold no for critical velocity in laminar region is 2100.
Minimum Reynold no for start of turbulent flow is 3000. However, in general, for given flow
behavior index n’, following table may be referred for corresponding Reynold no. in turbulent
regime (Values are evaluated from graph).
56
Cementing Manual
sdfgghv bbnbnn
CHAPTER 5
Axial Stress(𝜎a ): For a cylindrical test specimen subjected to uniaxial load along its axis, the
axial stress (𝜎a ) can be represented as:
The axial compressive force (𝐹) is applied normal to the flat surface (area 𝐴0) of the cement test
specimen (see Figure no 5.1)
Strain: The measure of the relative deformation that results from applied stress.
Axial Strain: For the cylindrical specimen (see Figure 5.1), the amount of axial dimensional
change (Δ𝐿) relative to the original length (𝐿0) in the direction of primary axial stress is defined
as the axial strain (𝜀a) and is shown by:
57
Cementing Manual
sdfgghv bbnbnn
Radial) Strain: For the cylindrical specimen (see Figure 5.1), the amount of diametrical
dimensional change (Δ𝐷) relative to the original diameter (𝐷0) in a direction perpendicular to
the primary axial stress is defined as the transverse (or radial) strain (𝜀t) and is shown by:
Unconfined Compressive Strength (UCS): The maximum stress a material can withstand before
failing, while being compressed without confining pressure.
Tensile strength (𝝈𝐓): The maximum stress a material can withstand before failing, while being
stretched
Young’s modulus (Y): Property of a linear elastic solid material that represents the material’s
stiffness, which can be further described as the ratio of stress to strain. Young’s modulus (Y) is
defined below by the ratio of axial stress (𝜎a) to the resulting axial strain (𝜀a) during an
unconfined compressive test:
Young’s modulus is expressed in Giga Pascal (pounds-force per square inch or Mega PSI).
Poisson’s ratio is dimensionless. Minus sign for the Poisson‘s ratio formula is required because
the two strain values in above Equation are of opposite sign.
Unconfined Compressive Strength (UCS): UCS is the stress at which the cement specimen fails
in a compression test without confining pressure. It is determined experimentally by
destructively testing the cement sample. The maximum stress recorded during the test is the
UCS and is described as:
𝑈C𝑆 = 𝑀AX{𝜎a(unconfined)}
Tensile Strength (𝝈𝐓): The tensile strength is the stress at which the cement specimen fails in a
tensile test. It can be determined by either direct method or indirect method. The direct tension
test is performed by applying a direct pull apart force to a dog bone shape (Briquette’s molds)
specimen, which gives the direct tensile strength (𝜎TD) of the specimen.
58
Cementing Manual
sdfgghv bbnbnn
The indirect tension test (also called Brazilian test) can be performed by applying a diametrical
compressive force along the length of a cylindrical specimen (Generally ϴ2’’X L1’’), which gives
the splitting tensile strength (𝜎TS) of the specimen.
Elastic Limit: The elastic limit is the stress or deformation limit where the material transitions
from elastic behavior to non-elastic behavior.
Briquette Mold to
cure sample for
evaluating tensile
strength
Cylindrical mold
and sample to
evaluate Tensile
strength (By
Brazilian Test
method), Young’s
Modulus, Poisson’s
Ratio and
compressive
strength.
59
Cementing Manual
sdfgghv bbnbnn
Concentric molds
with shaft to
evaluate shear
strength of cement
60
Cementing Manual
sdfgghv bbnbnn
2. Brazilian method: This method has advantage over previous one as no stress
concentration occurs in sample. In Brazilian test a test specimen disc is prepared with 2’’
in diameter and 1’’ in length. For accurate results, slow loading rate @ 1000 LB/ Minute
(within ASTM standard range) is set on UCS machine. To distribute the load evenly, 10°
contact of machine on circular sample cross-section is recommended for perfect
splitting (Double foam paper adhesive tape can be used to increase the contact area).
For testing tensile strength specimen is placed in UCS machine keeping flat base of
specimen disc in vertical direction (as shown in fig-5.3). Due to round shape of disc
specimen, applied load and its reaction split into two components (right angle with each
other) and their resultant will work at 90 degree to the applied load. As a result,
specimen disc split into two equal half along diameter.
61
Cementing Manual
sdfgghv bbnbnn
62
Cementing Manual
sdfgghv bbnbnn
confinement pressure. Cement sample compresses minutely under applied load and
expands on diameter. These changes in axial and diametrical dimensions are recorded by
micro meters and recorded on computer screen. Elastic properties can be calculated from
the drawn graph. Properties, in this test provides an idea of flexibility at ambient condition
(i.e. without application of pressure and temperature).
Where,
is Poison’s Ratio of the cement sample.
Y is Young’s modulus of elasticity of cement sample.
is density of cement sample.
is compressional wave velocity through cement sample.
is shear wave velocity through cement sample.
63
Cementing Manual
sdfgghv bbnbnn
Figure No. 5.6: Stresses on set cement sheath due to increase in Pressure (Left) and
decrease in pressure (Right) inside casing
Similarly during hermetical testing procedure, existing drilling fluid is replaced by water, a
negative head inside casing is created which resulted into casing deflation (See fig 5.6). Though
positive pressure during casing integrity testing is quit less in comparison to hydro-fracturing yet
introduction of negative pressure is critical and should be analyzed.
Formation mechanical properties also contributes towards cement sheath failure under high
pressure fluctuation. Soft formation with low Young’s modulus and high poison’s ratio deforms
easily under pressure and does not provide any back up support to cement sheath. Thus cement
may fail in tensile under Hoop stress if devoid of sufficient tensile strength.
On the other side hard formation with high Young’s modulus and low poison’s ratio does not
deforms easily under pressure and provides back up support to cement sheath. But in this case,
cement will face high radial compressive stresses and may fail in compression. As shown in
Graph no 5.1, stress regime shift from high in tensile to high in compression with increase of
formation Young’s Modulus. Hence an optimized cement slurry is required to design which can
fulfil all the condition of stresses and can withstand high pressure fluctuations. Therefore most
suitable cement slurry can be designed for any specific field if elastic properties of formation is
64
Cementing Manual
sdfgghv bbnbnn
known. Elastic properties of formation can be evaluated by using Vp and Vs from DSI log.
However for most of the well it has been observed that cement design of normal specific gravity
with Young’s Modulus around 1.0 Mpsi or lower are suitable to withstand stresses induced
during testing/ hydro-fracturing.
Graph No-5.1: Effect of formation Young’s modulus on cement sheath induced stresses
(+ΔPi =6927 psi).
Hence, it is clear that cement compressive strength is not the only important mechanical
property, and that the cement’s elastic properties play a significant role in maintaining the
integrity of the cased wellbore. In most configurations, especially when the casing expands
because of pressure increase or temperature increase, elastic cements are the best solution.
Expanding and flexible cement must also have low Young’s moduli to be properly confined by
the rock and to play their role in preventing microannulus formation. To increase cement
flexural strength, addition of fibre, latex and rubberized compounds are added in suitable dose
in cement slurry. One such expanding flexible cement slurry is shown in Chapter no-6 at 6.4.
65
Cementing Manual
sdfgghv bbnbnn
CHAPTER 6
Applications:
Used primarily for casing jobs.
May be used for squeezes and lost circulation plugs.
Advantages:
Wide range of water ratios.
Compatible with all cement additives. Produced predictable thickening time and
compressive strength.
Can be used at all depths and temperatures.
Highly sulphate resistant.
Resist strength retrogression at high temperatures.
Economical.
Limitation:
Lower compressive strength than portland cement.
Advantages:
Slag cement 'G' compositions developed, do not exhibit high temperature strength
retrogression as shown by class 'G' cement alone. This does not require addition of silica
flour.
Addition of silica flour can further improve the strength, comparable to class 'G' cement
silica compositions.
66
Cementing Manual
sdfgghv bbnbnn
6.4 Expanding and Flexible Cement: Cement for long term integrity
Expanding cements are used to improve cement bonding to the pipe and formation during
primary cementing. When cement enters setting phase and hydration process accelerates, a
volumetric shrinkage up to 4.6% occurs in normal Portland cement. Loss of hydraulic seal due to
micro-channel caused by set cement volume shrinkage and cement bond deterioration due to
high stress regime on cement sheath during hydro-fracturing leads to unnecessary well
intervention and secondary cementation jobs. . Hence a cement system is required which does
not shrink during cement hydration phase as well as it should be flexible enough to absorb
pressure fluctuation like hydro-fracturing, pressure squeeze, perforation, hermetical testing etc.
A cement system is designed by blending suitable cement additives with high compressive and
tensile strength, low Young’s Modulus and high Poisson’s ratio (Table no-6.1, 6.2 & Fig No-6.1).
67
Cementing Manual
sdfgghv bbnbnn
This cement slurry has been successfully field implemented in well# NDSGA for 9⅝’’ casing
cementation and in well#GNDGP_Z for 7’’ production casing of Ankleshwar Asset (Fig 6.2 & 6.3).
Application:
Besides primary cementing, it is useful in squeeze operations lo help seal off
perforations or holes in pipe.
Advantages:
It expands rapidly upon setting, improving bonding.
An effective tool for eliminating gas migration due to micro annulus.
Compatible with fluid loss additives.
Limitation:
Conventional, retarders and elevated temperatures (> 200°F BHCT) have a detrimental
effect on the expansive properties.
68
Cementing Manual
sdfgghv bbnbnn
69
Cementing Manual
sdfgghv bbnbnn
Additional Applications:
Can be used to cement casing to eliminate staging.
Seal off permeable zones.
Reduce gas cutting or prevent fall back.
Advantages:
May be used to 240°F BHCT.
Wide sp. gravity ranges.
Self-supporting.
Gels when pumping stops.
Early compressive strength.
Helps solve lost circulation problems.
Can be accelerated with CaCl2.
Limitations:
Conventional lignosulphonate retarders destroy the thixotropic properties.
High fluid loss.
Gel cannot be broken after excessive shutdown time during cementing operations.
6.6 Cementing Compositions for Geothermal and Thermal Recovery Wells .
High temperature cementing compositions, Lime-magnesia-silica and Lime-alumina-silica
systems, have been reported in use for geothermal and fire flooded wells.
High alumina cement, is widely used because of its greater resistance to thermal shock and can
withstand wide - ranging temperature fluctuations (1200°C)
Advantages:
Resist strength retrogression with silica flour (upto 300°C); crushed alumino-silicate fire
brick, perlite (temp. > 300°C).
Rapid compressive strength development with low permeability.
Resist corrosive water.
Provide more efficient thermal insulation, with perlite.
Limitations:
Require larger concentration of retarder.
More expensive than standard cements.
6.7 Light weight Cementing Compositions for Cyclic Steam Stimulation Thermal
Recovery Wells
“Cyclic steam stimulation”, or “huff n’ puff” is the most widely used steam injection method for
heavy oil recovery; its popularity derives from quick return. There are three stages of CSS - in first
stage steam is injected in the reservoir at a high rate and high pressure for a period of three to
four weeks thereafter in 2nd stage well is closed for few days in soaking of steam for heat
distribution in the reservoir. In third stage well is allowed to flow heated oil and condensed steam
till its production declines to artificial lift (Figure no-6.4). The steam cycles are optimized for
repetition of cycle after a fixed period among the producing wells.
70
Cementing Manual
sdfgghv bbnbnn
Table no-6.3:Composition and properties of 1.50 sg cement slurry tested at 75 & 350°C @
3000 psi
Component % BWOC Properties Result
Cement 100 Thickening time 148
Water 125 (Minute)
ID9 25 Initial Consistency (BC) 17
(Light weight thermally API Fluid Loss 68
stable cement (ml/30minute)
additive) Rheology (n’/k’ in 0.827/0.441
Silica Flour Fine 40 Pa.s^n)
Metakaoline 25 Free Fluid (%) Nil
Grpahite 15 Compressive strength 2590
Fluid Loss 1.0 after exposure to 350°C
Friction Reducer 0.5 (PSI)
Anti-settling Agent 0.4 Tensile Strength (PSI) 429
Young’s Modulus 0.59
Defoamer 0.1
(Mega PSI)
Poisson’s Ratio 0.31
Stability Stable
Permeability (m Darcy) 0.065
Advantages:
Resist strength retrogression under temperature cycling upto 350°C.
Due to light weight, suitable for depleted reservoir.
Inspite of low SG, good compressive strength development with low permeability.
Single cement system replaces lead + tail thermal blend and associated storage
inconvenience. Hence this cement slurry can be used for all steam injection wells.
Limitations:
Homogeneous dry blending require due care.
71
Cementing Manual
sdfgghv bbnbnn
(1)
(2)
(3)
(4)
(5)
Depending on the prevailing temperature and pressure, calcium carbonate (CaCO3) exists in
different forms. These include calcite, aragonite, vaterite and ikaite. However, calcite is the most
thermodynamically stable form at low temperature and is the most expected polymorph of
CaCO3.The carbonation is of significant concern if the CO2 enters the cemented annulus. The
surface area of the cement sheath that contacts CO2 should be minimized to help prevent
carbonation. This can be achieved by reducing the permeability of cement, preventing the
formation of cracks and micro-annulus, and reducing the components in the cement sheath
prone to attack from CO2.
The second step of carbonation of cement is a long term process. In case of long term exposure
to carbonic acid, or if the carbonic acid is refreshed, the calcium carbonate formed in the first
step further reacts with the acid to produce a more soluble product, calcium bicarbonate. This
reaction results in increased porosity, permeability, and loss of overall mechanical integrity. This
can lead to inefficient or even potential loss of zonal isolation in extreme cases. Eq. 7 illustrates
this mechanism.
72
Cementing Manual
sdfgghv bbnbnn
(6)
(7)
During experimentation of cement samples exposure to CO2, it has been observed that, cement
slurries with better particle packing and low porosity & permeability show least impact. Particle
packing can be done by blending small, medium & larger size additives like Silica Fume, Latex, fly
ash and Silica flour fine etc. in suitable doses.
One such design is prepared as follows;
Table no-6.5: XRD results Before and after exposure to CO2 environment @ 170 Deg C
Sl.NO SAMPLE DETAILS QUARTZ CALCITE MAGNESITE
(%) (%) (%)
6.9 Cementing solutions for loss prone fields and depleted reservoir:
Cementation in loss prone fields and depleted reservoir has always been a challenging task. To
avoid cement slurry contamination, density hierarchy has to be maintained. Hence cement
slurry density is kept always more than drilling fluid density. Due to presence of cement slurry,
annulus pressure head increases which makes situation worst if already losses are encountered
due to low formation strength in depleted reservoir. Under this situation well security
management is very difficult. Hence every efforts are to be made to stop the loss prior to
cementation.
In case of vugs and channels in formation, loss control by conventional LCM pills is very difficult.
Drilling and cementing is performed without any fluid return.
Cementation is executed in loss prone depleted reservoir under two circumstances:-
1. To handle the losses during drilling before reaching the target depth.
2. Primary cementation after well is drilled under loss condition and casing is lowered.
6.9.1 During drilling & before reaching target depth if losses are encountered and are not
controlled, following three proved solutions are designed:-
73
Cementing Manual
sdfgghv bbnbnn
6.9.2Rapid Setting Fluid Pill: RSF pill is developed as temperature activated pill from
indigenously available chemicals. It can be used for curing lost circulation and formation
strengthening. It is chemically stable up to 140 Deg C (284 Deg F). RSF pill is an excellent
techno-economic solution for curing losses, both in producing and non-producing reservoir
zones. RSF pill can be formulated and placed easily against loss zones by conventional balanced
plug method. The smaller particle size makes it easy to pump through any BHA as a single pill.
Average cost of RSF pill is around 1.25 to 1.50 Lakhs for 50 bbl (8.0 m 3). RSF pill is easily soluble
with acid within 90 to 120 minutes.
Ingredients:
1) Dead Burnt Magnesite (DBM),
2) Magnesium Sulphate,
3) Boric Acid as retarder.
4) Filler material as MCC and/ or Wollastonite fibres.
Properties:-
Enough compressive strength (around 200 psi in 6.0 hours).
Fig No-6.5: RSF Pill molds
Non damaging (as 90-100% acid soluble). after set
Density less than cement plug.
No effect on setting time by contamination i.e. high resistance.
Rapid, right angle and controllable setting.
Short WOP (Waiting on Pill setting).
Zero shrinkage.
Ease of drill-ability.
6.9.3 Cross-linked Polymeric Gel Pill: Cross-linked polymer gel used as LCM provides circulation
lost control while drilling. This gel pill is preferably used in non-producing zones. Gelation
process is completed in 100 -120 minutes. In case longtime is required, retarder can be added to
get the sufficient placement time. This polymeric cross linked rigid gel provides sufficient
pressure barrier to allow circulating fluid to develop filter cake against formation. As this gel
does not gain any strength, hence after placement, it is followed by fibre based light weight
cement slurry for capping action.
Ingredients:
1. High molecular weight PHPA / Alcoflood 935– (0.8% to 1.1%)
2. Sodium Chloride- 0.5%
3. Sodium Thiosulphate- 2000 ppm
74
Cementing Manual
sdfgghv bbnbnn
4. Calcium Chloride-0.2%
5. HMTA -0.5%
6. Hydroquinone – 0.3 to 0.4%.
Properties:-
Polymeric gel is stable for long time.
Maintains fluidity.
Cross-linking process starts above 45-55 deg C and is
completed in 90-120 minutes. Gelation time: 4-5 hours.
Gel sticks to formation and is malleable in nature.
15 % acid can disintegrates the gel matrix.
Sp. Gr. 1.04.
It is chemically stable up to 100 deg C.
6.9.4 Microbubble light weight cement slurry: micro-bubble Fig no-6.6: Cross link gel Pill
light weight cement slurry has designed with indigenously after placement in vugs/
available surfactants. In spite of low density this slurry provides channels
with adequate compressive strength. It is compatible with API
class G cement and with most cement additives.
Normal cement slurry (1.90 g/cc) travels downwards against cavernous/ vugs and unable to seal
loss zone. Microbubble cement slurry does not spread against channel due to light weight &
gelation properties and hence seal cavernous/ vugs as shown in figure 6.7.
Ingredient:
1. Cement-100%
2. Water-44%
3. Surfactant- 0.5 to 1.0%
If this cement slurry is to be used at temperature more than 60 Deg C, suitable retarder dose
may be used. Being light in weight, this cement slurry reduces significant pressure head in
annulus in comparison to normal cement slurry. During preparation, first normal cement slurry
of 1.90 SG is prepared and stirred in batch mixture. Surfactant is added to cement slurry as per
slurry design to achieve desired specific gravity.
Fig no-6.7: Comparison of normal cement slurry with Micro-bubble cement slurry in terms
of spread against channels.
75
Cementing Manual
sdfgghv bbnbnn
Table no-6.6: Following are few combination of designed Microbubble cement slurry:-
Composition Sp. Gr. Compressive strength
Cement-100% + Water-44% + Dispersant- 1.40 1000 psi in 96 hours
0.2% + Retarder-0.2% + Surfactant-0.5%
Cement-100% + Water-70% + Silica Fume- 1.40 1500 psi in 24 hours
35% + Dispersant-0.2% + Retarder-0.2% +
Surfactant-0.5%
Cement-100% + Water-50% + Dispersant- 1.25 500 psi in 24 hours
0.5% + Latex-5% + Metakaoline-10% +
Surfactant-1.5%
Field Implementation: It has been field implemented in well # NMAB of Cauvery Asset. 1.5 m3
cement slurry of specific gravity 1.20 g/cc was used near cellar at around 12m to stop high
seepage losses. At depth 1038m, observed static loss of 7.5 m3/ hour. Pumped 5.0 m3 micro-
bubble cement slurry of specific gravity 1.50 g/cc. After WOC no static loss was observed. If high
compressive strength is not the requirement, this slurry can be used for primary cementing as
next phase drilling requires only 500 psi compressive strength.
6.10 Primary cementation after well is drilled under loss condition and casing is lowered:
Once the well is drilled up to target depth and casing is lowered, primary cementation has to be
executed. The most desirable parameter for primary cementation is good compressive strength
(preferably more than 2000 psi) for proper zonal isolation. Generally higher the cement slurry
weight higher the compressive strength. But due to depleted reservoir, normal weight (1.90
g/cc) cement slurry cannot be used. Hence achieving good compressive strength with light
weight cement slurry is very challenging. Following light weight cement slurry options are
suggested for depleted reservoir.
1. Light weight cement slurry using PVC and silica fume.
2. Light weight cement slurry using hollow glass sphere (HGS)
6.10.1 Light weight cement slurry using PVC and silica (13 ppg) – Slurry Design for CBM
wells:
PVC is a thermoplastic material which consists of PVC resin compounded with varying properties
of stabilizers, lubricants, fillers, pigments, plasticizers and processing aids. Different compounds
of these ingredients have been developed to obtain specific group of properties for different
applications. However the main compound is PVC resin and with these properties PVC resin can
be used in formulation of light weight cement slurries. Light weight cement slurry of 12 - 13 ppg
was prepared and field implemented in various ONGC wells with good results. The yield of slurry
is 2 m3/MT and the cost was 1.56 times less than slurry using HGS.
Ingredients:
1. Cement -100 %
2. Water – 100%
3. PVC- 70%
4. Silica Fume- 35%
5. Fluid loss control additive-0.8%
76
Cementing Manual
sdfgghv bbnbnn
6. Dispersant- 1.2%
7. Defoamer – 0.1%
Above cement slurry exhibits a good compressive strength of 2200 psi in 24 hours and all the
parameter of cement slurry are within desired range. This cement slurry is well proven field
implemented.
Implementation:
Following are the details of well of CBM Asset where PVC + Silica Fume based light weight
cement slurry is used.
6.10.2 Light weight cement slurry using Hollow Glass micro-Sphere (HGS)-13 PPG:
Hollow Glass Microspheres are a manufactured product from borosilicate glass, which obtain a
high strength-to-weight ratio, providing greater survivability under down-hole pressure. The
beads are manufactured to achieve near perfect sphericity and predictable crush ratings, the
most commonly used being 2000, 3000, 4000, 5000, 6000, 10,000 and 18,000 psi nominal crush
resistances. For cement slurry design in ONGC, IDT has used HGS 5000. This light weight cement
slurry uses HGS 5000*, Metakaolin and Silica Fume as aggregates. The yield of slurry is 1.4
m3/MT and ~1.56 times costlier than the PVC-Silica Fume slurry.
Ingredients:
1. Cement -100 %
2. Water – 70%
3. Metakaoline- 10%
4. Silica Fume- 10%
5. HGS 5000 – 12%
6. Fluid loss control additive -1.0%
7. Dispersant – 0.6%
8. Low temperature retarder- 0.5%
9. Gas Stop additive– 0.2%
10. Defoamer – 0.2%
A compressive strength of 3250 psi in 24 hours is recorded by crush method and all the
parameter of cement slurry are within desired range.
77
Cementing Manual
sdfgghv bbnbnn
6.11 Other technical methods to control loss in depleted reservoir during cementation:
External Casing Packers may be positioned in the casing string directly above a lost
circulation zone. The packer effectively prevents the loss of cement slurries into the lost
circulation zone. For these applications, a second stage cementing operation is normally
performed above the ECP, after setting the packer.
In case any intermediate liner is lowered to cover depleted formation layer (e.g. Bassein
formation is proposed to cover by intermediate liner to reach up to Panna), it should be
lowered with top packer seal as cement rise up to liner hanger is not assured. After
cementation job first check the integrity at liner hanger top, proceed further if found OK,
otherwise seal the hanger top by a cement squeeze job prior to drill the landing collar.
After drilling landing collar, check the shoe integrity. If found OK, proceed for next phase
drilling otherwise improve the shoe integrity by a cement squeeze job.
In case of loss situation, extra volume of cement slurry may be planned based on actual
loss rate at the time of final mud conditioning.
In case complete loss situation where cement rise even with light weight cement slurry is
not assured, use of hybrid swellable packer is suggested. Hybrid swellable packer in the
annulus section avoids any futuristic annulus charging from formation fluid.
6.12 Cement slurry design for low temperature environment of deep sea surface
casing
Deepwater environments are challenging for cementation because the seafloor temperature are
low (approx. 3 - 4 °C) and the weak formations require lightweight cement slurries. Cementation
of conductor casing in deep water require special slurries. Cement slurry need to be accelerated
and simultaneously of sufficiently low density.
Further cement slurry properties needed are short transition times, low fluid loss and an
acceptable rate of strength development, much as when dealing with annular gas flow potential.
Low temperatures slows the cement hydration process and extend transition times, which
allows fluid influx.
The simplest means for density reduction is the addition of water, along with extenders (e.g.
bentonite / sodium or potassium silicates / diatomaceous earth). This process is economical, but
it degrades ultimate cement performance in proportion to the amount of excess added water.
Density reduction with water along with extenders like bentonite results in unacceptable
permeability and low compressive strength. Adequate / mandatory compressive strength
development requires extended WOC, which reflects in higher rig costs.
Considering above factors, a light weight cement slurry of 12.5 ppg for deep sea environment is
designed by using following additives:-
Test Conditions:
Sp. Gr. of slurry BHST, 0C BHCT, 0C BHP, psi RT, min
78
Cementing Manual
sdfgghv bbnbnn
Composition % BWOC:
Water HGS Micro Fly Gas Stop Halad 344 CFR-3 D-Air
4000 Ash (PH) (PH) (PH) 3500L
(PB)
7.44 8 10 0.58 0.3 0.2 0.02
Gal/sac
k
Results:
Thickening Initial Fluid Loss Pv/ Yp Compressive Gas Free
Time BC (ml/30 strength tight Fluid
(Minute) minute) after 24 hrs Charact
er
505 10 52 143.48/8.68 987 psi Yes Nil
SGSA Chart
Tail slurry of 15.8 ppg with 0.5% accelerator (CaCl2), TT-291 min covering about 100-150m is
pumped.
6.13 Cement slurry design for HPHT wells and special considerations
The most common HPHT definition is when bottom hole temperature exceeds 300°F (149°C)
and/ or bottom hole pressure exceeds 10,000 psi. Cementation of HPHT wells encounters a wide
range of unique challenges like;
79
Cementing Manual
sdfgghv bbnbnn
80
Cementing Manual
sdfgghv bbnbnn
before pull out of the drill string. This will reduce effect of surge/swab while casing/liner
lowering and reciprocation.
b) Break gel intermittently during casing lowering. After casing lowering, reach stepwise up
to planned circulation rate and plot graph between pressure v/s discharge rate, mud
properties.
c) Circulate well at planned circulation rate for 2 to 3 times of well volume to lower BHCT.
d) Time gap between end of circulation and start of cement job should be minimum.
e) The important factors to achieve a good mud removal are: (a) Improving pipe stand-off,
(b) increasing Pv/Yp ratio, (c) decreasing mud gel strength, and (d) increasing flow rate.
f) Use of pre-flush/ chemical wash/ spacer ahead of slurry to act as a buffer between
possibly incompatible mud and cement. To avoid slurry contamination, at least 200m
(650 ft) of spacer ahead and 50m (170 ft) behind cement slurry to be maintained for
separation from mud during displacement. Difference between spacer and mud
densities and cement and spacer densities should be around 10%. To get effective flow,
minimum of 1.33 m/sec annular velocity should be considered. However in case of
HPHT wells, it is not possible to achieve 1.33 m/sec annular velocity always, hence
rheological hierarchy of well fluids should be optimized at feasible discharge rate by
using software simulation.
6.13.1.4 Cementing Computer Program
Cementing operation could be optimized by simulating it first in cementing computer
program. It will give an overview of the proper flow pump sequence, pumping schedule
(include stage timing, flow rate, volume for each fluid, worse depth scenario regarding
collapse and burst), and centralizer placement. It also gives ECD predictions and the efficient
displacement rate. The program can give illustrations of pore and fracture pressure window,
which help in deciding the best slurry density, drilling fluid conditioning, spacer, lead or tail
slurry etc.
In critical well conditions, set cement sheath characteristics should be analyzed using
advanced software. The software can quantify the risk of wellbore set cement sheath failure
by applying stress analysis and sensitization criteria. The software analysis of radial and
tangential stresses can determine cement sheath performance in compression, tension or
both, enabling the design of the set cement behind the casing.
6.13.1.5 Contingency Planning:
Make sure that contingency slurries are developed as the well progresses. Setting any
casing at deeper depth can have a profound effect on the slurry design due to increased
temperature and pressure condition and may take a week of lab testing if pilot studies
are not already underway.
As contingency plan, Lab testing to obtain a suitable Kick-off plug/ plug designs for shoe
squeezes should be made available.
6.13.2 Slurry Design
Cement slurry system, pre-flush and spacer should be designed and tested in the laboratory to fit
the objective of the cementing job. When mixing slurry, laboratory testing needs to be run to
ensure right slurry properties at surface and down-hole conditions. Mixing sequence/ technique
need to be followed since some of the additives are sensitive to shear. In general retarder should
be blended just before the job. Laboratory tests simulated at appropriate period of ambient
81
Cementing Manual
sdfgghv bbnbnn
pressure and temperature to provide proper mixing energy. The slurry should be tested ± 50°F
(10°C) from targeted BHCT (Bottom Hole Circulation Temperature).
Key areas to be considered in designing an HPHT cement slurry are:
• Bulk cement sampling
• Temperature
• Cement selection
• Additive selection:
Retarder
Fluid Loss Aid
Silica
Weighting Agent
Gas Migration Control
• Slurry Sensitivity
82
Cementing Manual
sdfgghv bbnbnn
significant changes in thickening time. Higher dose may delay the setting process which in turn
may lead the entry of gas into the cement in high pressure wells. For extreme temperature
conditions, thickening time for a cement lot should be measured with ±5% of the retarder
concentration. Variance in thickening time due to concentration sensitivity should be within
acceptable for safe cement job execution.
B) Fluid Loss Control
Maintaining constant fluid loss in HPHT well is necessary to preserve the chemical and physical
characteristic of the cement slurry, especially due to high hydrostatic pressure in deep wells. On
the other hand, it needs to prevent the development of filter cake that could cause bridging in
the annulus. Fluid loss is crucial, especially in deep wells having narrow clearance between
wellbore and liner/casing.
For high temperature application, the latex based fluid loss additives are widely used, the
advantage being that latex does not viscosify adversely.
The design criteria for fluid loss control for HPHT cementing operation are linked to dynamic
filtration rather than static filtration. Conditioning with stirred fluid loss cell is preferred.
Recommended API Fluid Loss (For HTHP wells) < 50 ml/ 30 min
C) Silica
Above 230°F (110 degC) BHST, commonly used Portland cement undergo retrogression
phenomenon (i.e. it loses strength and gain permeability, which can be minimized/ prevented
by adding at least 35 % silica.
In HPHT wells, changes in down hole temperature and pressure in later stage can crack or even
shatter the cement sheath; radial pressure/temperature fluctuations can create a micro
annulus. To avoid such failures high temperature flexible cement having lower Young’s modulus
should be used. Suitable expanding agent along with flexible additive provides desirable
characteristics to set cement. Use of blend of Class G cement with 40% silica flour, prevents
mechanical strength retrogression and also provides retardation property.
Two forms of silica are normally available:
• Silica flour (fine)
• Silica sand (coarse)
The concentration of silica added to cement should be 35-40%.
Silica flour must be pre-blended with the cement. Where large slurry volumes are to be
pumped, pre-blended silica is only practical option.
Pre-blending of silica with cement adds a significant risk as the bulk is often not fully
homogeneous and sampling errors can occur. With subsequent transfers, the blend becomes
more homogeneous. However, it may undergo some changes (aeration) due to moisture in the
compressed air transfer system. Therefore, samples taken from a blend at the yard may not
match those taken at the rig. Variation in the flour content of a blend can impact the retarder
response. Silica sand should not be used if temperatures exceeding 572°F [300°C] are
anticipated. Because of changes in the crystalline structure, thermal expansion of quartz is
relatively high at these temperatures, and thermal cycling could eventually disrupt the cement.
Thermally stable cement system like High Alumina cement may be used beyond 300°C.
D) Weighing Agents
It is crucial to maintain hydrostatic pressure in the well to balance or exceed the formation
pressure. Cement slurry with density over 16.5 ppg (1.98 SG) require weighing agents such as
hematite, tri-manganese tetra oxide.
83
Cementing Manual
sdfgghv bbnbnn
84
Cementing Manual
sdfgghv bbnbnn
1. Spacer Stability
The ability of the spacer to support the weighting agent on surface and under down-hole
conditions should be confirmed. This is particularly critical where pore and fracture gradient
margins result in spacer density being very close to mud weight. Prior to pumping, the
density should be confirmed with a pressurized mud balance.
The down-hole stability should be assessed using hot roller for temperature/ HPHT
consistometer slurry cup for pressure and temperature condition after leaving for a
minimum of 1 hour.
85
Cementing Manual
sdfgghv bbnbnn
2. Spacer Rheology
In many cases the ability to achieve turbulent flow of the spacer, or a density hierarchy
between the spacer and the drilling fluid is compromised, due to the small difference
between pore and fracture pressures, rheology of the spacer and pipe movement will be
the only available methods for achieving good mud displacement.
To optimize spacer rheology it should be determined at simulated down-hole temperatures
(along with the mud) to ensure effective mud displacement. Spacer rheology should
preferably be 20% higher than mud rheology and 20% less than cement slurry rheology.
Surface rheology measurement should also be taken to provide a quality control step on
the rig.
3. Spacer Compatibility
It is critical that the compatibility of the spacer is confirmed with both the mud and the
cement. Using a range of mixtures (as a minimum 95/5, 75/25, 50/50, 25/75, 5/95), the
rheology should be determined at BHCT. In the absence of HPHT rheometer, It is advised
to condition the spacer in HPHT consistometer at BHCT & cool down to 88°C for measuring
its rheology.
10 minute gels should also be included. If the 100 rpm of admixtures is 25% greater than
the highest 100 rpm reading of the uncontaminated fluids, the spacer design should be
reviewed. If plastic viscosity/yield point or 10 minute gels suggest the slurry may become
un-pumpable, or separate into one or more phases, the spacer design should be changed.
In addition, the thickening time & compressive strength of the cement with spacer
contamination in the ratio of 90:10 must be determined.
Oil-based drilling fluids pose additional problems during cementing operations compared
to Water based muds because they frequently exhibit poor interfacial compatibility with
water-based fluids. There is a potential to form interfacial mixtures that can be extremely
viscous and non pumpable. An oil film remaining on the pipe surface from the drilling fluid
can hinder a good cement-to-pipe bond.
For Oil based muds the Spacer Surfactant screening test should be performed using a
wettability tester as per latest API 10B 2.
Few cement slurries design for HPHT wells along with parameters under different temperature
and pressure conditions are shown below;
86
Cementing Manual
sdfgghv bbnbnn
Results:
Thickening Initial Fluid Pv/ Yp Compressive Gas tight Free Stability
Time BC Loss strength Character Fluid
(Minute) (ml/30 after 24 hrs
minute)
320 30 26 93/20 2500 Yes Nil T-2.09
M-2.10
B-2.11
Results:
87
Cementing Manual
sdfgghv bbnbnn
Composition % BWOC:
Wat Silic Mangane Anti- Dispersa F/L Retard Retard Retard Gas
er a se Tetra settli nt Contr er-1 er-2 er Block
Oxide ng ol Enhanc Additi
Agent Additi er ve
ve
46 45 65 0.8 0.7 0.5 0.6 1.2 2.0 0.5
Results:
Thickening Initial Fluid Compressive Gas tight Free Stability
Time BC Loss strength Character Fluid
(Minute) (ml/30 after 24 hrs
minute)
317 30 20 3100 Yes Nil Stable
88
Cementing Manual
sdfgghv bbnbnn
CHAPTER 7
Cementing Equipment
There are a wide range of cementing equipment available in oil industry which can be used for
1. Cementing operations.
2. Allied jobs like testing of high pressure wells, oil spotting, fracturing jobs and other well
stimulation jobs.
Following are the cementing equipment commonly used for cementing operations:
i. Cementing units
ii. Cement-mixer
iii. Cement silos
iv. Bulk storage
v. Batch mixer/recirculating mixer/homogenizer
89
Cementing Manual
sdfgghv bbnbnn
Cementing Equipment
90
Cementing Manual
sdfgghv bbnbnn
Cementing Equipment
91
Cementing Manual
sdfgghv bbnbnn
Cementing Equipment
92
Cementing Manual
sdfgghv bbnbnn
Cementing Equipment
There are three types of bulk cement plants that do this fast and efficient job of handling and
blending cement materials:
1. The mechanical screw conveyor
2. The pneumatic system
3. The new pneumatic plant that can be dismantled and rebuilt quickly.
They can be moved from one location to another location. Bulk cementing offers many
advantages such as:
1. Cement protected against weather while being hauled to well.
2. No caking, lumping, and spoiling of cement at well.
3. Eliminating wastage from two to ten percent as compared with dumping sack cement in
to mixer.
4. Industrial hazard is reduced.
93
Cementing Manual
sdfgghv bbnbnn
Cementing Equipment
Varied conditions of terrain scope of the well-servicing operation and other factors have
resulted in a wide range of transports and storage bins used to deliver bulk cement at well site.
At bulk blending stations, cement is moved pneumatically at 30 to 40 psi air pressure into
weather tight bins or tanks for a specific job, the cement with dry ingredients is loaded in to bulk
transport units of about 300 cu. ft. capacity. Water-borne vessel using the pneumatic pressure
system may be equipped with their own weighing and blending plants, or they may obtain
weighed and blended materials from a support vessel or from nearby on-land stations.
6.4 Pneumatic Bulk Material Handling System
A typical installation on an offshore platform might include the cement/stimulation skid units,
pressured tanks with high level indicator, mud surge tanks and scales, cement surge tanks and
an air compressor. Both cement and mud may be handled through tailored pneumatic bulk
material handling systems.
Components can be mounted on a single skid base or located separately, depending on the
requirement, portable diesel or electric powered compressors may be incorporated in the
systems.
Pressurized tanks are available in any number of sizes and designs, to fit requirements. The type
of tanks-cone-bottom or horizontal air slide and the size will vary according to space limitations
and the permissible deck load. Typical sizes may be 8, 9, 10, 12 or 13 feet diameter. Capacity
varies with type of pressurized tank selected. Supports for the tanks are designed for fixed or
floating rigs. One of the newest developments or specialized bulk material handling is the
unique Heli-Bins system developed for remote drilling locations that require supply by
helicopter or light aircraft. A typical application involves three 530 cu. ft. non pressure tanks
built of light-weight materials and pressurized tank with sack cutter. These elements are air
lifted in to a remote water or land locations and sacked cement, drilling mud or other dry
materials placed into the 530 cu. ft. tanks via cutter and 28 cu. ft. tank. The dry materials can
then be discharged into a mud system or cementing hopper much faster than is possible
by manual sacks cutting alone, and also the intermixing of additives is simplified and improved.
94
Cementing Manual
sdfgghv bbnbnn
CHAPTER 8
Mechanical Aids
Mechanical aids are used with the casing when casing is lowered. They serve many functions
such as cake-removing, keeping casing into center, inducing turbulence, holding cement slurry
weight in weaker zone etc.
Floating equipment are commonly used in lower sections of casing to reduce derrick stress by
allowing the casing to float in place. The guide-shoe directs the casing away from edges and
minimizes caving, as the casing passes through deviated section of the hole.
8.1 Centralizers
Centralizers are heavy steel guides on springs that fit around the out-side of casing. The
centralizers are having bow type steel guides and designed to prevent overstressing in tight or
crooked holes (Fig. 8.1). The design of centralizers varies considerably depending, on the
purpose and the requirement of customer. API standard (10D) describes the minimum strength
requirement. These requirements are based on starting force, restoring force and running force
(maximum force required to move a centralizer through a specified wellbore diameter). Starting
force is the maximum force required to insert a centralizer into a specified wellbore diameter.
Restoring force is the force exerted by the centralizer against the borehole to keep the pipe
away from the borehole wall.
The casing is centered to obtain a uniform cement sheath. The centralizers will also effectively
center the casing even in highly deviated holes.
Number and placement of centralizers is based on casing load, hole and casing size, hole
deviation and bore hole geometry. Specification of centralizers has been given in API 10D. There
are three types of centralizers: rigid, semi-rigid and spring bow.
Rigid centralizers are built with a fixed bow height and are sized to fit a specific casing or hole
size. Rigid centralizers must be smaller than any restrictions they must pass through;
consequently, the amount of standoff is limited.
95
Cementing Manual
sdfgghv bbnbnn
Mechanical Aids
Turbolizers: Turbolizers are centralizers with fins attached inside of bows to induce turbulency
along with providing centralization.
Spirolizers: Spirolizers have solid blades wrapped around a metal body at an angle. Therefore its
reduced flow area between the spiral provides and creates vortex motion to increase fluid
velocity with direction. Spirolizers are designed to be used in deviated or horizontal sections of
the well.
Stop Collars: Stop collars are used to keep centralizers, turbolizers or spirolizers to keep in
place.
96
Cementing Manual
sdfgghv bbnbnn
Mechanical Aids
However, these baskets are designed only to separate different density fluids and not able to
take hydrostatic head of fluids. For loss prone zones, ECP should be used.
Fig. 8.4: Regular Guide Shoe. Fig. 8.5: Spring loaded Float Collar and float shoe.
97
Cementing Manual
sdfgghv bbnbnn
Mechanical Aids
the fluid column in the well (Fig. 8.5). It prevents fluids from entering the casing while pipe is
lowered in to the hole. Since the pressure of the mud in the hole can collapse the casing, some
mud is needed in the pipe. This mud can be supplied from the surface or from the bottom by
employing a fill-up device in the float shoe.
The object of only partially filling the casing is to keep it light enough to float into the hole.
Floating the casing into the hole reduces some of the load that the derrick has to support. The
ball float valve assembly usually consists of a fabric-reinforced plastic seat with a moulded
rubber lip seal to prevent communication between reinforced plastic ball cage and seat. This
reinforcement eliminates the possibility of mud cut after prolonged circulation of mud or
cement containing a large amount of abrasive materials. The flow area through the valve is
designed to eliminate high pressure surges.
The flapper float shoe is designed for use when abnormally large amounts of lost circulation
materials are needed. Its unrestricted opening helps to prevent clogging and it allows a more
efficient flow of fluids. The flapper, which is spring loaded for quick closing, has a wear resistant
moulded rubber seat for positive back-sealing.
98
Cementing Manual
sdfgghv bbnbnn
Mechanical Aids
the cement in place with a positive check valve. Rig time is reduced because surface filling
operations are unnecessary i.e. saves costly rig time.
Float collar provides a seat for the bottom and top plugs used for cementing operations. The ball
size should be checked prior to lowering/connecting of float collar. Establish mud circulation
before dropping the ball in order to actuate or convert differential float collar into NRV.
c) Coil Tubing.
By using coil tubing retainer is set hydraulically.
99
Cementing Manual
sdfgghv bbnbnn
Mechanical Aids
100
Cementing Manual
sdfgghv bbnbnn
Mechanical Aids
plug is dropped and displaced. When all the cement slurries has been placed, a closing plug
closes the ports by sliding a closing sleeve over the side ports. The free fall stage cementing
method is used when the first stage cement is not required to fill the annulus from the bottom
of casing all the way to the stage tool or when the distance between the tool and the casing
shoe is fairly long. The primary advantage of this method is that the shut-off plug used in the
first stage prevents over displacement of the first stage cement (Fig.8.8).
The displacement stage cementing method is used when the cement is to be placed in the entire
annulus from the bottom of casing upto or above the stage tool. The displacement method is
used in deep or deviated holes in which too much time is needed for a free falling plug to reach
the tool. Fluid volume must be accurately calculated and carefully measured to prevent over
displacement or under-displacement of the first stage. Two stage cementing is the most widely
used multistage cementing technique. However, when a cement slurry must be distributed over
long column and hole conditions will not allow circulation in one or two stages, three stage
method can be used. The same steps are involved as in the two stage methods, except that
there is an additional stage.
Note: For high angle wells (If well angle at stage collar is > 30°), hydraulically operated stage
collar is recommended.
101
Cementing Manual
sdfgghv bbnbnn
Mechanical Aids
piston shears free, uncovering the ports. The external sleeve contains a ratchet mechanism that
permanently holds the set position. The cement is pumped and, unlike stage equipment, the
ports are not closed.
Basket shoes use a basket instead of an expanding rubber element to pack off the annulus. They
provide the same function as a packoff shoe but are limited to low differential pressure
applications and do not create a true hydraulic seal.
102
Cementing Manual
sdfgghv bbnbnn
Mechanical Aids
Although the conventional wiper plugs are widely used, plugs of other designs are also available
for primary cementing like balls, wooden plugs, subsea plugs and tear drop or latch down
devices. The latch down casing plug and baffle may be used with most conventional floating
equipment but commonly, they are used in small diameter tubing for inner string cementing.
This type of plug system, supplementing the float valve prevents fluid from reentering the casing
string. When all the cement has been pumped, the latch down plug permits surface pressure to
be released immediately and also prevents the cement and plug from being backed up into the
casing by compressed air below the plug. If completions are made fairly close to the float collar,
the latch down plug system eliminates the need to drill out the cement.
103
Cementing Manual
sdfgghv bbnbnn
CHAPTER 9
m/sec
104
Cementing Manual
sdfgghv bbnbnn
A Jet velocity exceeding 70 m/sec is considered sufficient for good penetration rates.
9.1.5 Pressure Surges
The faster running in pipe does not substantially reduce the overall trip time, but it may on the
other hand produce heavy pressure surges sufficient to cause mud loss.
The amount of surge pressure is influenced by the speed of pipe, the viscosity of drilling fluid,
the annular clearance, the length of drill string, diameter of nozzles and bottom hole
assemblies. The pressure is developed due to the displacement of fluid in the direction opposite
to pipe movement.
105
Cementing Manual
sdfgghv bbnbnn
TABLE 9.I
Recommended Value of Torque for Tightening Casing Pipes
(xv) Running in speed of the casing should be calculated considering surge pressure
generated and fracture value of the weak formation to avoid inducing loss.
(xvi) Casing is lowered with a differential float collar for automatic filling of casing with
drilling fluid. If regular type of float collar is used, casing is to be filled in after every 05
(Five) joints.
(xvii) Last casing pipe on which BOP and safety equipment is to be installed should be lowered
with matching nipple having good threads in order to avoid any gas or oil leakage.
(xviii) Lower last two pipes with mud circulation.
(xix) Casing string is not to be rested on the bottom or kept under load.
(xx) Hole is flushed with well conditioned mud and casing should hang free in the hole, to
ensure reciprocation during flushing.
106
Cementing Manual
sdfgghv bbnbnn
CHAPTER 10
10.1 Description
(i) Organisational and technical measures for cementation include the following:
(a) Preparation of a plan of cementation.
(b) Selection and preparation of site for placing cementing equipment.
(c) Placement of cementing units, batch mixers, cement bulk handling units and other
equipment.
(d) Loading and transfer of cement into cement mixers.
(e) Making connection of high pressure and low pressure line manifolds and connection of
cementing units with bunkers/silos. Pressure testing of lines at 150% of working
pressure.
(f) Prepare mixing fluid, blending of chemicals and preparation of buffers.
(ii) Preparation for cementing starts right from the moment when information is received
from the drilling department. Cementing section gets informed about the depth and size
of casing, diameter of the well, bottom hole temperature, pressure and mud parameter as
well as condition and behaviour of well (Circulation loss, kick, presence of salts in mud and
their type etc.)
(iii) A plan of cementation is prepared based on the data furnished and is to be circulated to
all concerned with specifically mentioning associated risk if any (Refer Annexure-1).
Cementing materials are selected and volume of cement slurry to be used and operation
time is calculated. After this, the cement slurry is designed for the bottom hole conditions
of well for thickening time and other parameters like fluid loss, free water, stability, gas
tight characteristics etc.
(iv) Lay-out plan of cementing equipment with number of cementing units, cement mixers
and other equipment is also included in the cementing plan. Working plan also included in
the cementing plan. Working plan also includes volume of displacement fluid, volume of
mixing fluid, type and quantity of chemicals, displacement rate and permissible working
pressure.
(v) The plan is finalised jointly with the drilling and mud department.
Cementing equipment to be used for cementation should reach drill site well in advance before
cementing operation. Cementing units and cement mixers are placed and hooked up with well
head as per the approved plan.
107
Cementing Manual
sdfgghv bbnbnn
(i) Clean measuring tanks of cementing units, check size of liner and piston, safety pins
required for the maximum pressure during cementation. Working of pressure gauges,
safety valves and locking devices, required jet sizes for preparation of cement slurry of
desired weight are required to be checked.
(ii) Cement mixing bunkers/silos should be cleaned of old cement, cement lumps etc.
before loading fresh cement.
(iii) Cementing head should have high pressure valves. Before transporting it to drill site, it
should be tested at one and a half times the maximum expected working pressure.
Cementing head should be able to accommodate bottom and top plugs in it.
(iv) If expected working pressure during cementation exceeds 200 kg/cm2, working joints of
High Pressure (HP) lines of cementing units should be checked and pressure tested
before sending them to drill site.
(v) If casing is planned to be reciprocated/rotated during cementation, required additional
equipment should be fabricated and technological hook up of HP line with casing head
should be taken into consideration.
(vi) Required number of pumping units, cement mixers/silos and other equipment should be
determined on the basis of type and volume of cement job. Batch mixer for conditioning
cement slurry should be available.
(vii) Before placement of cementing equipment at site the area should be made free for
hook-up of cementing vehicle, if needed additional tanks, water lines should be made
available. Proper lighting arrangement is to be made if cementing is to be done at night.
(viii) While setting up and connecting cementing units and cement mixers, the following
instructions should be adhered to:
(a) Approach (passage) to the cement vehicles should be free for movement.
(b) Water tank & water line should be close to the cement mixers
(c) There should be free passage between cementing units and cement mixers for easy
working.
(ix) Cementing units should be placed horizontally as far as possible with its measuring tank
facing the weII. Layout and connections of the cementing units are made in such a way
108
Cementing Manual
sdfgghv bbnbnn
109
Cementing Manual
sdfgghv bbnbnn
CHAPTER 11
110
Cementing Manual
sdfgghv bbnbnn
HPHT wells:
1. The slurry should be tested ± 50°F (10°C) from targeted BHCT (Bottom Hole
Circulation Temperature).
2. For extreme temperature conditions, thickening time for a cement lot should be
measured with ±5% of the retarder concentration. Variance in thickening time due
to concentration sensitivity should be within acceptable for safe cement job
execution
3. If well deviation is below 15 deg - Free Fluid test is run vertical
4. If well deviation is above 15 deg - Free Fluid test is run at 45 deg
5. Spacer should be compatible with cement slurry and mud system.
6. Spacer height should be 200-300m in the annulus or volume should be sufficient for
8-10 minute of contact time.
7. Expandable liner hanger to be used.
Don’ts
1. Slurry design of one lot should not be used in another lot. Slurry design of same
lot should be retested after six months.
2. Retarder sensitivity test to be carried out to check its TT at higher and lower doses
and variation in density.
3. To reduce circulating temp further pump Fresh mud kept at ambient room temp.
4. For Liner cementation be careful about cement rise never raise cement above
hanger top.
5. Overlap in HPHT liner can be increased from 100 to 200 m and raise cement in
overlap up to 100 mts. only.
6. Must consider break in pumping while designing slurry, give a break of 10 mins. to
consider dropping of plug during actual cementation.
7. In case of cement plug placement in HPHT well, avoid use of small diameter tail
pipe. Uniform diameter pipe is recommended for plug placement.
111
Cementing Manual
sdfgghv bbnbnn
Don’ts
1. Well should not be kept idle for long time after pull out prior to casing lowering.
Don’ts
1. Do not use centralizer on casing couplings.
112
Cementing Manual
sdfgghv bbnbnn
Don’ts
1. Avoid unnecessary circulation as it may result in wellbore erosion and enlargement.
2. Circulation pressure should be limited to the activation pressure of hydraulically
operated accessories.
11.6 Equipment
Do’s
1. Check the cementing units and bunkers to avoid any breakdown during the operations.
2. Clean the tanks of cementing unit thoroughly.
3. Pressure test the cementing head and all connecting lines.
4. Check and calibrate the pressure gauges.
5. Ensure that cementing line and end connections from ground to derrick floor is of
proper rating and anchored properly.
6. Ensure correct liner size of mud pump is considered for displacement calculation and
discharge. Mud pump efficiency should be considered based on efficiency observed
during previous job.
7. Cementing head, swivels and HP valves should be serviced and tested prior to hook up.
8. Ensure proper lineup for displacement hose to avoid bypass of displacement fluid.
9. Welding is not recommended on any casing joint in grade above J-55 casings.
Don’ts
1. Never hammer pressurized lines.
2. Never weld swivels, hammer union etc.
3. Never puncher bottom rubber wiper plug diaphragm at surface.
Don’ts
1. Do not mix cement additive long before cement slurry preparation, except for pre-
hydrated additives.
2. Avoid pilferage and intermixing of mixing water during chemical mixing.
113
Cementing Manual
sdfgghv bbnbnn
Don’ts
1. Do not plan slurry volume more than that of total casing volume as far as possible.
2. Do not continue pumping if any leakage in lines is observed. Resume pumping after
fixing the leakage.
11.9 Displacement
Do’s
1. Determine displacement rate on the basis of the type of casing string to be cemented.
2. Release the top plug out of cementing head with minimum time lag.
3. Ensure that there is no bypass of the displacement fluid. Observe the anticipated mud
return rate throughout the job.
4. Mud return is measured in trip tanks or by other means. High return rate is predicted
during the free fall period. Slow return is an indication of lost circulation.
5. Check the return fluid: observe pH change, funnel viscosity and density to detect
contamination with cement slurry.
6. After bumping the top plug, leave casing open during WOC, if NRV is ok. If not, close the
well with differential pressure and monitor.
7. For sub-hydrostatic and shallow wells, displace with water and pressure test the casing
immediately after the top plug bumps.
8. Always keep cementing unit lined up for any exigency.
9. In case sudden pressure increase is observed during displacement, switch over to
cementing unit and attempt to displace with pressure limited up to formation strength.
Don’ts
1. Do not reduce displacement rate if loss is observed.
2. If NRV function is OK, never close valves of cementing head.
11.10 Monitoring
Do’s
1. Data comparisons with calculated predictions and post analysis of the job.
2. Calculate material balance for mix water, cement and cement additives and
compare with volume of each slurry pumped.
3. Prepare a summary of the completed job.
114
Cementing Manual
sdfgghv bbnbnn
CHAPTER 12
Types of Cementation
12.1 Description
1. Cementing technology is determined by the type and size of casing to be cemented,
geological and technical conditions of the well, availability of cementing equipment and
experience of cementation in the particular region/area. Diversity of geological and
technical conditions during drilling has led to creation of various methods of cementation.
All the known methods of cementation are divided into primary and secondary
cementation. Primary cementation is carried out immediately after lowering of casing pipe
in drilled hole and secondary cementation is done after the primary cementation, i.e. re-
cementation or repair jobs, elimination of communication between formations, annular
leakage, liquidation of water or gas flow and well abandonment etc.
2. Incase due to some limitations it is not possible to have cement rise up to the desired
height in one stage, it is recommended to use one of the following specialized methods of
casing cementation.
a. Use two or more stages with time gap.
b. Lower and cement casing in sections.
c. Use method of reverse cementation.
3. In order to prevent cement slurry contamination with well fluid below stage collar, cement
basket is recommended to be used. ECP is recommended to be used for casings isolating
abnormally high pressure zones or formations with substantial difference in formation
pressure. ECP in combination with stage collar may be used to isolate fractured basement
to avoid entering cement slurry in the basement.
4. While using above mentioned methods of cementation following conditions should also be
observed.
i. Hydrostatic head of buffer, mud and cement slurry column should be 5—-10% more
than formation pressure;
ii. Value of total pressure acting on formation during cement placement in dynamic
condition should be less than hydro-fracturing pressure or pressure at which lost
circulation starts;
iii. There should not be any discontinuity of cement sheath in the cemented interval.
5. Main objective of any cementation job is to isolate productive horizons and ensure
maximum production of Oil and Gas.
6. Number of measures are taken to ensure total displacement of mud in the annulus. Some
of the most effective measures for better displacement are enlisted below:
115
Cementing Manual
sdfgghv bbnbnn
Types of Cementation
116
Cementing Manual
sdfgghv bbnbnn
Types of Cementation
Maximum axial load on hook during reciprocation should not exceed 80% of casing load.
The value of maximum permissible load on hook during reciprocation should be calculated
and indicated in the cementation plan.
8. After pumping cement slurry into the well, top plug (Fig. 12.1) is dropped and then
displacement fluid is pumped. With the help of double plug container, static time for
installing cementing head after circulation can also be removed. Cleaning of manifold from
cement slurry, displacement fluid and other auxiliary operations should be carried without
losing any time.
9. Displacement fluid of minimum permissible specific gravity as per GTO is recommended to
be used for decreasing radial elastic deformation of the cemented casing caused by
pressure decrease inside casing (during well completion and production). If conditions
permit, displacement can also be done with water and hermetical test thereafter, saving
precious rig time without harming cement bond. (Guidelines for Hermetical testing of
shallow hydrostatic and sub-hydrostatic wells issued by IDT on 22.03.2016)
10. Completion of displacement of cement slurry can be determined by increase in casing
pressure after plug hitting.
Displace with mud at pre-determined pumping rate, slow down displacement after 95% of
calculated strokes are pumped and thereafter bump the plug gently. If bumping pressure is
not holding, stop pumping immediately and keep the well under differential pressure.
11. If the top plug fails to land on float collar, number of extra displacement strokes over the
calculated strokes should not exceed 50% of calculated shoe track volume to ensure
cement around shoe. If top plug bumping is ok, check floats function by releasing pressure
slowly. Release the pressure through properly secured and anchored line.
12. If float is holding, keep the cementing/circulating head valve open to avoid pressure build
up inside casing due to thermal expansion. If float is not holding (also when only guide shoe
is used), keep the well under pressure of differential head for 6 to 8 hrs to avoid back flow
of cement slurry.
13. In case of long cement column or if gas is expected, keep the well under pressure through
annulus for 6 to 8 hours, limited to fracture limit of the formation.
14. The pressure increase after plug hitting, should not be more than 80% of the pressure at
which casing pipe had been tested before landing.
15. After completion of displacement excess pressure in well is bled to atmospheric pressure
and flow of displacement fluid is observed to check whether NRVs in float collar and float
shoe are working properly. If there is no flow, NRVs are working properly. If NRV is ok, well
is left open for WOC.
16. In case NRVs are not holding, displacement fluid equivalent to the volume returned from
the well should be pumped back. In such a case during WOC, pressure equivalent to
differential pressure at the cementing head be monitored and controlled. Pressure during
WOC should not exceeds differential pressure and to be bled periodically if necessary.
17. During WOC, casing should hang on the travelling system. This enables to decrease hook
load upto the initial value spontaneously, in case hook load is increased. This information
should also be recorded.
18. During WOC, condition of the cemented annulus should also be observed.
19. No operation connected with drilling of cement plug or float shoe and float collar should be
taken up before completion of WOC and BOP installation (or casing head).
20. Time for WOC is established depending on the minimum required compressive strength
development time throughout the cemented interval taken by a cement slurry (based on
laboratory tests).
117
Cementing Manual
sdfgghv bbnbnn
Types of Cementation
21. Cementation of large diameter casing is often done through drill pipes (stab in
cementation) (Fig. 12.2). This method of cementation cuts down displacement time and
contamination. Technology of cementation through drill pipes or stab-in cementation
includes the use of stab-in stinger, stab-in receptacle and special plugs.
118
Cementing Manual
sdfgghv bbnbnn
Types of Cementation
2. Multiple stage cementing is carried out with multiple stage cementing collar (Fig. 12.3)
which is placed on casing in the selected intervals of the well.
Depth at which stage collar is to be fixed should be decided from logs: Stage collar should
be preferably placed against stable formations (e.g. clay, shales) in nominal gauged hole.
Casing centralizers should be placed 2-3 m above and below the stage collar to help center
the tool. Stage collar is placed at the depth selected in advance before landing the casing.
Multiple stage collar (Fig. 12.3) consists of the main body which is fixed on the casing.
There is a steel cylinder inside the body (housing). Internal drillable sleeves are fixed in the
cylinder with the help of shear pins. Each sleeve has opening plug seat and top plug seat in
119
Cementing Manual
sdfgghv bbnbnn
Types of Cementation
its upper position. Rubber packing is used to hermetically seal these sleeves. There are
some ports in the stage cementer for establishing circulation. These ports are sealed off by
the closing sleeves. Closing plug, shut off plug and free fall plug (bomb) are also included in
the multiple stage cementer set (Fig 12.4).
3. Cementation with stage collar is carried out in the following sequence (Fig. 12.5). Buffer
and calculated volume of cement slurry are pumped into the well. After this, 1st stage seal
off plug [shut off plug (Fig. 12.3)] is released and displacement carried out until the plug is
seated on baffle plate.
4. Next step is to open stage collar port. Port are closed by lower sleeve which is held by
shear pins having specific shear strength. These pins can be sheared up by applying only
pressure (In case of hydraulic stage collar). Another way is to drop the opening bomb which
seats on lower sleeve seat (In case of mechanical and hydraulic stage collar). After seating
of bomb, pressure is applied for shearing pin. For highly deviated wells, hydraulic stage
collar is recommended. The pressure requirement to open ports in hydraulic stage collar is
much more as compared to opening bomb plug method. Hence, to avoid fracture of weak
formation, if any, by sudden surge of pressure after opening ports, use of opening bomb is
suggested. Pressure drop and establishment of circulation are indications that ports have
been open.
5. 1st stage cement rise should be planned at least 100m below the position of stage collar.
However, cement rise upto stage collar may occur (though possibility is less) due to cement
slurry channeling through mud. Therefore, after cementation of first stage and after
opening ports of the stage collar, well should be circulated in order to wash out excessive
volume of cement slurry from the annulus (above the stage collar) and to condition mud as
per requirement.
6. Second stage should be cemented in accordance with the normal cementing technology;
pump buffer and cement slurry, release top plug and displace till it reaches the stage collar.
After this, in addition to the working pressure, apply additional pressure as specified by
manufacturer (determined by number and shear strength of shear pins) for shearing the
pin and sealing off the ports with sleeve. This process is controlled by releasing pressure at
the cementing head upto zero. If there is no return from the well it is an indication that the
ports have been sealed off.
7. If planned cement rise is quite high, stage collar should be placed in the middle of the
projected height of cement rise. If two pay horizons are to be isolated stage collar should
be placed 10—30 m below the upper hydrocarbon bearing formation.
In any case stage collar is recommended to be put against clay or other low permeable
formations.
8. All the stage collars are supplied with technical specification with their dimensions and
pressures for opening and closing the ports. Table 12.1 gives the data of one brand of
Multiple Stage Cementer Collar.
Note: For high angle wells (If well angle at stage collar is > 30°), hydraulically operated stage
collar is recommended.
120
Cementing Manual
sdfgghv bbnbnn
Types of Cementation
121
Cementing Manual
sdfgghv bbnbnn
Types of Cementation
122
Cementing Manual
sdfgghv bbnbnn
Types of Cementation
2. Quality of cementation depends a lot on the reliability of multiple stage packer cementing
collar which should ensure hermetic sealing while landing casing and during cementation of
first stage, obstacle free movement (passage) or bottom plug and hermetic sealing during
pressure testing and production of the well.
3. Multiple stage packer cementing collar is an integral part of the casing and it is set at the
calculated depth. This packer cementer is set in such a way that it could seal annulus
between casing and borehole.
In case packer cementer is to be installed in open hole, position for its installation should be
selected from the caliper log. It should be placed in nominal hole against stable formation
(clay, marl etc.). Casing centralizers should be placed above and below the packer stage
collar for proper centering.
Multiple stage packer cementing collar (see Fig. 12.6) is analogical to ordinary stage collar in
its design but it also has a rubber packing of element that replaces the need of one or more
cement baskets on the casing below a regular type of stage cementer. After completing first
stage and releasing free fall plug (bomb) packer is opened at manufacturer’s operating
pressure to open slotted ports. After this remaining cement slurry is washed out (if it has
raised above stage collar during cementation of first stage) and complete circulation is
established.
4. Cementation of second stage is carried out in accordance with normal practice.
5. All cementation jobs with the help of multiple stage packer cementing collar should be
carried out only after carefully going through the instructions of its use and after testing it
on the surface.
123
Cementing Manual
sdfgghv bbnbnn
Types of Cementation
124
Cementing Manual
sdfgghv bbnbnn
Types of Cementation
125
Cementing Manual
sdfgghv bbnbnn
Types of Cementation
4. Pressure required for shearing the pins holding liner wiper plug (Fig. 12.7-6) as per
manufacturers specification.
5. Before cementing liner or section of the casing in some particular interval, it is hanged on
the slips of liner hanger (7). After this drill pipes are opened and backed off and seal off the
liner hanger. (5) tested by flushing well. While doing this pulling out of drill pipes (after
disconnecting them from casing) for more than the length of nipple (connecting pipe) is
categorically prohibited in order to avoid packer coming out of the nipple section of the
casing.
6. Backing off of drill pipes from casing should be done in accordance with the instructions of
the operating manual.
7. After disconnecting kelly cementing head is installed on the drill pipe through crossover.
After this circulation is established through cementing head before carrying out cementing
jobs (Fig. 12.7-A, B, C).
8. After cementing operation, drill pipes are installed on the upper end of the section of casing
for reverse circulation (Fig. 12.7-E) after which drill pipes are pulled out completely.
9. Often liner hanger is placed on slips or tongs. Slips or tongs are fixed at the shoe of previous
casing. Hydraulic set liner hanger (left) and mechanically set ‘J-slot’ hanger (right) are shown
in Fig. 12.8.
At present there is a range of liner hangers and setting tools with different features
available. Generally a liner hanger is composed of the following:
a. Setting Assembly: This has either a mechanical or hydraulic mechanism. Mechanical set
hangers can be operated either by rotation or reciprocation. In both cases pipe
movement will release a slip bowl from the retracted position by means of a ‘J-slot’ or
dog spring mechanism. The slips move into the hanging position supported by an upper
cone thereby transferring the liner weight to the upper casing.
b. The hydraulic set hangers: They are operated by hydraulic pressure. Some slip releasing
systems are actuated by dropping a ball, once the liner is in place, which will land in a
catcher sub. Further pressure will move a piston type assembly or shear pins which will
release the slips (Fig. 12.8).
c. Setting Sleeve: This is run above the setting assembly and has a thread matching the
liner setting tool. It is used to run the liner to depth.
d. Tie Back Sleeve: Screwed on top of the liner, it has an internal polished surface to
provide a seat and seal for future tie back liners or casings (Fig. 12.9).
e. Liner Packers and Liner Hanger-Packers: Liner packers are separate tools that screw on
top of the liner hanger. ‘They are usually weight operated with special setting tools,
which operate the hanger at the same time. Liner packers can be set at any time after
the liner hanger has been set. A tie back sleeve can be placed on top of packer for future
extensions of the liner (Fig. 12.10).
Liner Hanger Packers: A tool which combine the functions of hanger and packer: Packing
elements could be either compressed in a separate operation or compressed at the time
the hanger is set. The later system is not used for cementing.
f. Setting Tools: These are used to run and cement liners. They usually have a left hand
threaded nut which engages coarse left-hand threads in the liner hanger, to support the
liner as it is run. A sealing system preventing upward flow through the tool during the
cementing operation. The liner wiper plug is attached to the setting tool by shear pins
126
Cementing Manual
sdfgghv bbnbnn
Types of Cementation
which shear after the pump-down plug has landed and pressure had been applied. This
allows displacement of the wiper plug down the liner (Fig. 12.11).
127
Cementing Manual
sdfgghv bbnbnn
Types of Cementation
128
Cementing Manual
sdfgghv bbnbnn
Types of Cementation
129
Cementing Manual
sdfgghv bbnbnn
Types of Cementation
130
Cementing Manual
sdfgghv bbnbnn
Types of Cementation
CEMENTING CEMENTING
STUBLINER TIE BACK CASING
131
Cementing Manual
sdfgghv bbnbnn
CHAPTER 13
Secondary Cementation
13.1 Description
Cement plugs placement objective is to get a stable gas, water & oil impermeable cement
column of cement stone having sufficient strength at desired depth. Cement plugs are
placed in cased as well as in open holes.
Placement of cement plugs has many things in common with casing cementation but at the
same time it has its own peculiar features. Volume of cement slurry used is less, there is no
shoe, float collar, plugs etc. Plug has nothing to hold it from under and it may be pushed
downwards under the action of difference in sp. gr. of mud and cement slurry.
Plug job is supposed to be technically more complicated as compared to normal cementing
operation. It is more difficult in deep wells with high temperatures and pressures. Executors
of the job should take into consideration geological, technical and other subjective factors.
The experience of cement plug jobs has shown that in deep wells accidents and
complications do occur.
(a) Due to poor organisation of the job,
(b) Poor preparation of well bore,
(c) Poor conditioning of mud,
(d) Wrong treatment of cement slurry,
(e) Mistake in calculation of chemicals,
(f) Volume of displacement fluid.
Most common complication during placement of plug is stuck up of tubing as a result of
premature setting or thickening of cement slurry.
Cement plug should be placed only after thorough preparation of well bore i.e. bottom of
the well should be continuously flushed for 2-3 hours and till drilling fluid has normal
parameters. On the basis of existing loads, cement plugs are divided into two categories·
(a) For testing pressure of fluid or gas.
(b) For testing load of the string during side tracking and use of DST etc. Cement plugs
placed in this category should have high compressive strength.
In most of the cases cement plugs are placed with pressure balance in annulus as well as in
pipes. For this sp. Gr. Of mud and displacement fluid should be the same. In order to have
uniform mud, well is circulated till mud parameters becomes uniform after reaching bottom
at desired depth. In this case cement slurry placed at desired depth should be balanced in
annulus and pipes.
Squeeze cementing is carried out for pumping cement into formation under pressure.
Cement slurry is squeezed through damaged threaded joints or through perforations in the
casing for repair or for shut off water. After determining the interval to be repaired, casing is
perforated (if it is required) and cement is squeezed through these perforations after
lowering drill pipe 2-4 m above (some times below) these perforations while doing so, well
132
Cementing Manual
sdfgghv bbnbnn
Secondary Cementation
1. Circulate and condition well fluid at maximum possible rate for wellbore cleaning,
homogeneity (and lowering of wellbore temperature to circulating temperature in HPHT
wells).
2. Check for wellbore stability and note down the hook load. If found unstable, circulate the
well with suitable well fluid parameter.
3. Use 5" drill pipe with diverter tool (Fig No-13.1)
In hole size of 12- ¼” and larger
In 9-5/8" casing or larger
4. Avoid diverter tool if pressure limitation is expected during reverse circulation after cement
placement which may induce loss in the well.
5. To avoid stuck up of pipe due to cement on the lower side in an inclined hole, plan direct
circulation and the string must be in continuous reciprocation and rotation.
6. In case of smaller size hole/casing, use combination
string (preferably with 3 ½” or 2 7/8" drill pipe) with
tail pipe of 2 7/8" tubing. Minimum length of tail pipe
should be more than the intended length of cement
plug and spacer/pre-flush together to be placed.
7. Avoid using tubing string for squeeze jobs in deep
wells.
8. Plan longer cement column for highly deviated hole.
9. Calculate the height of cement column with drill
Fig No-13.1: Diverter Tool pipe/tubing inside cement slurry and displacement
volume accordingly.
10. Length of cement plug preferably be kept at minimum particularly in slim holes with narrow
annulus clearance.
133
Cementing Manual
sdfgghv bbnbnn
Secondary Cementation
11. For displacement of cement slurry, use cementing unit for accurate volumetric
displacement.
12. Underbalance the plug by 300 to 500 liter volume according to the size of the casing, if
substantial difference is there between mud and cement slurry SG.
13. Keep lines/valves/ change over connections ready before start of cementation to facilitate
immediate reverse circulation after plug placement & pulling out without loss of any time.
14. For large/deviated hole, rotate the string (during cement pumping and displacement) to
increase the chances of cement plug success. String should be kept in rotation while pulling
out also. Carry out safety pullout immediately after reverse wash. Option of direct wash
may be considered in highly deviated wells if rotation is possible.
15. Monitor hook load continuously throughout cementing operations including pulling out of
string for reverse wash. In case of increase in hook load, pull out fast to safe position and
immediately carry out direct wash at full SPM to avoid any complication.
16. Pulling out speed should not be more than 10-15 m/minute while string is in cement and
thereafter at high speed. In normal case, after pulling out minimum 100m above plug top,
carry out reverse wash
17. It is good practice to pull out in stands; break stand from working joint while pull out.
18. In all the cases of direct or reverse circulation, slurry thickening time should consider job
time, wash time and with contingency.
19. After carrying out the reverse wash / squeeze operation, ensure the opening of BOP
through physical inspection.
20. In case of problem in closing pipe ram for reverse circulation (after cement placement and
pulling out), resort to direct circulation with reciprocation to flush out residual cement to
avoid any complication.
21. In case of any problem in pulling out from bottom after cement placement, attempt to
rotate the string.
22. Keep cementing unit in readiness after cement pumping and also for any pressure
application required in case circulation could not be established after pulling out. In case,
pressure shoots up during initiation/process of reversing out, apply pressure through drill
string by cementing unit up to the safe limit of the minimum rating of running string
components or fracture limit of formation in case of open hole.
23. In case cement plug is required to be repeated, ensure that previous cement cuttings are
cleared and flushed out of hole properly (if required, use viscous sweep). Otherwise large
chunk of cement cuttings are likely to block drill pipe/annulus during reverse/direct wash,
resulting in well complication.
24. In very deep wells with high mud weight to increase the chances of successful placement of
cement plug, mechanical separation inside the string may be done using sponge ball to
avoid the contamination and cement plug failure.
To avoid the chances of stuck up of pipe with cement during cement plug placement in very
deep wells with high mud weight, fiber tubing may be used @ two times the cement plug
134
Cementing Manual
sdfgghv bbnbnn
Secondary Cementation
length. This will help in case of a stuck situation to snap the fiber tubing from metal tubing
/drill pipe and thereby saving the well as fiber tubing can be drilled out later.
25. In case of a secondary job in a well with brine solution which is likely to accelerate the
cement setting time, sufficient care should be taken to avoid flash setting of cement.
Sufficient amount of pre-flush and after flush in proportion (minimum 100m ) to be pumped
ahead and behind slurry to avoid contamination. If brine weight in the well is more than
1.09 SG (9 ppg), it may be replaced with mud.
26. In loss condition, cementitious material viz. RSF pill/cement slurry may be placed. The
specific gravity, thickening time, thixotropic property and volume of RSF pill/cement slurry is
based on the severity of the loss.
27. Always wash the string in loss condition also. If well condition does not permit wash at
deeper depth, pull out to shallower depth and wash the string/ annulus. In case of total
loss/ severe loss, wash volume to be monitored.
28. Thixotropic cement may be used in case loss cannot be brought under control using
conventional cement.
29. All precautions to be taken during tagging and drilling of cement
Never attempt to tag cement with open end drill pipe/ tubing.
Go slowly with bit (preferably without nozzles) rotation and mud circulation below the
depth of reverse/ direct wash. Monitor the torque & pressure. Also, lift the string
intermittently.
135
Cementing Manual
sdfgghv bbnbnn
Secondary Cementation
136
Cementing Manual
sdfgghv bbnbnn
Secondary Cementation
10. The simplest way to carry out a squeeze is to place a balanced plug and squeeze it by
applying pressure with the annulus closed. However, a packer must be used if the pressure
during the squeeze will exceed the maximum allowable pressure at any point above the
planned depth of the cementation.
11. In vertical wells minimum 25 m plug above the perforation should be there after squeeze, in
case of horizontal wells it should be 50 m.
Preparations
In deviated wells with less than 30° hole angle, a viscous pill of approximately 100m
length can be used as a bottom support for the cement plug.
If there are any perforations below that need to be protected from the squeeze
pressure and/or cement that might work its way down the hole, a drillable bridge plug
must be set above the perforation, approximately 7m below the interval to be squeezed.
13.5 Block cementation using a Cement Retainer
The following procedure should be adhered to when preparing for block cementation
(Circulation squeeze using a cement retainer):
i. Set a drillable cement retainer above lower most perforations to be squeezed.
ii. Before stab-in, circulate and run-in slowly into the retainer and establish hermeticity of the
string.
iii. Now, release the weight and attempt to establish circulation behind the casing, with
pressure less than fracture pressure of the formation.
iv. Use pre-flush and after flush before and after cement slurry.
v. Displace the batch-mixed cement until the first spacer reaches the end of the stinger.
vi. Stab in stinger into cement retainer immediately.
vii. Squeeze maximum 70% of the cement slurry.
viii. Pull out drill pipe from cement retainer approximately 15m. above the upper perforations
ix. Reverse wash the string.
x. POOH
xi. Block cementation is not recommended in case mud weights is more than 1.8 gm/cc.
13.6 Well Abandonment Procedure
Well abandoning procedure is recommended to prevent pressure build up or cross flow in the
well and its surroundings in future. Abandonment shall also prevent contamination of fresh
137
Cementing Manual
sdfgghv bbnbnn
Secondary Cementation
water aquifers and leakage of any well bore fluid to the surface.
There are two types of abandonment
Temporary well abandonment
Permanent well abandonment
Tag the cement plug, load test with 8 MT of weight and pressure test with 1,000 psi
wherever possible.
The bore hole including the space between the cement plugs shall be filled with
drilling fluid of sufficient specific gravity and other properties so as to enable it to
withstand any subsequent pressure which may develop in the bore hole.
138
Cementing Manual
sdfgghv bbnbnn
Secondary Cementation
139
Cementing Manual
sdfgghv bbnbnn
Secondary Cementation
Open 9⅝’’ x 7’’/ 5½’’ and 13⅜ x9⅝’’ annuli valve one by one & try to establish
circulation individually with required mud (within LOT value).
Place a balanced cement plug of calculated volume and try to raise minimum 30 m
cement slurry in annulus one by one by operating annulus valves and closing BOP
such that 30m plug remains inside casing above perforation. Pump/Squeeze slurry
up to 1,000psi/ within LOT value.
If circulation does not establish, in addition to squeeze against perforation, outer
most annulus to be top filled with cement slurry through tubing after removal of
Well Head.
In case of 4 casing policy (18⅝’’/ 20’’ surface casing), perforation to be done 20 – 30
m above 18⅝’’/ 20’’ shoe depth assuming that there is no hydrocarbon show above
20’’ casing shoe.
After removing all well heads a plate (Minimum thickness of 10 mm) to be welded
on the outermost casing with vent line and provision for pressure gauge.
If casings are retrieved, place a progressive surface plug of 60 m height covering all
the annulus and inner most casing stub.
II. For Offshore Wells with Surface BOP:
Check 20’’ x 13⅜’’ annulus and 13⅜’’ x 9⅝’’ annulus for any activity. Fill both annuli
with suitable mud.
Perforate 9⅝’’ and 13⅜’’ casings 25m above 20’’ shoe (13⅜’’ or 9⅝’’ shoe in case of
3 casing/ 2 casing policy respectively) position with 8 shots per foot. Open
13⅜”x9⅝” and 20’’X13⅜’’ annuli valve one by one & try to establish circulation
individually with required mud (within LOT value).
Place a balanced cement plug of calculated volume and try to raise minimum 30 m
cement slurry in both annuli one by one by closing BOP and operating annulus
valves such that 30m plug remains inside casing above perforation.
Squeeze slurry up to 1,000psi/ LOT value.
III. For Offshore Wells with Sub-surface BOP:
Place a cement plug of 100 m length such that top of cement plug is at about 100m
below well head.
d. Surface abandonment plug for offshore:
I. With surface BOP:
If MLS (Mudline suspension) is used and it covers all the casings, retrieve all casings
from MLS. However if there is any pressure in any of the annulus (20’’X13⅜’’ & 13⅜’’ X
9⅝’’), it needs to be subdued. After well is subdued and casing is retrieved from MLS,
Place Corrosion/ (T/A) Cap which covers all the annulus and inner casing stub.
If MLS is not used, check for any annulus activity. Subdue the well if any activity is
observed. Cut 9⅝’’ casing from 15m, 13⅜’’ casing from 10m and 20’’ casing from 5m
below sea bed. Cut and retrieve all the casings and place a progressive surface plug of
60 m height covering all the annulus and inner most casing stub. After cement plug
placement, wash down the cement up to 2m to 3m below sea bed. Cut and retrieve
back 30’’ casing at 2m below sea bed.
II. With Sub-surface BOP:
When well head is not retrieved and annuli are sealed by energization, no surface
140
Cementing Manual
sdfgghv bbnbnn
Secondary Cementation
141
Cementing Manual
sdfgghv bbnbnn
Secondary Cementation
Results:
142
Cementing Manual
sdfgghv bbnbnn
Secondary Cementation
UCA chart:
143
Cementing Manual
sdfgghv bbnbnn
Secondary Cementation
Results:
Note: Supported formation should be selected as KOP for side track and cement plug should be
planned accordingly.
144
Cementing Manual
sdfgghv bbnbnn
CHAPTER 14
If cement column during its setting exerts a pressure equal to density of mix water, then most
effective method to reduce the potential gas flow is to minimise the Cement column. Thus the
height of cement column should be reduced to compensate the loss of hydrostatic head during
setting by increasing adequately the column of drilling fluid or allternatively increasing its
weight.
The other possible technique is to use cement slurry with varying thickening time, so that API
thickening time difference is two hours between initial set of tail and lead slurry slurry at the
bottom sets before slurry at the top.
The potential for annular gas can be reduced by applying a surface pressure on the cement
annulus after cement placement. The imposed pressure accounts for the loss in cement
hydrostatic head that occurs as the slurry thickens. This technique requires that cement used for
cementing should develop strength soon after its initial set. In this method BOP should be closed
immediately after cement placement and pressure is applied on the cemented annulus during
the time the cement attains its initial set considering fracture of weakest formation.
Static Gel Strength (SGS) development is one of many factors that contribute to decay of
hydrostatic pressure. As gelled fluid interacts with the casing and the borehole wall it loses its
ability to transmit hydrostatic pressure. It also contributes to the ability of slurries to suspend
145
Cementing Manual
sdfgghv bbnbnn
solids under static conditions. Experimental data has shown that gas cannot freely percolate
through cement that has a SGS ranging from 250 to 500 lbf/100ft 2 or more. The industry has
conservatively adopted the upper end of the range as the accepted limit. It is considered that
hydrostatic head start to reduce when SGS reaches critical gel strength (generally considered as
100 lbf/100ft2). So the time period for SGS to reach from 100 lbf/100ft2 to 500 lbf/100ft2 should
be less than 45 minutes (API STD 65-2).
The multiple stage cementing technique has been applied successfully in preventing annular gas
migration by selective cementation of casing in place. Each cement column is allowed to set
prior to placing a subsequent stage.
Most recent development is compressible cement system which is designed to maintain a fluid
gradient near its original density during its initial hydration. These cements are formulated to
contain minute gas bubbles, which make new cement system compressible so that new bubbles
expand to maintain a near constant bottom hole pressure, thus providing an adequate
hydrostatic overbalance. In addition, the presence of gas bubbles make the cement column to
transmit pressure throughout its length, which may get interspersed due to differential setting
of cement, because of difference in temperature and permeability of formation, cement
additives has been developed to prevent annular gas leakage.
External Casing Packer (ECP) can also be used to contain activity from uncemented zones below.
Sustained Casing Pressure (SCP) is defined as any measurable annular pressure at the casing
head that rebuilds to essentially the original annular pressure after being bled down and is
attributable to cause (s) other than;
(a) An artificially applied annular pressure (i.e. gas lift) which remains isolated from other
annuli. Or
(b) Temperature fluctuation in the well (Thermal pressure)
The principle concern for wells that exhibit a sustained casing pressure is that a down-hole
situation is developing or has developed that can result in an underground blowout. Wells are
designed so that the innermost casings are the strongest. Only the production casing is designed
to withstand the pressure of the deepest producing formation. Thus production casing provides
a redundant barrier to a blowout in the event of a failure of the production tubing. This
redundant protection allows the tubing to be safely repaired. However, if a tubing leak develops
and pressure is allowed on the production casing, there is no longer a redundant barrier
present. If the production casing fails, the next outer casing string is generally not designed to
withstand formation pressure. In such a situation, blowouts of sufficient flow rate to jeopardize
the production platform becomes a possibility. The magnitude of the leak rate is as important as
the magnitude of the pressure when determining the potential hazard posed by sustained
casing pressure. API has issued following standards related to SCP management;
1. API RP 90: Annular casing pressure management for offshore wells
2. API RP 90-2: Annular casing pressure management for onshore wells
3. API STD 65-2: Isolating Potential Flow Zones During Well Construction
146
Cementing Manual
sdfgghv bbnbnn
This problem has also taken its toll on Oil and Gas Industry in the world as well as in India. There
are more than 8000 wells with this problem in Gulf of Mexico. In Indian offshore, out of more
than 100 SCP wells, following four cases are reported;
Case 1:
B-121 Blowout occurred leading to fire and the whole platform melted. Relief well was drilled to
control the blowout.
Case2
Sinking of wells of HC platform. All the wells are planned to be liquidated.
Case 3
NSBX: Severe gas leakage through holes of 20” & 30” casing, controlled with ingenious method
of clamping holes and circulating through 13 3/8” casing perforation up to 13 3/8”*20” annulus.
Case 4
BE-10H: 20” casing parted and the original well had to be abandoned and a new location was
drilled through the slot.
In ONGC, a Kick off meeting of SCP Committee was carried out on 23/01/2015 in Mumbai
offshore. Based on data received for 1671 wells, it was found that 104 wells were Critical wells
based on SCP Categorization criteria followed in ONGC which in turn is as per Inspection &
Reporting Requirements (IRR) for Wells and Well Platforms, November 2001. Out of those 104
SCP critical wells, Water Injection wells (51 nos) constitutes 49 % of inventory , followed by Gas
lift wells (27 nos) which constitutes 26 % , 17.3 % by Self flow oil wells(18 nos) and 6.7 % and
0.9% by Gas producer (7 nos) and ESP (1) wells respectively.
147
Cementing Manual
sdfgghv bbnbnn
148
Cementing Manual
sdfgghv bbnbnn
3. Use of stinger i.e. inner string to cement 20" casing as it will avoid contamination of
slurry during pumping and displacement which will provide good cement rise up to
surface is guaranteed. Experienced supervisor from Drilling services has to be present at
the time of stinger job for successful implementation.
4. Wherever applicable, ECP should be set in annulus to stop gas migration. Potential gas
zones and potential flow zones should be clearly demarcated and depth of ECP to be
decided accordingly. In all such cases where ECP use are recommended, caliper log
should be taken to decide on setting depth of ECP.
5. Cement slurry properties of 9⅝" casing may be modified to achieve long term integrity.
Enhancement of mechanical properties can be achieved with the help of special
additives which can prevent development of
cracks when subjected to cyclic stress during
testing and stimulation jobs where high
pressure is involve.
6. Using sea water as displacement fluid during
displacement of cement slurry in 9⅝" casing
may be explored which can prevent de-bonding
between cement and casing and formation of
micro annulus when well is tested with lighter
brine.
7. Proper care to be taken to plan centralizer
spacing as per software and use of non-weld
centralizers in all production casing and liner
job must be ensured so as to achieve at least
70% standoff. Non weld centralizer has ability
to reduce friction and do not break during
running- in of casing.
8. Care should be taken to improve mud
displacement while dealing with SOBM mud.
Design of sacrificial mud and volume of mud
cleaner should be designed properly to obtain Fig 14.1: Cement rise upto surface
water wetting of formation and casing. Proper in outer most casing
surfactants have to be used for cleaning the oil film.
9. Cement Bond evaluation logs must be recorded and analyzed in detail to exactly know
actual cementation job performed on the rigs along with data of mud circulation, time
logs, and mud loss data during actual cementation job. Post analysis of each job must be
done to predict cause of failure and lessons learnt to improve further in future. True
reporting of mud loss is also vital in maintaining a comprehensive data record.
10. In all marginal / new fields, CBL has to be carried out for production, intermediate and
surface casings to confirm that cement rise takes place as per plan to targeted depth
and good quality bond is intact.
149
Cementing Manual
sdfgghv bbnbnn
CHAPTER 15
Cementing Calculations
15.0 General
1. Calculations for cementing operations are made to determine the following:
(a) Quantity of materials required for successful cementation.
(b) Operation lime.
(c) Type and number of cementing equipment.
2. Type of cementing material is usually selected on the basis of following factors: Formation
pressure anomaly, bottom hole temperature, mud weight, saturation of formation fluid in
the section of well bore and rock constituents.
3. Selected cementing materials should ensure SG of cement slurry, for creating required
hydrostatic head along with mud and buffer, which should not exceed 85-90% of hydro-
fracturing pressure of the interval to be cemented.
4. While designing cement slurry, following parameters should be determined: rheology, SG,
thickening time, and compressive strength of cement stone at the bottom hole
temperature and pressure conditions.
5. Annular volume should be found out from the caliper log. More accurate and complete
information about cavings, tight section of well bore and key seals is to be considered.
Bulk density: Mass of many particles of the material divided by the total volume they
occupy. The total volume includes particle volume, inter-particle void volume, and internal
pore volume. E.g. bulk density of OWC is 1505.47 kg/m3. More commonly used term
“sack” means 94 lbs, which is the mass 1 ft3 of OWC, as per bulk density.
150
Cementing Manual
sdfgghv bbnbnn
Cementing Calculations
Absolute density: Mass of many particles of the material divided by the total volume they
occupy. The total volume includes particle volume only and exclude inter-particle void
volume and internal pore volume. E.g. absolute density of Class G OWC is 3140 kg/m3.
Specific Gravity: Density relative to water. E.g. SG of OWC is 3.14 {density of OWC (3140
kg/m3) divided by density of water (1000 kg/m3)}.
Example:
Rqrd for 1MT Volume rqrd for 1MT
Material SG % BWOC
OWC (kg) OWC (m3)
OWC 3.14 100 1000 0.318471338
Water 1 46 460 0.46
Haematite 4.95 16 160 0.032323232
DO60 1.1 0.8 8 0.007272727
DO65 1.43 0.1 1 0.000699301
D121 1.38 0.1 1 0.000724638
DO47 1 0.1 1 0.001
Total 1631 kg 0.820491236 m3
151
Cementing Manual
sdfgghv bbnbnn
Cementing Calculations
Example:
Rqrd for 1MT Volume rqrd for 1MT
Material SG % BWOC
OWC (kg) OWC (m3)
OWC 3.14 100 1000 0.318471338
Water 1 46 460 0.46
Haematite 4.95 16 160 0.032323232
DO60 1.1 0.8 8 0.007272727
DO65 1.43 0.1 1 0.000699301
D121 1.38 0.1 1 0.000724638
DO47 1 0.1 1 0.001
Total 1631 kg 0.820491236 m3
152
Cementing Manual
sdfgghv bbnbnn
Cementing Calculations
Example 1:
Following are the well parameters:
Drilled Depth 3514m
Casing Shoe Depth 3510m
Float Collar Depth 3486m
Casing 5 ½”, 20 PPF, P-110 (ID=4.778”)
100% OWC + 46% Water + 16% Haematite + 0.8% DO60
Slurry Design
+ 0.1% DO65 + 0.1% D121 + 0.1% DO47
(Always use caliper log for volume calculation. If not available, use prior experience in that
particular field.)
Casing Size = 5.5“, Ann Vol Capacity = (IDh2 – ODc2)/1973.52 m3/m, Dh & Dc are in inch
20 PPF
Depth Hole Dia
Volume
Length (m) (inch) from Ann Vol Cap (m3/m)
From (m) To (m) (m3)
caliper
a b c = b-a d e = (Dh2 – ODc2)/1973.52 f = e X c
2730-2725 = (From log) = (9.52 – 5.52)/1973.52
2910 3120 6.38
210 9.5 = 0.03040
3120 3225 105 9 0.02571 2.7
3225 3383 158 8.75 0.02322 3.67
3383 3510 127 10.75 0.043228 5.49
Total slurry volume 18.24
153
Cementing Manual
sdfgghv bbnbnn
Cementing Calculations
3. Mix water:
As per slurry design, water to be used is 46% BWOC.
Hence, water required for 22.58 MT OWC = 46% of 22.58 MT = 10.38 MT = 10.38 m3
Haematite 16 3613
DO60 0.8 181
DO65 0.1 22.58
D121 0.1 22.58
DO47 0.1 22.58
5. Displacement:
Float collar depth = 3486m
Displacement = Float collar depth X Vol capacity of casing
= 3486m X = ltr/m = 40.33 m3
154
Cementing Manual
sdfgghv bbnbnn
Cementing Calculations
Example 2:
Drilled Depth 1545m
Casing shoe depth 1540m
Float collar depth 1516m
Casing 13 ⅜”, 68 PPF, N-80 (ID =12.415”)
Slurry design Lead Slurry: 100% OWC + 70% Water + 2% Bentonite
Tail Slurry : 100% OWC + 44% Water + 0.3% CFD + 0.1%
DO47
Avg hole dia 18”
Annulus rise 600m (400m lead slurry + 200m tail slurry)
MW 1.20
Volume of slurry required for 400m rise (Lead slurry) in annulus = 73.48 l/m X 400m = 29.4 m3
Volume of slurry required for 200m rise (tail slurry) in annulus = 73.48 l/m X 200m = 14.7 m3
Volume of slurry required for shoe track = Vol. capacity of casing X shoe track length
Dry OWC required for lead slurry (29.4 m3) = 29.4m3/1.026m3 per MT = 28.65MT
Yield of tail slurry = Summation of volume of all constituents required for 1 MT of OWC
= Vol of 1MT OWC + Vol of 440 kg water + Vol of 3 kg CFD + Vol of 1kg DO47
= = 0.77 m3 per MT OWC
Dry OWC required for tail slurry (16.57m3) = 16.57m3/0.77m3 per MT = 21.52MT
Total dry OWC requirement = 28.65MT + 21.52MT = 50.17MT
155
Cementing Manual
sdfgghv bbnbnn
Cementing Calculations
3. Mix water:
As per slurry design, water to be used is 70% BWOC for lead and 44% for tail slurry.
Hence, water required for lead slurry (28.65MT) = 70% of 28.65 MT = 20MT = 20 m3
water required for tail slurry (21.52MT) = 44% of 21.52 MT = 9.5MT = 9.5 m3
4. Quantity of cement additives:
Material % BWOC Requirement (kg)
5. Displacement:
Float collar depth = 1516m
Displacement = Float collar depth X Vol capacity of casing
= 1516m X = ltr/m = 118.4 m3
6. Pump pressure to land plug
SG of lead slurry = 1.65
SG of tail slurry = 1.90
Differential pressure after final placement
= Annular hydrostatic head - Casing hyd. Head
={ }-{ }
= 30.32 kg/cm2 = 431 psi
156
Cementing Manual
sdfgghv bbnbnn
Cementing Calculations
Example 3:
Placing a 100m cement plug 50m in open hole and 50m in casing
Hole dia 9.25”
Casing ID 8.681” (9 ⅝”, 47PPF)
OETP 2550m.
Preflush and afterflush 50m length each
String inside the casing 5” Drill pipe, 19.5 PPF (ID=4.276”)
Slurry design to be used 100% OWC+ 44% water + 16% Haematite +
0.8% DO60 + 0.1% DO65 + 0.1% D121 + 0.1%
DO47
157
Cementing Manual
sdfgghv bbnbnn
Cementing Calculations
Where,
AOD = cross-sectional area (in2) of casing outside diameter
mcsg = casing weight (lbm)
mfluid = weight of fluid inside casing (lbm)
(ph)ann = hydrostatic pressure of annular fluid(s) (lbf/in2).
Where,
AID = cross-sectional area (in2) of casing inside diameter
(ph)csg = hydrostatic pressure of fluid(s) in casing (lbf/in2).
Fig No. 15.1: Diagram for
pressure to lift Casing
When pumping, the pump pressure (pp) acting on the inner-diameter cross-sectional area (AID)
must be added to the above equation.
Where,
PBH = effective pressure at the bottom of the hole; PBH = (ph)csg + Pp.
If ⃤ F is positive, the casing may come out of the well. Working this problem backward, the
value of pp that gives a ⃤ F value of zero is the critical pump pressure above which the casing
may be pumped from the well.
The service crew should ensure that the pump pressure during the treatment never exceeds this
value unless the casing is restrained.
158
Cementing Manual
sdfgghv bbnbnn
Cementing Calculations
Ppmax =
Example:
Consider a 13 ⅜”, 61 ppf casing set at 244 m with 1.77 SG cement and 1 SG water for
displacement. Is there danger of the casing coming out of the well? Consider 25m cement is left
in the casing.
Under static conditions:
= [( PSI) X ( ] + [{ –
}X( )] – (244 X 3.28 X 61)
= -9682.85 lbf
The negative force indicates that there is not enough buoyancy to float the casing under static
conditions. The pump pressure at the end of displacement is
Pp = = 239.8 PSI
This pump pressure balances the hydrostatic-pressure difference between the fluid in the
annulus and the fluid in the casing. Maximum allowable pump pressure to avoid lifting the
casing from the well:
Pp,max =
Therefore, for this casing, the pump pressure must be maintained below 308.63 PSI, or other
precautions should be taken to avoid having the casing come out of the well.
159
Cementing Manual
sdfgghv bbnbnn
CHAPTER 16
Cement Evaluation
Cementation of a well is a very important aspect of completion, which determines the
productivity of the well. A good primary cementation should ensure a long and trouble free
economic life of a well. It ensures effective zonal isolation and trouble free production, prevents
loss of expensive rig-time on secondary repair jobs and avoids annular leakage problems.
Once primary-cementation is over, bond-logging and perforation must be considered. The
purpose of this chapter is to discuss the methods of locating cement behind the casing. This
involves the evaluation of quality of cement placed behind the casing, which in other words
determines the quality of bond of cement to casing and formation.
The main objectives are to highlight the following points:
The length of annular cement column.
The quality of bond of cement to casing and formation.
Effective seals between different producing horizons.
160
Cementing Manual
sdfgghv bbnbnn
Cement Evaluation
Fig No-16.1: Temperature rise showing TOC Fig No-16.2: Radioactive tracer distinguishes
the top of cement
With this method the top of cement can be accurately determined when initial portion of
cement slurry is rendered radioactive. Fig. l6.2 illustrates how a radioactive tracer survey
(gamma-ray Iog) distinguishes the top of good cement.
The tracer is added as a soluble salt to the mixing water and it is thoroughly mixed with the
slurry. Adding a radioactive tracer to the upper most portion of the cement slurry is a good
insurance in case if too much time lapses alter cement is placed for a temperature survey to be
accurate. It is not necessary to be so prompt with a tracer survey and with a long halflife of
tracer, the survey can be conducted at any time in the life time of tracer. The main advantage of
the radioactive tracer method is that it positively and accurately determines the location of
tracer. Its main disadvantages are:
i. Its use requires observance of health precautionary measures.
ii. It is more expensive.
iii. Conducting a base survey of natural gamma radiation is essential.
161
Cementing Manual
sdfgghv bbnbnn
Cement Evaluation
For convenience, cement evaluation tools are often classified according to the frequency of the
sound waves they employ: sonic (low frequency) and ultrasonic (high frequency). CBL-VDL, CBT,
SBT, SBL are examples of sonic and USIT, CAST-V, URS, Isolation Scanner are examples of
ultrasonic logs developed by different manufacturers.
a) CBL-VDL:
Generally in a sonic logging tool, there is a transmitter and two receivers located 3ft and
5ft from the transmitter.
The CBL tool emits an acoustic-energy pulse that travels in all directions through the
borehole fluid as an expanding spherical wave of sound. When the sound pulse strikes
the inner casing surface, some of it is refracted according to Snell’s law. Calculations
show that the wave front striking the casing at an angle of approximately 17° will refract
parallel to the casing wall (see Figure 16.3). The passage of the wave pulse through the
casing wall acts as an intermittent pressure pulse, causing the steel of the casing wall to
cycle through compression and tension. Cycling the steel through compression and
tension causes the casing to ring, creating sonic waves that travel through the casing
fluid and reach the logging-tool receiver. The pressure pulse loses energy as it travels
inside the casing wall. This loss of strength, or decay, is commonly referred to as sound
attenuation.
The sound travels through
the casing and borehole fluid
to two receivers that are 3 ft
apart (amplitude and travel
time measurement) and 5 ft
apart (full waveform
measurement).
At the 3-ft receiver, the first
arrival amplitude (known as
E1 or E2), or the attenuation
rate of the received signal, is
related to the cement’s
acoustic properties and the
casing wall thickness (see
Figure 16.4), as long as the
cement is set (capable of
transmitting shear waves)
and acoustically coupled to
Fig No. 16.3: Schematic of Cement Bond Logging Tool the casing.
Cement compressive strength
can be derived from casing-size, casing-thickness, amplitude or attenuation data. Inputs
of casing size, casing thickness, and cement compressive strength will result in
162
Cementing Manual
sdfgghv bbnbnn
Cement Evaluation
predicting the tool amplitude or downhole attenuation measurement. Each type of tool
has similar but unique charts (consult each service company).
163
Cementing Manual
sdfgghv bbnbnn
Cement Evaluation
Fig No.16.6: Un-cemented Casing (Left) and fully Cemented Casing (Right)
164
Cementing Manual
sdfgghv bbnbnn
Cement Evaluation
microannulus at the casing-cement interface, gas-cut or foamed cement, mud, water, gas or
sloughed formation particles. Good acoustic coupling of the cement to the casing and the
formation is required for signal transmission through all of the conductors. The E1 curve of the
free casing waveform should appear on the display between 300 microseconds (μs) to 400
microseconds (μs) when the signal is received at the 5-ft receiver (the travel time of sound
through steel is 57 μs/ft).
The presentation of the composite waveform on the log may be in the form of a “total energy
wave” (signature plot, X-Y plot, etc.) or a linear form commonly called a VDL (variable density
log) or microseismogram. The presentation is scaled from 200 to 1200 μs. A total energy
waveform would be very messy, and no details could be observed. Linear presentation makes it
much easier to separate casing signals from formation signals. Casing signals will always be
straight unless the logging tool is eccentered, and casing collars will be evident. Formation
signals usually vary and are rarely straight. The presentation will mimic an open hole sonic DT
(Sonic DT is the duration of time sound travels through a given distance in the formation,
typically measured in μs/ft.).
Track no-03:
Cement bond log (CBL) is represented by a continuous line curve in mV. Scale for track 3 may be
from 0 to 100 mV or 0 to 50 mV sometimes in combination with 0 to 10mV dotted line curve for
amplified scale purpose. CBL denotes cement bond with steel casing and its signal is received at
3ft receiver (Generally) in logging tool sonde.
165
Cementing Manual
sdfgghv bbnbnn
Cement Evaluation
Track no. 4:
It is the presentation of full waveform received at 5’ receiver is in VDL (Variable Density Log)
form in black and white strips. Positive amplitudes become blacker as they increase. Negative
amplitudes become whiter as they decrease. In case of good cement bond with casing as well as
formation, formation arrival will make zig-zag wavy black and white pattern.
Table no.16.1 shows slowness (Δt) of acoustic waves in different medium. The waveform
received is affected by the quality of the cement’s acoustic coupling to the formation and casing,
the shear strength of the cement, the thickness of the cement sheath, thickness of the casing
wall, formation density and compressive strength.
Presentation of full waveform received at 5’ receiver is in VDL (Variable Density Log) form in
black and white strips. Positive amplitudes become blacker as they increase. Negative
amplitudes become whiter as they decrease. In case of good cement bond with casing as well as
formation, formation arrival will make zig-zag wavy black and white pattern.
166
Cementing Manual
sdfgghv bbnbnn
Cement Evaluation
Bond Index:
The free-pipe amplitude value is entered at 0% Bond Index. The 100% cemented amplitude is
entered at 100% Bond Index. For example, the free-pipe amplitude is 70 mV and the 100%
cemented amplitude is 0.2 mV (read from and area of the log with the lowest amplitude-Fig
16.8). Therefore, an 80% Bond Index would have an amplitude of about 0.6 mV. Percent Bond
Index is determined by drawing a line across from an amplitude found on the log to the diagonal
line and reading down to the “Bond Index.”
167
Cementing Manual
sdfgghv bbnbnn
Cement Evaluation
Fig No.16.9: Tool Eccentric (Left) and Cause of Cycle Skip & Cycle Stretch (Right)
168
Cementing Manual
sdfgghv bbnbnn
Cement Evaluation
the leading edge of E1 increases, which also increases the TT. This increase in TT is called “cycle
stretch.” When the E1 amplitude falls below the gate detection level, the measurement detects
the next available curve— the leading edge of the E3 curve. This causes the TT curve to “skip” to
a much greater value. Cycle stretch and cycle skip infer very high-shear-strength cement in
contact with medium- to thin-wall casing. Cycle stretch and cycle skip are generally an indicator
of good log quality over that section of the log.
A second method to discriminate between a channel and a microannulus involves beginning with
a zero-pressure pass, followed by pressuring up to 1000 psi and observing any changes in the
amplitude or attenuation and VDL. If no changes occur, increase the pressure in 500-psi
increments until amplitude or attenuation and VDL changes are observed. Typically, 2500 psi is
169
Cementing Manual
sdfgghv bbnbnn
Cement Evaluation
Where,
r is the casing radius, in.;
P is the pressure, psi;
E is Young’s Modulus of Elasticity for Steel (30 x 106 psi);
tw is the casing wall thickness, in.
The SBT tool employs high-frequency focused transducers mounted on six pads. Motorized arms
position each pad with a transmitter and receiver against the casing wall. The tool can be used
in casing sizes from 4.5 in. to 16 in., with any type or density of fluid in the casing. A full
170
Cementing Manual
sdfgghv bbnbnn
Cement Evaluation
waveform is produced from the 5-ft, omnidirectional transmitter-receiver module that is run in
conjunction with the pad section. As the transmitters are fired sequentially, amplitude
measurements are made on two consecutive and adjacent receivers. A transmitter on the fourth
adjacent pad is fired, and amplitudes at the same two receivers (in the opposite direction) are
measured (somewhat analogous to the CBT). Energy (amplitude) losses across the receivers are
averaged, producing a direct attenuation measurement over a short distance.
Fig No.16.11: Segmented Bond Tool (SBT) construction and Pad Arrangement
Thus, the measurements are compensated for transducer variations. Calibrations of matching
transmitter/receiver pairs are not required. Following acquisition of Segment 1, the remaining
Segments 2 to 6 are acquired, and the tool cycle begins again.
171
Cementing Manual
sdfgghv bbnbnn
Cement Evaluation
A cement map is a graphic interpretation that is subject to certain user inputs. The interpreter
must understand how the cement map was constructed and know whether reasonable inputs
were used in its construction. In the case of the SBT cement map, six regions across the map left
to right correspond to the values in each of the six individual attenuation measurements. Higher
attenuation rates (better cement) will appear as darker regions on the cement map. Normal
user input is automated, and based on inputs of casing size and weight as well as cement
172
Cementing Manual
sdfgghv bbnbnn
Cement Evaluation
compressive strength. The parameters are stated in the log header. For deviated wells, the RB
curve mentioned earlier can be used as an input to orient the low or high side of the hole to the
middle of the cement map. The purpose of this high-side/low-side option is to detect whether
cement anomalies correlate with the high or low side of the casing. The most useful feature of a
cement map is the detection of uncemented channels over significant intervals as opposed to
isolated voids. The SBT Interpretation Chart (see Figure 16.13) depicts the relationship between
casing wall thickness and cement compressive strength. The chart should be used as a guideline
when evaluating conventional cements (Class H, Class G, etc.) that are not mixed with volume
extending additives. When evaluating foamed cements or other cement systems containing low-
density additives (e.g. microspheres) or volume extending additives, the relationship between
cement compressive strength and cement acoustic impedance tends to be less reliable.
Fig No.16.13: SBT log Interpretation for Attenuation to Compressive Strength for
Classes G and H Cement
NOTE: Draw a horizontal line from the attenuation measurement on the y-axis, and a vertical line from the
casing-thickness on the x-axis. The point at which both lines intersect is the apparent cement compressive
strength.
173
Cementing Manual
sdfgghv bbnbnn
Cement Evaluation
casing wall. Excessive internal scale or residual cement may not permit effective
acoustic coupling. The two curves should be scaled 140 μs/ft to 40 μs/ft, and should
track each other within 4 μs/ft to 5 μs/ft, except across casing collars where greater
separation will be present. The two curves should center over the 57-μs/ft value, which
is the TT of steel casing. Finally, the DTMN and DTMX curves are excellent indicators of
instrument integrity. Should one of the transducers or related circuitry fail, its DTMN
and DTMX curves will depart significantly from the standard behavior of the other
transducers.
5. Scale the ATC1, ATC2, …ATC6 attenuation rates to 20–0 dB/ft.
6. On the SBT, scale the Attenuation Rate to 0–9 dB/ft and the Cement Map using the SBT
interpretation chart. The minimum coloration value should be equal to that of free pipe
on the chart (based on casing wall thickness) (see Figure 16.13).
7. The SBT can be run in any casing-fluid density, and in casing sizes up to and including 16
in. Larger sizes have been logged with special arm extenders; however, the log quality is
lower.
8. For perforation, in general, cement compressive strength of 2000 psi is considered to be
adequate. Hence, prior to recording actual log, SBT tool should be calibrated for 2000
psi cement compressive strength. However, for specific operation like hydro-fracturing,
requirement of cement compressive strength may vary and accordingly tool calibration
to be done by operator.
9. Generate a receiver-calibration and verification summary.
The basic principle of the CET tool is illustrated in Fig. 16.14. The tool consists of 8 ultrasonic
transducers arranged in a helical array over 2 feet. Each transducer in turn transmits a signal
incident on the casing wall and then receives its reverberant echo, measuring in a first lime
window the peak amplitude of the first reflection (W-1) and in a second time window of an
amplitude representative of signal decay (W-2).
174
Cementing Manual
sdfgghv bbnbnn
Cement Evaluation
The incident acoustic pulses cause the casing to resonate in its thickness mode and the decay
rate of the reverberant echo depends on the acoustic impedance of the cement in each sector
behind the casing.
The measured decay is calibrated in terms of acoustic impedance.
From these measurements, which are repeated for each of the 8 transducers, the maximum and
minimum values of apparent cement compressive strength are computed with an empirical
relationship and displayed on the CET log.
A 9th transducer in the Sonde is used to measure the transit time of the mud at down hole
conditions. This permits the conversion of 8 transit times into caliper measurements and 8
apparent radii are made available with a 45° separation. From these radius measurements
several different casing geometry parameters can be calculated. The CET calipers also measures
175
Cementing Manual
sdfgghv bbnbnn
Cement Evaluation
Although CET has several unique features but it has yet to find favor as a popular cement
evaluation tool like CBL -VDL which still remains the primary service tool for all cement
evaluation jobs throughout the petroleum industry. The main reasons due to which CET could
not get much success are:
Does not give any idea about the bond between cement and formation.
Cannot be used with heavy muds inside the casing which will absorb the CET signals.
Even a small air bubble inside the casing fluid will seriously affect the CET signal which
will give false indications of gas.
For proper cement evaluation the CET log cannot be used alone, it requires recording of
CBL-VDL as companion log.
Since CET log cannot be used alone it requires extra rig time for recording CBL-VDL and
involves extra expenditure.
176
Cementing Manual
sdfgghv bbnbnn
Cement Evaluation
177
Cementing Manual
sdfgghv bbnbnn
Cement Evaluation
NOTE: Acoustic impedance change with microannulus size, using a 4.7-in. diameter, 9-mm thick casing.
Copyright of the Society of Petroleum Engineers, reproduced with permission.
178
Cementing Manual
sdfgghv bbnbnn
Cement Evaluation
NOTE: Depending upon the microannulus size, there is an effect on both CBL and ultrasonic tools.
Copyright of the Society of Petroleum Engineers, reproduced with permission.
179
Cementing Manual
sdfgghv bbnbnn
ANNEXURE-I
CEMENT PROGRAM
Version 1.0
Revision Summary
Version Date Prepared/Revised By Reviewed by Summary of revisions (include section or page number)
#
V 1.0 07-11-2019 XYZ XYZ -20” SURFACE Casing Shoe @ 1150 M
-Lead TOC: SEA BED;
-Place 150 Mtr length Tail Slurry From Bottom -Leave
20 Mtr. shoe track inside casing.
Approval
Submitted by Digital Signature
XYZ XYZ
Reviewed and Approved by Digital Signature
XYZ XYZ
180
Cementing Manual
sdfgghv bbnbnn
To have top of cement at SEABED. Designed job with 120% and 150% of Lead and Tail slurry,
Red oxide iron is mixed with Drill Water to check the
returns on surface.
Potential Shallow Gas Migration Design 15.8ppg and 12.5ppg Tuned light Gas Tight Slurry
To mitigate shallow gas flow and risk of losses
Provide Casing Support and achieve 500PSI to Drill Ahead 17 ½ Designed 150 mtrs of 15.8 ppg tail slurry to Achieve good
OH. compressive strength.
• Flush the cement & Test lines with fresh water @5BPM to the rig floor after cement job
• Blow the air Through Bulk lines couple of hours prior to cement job to make sure all the lines are clear
of blockage.
• If Floats are not Holding Pump back return volume without exceeding 400 PSI.
• Don’t Mix and Dump Cement from Surge tank before Displacement
181
Cementing Manual
sdfgghv bbnbnn
WELLBORE GEOMETRY
FORMATION DATA WELLBORE SCHEMATIC
Pore Pressure: 9.0 PPG at TD
Fracture Gradient: 11.8 PPG at TD
WELL DATA
Hole size: 26’’ TD: 1157 m MD/RKB
Deviation angle: Vertical
Open H excess: OH Excess: 120% on lead & 150% on
tail
Water Depth 567.6 Mtr. MD/RKB
Air Gap 28.4m MD/RKB
Seabed Temperature 9.7 Deg. C
BHST: 33.00 Deg. C
BHCT: 25.00 Deg. C
CASING
OD: 20 Casing
ID: 18.73’’
Depth: 1150 m MD/RKB
Weight: 133 PPF
PREVIOUS CASING
OD: 36in Casing
ID: 33’’
Depth: 668 m MD/RKB
Weight: 310#
TOP OF CEMENT
Theoretical TOC: +/- 596 MD/RKB
DRILLING FLUID
Type: WBM
Mud 11.4 PPG
KEY ASSUMPTIONS
• This is Initial version of program based on well data/fluid properties (MD, TD, Mud Data, OH and
Temperature) from EDP. Landing string is considered to be 5 7/8in DP
• Propose 120% excess over volume of 12.50ppg (gas tight slurry capability for Shallow environment).
150% on 15.8ppg Tail Slurry with gas tight property. Considered 36.0 C BHST and 23.0 C BHCT to
design this slurry.
• The set-up time (i.e. the thickening time) of the cement slurry is design with Minimum of 2.0 hours’
safety factor to minimize risk to allow extra time in case of problem (loss).
182
Cementing Manual
sdfgghv bbnbnn
2 JOB EXECUTION
PRE-CEMENTING CONSIDERATIONS
• Tank requirement: one pit for lead mix fluid and one Pit for tail. Ensure that all tanks are clean.
• Centralizer to be pre-install offline on the casing as per Casing Tally.
CENTRALIZATION PROGRAM
(As per cementing software)
All equipment (Cement unit; Silo system) should be tested and ready for the job. Keep evidence of
readiness of the equipment onboard and send the scan copy to base Engineer. Batch Mixer should be
used as backup in case of mixing system failure. In that case, Batch mixing of 100bbl should be
carried.
Water salinity should be tested 2 days before the job and kept it ready for cement job. Salinity should
be less than 500PPM.
Rig pump efficiency should be checked during the circulation. It is Supervisor responsibility.
All siloes should be fluffed at least 10-15 min prior the job and ensured that all cement line and siloes
are clean and free of hard cement before the job.
Any deviation from the plan has to be communicated to base Engineer before proceed.
Shoe used is an autofill casing and per default, it’s deactivated. Supervisor will check to ensure that
Autofill is not activated.
183
Cementing Manual
sdfgghv bbnbnn
2- After landing the Casing, Circulation with one inner String volume and observe full return from 2 ball
valves prior cement job.
3- Flush the line with 10 bbl. of Drill water from Cement Unit and pressure test lines to 300Psi/3000 psi.
4- From Cement unit pump 40 Bbl. of Drill water. Pumping rate 6-7BPM.
5- Mix and pump 800 Bbl. Tuned Light Blend as per lab report attached 12.5 PPG Top of cement at seabed
considering 100% Open Hole Excess. Pumping rate 6 BPM.
6- Mix and pump 352 bbl. of Tail slurry 15.8 PPG as per Lab Report Considering 150 m Cement rise from
the bottom and 150% Open Hole Excess. Pumping rate 6 BPM.
7- Start Displacement at 6-7 BPM with 20 bbl. of HI-VIS Pill. (Viscosity of pill should be at least 200 Sec to
be confirm by the supervisor onboard) from Cement Unit.
8- Complete the displacement with 86.5 bbl. (excluding line volume) of Sea Water from Cement Unit.
Displacement rate 6-7 BPM Leaving 20m Plug inside 20’’ Casing. Keep controlling Losses with pumping
rate if possible by observing return from 2 ball valves in the Lower Housing Head.
9- Bleed Off and Check NRV through Cement Unit and Monitor Return.
10- In case the float is not holding, Pump back the return volume and keep the well closed under Final
pressure not more than differential pressure (400 PSI), and wait for 6 hours and keep all 2 valves in the
Lower Housing Close after completed of the Displacement.
12- After 12 Hours open one valve in the wellhead to check any trap of gas with the help of the ROV and
leave it open. Keep record of the video and share it with asset team.
Notes:
• Final Chemicals Consumption will be as per Rig Pit Dead Volume.
• In case of change of depths mentioned above, contact base for review of the program.
184
Cementing Manual
sdfgghv bbnbnn
• Salinity of drill water for mixing cement should be less than 500 PPM.
• Consider physical and digital volume count for displacement.
• All volume calculations are to be checked/re-calculated as per actual depths and sizes. Displacement
volume to be calculated based on the actual size and grade of drill pipe used.
• Keep 3 gallon of mix fluid sample used for the job for any post job analysis.
• Collect 3-4 random samples of slurry and keep in oven at BHST (35 degC).
• Job shall be in accordance with HSE policies and guidelines.
Description Stage No. Density Rate Yield Water Req. Volume Bulk Cement Duration
(ppg) (bbl/min) (ft³/sack) (gal/sack) (bbl) (94lb sacks) (min)
PDM-D LEAD SLURRY 3 12.50 6.00 1.8636 7.448 800.0 2236.05 123.70
PDM-D TAIL SLURRY 4 15.80 6.00 1.1640 5.086 352.23 1698.91 58.70
185
Cementing Manual
sdfgghv bbnbnn
186
Cementing Manual
sdfgghv bbnbnn
187
Cementing Manual
sdfgghv bbnbnn
SIMULATION RESULTS
2D FLUID POSITIONS CHART
188
Cementing Manual
sdfgghv bbnbnn
4 CONTINGENCY PLANS
Risk Risk impact Mitigation Plan Contingency plan
Is the well static Cement may be Ensure that well is static before If there is gas in the
before unable to provide cementing is started. mud or the well is
cementation? satisfactory barrier. flowing gas or water,
continue circulating
and increase MW.
The rig cannot Inefficient Design slurry with sufficient if the rake is not able to
supply displacement of thickening time considering provide mud at all then
displacement cement, lowest displacement rate at we shift to rig pumps
mud to cement contamination of which cement can be displaced. for entirety of
unit at planned mud, spacer and displacement.
rate. cement, leading to a Program designed with lowest
poor CBL. possible pump rate.
Improper mud poor mud removal, Condition mud before cement Squeeze for remedial
conditioning slurry channeling and job. First, circulate out all the cementing
contamination, poor cutting and foreign materials.
bonding and poor Then lower the rheological
zonal isolation properties of mud to as lowest
as well permits. Job design and
pump schedule optimisation
189
Cementing Manual
sdfgghv bbnbnn
190
Cementing Manual
sdfgghv bbnbnn
to displace or circulate
out cement with rig
pumps
Cement Cement job will not Ensure cement equipment is Rig pump will be used
pumping meet objective serviced and maintained before to circulate all the
equipment each job. Prior to the job, cement out of the well
malfunction calculate minimum top of
during job cement required and cement
volume required if equipment
fails.
Improper Bulk cement delivery Validate air volume rate and Clean/ check/ repair/
cement supply issues. Density pressure will meet job upgrade bulk air
control problems, requirements. Use pressurized compressor and
cannot mix at mud balance to check slurry moisture control
designed job rates. density. Verify competency of
Job time exceed bulk operator.
thickening time.
Rig alarm during Cement job in Continue mixing and pumping Secure equipment and
cement job progress with cement until the announcement is made assemble in the
in the well/ casing/ to confirm the alarm designated muster area
tubing
191
Cementing Manual