FIRE HYDRANT SYSTEM - INSTALLATION TESTING

AND COMMISSIONG CERTIFICATE

I.CUSTOMER: M/S. WALMART INDIA PVT LTD Date: - 25.10.2019

Best Price Modem Whole Sales


Survey No. 840, Thukkivakkam Village
Thirupathi- 517506

II. System Commission Report

The Following system has been tested and commissioned


 PUMP ROOM
 EXTERNAL HYDRANT
 SPRINKLER SYSTEM

III. ACCEPTANCE TEST WITNESS

This is to certify that system mentioned above has been successfully installed, commissioned and
demonstrated at the site. The system has been Working accepted and conforms

The Fire – Hydrant System’s contractor performed the acceptance Test on the system with 12 Kg
pressure. The Project Manager ensured that this being done with the First level Training.

IV. DOUCUMENTATION
Provided with this Records completion of Fire Hydrant System’s Reports indicating that all installed
devices have functioned properly. And the handing over will be done after completing of additional work

V. The undersigned has agreed to comply with the warranty terms & conduction.

___________________________ ________________________
SITE ENGINEER NAME & SIGN CUSTOMER NAME & SIGN

Page 1 of 1