Project: MOUDA II - B & F - CIVIL & STRUCTURAL WORKS - BOQ

S. No. ITEM UNITS PLAN (TENDER) TILL DATE ACTUAL

1 PILES Nos 988 581 1293

2 PCC CUM 2652 1852 2869

3 RCC CUM 14777 12723 21725

4 REBAR MT 1540 969 1355

5 STRUCTURAL STEEL MT 1685 1509 3260

ANCHOR BOLT + HIGH


6 STRENGTH BOLTS MT 90 0 0
S - BOQ

REMARKS
Project: MHPS-Mouda FGD
LIST OF BUILDINGS/STRUCTURES CONSIDERED FOR CIVIL & STRUCTURAL WORKS
Rev H 25-Aug-20
RCC QTY (Cum) RCC QTY (Cum) STRUCTURAL STEEL (MT) STRUCTURAL STEEL (MT) STRUCTURAL STEEL (MT) EXCAVATION BACKFILLING MURRUM FILLING
NO. OF PILES (nos.) PCC QTY (Cum) REBAR QTY (MT) HIGH STRENGTH STRUCTURAL REMARKS
SUB STRUCTURE SUPER STRUCTURE ROLLED STEEL ANCHOR BOLT (Cum) (Cum) (Cum)
S. No. STRUCTURE / BUILDING STEEL BOLTS
PLAN TILL DATE ACTUAL PLAN TILL DATE ACTUAL PLAN TILL DATE ACTUAL PLAN TILL DATE ACTUAL PLAN TILL DATE ACTUAL PLAN TILL DATE ACTUAL PLAN TILL DATE ACTUAL PLAN TILL DATE ACTUAL

1 Absorber - A (1) (600mm pile) 32 32 80 1.3 1.3 21.05 366.40 366.40 1016.15 29.3 29.3 61.0 1115.8 100.9

2 Absorber - B (2) (600mm pile) 32 32 80 1.3 1.3 21.05 366.40 366.40 1016.15 29.3 29.3 61.0 1115.8 100.9

3 Booster fan (Unit - 3) (600mm pile) 15 15 27 9.3 9.3 8.90 241.40 241.40 376.00 19.3 19.3 19.6 199.0 36.0

4 Booster fan (Unit - 3) (600mm pile) 15 15 27 9.3 9.3 8.90 241.40 241.40 376.00 19.3 19.3 19.6 199.0 36.0

5 Booster fan (Unit - 3) (600mm pile) 15 15 27 9.3 9.3 8.90 241.40 241.40 376.00 19.3 19.3 19.6 199.0 36.0

6 Booster fan (Unit - 3) (600mm pile) 15 15 27 9.3 9.3 8.90 241.40 241.40 376.00 19.3 19.3 19.6 199.0 36.0

Rebar quantity for


9 Pipe Rack (Segment-1 to 19) 600mm pile 160 0 0 19.0 19.0 189.25 350.00 350.00 1883.42 35.0 35.0 29.3 430.0 430.0 731.5 1.2 21.5 14708.5 8284.6 5033.7
segment-13 to 19 only.

10 Staircase & Elevators (34 42) (600mm pile) 6 6 38 2.0 2.0 8.28 23.20 23.20 159.28 2.3 37.0 37.0 115.3 0.1 1.9 532.4 316.9 210.2

11 Lime stone slurry Pump (65) 0 0 0 2.5 2.5 1.77 14.51 14.51 14.92 1.5 53.0 14.5 23.6

12 Lime stone slurry Tank (63 & 64) 0 0 64 5.3 5.3 38.7 116.0 116.0 338.6 9.3 9.3 20.6 680.2 388.8

13 Secondary HC Feed Tank (87) 0 0 0 1.5 1.5 2.7 22.0 22.0 23.5 1.8 1.8 1.4 87.0 62.1

14 Waste Water Tank (89) 0 0 0 2.8 2.8 6.4 54.0 54.0 32.4 4.3 4.3 2.0 190.4 158.0

15 Filterate Water Tank (91) 0 0 0 3.6 3.6 7.3 74.0 74.0 35.0 5.9 5.9 2.2 216.1 181.8

16 Primary HC Feed Tank (93) 0 0 0 2.9 2.9 7.2 56.0 56.0 35.4 4.5 4.5 2.2 217.3 181.7

17 Auxiliary Absorbent Tank 0 0 0 0.8 0.8 33.7 147.4 147.4 183.7 11.8 11.8 47.2 834.3 661.1
(45)

18 Process water tank 0 0 0 1.5 1.5 6.4 22.0 22.0 46.8 1.8 1.8 3.0 224.2 176.8
(47 - 48)

19 Clarified Water Tanks (84) 0 0 0 1.0 1.0 2.0 7.0 7.0 29.9 0.6 0.6 1.9 92.5 59.4

Rebar quantity for


21 Electrical bldg (55) (600mm pile) 119 119 232 264.0 264.0 166.01 851.00 851.00 1106.03 1528.0 1528.0 1583.3 238.0 238.0 249.0 0.0 0.0 0.9 3674.3 2631.8 244.3 Foundation only.

Rebar quantity for


Limestone Slurry Preparation & Gypsum Foundation only.
23 Dewatering Building (61) (760 mm pile - 94 94 184 120.0 120.0 194.63 774.00 774.00 804.10 1326.0 1326.0 1601.5 210.0 210.0 195.0 69.5 3.4 3917.8 2072.3 1175.7 Includes Day Silo and
Plan; 600 mm Pile - Actual) Transfer Tower
foundations

Rebar quantity for


24 Truck Tippler (74) (600mm pile) 25 0 0 114.0 114.0 109.0 530.0 530.0 1100.0 330.0 330.0 995.0 86.0 86.0 379.3 7444.0 6283.0 43.8 Foundation only.

Only LC-1A/1B
conveyors are
25 Conveyor Galleries (75 .1a - 1b ) (600mm 40 40 0 26.0 26.0 13.40 282.00 282.00 121.40 0.0 0.0 0.0 29.0 29.0 10.4 239.0 239.0 127.4 12.0 978.2 667.0 233.5 calculated and Rebar
pile) quantity for Foundation
only.

33 Limestone Silo (Bulk) (79) (760mm pile) 24 24 138 211.8 211.8 44.34 161.00 161.00 1058.71 26.3 255.7 255.7 894.0 6.0 2567.4 879.9 850.5

35 Gypsum Storage shed (101) (600mm pile) 72 72 218 139.0 139.0 47.37 588.00 588.00 700.96 1682.0 1682.0 2298.4 227.0 78.0 78.0 81.4 3.6 3378.4 1660.2 1035.2

Maintenance
platform,Cladding
36 Lime Stone Shed 10 0 0 14.0 14.0 6.7 63.0 63.0 58.8 7.0 7.0 6.4 9.2 9.2 36.8 0.5 361.5 297.8 runner, sheeting and
steel stair case are not
included.

Miscellaneous Pumps - Gypsum bleed


37 pumps for unit #3 (32), Absorber drainage 0 0 0 1.8 1.8 1.00 13.00 13.00 6.83 1.3 32.8 11.4 14.6
pumps for unit #3 (36)

38 Gypsum bleed pumps for unit #4 (40) 0 0 0 1.8 1.8 1.00 13.00 13.00 6.83 1.3 32.8 11.4 14.6
Absorber drainage pumps for unit #4 (44)

Process water pumps(49) , Mist eliminator


39 wash water pumps (50), FGD DM primary 0 0 0 11.8 11.8 5.97 58.60 58.60 42.87 5.9 184.7 59.8 82.1
cooling water pump (52), FGD Auxiliary
cooling water pump(53)

40 Auxiliary absorbent slurry pump (46) 0 0 0 1.7 1.7 1.49 7.10 7.10 8.71 0.7 38.7 12.8 17.2

41 Primary hydrocyclone feed pump(94) 0 0 0 1.1 1.1 0.96 6.40 6.40 5.93 0.6 32.1 11.9 14.3

42 Filtrate water pump (92) 0 0 0 1.3 1.3 1.05 6.40 6.40 7.51 0.6 30.0 9.1 13.3

43 Waste water pump(90) 0 0 0 1.3 1.3 0.70 6.40 6.40 5.52 0.6 22.5 7.0 10.0

44 Second stage hydrocyclone feed pumps 0 0 0 1.3 1.3 0.56 6.40 6.40 3.85 0.6 19.4 6.9 8.6
(88)
Project: MHPS-Mouda FGD
LIST OF BUILDINGS/STRUCTURES CONSIDERED FOR CIVIL & STRUCTURAL WORKS
Rev H 25-Aug-20
RCC QTY (Cum) RCC QTY (Cum) STRUCTURAL STEEL (MT) STRUCTURAL STEEL (MT) STRUCTURAL STEEL (MT) EXCAVATION BACKFILLING MURRUM FILLING
NO. OF PILES (nos.) PCC QTY (Cum) REBAR QTY (MT) HIGH STRENGTH STRUCTURAL REMARKS
SUB STRUCTURE SUPER STRUCTURE ROLLED STEEL ANCHOR BOLT (Cum) (Cum) (Cum)
S. No. STRUCTURE / BUILDING STEEL BOLTS
PLAN TILL DATE ACTUAL PLAN TILL DATE ACTUAL PLAN TILL DATE ACTUAL PLAN TILL DATE ACTUAL PLAN TILL DATE ACTUAL PLAN TILL DATE ACTUAL PLAN TILL DATE ACTUAL PLAN TILL DATE ACTUAL

45 Clarified water pumps(85) 0 0 0 1.3 1.3 1.40 6.40 6.40 11.48 0.6 45.0 13.5 20.0

47 Sumps (33) 0 0 0 2.6 2.6 2.7 16.3 16.3 33.8 23.0 3.9 3.9 2.7 144.3 33.8

48 Sumps (41) 0 0 0 2.6 2.6 2.7 16.3 16.3 33.8 23.0 3.9 3.9 2.7 144.3 33.8

49 Sumps (66) 0 0 0 2.6 2.6 2.7 16.3 16.3 33.8 23.0 3.9 3.9 2.7 144.3 33.8

50 Sumps (83) 0 0 0 2.6 2.6 2.7 16.3 16.3 33.8 23.0 3.9 3.9 2.7 144.3 33.8

52 Ball mill Foundation 0 0 0 0.0 0.0 12.00 0.00 0.00 454.00 567.1 227.6 112.0

53 Pump House for Unit-3 (600mm pile) 28 28 34 44.0 44.0 632.6 189.0 189.0 513.3 0.0 0.0 0.0 19.0 19.0 34.7 24.0 24.0 93.1 0.2 1.2 1443.2 771.0 6.0

54 Pump House for Unit-4 (600mm pile) 32 32 34 49.0 49.0 633.1 210.0 210.0 522.4 0.0 0.0 0.0 21.0 21.0 35.9 27.0 27.0 116.1 0.2 1.4 1464.2 783.0 6.0

61 Remote IO Room (600mm pile) 12 0 0 16.0 16.0 4.4 109.0 109.0 65.9 48.0 48.0 39.1 16.0 16.0 7.4 286.0 206.7

67 Drain layout-Absorber Island-unit-3 0 0 0 0 0 8.3 0 0 31.6 0 0 1.6 56.0

68 Drain layout-Absorber Island-unit-4 0 0 0 0 0 11.5 0 0 46.8 0 0 2.5 79.5

69 Drain layout-Common facilities-unit-4 0 0 0 0 0 7.9 0 0 32.3 0 0 1.8 63.0

71 DG Set 0 0 112.3 0 0 33.5 0 0 1.5 147.5 2.3

Summary of Plan and Actuals 988 581 1293 2652 1852 2869 9558 7793 15208 5219 4929 6517 1540 969 1355 1685 1509 3260 17 0 0 73 0 0 48307 27247 9515