PRECEDENCE DIAGRAM METHOD


508(1) 9 250 days 1702(1)a 10 219 days 1712(2) 12 235 days
1710(2)b 11 234 days
Structure Excavation
Hand-Laid Rock Embankment (Common Soil) Grouted Riprap Class "B" Concrete Slope Protection
START FS FS-214d FS-188d FS-214d
0 0 36 36 68 68
48 48
250 250 255 255 302 302
281 281

A.1.1(8) 1 302 days

FS Provision of Field Office for


the Engineer (Rental Basis)
0 0
302 302
A.1.4(1) 3 302 days

FS Provision of Progress
Photographs

0 0 FFSS FS
302 302 FINISH
FS FS+293d
B.4(1) 4 6 days

FS Construction Survey and


Staking B.5 5 3 days
0 287
FS Project Billboard/Signboard
6 293

B.7(1) 6 302 days 6 293


9 302
FS Occupation Safety and Health
Program

0 0
302 302

B.9 7 302 days

FS Mobilization/Demobilization

0 0
302 302
B.15(1) 8 302 days

FS Detour/Access Road

0 0
302 302

Prepared by: Implementing Agency: Checked by: Submitted by: Recommending Approval: Approved:
Republic of the Philippines
O.G. SANTOS CONSTRUCTION DEPARTMENT OF PUBLIC WORKS AND
ROSALITO C. PASO ROSALIA E. PLAZA JULIUS S. URIARTE NOEL R. OCLARIT
HIGHWAYS OFFICE OF THE DISTRICT ENGINEER
Surigao del Sur 2nd District Engineering Office
Contractor Project Engineer III Chief, Construction Section Caretaker Office of the District Engineer District Engineer