Professional Documents
Culture Documents
PP Aaa PP1 102
PP Aaa PP1 102
PP Aaa PP1 102
SKIKDA, ALGERIA
OPERATING MANUAL VOLUME I, SECTION 2-1:
KBR
TABLE OF CONTENTS
1.0 INTRODUCTION................................................................................................... 3
2.0 SYSTEM DESCRIPTION ...................................................................................... 5
2.1 Acid Gas Absorber............................................................................................................5
2.2 Amine Regeneration .........................................................................................................5
2.3 Solvent Storage Facilities .................................................................................................7
3.0 OPERATIONS....................................................................................................... 9
3.1 Normal Running ................................................................................................................9
3.1.1 Feed Gas Flow ...............................................................................................................9
3.1.2 Amine Circulation Rate...................................................................................................9
3.1.3 System Inventory..........................................................................................................10
3.1.4 Skimming Operations ...................................................................................................10
3.1.5 Foaming........................................................................................................................10
3.2 Typical Operating Parameters ........................................................................................11
3.3 Temporary Operation......................................................................................................14
3.3.1 High CO2 versus Low CO2 ...........................................................................................14
3.3.2 Air Coolers and Condensers ........................................................................................14
3.3.3 Activated Carbon Filter to Absorber or Storage ...........................................................14
3.3.4 Feed Gas Compressor Offline......................................................................................14
4.0 START-UP .......................................................................................................... 15
4.1 Prior to Start-up...............................................................................................................15
4.2 AGRU Section Start-up...................................................................................................15
5.0 SHUTDOWN ....................................................................................................... 18
5.1 Normal Shutdown ...........................................................................................................18
5.2 Process Upsets and Production Loss.............................................................................19
6.0 SAFETY/EMERGENCY SHUTDOWN................................................................ 20
6.1 Safety Critical Shutdown Systems..................................................................................20
6.1.1 I-1200 – Acid Gas Removal, Unit 12 ESD ...................................................................20
6.1.2 I-1210 – 12-MD21 Vapor Breakthrough Protection......................................................20
6.1.3 I-1220 – 12-MD22 Low Level Trip................................................................................20
6.1.4 I-1230 – 12-MD39 Low Level Trip................................................................................20
6.1.5 I-1250 – 12-MJ22A/B/C Lean Solvent Booster Pump Protection ................................20
6.1.6 I-1251 – 12-MJ21A Lean Solvent Pump Protection.....................................................20
6.1.7 I-1252 – 12-MJ21B Lean Solvent Pump Protection.....................................................20
6.1.8 I-1253 – 12-MJ21C Lean Solvent Pump Protection.....................................................20
6.1.9 I-1255 – 12-MD21 Solvent Backflow Protection...........................................................21
6.1.10 I-1275 – 12-ML21-MJ01 Anti-Foam Pump Protection .................................................21
6.1.11 I-1391 – Depressure 13-MC01 Dryer Pre-Cooler Area................................................21
6.2 Pressure Safety Valve Summary....................................................................................21
6.3 Fire Protection Equipment ..............................................................................................22
7.0 ATTACHMENTS ................................................................................................. 24
7.1 Attachment I: Equipment List ..........................................................................................25
7.2 Attachment II: Utility Consumption.................................................................................27
7.3 Attachment III: AGRU Solvent Flowrate Calculator .......................................................27
Page 2 of 27
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-102
OPERATING MANUAL VOLUME I, SECTION 2-1: REVISION 5
AGRU & aMDEA STORAGE 16-November-13
1.0 INTRODUCTION
This operating manual pertains to the Unit 12 Acid Gas Removal (AGRU) facilities as
shown on Process Flow Diagrams PR-12-PR32-024, 025 and 026 and P&ID’s
PR-12-SYPI-021 through 030A and PR-12-SYPI-034.
This operating manual also pertains to the Unit 02 aMDEA Solvent Storage facilities
as shown on Process Flow Diagram PR-02-PR32-021 and P&ID’s PR-02-SYPI-021
and 022.
The Acid Gas Absorber, 12-MD21, is located downstream of the Feed Gas
Compression Unit 01 and upstream of the Dehydration Unit 13.
The purpose of this AGR Unit is to remove carbon dioxide gas (CO2) from the feed
gas stream leaving Unit 01 Feed Gas Compressor Aftercooler, 01-MC01. This Unit
reduces the CO2 levels to less than 50 ppmv to prevent freezing out in the
downstream Liquefaction Unit 15. Activated Methyl DiEthanol Amine (aMDEA) is
used to absorb the acid gases in the packed section of the absorber and then
regenerated by driving the gases off in the regenerator column.
The regeneration facilities for the acid gas removal unit process the rich amine
leaving the absorber bottoms by flashing the rich amine to low pressure in the HP
Flash Column, 12-MD22, and reboiling any remaining acid gas from the amine in the
regenerator column, 12-MD27.
The CO2 and trace hydrocarbon vapors leaving the AGRU regenerator are sent to
the Thermal Oxidizer in Unit 65 where the hydrocarbons are burned off and non-
flammable vapor is discharged to the atmosphere.
The storage facilities for the aMDEA consist of two storage tanks and associated
pumps. The smaller tank, 02-MF22, holds the concentrated aMDEA as purchased
and the larger tank, 02-MF21, holds the diluted 40 wt% aMDEA used in the process
equipment.
Refer to the sketch on the next page to locate the gas flow through the absorber and
the lean/rich amine liquid flow loop through the absorber and regenerator.
Page 3 of 27 KBR
Acid Gas Removal Unit PR-02-SYPI-
022
PR-02-SYPI-
02-FV1029 Azote 021
12PIC 12FI
1352 RO Azote
1266 M
12H
Azote
O 12- O 3.9 T/H
ZL S 02FIC
F 1005 1005 F 2.25 ba 1029
45 *C 401 M3 02FI
12HIC I 65-MB07 8 M3 1004A
1005 13-HZ-1072 MDEA Eau
1391
deminéralisée
PR-12-SYPI-
024
SKIKDA, ALGERIA
1006
Pompe de 1043
reflux
12-FV1028
12TI 199 T/H 12-FV1076
NEW LNG TRAIN SKIKDA PROJECT
1002 10.7 ba
48 *C
<
Solvent make
I 12FY PR-12-SYPI-
Page 4 of 27
1255 12FIC 1113 034
1117
12FIC
OPERATING MANUAL VOLUME I, SECTION 2-1:
1113
12-LV1054
12LIC
12-XV1008 12-FV1117 1054A
12FI
12LIC
1070 1054B
PR-12-SYPI- PR-12-SYPI-
021 029 Reboillers
Lean solvent Hot oil
I pumps
12PDI 12-MJ21 A/B/C
5830
1009
12PIC 199 T/H
1148
10.7 ba Booster Pumps
12FI 48 *C
1144 12-MJ22 A/B/C
PR-12-SYPI-
PR-12-SYPI- PR-12-SYPI-
REVISION 5
022
023A 023
36'’
12-ML21
Feed gas from 01-MC01 Anti foam
SP Package
12LIC 12PDI 50% 50% 50%
1012
16-November-13
DOCUMENT NO.
KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-102
OPERATING MANUAL VOLUME I, SECTION 2-1: REVISION 5
AGRU & aMDEA STORAGE 16-November-13
Page 5 of 27 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-102
OPERATING MANUAL VOLUME I, SECTION 2-1: REVISION 5
AGRU & aMDEA STORAGE 16-November-13
reboilers are arranged as two 50% units and are shell and tube, kettle type
exchangers.
The regenerator column is arranged with a total liquid draw-off pan below the packed
beds to direct the liquid to the reboilers. The reboilers are located so that they are
symmetric to the column. A weir plate in each of the reboiler shells ensures that the
tubes are flooded, but with sufficient vapor space to allow vapor (steam) to flow from
the reboilers back into the column. The vapor enters the column below the draw-off
pan, rises through chimneys and up through the packed beds. Liquid overflowing the
weir flows by gravity from the bottom of the reboiler shells back to the bottom section
of the regenerator column.
The vapor leaving the top of the regenerator columns is condensed in the air cooler
Solvent Regenerator Condenser, 12-MC34. The condensate flows to the Solvent
Regenerator Reflux Drum, 12-MD39, where the liquid and vapor are separated. The
uncondensed vapors are sent, under pressure control, to the Thermal Oxidizer in
order to reduce the concentration of volatile organic carbon (VOC) in the vented gas
to below 150 mg/Nm3. The condensed fluid from the reflux drum, mainly water, is
pumped back as reflux to the regenerator by the Solvent Regenerator Reflux Pumps,
12-MJ33/A.
The hot lean amine leaves the bottom of the Solvent Regenerator and is pumped by
the Lean Solvent Booster Pumps, 12-MJ22-A/B/C, through the Lean/Rich Solvent
Exchanger, 12-MC22-A/B/C. Here the lean amine is cooled by cross exchange with
the incoming rich amine feed. This lean amine stream is cooled further in the Lean
Solvent Air Cooler, 12-MC21, before being sent to the high pressure Lean Solvent
Pumps, 12-MJ21-A/B/C. This stream is on flow control. No temperature control takes
place at the Lean/Rich Solvent Exchanger, since both lean and rich amine streams
are flow controlled and hence the temperatures of the streams find their own
equilibrium. The temperature downstream of the Lean Solvent Air Cooler is controlled
by means of a bypass around the exchanger. The temperature is set so that the lean
amine feed to the absorber is slightly above the feed gas temperature to the
absorber. This is to minimize the risk of condensing hydrocarbons out of the feed gas
when it contacts the lean amine. Hydrocarbons in the amine circuit can cause
foaming and can sometimes cause fouling in heat exchangers.
3. Activated Carbon Filter
Impurities other than hydrocarbons can also cause foaming in the amine circuit. In
order to minimize impurities buildup, approximately 10% of the total flow downstream
of the Lean Solvent Cooler is routed (by automatic flow control) through the Lean
Solvent Prefilter, 12-ML33-MD01, the Activated Carbon Filter, 12-ML33-MD02, and
the Lean Solvent Post-Filter, 12-ML33-MD03, back to the suction of lean solvent
pump, 12-MJ21-A/B/C.
The discharge of the post filter, 12-ML33-MD03, can also be routed back to the 40%
storage tank, 02-MF21. When operated in this mode, the solvent is returned under
level control to the Solvent Regenerator by 02-MJ21. This amine from storage is
approximately 40°C and enters the regenerator bottoms section (129°C).
4. Antifoam Injection
Additional measures to counteract foaming are provided by the Antifoam Injection
Package, 12-ML21. This can be used to dose small amounts of antifoam agent into
the amine circuit, either continuously or in a batch dosing arrangement. The antifoam
Page 6 of 27 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-102
OPERATING MANUAL VOLUME I, SECTION 2-1: REVISION 5
AGRU & aMDEA STORAGE 16-November-13
can be injected downstream of the Lean Solvent Cooler or into the rich solvent
upstream of the Lean/Rich Solvent Exchanger. The antifoam is silicone based and
forms an emulsion with the amine solvent. Passing through the filter package, 12-
ML33, and pumps breaks up this emulsion and reduces the effectiveness of the
antifoam. The antifoam should be regularly injected to maintain the emulsion and
prevent foaming. The concentration of antifoam should be 50 ppm (wt%), however
the concentration cannot be directly measured. The AGRU has approximately 400 m3
of solvent circulating, so 20 L of antifoam will be required for the initial charge. 10 L
per day will need to be injected to maintain the emulsion.
The concentration of MDEA and activators in the lean amine solution is monitored by
regular sampling and testing. The desired concentration of 40% w/w AMDEA/Water
is maintained by adding demineralized water to the Solvent Regenerator Reflux
Drum, 12-MD39, or by adding make-up amine solution at a higher concentration from
Solvent storage tank, 02-MF21. The concentration of AMDEA can also be increased
by more hot oil circulation through the reboilers to vaporize the water content and
water removal from the reflux system until the solvent concentration is achieved.
Periodic make-up of amine solution is required to offset continuous small losses due
to carry-over and larger intermittent losses caused by leaks and spills. Make-up
solution from the Solvent Storage Tank, 02-MF21, is fed to the system by the Solvent
Transfer Pump, 02-MJ21. The Solvent Storage Tank can also accept the full
inventory of solvent pumped to it from the Acid Gas Removal Unit when maintenance
of the facilities is required
5. Solvent Drain Drum
The Solvent Drain Drum, 12-MD30, located in a sump, collects liquid drainage of
solvent from Unit 12 equipment through a closed amine drain system. This drainage
can be from any equipment which requires maintenance, e.g. pumps, filters, level
instruments, etc. Oil skim connections on the Acid Gas Absorber, 12-MD21, HP
Flash Drum, 12-MD22, Solvent Regenerator, 12-MD27, Solvent Regenerator Reflux
Drum, 12-MD39, and Solvent Storage Tank, 02-MF21, also discharge to the Solvent
Drain Drum.
The Solvent Drain Drum is a horizontal vessel, arranged so that any drainage feeds
into the central stilling section. At one end there is an overflow baffle so that
hydrocarbons which collect on top of the solvent in the stilling section can flow over
into an oil collection compartment. At the other end there is an underflow and
overflow baffle arrangement so that solvent free of hydrocarbons can flow into a
solvent collection compartment. Each end compartment contains a pump. The oil
compartment contains the Skim Oil Pump, 12-MJ26, which pumps the oil to the
Warm Flare Drum, 65-MD01, for disposal. The solvent compartment contains the
Solvent Drain Pump, 12-MJ25, which pumps the solvent either back into the amine
circuit or to the Solvent Storage Tank located in the common facilities via the Solvent
Charge Filter, 12-MD28. The Solvent Drain Drum is blanketed with nitrogen to
prevent solvent contact with air that can degrade the solvent.
2.3 Solvent Storage Facilities
The Acid Gas Removal Common Solvent Storage facilities are located remotely from
the AGRU gas processing facilities. There are two storage tanks used for Solvent
Storage. They are used to make up solvent for the process.
Page 7 of 27 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-102
OPERATING MANUAL VOLUME I, SECTION 2-1: REVISION 5
AGRU & aMDEA STORAGE 16-November-13
One storage tank, Mixed Solvent Storage Tank, 02-MF22, is used for storage of the
concentrated amine. The solvent is activated MDEA (aMDEA) which is supplied by
BASF. The solvent is delivered as a solution that consists of MDEA, activator, and a
small amount of water (approx. 91% MDEA and 9% water mixture). The premix
solution is delivered in isocontainers and pressured by nitrogen into the Mixed
Solvent Storage Tank, 02-MF22. A nitrogen blanket is provided to protect the solvent
from contact with air. The Mixed Solvent Supply Pump, 02-MJ22, has a capacity of
10 m3/hr. A minimum flow line is provided to protect the pump. Expected losses from
the Acid Gas Removal Unit are between 5 and 10% of premix inventory per year.
The Solvent Storage Tank, 02-MF21, which is the larger tank, is used for storing the
diluted amine used in the process equipment. Demineralized water is used to dilute
the premix solution to give a target composition of 40% w/w amine and 60% w/w
water for the solvent used in the Acid Gas Removal Unit. The Solvent Storage Tank,
02-MF21 is sized to hold the total solvent inventory (400 m3) of the Acid Gas
Removal Unit during shutdown and maintenance periods. Since the solvent will
degrade in the presence of air, a nitrogen blanket is provided to minimize contact
with air. The Solvent Transfer Pump, 02-MJ21, capacity (25 m3/hr) is based on a loop
filling time of 16 hours. A minimum flow line is provided to protect the pump.
Page 8 of 27 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-102
OPERATING MANUAL VOLUME I, SECTION 2-1: REVISION 5
AGRU & aMDEA STORAGE 16-November-13
3.0 OPERATIONS
3.1 Normal Running
This section provides a description of the operating parameters for the AGRU &
AMDEA Storage System. Refer to the table in Section 3.2 for a list of typical
operating variables for this system.
3.1.1 Feed Gas Flow
The feed gas flow through the Acid Gas Absorber 12-MD21 is indicated by 12-FI-
1023 but is not controlled directly at this point. The feed gas flow is proportional to
the overall LNG production rate.
The overall LNG production rate is controlled by flow controller 15-FIC-1057 which is
reset by 15-TIC-1056. This 15-FIC-1057 is the flow rate of LNG leaving the Main
Cryogenic Heat Exchanger (MCHE) and travelling through the LNG
expander/generator, 15-MJ02. Control Valve 15-FV-1057B downstream of the LNG
expander/generator controls the LNG production flow rate.
3.1.2 Amine Circulation Rate
The circulation of liquid amine through the absorber/flash drum/regenerator loop is
controlled by 12-FIC-1117. The design case amine circulation rate is 423 t/h of 50%
weight solvent when the feed gas is running 2% CO2 (AGRU section design rate).
When the feed gas is only 0.21% CO2, the amine flow can be reduced to 200 t/h of
40% weight solvent) and still keep the packing surface wetted sufficiently to reduce
the CO2 to less than 50ppm.
Normal amine concentration is designed to be 40% by weight with water. Additional
demin water can be added to the reflux drum to bring the amine concentration down.
Water can be removed from the reflux system to increase the amine concentration.
As the CO2 concentration in the feed gas increases the lean solvent flowrate will also
need to increase to meet the less than 50 ppmv CO2 requirement. However, the lean
solvent will start to erode the carbon steel pipe if the velocity exceed 2 m/s. To
prevent this erosion the maximum lean solvent flowrate is limited to 10,160 t/d. As
the CO2 concentration approaches the 2% CO2 design case the solvent will need to
be concentrated up to 50% by weight to continue producing LNG at the design rate.
During turndown cases, the lean solvent flowrate must be reduced to match the feed
gas rate. If the solvent flowrate exceeds that required by the feed gas flowrate, the
solvent will absorb methane from the feed gas after absorbing all of the CO2. Excess
solvent circulation will be indicated by:
• Higher flowrates from the overhead of the HP Flash Column, 12-MD22
• Higher flowrates and hydrocarbon content in the acid gas vent from the
Solvent Regenerator Reflux Drum, 12-MD39
The solvent circulation rate is also limited to 3290 t/d to prevent channeling in the
Acid Gas Absorber, 12-MD21. While decreasing the solvent circulation rate, carefully
monitor the CO2 analyzer, 13-AT-1008, to ensure the feed gas meets the less than
50 ppmv CO2 requirement. Increase the solvent flowrate as necessary to prevent
CO2 breakthrough.
Refer to Attachment III which correlates the feed gas flowrate to the expected solvent
circulation rate.
Page 9 of 27 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-102
OPERATING MANUAL VOLUME I, SECTION 2-1: REVISION 5
AGRU & aMDEA STORAGE 16-November-13
adjusting the stroke on the pump. 10 liters per day of anti-foam will need to be
injected to maintain the emulsion in the amine and prevent foaming. This rate may
need to be adjusted up or down based on operating experience. Close monitoring of
the pressure differential across the three towers will establish the best antifoam
addition rate for this plant. The laboratory can also run a foam test in the lab to help
adjust the antifoam injection rate. The foam test is run by shaking up a sample and
measuring the volume of the foam and time in seconds for the foam to subside after
shaking stops. Foaming tendency is considered low when the foam volume is not
higher than three hundred (300) mL and the collapse time is twenty (20) seconds or
less.
To prevent foaming from occurring, anti-foam needs to be injected on a regular basis.
When operating at design rates 10L/day of antifoam should be injected. If pressure
differentials across the three towers are higher than normal, then additional antifoam
may need to be injected. Perform oil skimming on all vessels and tank 02-MF21 to
confirm the liquid hydrocarbons are removed before adding additional antifoam.
On the Antifoam Injection Package 12-ML21:
1. Inject ten (10) L of antifoam to the system by decreasing the level by 3.5 cm
on 12-LG-1086 or 3.5% on level transmitter 12-LT-1090.
2. Allow the system to circulate for several hours, and monitor the pressure
differentials across the three towers.
3. If the pressure differentials across the towers are still high, but they have
improved repeat steps 1 and 2. If the results do not improve have the
laboratory perform a foam test to confirm if the pressure difference is related
to foaming before adding additional antifoam.
Note: The volume of the 12-ML21 discharge piping CH-12100/12101/12102 is
approximately 17L.
Page 11 of 27 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-102
OPERATING MANUAL VOLUME I, SECTION 2-1: REVISION 5
AGRU & aMDEA STORAGE 16-November-13
Page 12 of 27 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-102
OPERATING MANUAL VOLUME I, SECTION 2-1: REVISION 5
AGRU & aMDEA STORAGE 16-November-13
Page 13 of 27 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-102
OPERATING MANUAL VOLUME I, SECTION 2-1: REVISION 5
AGRU & aMDEA STORAGE 16-November-13
Page 14 of 27 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-102
OPERATING MANUAL VOLUME I, SECTION 2-1: REVISION 5
AGRU & aMDEA STORAGE 16-November-13
4.0 START-UP
This section outlines the steps necessary to place the AGRU & AMDEA Storage
System in service. For the purpose of this section of the operating manual, it is
assumed that the following conditions exist: utilities are in service, feed gas is
available, downstream units are ready for feed gas, commissioning of the system has
been completed, and system is purged of air and ready for start-up.
4.1 Prior to Start-up
1. Confirm that the aMDEA solution is ready and available from Unit 02.
2. Prepare enough 40% amine to fill the absorber/regenerator system.
Approximately 400 m3 is needed to inventory the AGRU & aMDEA Storage
System. The target amine concentration is 40% +/- 2%.
3. For the initial start-up an antifoam content of about 50 ppm (w/w) is required.
After a normal plant shutdown, only one third of this initial amount of antifoam
should be added prior to starting up again.
4. Note: In order to have reboiler heat for the regenerator, the Unit 18 hot oil
system has to be in service. Unit 18 depends upon heat recovery from the
16-MJ04-GT gas turbine exhaust so that equipment must also be in service
prior to Unit 18 hot oil.
• Unit 18 Hot Oil system
• Gas Turbine 16-MJ04-GT
• Propane Refrigeration Unit 16, 16-MJ04, PR Compressor
• MR HP compressor, 16-MJ03, on total recycle (same driver/shaft)
5. Confirm the Warm Flare header is in service.
6. Confirm Thermal Oxidizer 65-MB07 is in service
7. Confirm that absorber, HP Flash Column, and regenerator are under inert
nitrogen atmosphere in the range of 1-2 barg.
8. Confirm Low Pressure Fuel Gas Knockout Drum, 58-MD02, is in service to
receive a small vent flow from HP Flash Column, 12-MD22, overhead. If Hot Oil
Furnace, 58-MB01, is not in service, partially open 2” bypass globe valve
around 58-PRV-1001A/B to allow the small gas flow to bleed into flare line as
12-PIC-1148 releases gas from HP Flash Column, 12-MD22.
4.2 AGRU Section Start-up
Below is a summary of the major steps required for start-up of the AGRU.
1. Establish liquid amine inventory in the absorber, HP Flash Column, regenerator,
and associated equipment. Pump 40% amine from 02-MF21 using 02-MJ21
pump to HP Flash Column, 12-MD22. When 50% level is established in HP
Flash Column, fill regenerator, 12-MD27, to 50% level. Then, fill booster pumps,
12-MJ22-A/B/C, and solvent exchangers, 12-MC22-A/B/C, followed by lean
solvent cooler, 12-MC21, and activated carbon filters, 12-ML33-MD01/-MD02/-
MD03. Continue to fill the absorber, 12-MD21, to 50% level and, then, stop the
filling operation until more amine is needed in system after circulation is started.
Page 15 of 27 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-102
OPERATING MANUAL VOLUME I, SECTION 2-1: REVISION 5
AGRU & aMDEA STORAGE 16-November-13
2. Introduce feed gas to the absorber and pressurize this column to the feed gas
line supply pressure. Increase pressure on absorber to 40 barg with feed gas
using the 2” by-pass around the 36” isolation valve on the feed gas line to
absorber, 12-MD21, and open 36” isolation valve.
3. Start amine circulation at a low flow rate (20 – 30%). Establish amine circulation
with 12-MJ22 pumps and 12-MJ21 pumps to approximately 30% of normal
design through entire loop. Set amine flow controller, 12-FIC-1117, at desired
startup target flow rate (150 t/h).
4. Start the condenser fans on 12-MC34 and bring the solution to its operating
temperatures by feeding hot oil to the Reboiler and operating the lean solution
coolers. Establish normal reboiler temperature (approx. 129°C) in regenerator
bottoms, 12-MD27, with hot oil from Unit 18. Set the regenerator overhead
temperature at 119°C using 12-TIC-1043 and 12-FIC-1070 to control the flow of
hot oil.
5. Increase the circulation rate to 200 t/h. Establish normal temperature of lean
amine to top of absorber by turning fans on or off on lean solvent cooler, 12-
MC21, and 12-TIC-1102 to control bypass flow around cooler.
6. Start the feed gas flow at < 30% rate. Establish a flow of feed gas through
absorber to warm flare by adjusting 12-HIC-1005. Gas flow rate to absorber is
indicated on 12-FI-1023.
7. Establish the operating pressures and temperatures in the system. Pressure the
Regenerator 12-MD27 to 1.2 barg with feed gas. Set the pressure vent, 12-PIC-
1352, at 1.24 barg on reflux drum to avoid overpressure. Excess gas vents to
the Thermal Oxidizer, 65-MB07.
8. Start up the regenerator reflux pump, 12-MJ33, after a condensate level has
been established with demin water in the reflux drum, 12-MD39. Use
12-FIC-1356 to control demin water. Use 12-FIC-1076 to control the reflux flow
rate until the reflux drum level is lined out.
9. When CO2 has been reduced to acceptable limits (less than 50ppm), the sweet
gas can be allowed to flow to the dryers in the Dehydration System. Use the
2” bypass valve upstream of dryer precooler, 13-MC01, to pressure up
Dehydration System equipment to operating pressure (40-66 barg).
10. When the dry sweet gas is available from the dryers for defrost, the downstream
equipment can be purged and dried using defrost gas.
11. Check for foam activity. See steps for foam testing in section 3.1.5.
12. Add antifoam agent as necessary.
13. Check the solution strength.
Once the AGRU and Dehydration Systems are operating on spec, the downstream
units can be prepared for operation. When the downstream equipment (Units 7, 15,
16, 20) are dry, the Scrub Column can be cooled down to -30°C.
When the Scrub Column is ready (cool), the MCHE can be cooled down.
When the MCHE, He drum, N2 drum, and rundown are at or near operating
temperatures, the LNG feed flow can be increased which will increase the flow
through the absorber in the AGRU.
Page 16 of 27 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-102
OPERATING MANUAL VOLUME I, SECTION 2-1: REVISION 5
AGRU & aMDEA STORAGE 16-November-13
As long as the feed gas is low on CO2, the amine circulation rate can be lower than
design. Estimated amine circulation rate is about 200 t/h when feed gas is at
0.2% CO2.
When the feed gas flow is approximately 70% of design (+/- 10%), the feed gas
compressor can be started so that the absorber pressure can be increased from
about 40 barg to the normal pressure of 66 barg.
Depending upon feed stock and weather conditions, continue to increase the overall
LNG production rate up to desired value in increments of 5% every hour. Power
output of the gas turbines for Unit 16 and Unit 20 refrigeration units will most likely be
the limiting factor on LNG production rate.
Page 17 of 27 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-102
OPERATING MANUAL VOLUME I, SECTION 2-1: REVISION 5
AGRU & aMDEA STORAGE 16-November-13
5.0 SHUTDOWN
5.1 Normal Shutdown
Below is a summary of the major steps required for an AGRU Shutdown.
1. In a planned shutdown of the new LNG Train the production rate should
normally be reduced in a controlled manner generally in steps of 10% overall
rate. The LNG plant production minimum turndown rate is approximately 75%.
Even if the plant is shutdown the AGRU section may remain on circulation as
long as pressure can be sustained and necessary utilities remain available.
2. When the Feed Gas Compressor starts to go on total recycle/kickback,
shutdown the Feed Gas Compressor to bring AGRU absorber feed pressure
down to supply pressure (approx. 40 barg).
3. Even without feed gas flow through the AGRU absorber, the liquid amine
circulation should continue for several hours at normal temperatures to ensure
that the rich amine has been converted to lean amine in the regenerator and
completely degassed before cooling and moving to storage.
4. If the shutdown is only for a short duration, the lean amine can remain in the
equipment so that the subsequent restart can be shortened.
5. If the shutdown is going to be longer, the amine should be degassed and then
cooled.
6. Cool down the solvent by turning off the hot oil supply to the reboiler. Reduce
12-TIC-1043 and 12-FIC-1070 to gradually bring the hot oil flow to zero.
7. Pump/drain the aMDEA solvent to the 40% storage tank, 02-MF21, in Unit 02.
8. When tower pressures are no longer required to move amine to storage,
depressure the absorber by using 12-HIC-1005 on the absorber overhead line
to warm flare.
9. Wait for a day or two until the aMDEA solution has trickled off the column
internals and pump any remaining amine to storage.
To enable the columns to be entered and inspected by personnel, the packing has to
be flushed with water. Otherwise, washing with water is not necessary.
Flush/purge with Nitrogen until the flammable gases have been replaced by Nitrogen.
Open the top and bottom manways for ventilation for approximately 2 days. Using an
air mover to exhaust the nitrogen and air from the top manway will speed up this
process.
Drain the bottom sections again. Make sure that the oxygen content inside the vessel
is high enough (same as outside air) to enter without breathing apparatus. Confirm
temperature has dropped to near ambient before entry.
Check for toxic/inert gases such as CO/N2 before entering the columns.
Carry out normal plant inspection, applying standard protection measures.
aMDEA solution is not flammable. Hence, with regard to the aMDEA solvent for hot
work, i.e. welding inside the column, no unusual precautions need to be taken.
Page 18 of 27 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-102
OPERATING MANUAL VOLUME I, SECTION 2-1: REVISION 5
AGRU & aMDEA STORAGE 16-November-13
Page 19 of 27 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-102
OPERATING MANUAL VOLUME I, SECTION 2-1: REVISION 5
AGRU & aMDEA STORAGE 16-November-13
Page 20 of 27 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-102
OPERATING MANUAL VOLUME I, SECTION 2-1: REVISION 5
AGRU & aMDEA STORAGE 16-November-13
Set Pressure
Valve Number Description/Location
(barg)
Page 21 of 27 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-102
OPERATING MANUAL VOLUME I, SECTION 2-1: REVISION 5
AGRU & aMDEA STORAGE 16-November-13
Set Pressure
Valve Number Description/Location
(barg)
Page 22 of 27 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-102
OPERATING MANUAL VOLUME I, SECTION 2-1: REVISION 5
AGRU & aMDEA STORAGE 16-November-13
Description Quantity
Page 23 of 27 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-102
OPERATING MANUAL VOLUME I, SECTION 2-1: REVISION 5
AGRU & aMDEA STORAGE 16-November-13
7.0 ATTACHMENTS
The following attachments are included in this section of the Operating Manual:
7.1 Attachment I: Equipment List
7.2 Attachment II: Utility Consumption
Page 24 of 27 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-102
OPERATING MANUAL VOLUME I, SECTION 2-1: REVISION 5
AGRU & aMDEA STORAGE 16-November-13
Page 25 of 27 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-102
OPERATING MANUAL VOLUME I, SECTION 2-1: REVISION 5
AGRU & aMDEA STORAGE 16-November-13
12-MJ22- Lean Solvent Booster Pump 276 m3/hr rated capacity, each
A/B/C
Page 26 of 27 KBR
NEW LNG TRAIN SKIKDA PROJECT DOCUMENT NO.
SKIKDA, ALGERIA PP-AAA-PP1-102
OPERATING MANUAL VOLUME I, SECTION 2-1: REVISION 5
AGRU & aMDEA STORAGE 16-November-13
Available
Equipment No. Description Motor Load
(kW)
Page 27 of 27 KBR
PP-AAA-PP1-102 AGRU and aMDEA Storage Attachment III
11000
10000
Solvent Flowrate (t/d)
9000
8000
7000
6000
5000
4000
Solvent Flowrate
3000 50% solution 9163
40% solution 4265
0 5000 10000 15000 20000
Page 1 of 2
PP-AAA-PP1-102 AGRU and aMDEA Storage Attachment III
Note 1 - Turndown to 68.8% is the limit for reducing the solvent circulation rate with a 40wt% solvent
and 0.21% CO2
Note 2 - Turndown to 32.4% is the limit for reducing the solvent circulation rate with a 50wt% solvent
and 2.00% CO2
Page 2 of 2