Thilawar LPG Depot

For Cecagold Terminal Co,. Ltd

Myat Mi Ba Company Limited


Myat Mi Ba Company Limited

CONTENT PAGES
1 ENGINEERING EXECUTION..........................................................................................................5
1.1 EVALUATION FEED DESIGN............................................................................................................5
1.2 DETAIL DESIGN............................................................................................................................5
1.3 PROCUREMENT SUPPORT...............................................................................................................6
1.4 CONSTRUCTION SUPPORT..............................................................................................................6
1.5 COMMISSIONING SUPPORT.............................................................................................................6
2 ENGINEERING SCOPE..................................................................................................................7
2.1 PROCESS.....................................................................................................................................8
2.2 PROCESS FACILITY IN TERMINAL.....................................................................................................10
2.2.1 Product Tanks.................................................................................................................10
2.2.2 Pumps.............................................................................................................................11
2.2.3 Truck loading facility......................................................................................................13
2.2.4 Jetty Facility....................................................................................................................14
2.2.5 LPG bottling system........................................................................................................14
2.2.6 Import, Export and recirculation Lines............................................................................14
2.2.7 Plant Air system..............................................................................................................15
2.2.8 Compressor system.........................................................................................................15
2.2.9 Odorizating system.........................................................................................................15
2.3 PLOT PLAN................................................................................................................................15
2.3.1 General Plot Plan............................................................................................................15
2.3.2 Site Preparation and Grading Layout..............................................................................15
2.3.3 Earthwork.......................................................................................................................15
2.3.4 Rainwater.......................................................................................................................16
2.4 MECHANICAL.............................................................................................................................16
2.4.1 Scope of work.................................................................................................................16
2.4.2 Design Factors of tanks / Vessels....................................................................................16
2.5 MATERIALS...............................................................................................................................23
2.5.1 Materials for Tank (with capacity no less than 6000 M.ton)..........................................23
2.5.2 Material for Sphere Tank................................................................................................23
2.5.3 Materials for Sediment Tank..........................................................................................24
2.5.4 Materials for Tank (other else).......................................................................................24
2.5.5 Accessories.....................................................................................................................24
2.6 ARCHITECTURAL.........................................................................................................................25
2.6.1 Scope of work.................................................................................................................25
2.6.2 List of buildings...............................................................................................................25
2.6.3 Design Principle..............................................................................................................26
2.6.4 Structure style and building material..............................................................................27
2.7 STRUCTURAL..............................................................................................................................27
2.7.1 SCOPE OF WORK.............................................................................................................27

2
Myat Mi Ba Company Limited

2.7.2 STURCTURAL STYLE SELECTION......................................................................................28


2.7.3 MATERIAL.......................................................................................................................28
2.7.4 CODE...............................................................................................................................29
2.7.5 Basic Design Data...........................................................................................................30
2.7.6 PROBLEM SPECIFICATION...............................................................................................30
2.8 FIRE PROTECTION SYSTEM & WATER SUPPLY AND DRAINAGE.............................................................30
2.8.1 Codes and Standards......................................................................................................30
2.8.2 Water Source..................................................................................................................31
2.8.3 Firewater Demand..........................................................................................................31
2.8.4 Fire Water Tank..............................................................................................................31
2.8.5 Fire Water Pump.............................................................................................................31
2.8.6 Foam Skid.......................................................................................................................32
2.8.7 Firewater and Foam Network.........................................................................................32
2.8.8 Fire Hydrants..................................................................................................................32
2.8.9 Tank Cooling and Extinguish Equipment.........................................................................33
2.8.10 Firefighting for Pump Shelter and Loading Bays...........................................................33
2.8.11 Fire Extinguisher...........................................................................................................34
2.8.12 Jetty Firefighting System...............................................................................................34
2.8.13 Water Supply System....................................................................................................35
2.8.14 Sanitary Drain System..................................................................................................35
2.8.15 Oily Water System........................................................................................................36
2.9 CONTROL AND INSTRUMENTATION.................................................................................................36
2.9.1 Scope of Work.................................................................................................................36
2.9.2 General...........................................................................................................................37
2.9.3 BPCS (Basic Process Control System)..............................................................................37
2.9.4 IPS (Instrumented Protective System).............................................................................38
2.9.5 Technical Description......................................................................................................39
2.9.6 Local Instruments Selection............................................................................................42
2.9.7 Others.............................................................................................................................43
2.10 ELECTRICAL.............................................................................................................................44
2.10.1 Scope of Work..............................................................................................................44
2.10.2 Power supply and distribution system..........................................................................44
2.10.3 Lighting.........................................................................................................................45
2.10.4 Lighting protection and earthing system......................................................................45
2.10.5 Cable laid......................................................................................................................46
2.11 TELECOMMUNICATION..............................................................................................................46
2.11.1 General.........................................................................................................................46
2.11.2 Closed Circuit Television (CCTV System)........................................................................47
2.11.3 general wiring system..................................................................................................47
2.12 ANTI-CORROSION.....................................................................................................................47
2.12.1 Piping Above Ground....................................................................................................47
2.12.2 PIPING Under Ground...................................................................................................48

3
Myat Mi Ba Company Limited

2.12.3 STORAGE TANKS EXTERNAL COATINGS (Gasoil/gasoline, Jet Fuel, LPG, Fire Water)....48
2.12.4 STORAGE TANKS TANKS BOTTOM UNDERSIDE COATINGS...........................................48
2.12.5 STORAGE TANKS TANKS INSIDE COATINGS..................................................................48
2.13 AIR CONDITIONING &VENTILATION..............................................................................................49
2.13.1 Air conditioning System................................................................................................49
2.13.2 Ventilation System........................................................................................................49
3 STANDARDS AND RULES..........................................................................................................51
4 ENGINEERING DELIVERABLES...................................................................................................56
4.1 DETAIL DRAWINGS......................................................................................................................56
4.2 SPECIFICATIONS, DATA SHEETS......................................................................................................63
4.3 STUDY REPORTS.........................................................................................................................66
4.4 SOFTWARE................................................................................................................................67
4.5 PLAN AND PROCEDURES FOR REVIEW AND APPROVAL DOCUMENTATION..............................................69

4
Myat Mi Ba Company Limited

1 Engineering Execution

MMB will perform the detailed EPC of this PROJECT under Employer‘s
direction at the Headquater Office in Yangon.

1.1 Evaluation FEED Design


After the MOU date MMB will, as part of the contractual Lump Sum Price,
carry out a full review and verification of the Feed documentation presented,
clarify any inconsistencies and obtain any additional Information required to
completely the work. Updating with all data received as a result of the site
visit(s), information from Employer or from other sources, will be MMB’s
responsibility.

MMB will produce a Design Verification Document, check any errors,


omissions or discrepancies.

The Design Verification Document will confirm the hydraulic study and the
performance of the piping (flow rates and in/out pressure).

In order to meet these requirements, the review will include, but not be limited
to, the following:

 Review the P&ID‘s to ensure total consistency between these


documents.
 Review the equipment size/capacity and design margins to insure they
are adequate to meet the requirements.
 Review and confirm all battery limit incoming and outgoing streams to
insure all have been identified.
 Review and confirm the mechanical design conditions of the equipment
and piping systems to ensure they meet the necessary requirements.
 Review all material oi constructions to confirm correct selection with
reference to operating conditions and the process materials being
handled.

1.2 Detail Design


MMB will be responsible for the design and engineering within the defined
contract. All works performed will be in accordance with the engineering
specification, data, addenda drawing, and all other applicable document
contained within the contractor.

5
Myat Mi Ba Company Limited

MMB will supply sufficient qualified engineering personnel to the project


taskforce and maintaining the quality of engineering and design work.
Engineering work mainly includes development of engineering plans,
manuals, detailed schedules, preparing technical documents and drawings,
issuing approved documents and drawings for construction and providing site
support and services, editing training programs, conducting the training for the
Employer’s personnel, compiling the commissioning and start-up schemes
and plans, as well as carrying out these activities.

Scope of works for detail engineering will be carried out by MMB within the
specification, codes, standards and criteria as stated in the Tender & Contract
Specifications and will be performed in line with good engineering practice.

MMB will provide all necessary design and engineering service and facilities
to perform the work, including the following engineering disciplines.

 Process & piping;


 Plot Plan, Structural and Architectural;
 Water Supply and Drainage & Fire Protection System;
 Power Electrical;
 Control and Instrumentation;
 Telecommunication;
 Coating & Painting;
 Air conditioning & Ventilation;
 Mechanical;

1.3 Procurement Support


Engineering Department will maintain personnel in the Home Office to prepare
the relevant procurement documents such as Engineering Requisition
documents, participate the technical negotiation, review the Vendor's
technical documents and its qualification, and participate the factory test and
ex—factory inspection, etc.

1.4 Construction Support


Engineering Department will assign engineers with rich construction
experiences to provide support such as the construction methods,
procedures, and field installation alternatives, etc.

1.5 Commissioning Support


Engineers will provide support to the Commissioning and Start-up, together
with construction personnel, vendor’s representatives, solving the technical
problems that may arise during the Commissioning and Start-up.

6
Myat Mi Ba Company Limited

2 Engineering Scope

The Design and Engineering works shall be performed In accordance with


Employer's specifications, industry international standards and codes from
recognized organizations such as API, ASCI, ASTM, BS and ISO and local
authority’s requirement.

The Employer's specifications are the preferred codes. If the local authority’s
laws and regulations are more stringent then the Employer‘s specifications,
the former shall take precedence. Where a conflict between specifications,
codes and local authority's regulations occur, the matter shall be referred to
the Employer's Engineer for ruling.

All drawings are to be completed in accordance with Employer/Employer's


Engineer requirements. All drawings are to be revised to reflect actual “As
Built“ upon project completion. Full quality records and documentations for
the design calculations and drawings are to be maintained for all phases of
the project and collated in a project quality file.

The Contractor shall be responsible for the provision of all engineering, design
and construction services necessary to complete the project in conformity with
the requirements indicated within this Scope of Work. The general
requirement will include but not be limited to:

Verification of provided design data : Contractor shall, by site visit(s) and


otherwise, familiarize himself with existing facilities, field operation and site
details, verify the design data presented to him, clarify any inconsistencies
and obtain any additional information he may require to complete his work;
and check, correct and supplement any existing drawings required as a basis
for his work. Updating of all received data as a result of site visit, information
received from Employer etc. shall be the responsibility of the Contractor.
Performance of any additional studies or calculations required to further define
equipment or system requirements, or to demonstrate the adequacy of the
proposed design.

Preparation and updating on a regular basis of all drawings, specifications,


requisitions and another documents required for the purchase, fabrication,
testing and installation of all equipment, materials and facilities defined herein.

7
Myat Mi Ba Company Limited

Provision of procurement, expediting and inspection services for all equipment


and materials.

The Topographic Survey and Soil investigation Reports included in this


contract are for reference only. Any additional surface and subsurface
investigation required to be carried out for detail engineering shall be part of
Contractor's scope. Any modification or additional work resulted from the
surface and subsurface investigation shall be within Contractor's lump sum
cost.

Contractor shall carry out all necessary modification or additional works


required based on the results of engineering study by Contractor or by
Consultant employed by Employer. All cost for modification or additional
works should be included in the lump sum price submitted.

The below works will not be included:

 The Jetty
 The trestle
 The process piping and equipment on Jetty
 The Jetty firefighting system, The Jetty water supply and The Jetty oily
water
 The instrument and Electrical works on Jetty aha trestle

2.1 Process
 Scope of works:

The Construction of Myanmar Liquid Petroleum Gas Terminal & Storage


Project is located in Thilawa Special Economic Zone. It will be built to import
LPG by ship, store product and recycle the product from tank to tank. The
terminal shall use the oil jetty to export to Truck loading.

The process diagram shall contain:

 LPG barge unloading:

LPG MLH —> LPG pipeline (from jelly to terminal) —> LPG tanks

LPG tanks —> LPG vapour pipeline (terminal to jetty) —> LPG vapour MLH.

LPG which come from vessels or barges will be connected with LPG marine
loading hose and LPG vapour marine loading hose at first. And then
transmitted LPG with pipeline from jetty to terminal by ship pump. Meanwhile,

8
Myat Mi Ba Company Limited

the LPG vapour in LPG tanks will be transmitted to barges by compressors. At


last receive the LPG into tanks.

 LPG truck loading:

LPG tanks —> Truck loading pumps —> Truck loading arm

Loading process will be monitored and controlled by flow meters.

2.2 Process facility in terminal


The process facility of Myanmar Liquid Petroleum Gas Terminal & Storage
Project will consist of:

2.2.1 Product Tanks


 Tanks for LPG:

The products tanks arrangement shall be in accordance with:

4 X 3,300 M3 LPG storage tanks (Bullet);

Maximum tank filling rate for LPG tank farm is 500m3/hr.

Maximum tank emptying rate for tanks in LPG tank farm is 200m 3/hr.

2.2.2 Pumps
 Details of the Pumps to be provided in LPG pump station are as follows:

Tag No. Service Product Qty Capacity Head Remarks


(m3/hr) (m)
P-501A Truck LPG 1 60 125 Centrifugal
Loading
Pump
P-501B Truck LPG 1 60 125 Centrifugal
Loading
Pump

2.2.3 Truck loading facility


 The detail configuration of truck loading arm is as follows:

Tag No. Nominal Product Qty Capacity Max.Capacity Type


Diameter (m3/hr) of trucks(m3)
TLA-501A/ 3” LPG 2 60 35 Hose
TLA-501B Loading
Loading process will be monitored and controlled by flow meters through
continues monitoring of the volume for products.

9
Myat Mi Ba Company Limited

Truck drivers will be able to pre-set required batch product volumes and to
shut-down the whole system by means of local push buttons.

Loading shut-down should also be initiated automatically by means of various


signals through the overfill protection system.

Loading system will be connected to TMS which monitors the loading volume
and the inventory of the plant.

2.2.4 Jetty Facility


MMB will construct the products pipeline to jetty, process & instrument facility
in jetty, while the construction of jetty is not in the work scope of MMB.

Flow rates will be measuring via the automatic tank gauging (ATG) system, by
the difference of level in product tank.

All product oil will be loaded and unloaded by hose in jetty.

The setting of MLH is as follows:

Tag No. Nominal Product Qt Capacity


Diamete y (m3/hr)
r
MLH-501A 8” LPG 1 500

MLH-501A 4” LPG 1 500


Vapor

2.2.5 LPG bottling system (Optional)


LPG can be loaded from sphere tanks to bottle by LPG bottling pumps. 2(1 is
on duty, the other is standby) bottling pumps are set for 6kg and 12kg
automatic bottling; the capacity of each pump shall be 30m 3/hr, with discharge
pressure 13 barg. 1 sets of loading pumps are set tor 45kg manual bottling,
the capacity of pump shall be 6.5m3/hr, with discharge pressure 10.5 barg

2.2.6 Import, Export and recirculation Lines


Import line can also be used for export.

Import/export line can also be used for recirculation.

2.2.7 Plant Air system


One numbers of 350 m3/hr air compressors with one plant air receiver, one
discharge line filter and two air dryers shall be provided.

10
Myat Mi Ba Company Limited

Each Tank Farm shall be provided with a 2” Plant Air header. The material for
the pipe of plant air system will be carbon steel.

2.2.8 Compressor system


One numbers of 250 Nm3/hr compressors with separator and residual liquid

tank shall be provided

2.2.9 Odorizating system


Provide odorizating system for truck loading and bottling

2.3 Plot Plan


 Plot Plan will include the following:

General Plot Plan, General Layout for Pipeline and Cables / Underground
Service, Site Preparation and Grading Layout. Earthwork Volume Calculation,
Road and Paving Layout, Storm water Drainage System Layout, Typical
Drawing for Bund Wall, Road and Paving etc.

2.3.1 General Plot Plan


The interval between tanks is designed according to NFPA 30. External
reinforced concrete bund wall is designed for tank farm including crossover
stairs. A concrete flooring with 2mm HDPE is adopted for the containment
area of the bund walls.

The road for loading bay area’s material is RCC.

2.3.2 Site Preparation and Grading Layout


The grading and elevations will be consistent with the referenced drawing of
survey in detail design stage. In that stage, soil is moved to create a working
platform.

2.3.3 Earthwork
The work include cutting and filling and leveling up to required FGL level from
suitable cutting material, and removal of debris, trees, shrubs and any other
undesired material from site to suitable place.

2.3.4 Rainwater
The rainwater is accumulated from tank farm will go into the drainage network.

11
Myat Mi Ba Company Limited

There is a valve pit that is controlled by operator, in order to prevent from


discharging oily waste water.

The clean rainwater discharged from the terminal will be led to the Yangon
River.

2.4 Mechanical

2.4.1 Scope of work


The scope of mechanical design in this project mainly includes the
tanks/vessels of the followings.

 3 Nos. — 2,500 m3 LPG Sphere Storage Tank (LPG 501 to LPG 504)
 1 No — 30 x 17.5 x 2.2m depth Fire Water Pond

2.4.2 Design Factors of tanks / Vessels

 3000m3 LPG Bullet Storage Tank

Tank Volume: 3300m3

Tank diameter: 8m

Storage medium: LPG

Design pressure: 1.90 MPa

Design temperature: -400 - 50°C

Weld coefficient: 1.0

Filling coefficient: 0.9

Test pressure: 2.9MPa

Corrosion allowance: 1.5mm

Design Wind Velocity: N/A

Seismic User Group: N/A

Peak Ground Acceleration: N/A

Shell thickness: 37.8 mm

12
Myat Mi Ba Company Limited

Number of supports: 12 (TBC)

Design and const. code: ASME Sec. VIII. Div.2

2.5 Materials

2.5.1 Material for Sphere Tank


Shell: SA 537 Class 1

Nozzles and flanges: SA350

Stiffer Ring: SA 537 Class 1

Anchor Bolt rods: SA-36

2.5.2 Accessories
Accessories consist of:

 Safe Relief Valve for LPG Tank;


 shell manholes, roof manhole, platforms, spiral stairways, vents, inlet
nozzles, outlet nozzles, dip hatches, other shell & roof nozzles etc. as
required.
 Anchorage as per calculation and project requirement

2.6 Architectural

2.6.1 Scope of work


The scope of work for architecture in this project shall include: Guard house,
Office building, pump sheds, truck loading sheds, air compressor building,
compressor workshop, diesel generator shed, transformer substation. All the
buildings and sheds are not included furniture.

The total area of this group of buildings is approximately 4250m 2.

Ite Building Floor Building Size Stories Structure Quantity


m Name Area (Length x Style
Width)
1 Staff 54 9x6 1 Reinforced 1
House Concrete
Frame
Structure

13
Myat Mi Ba Company Limited

2 Office 450 30 x 15 1 Reinforced 1


Building Concrete
Frame
Structure

2.6.2 List of buildings


It Building Floor Building Size Stories Structure Quantity
e Name Area (Length x Style
m Width)

7 Air 77 11 x 7 1 Light Steel 1


Compressor Shed
Building
9 LPG Pump 187.5 15 x 12.5 1 Light Steel 1
Shed Shed
1 LPG Truck 168 21 x 8 1 Light Steel 1
0 Loading Shed
Shed
1 Diesel 270 15 x 18 1 Light Steel 1
1 Generator Shed
Shed
1 Transformer 420 21 x 20 1 Reinforced 1
2 substation concrete with
fire Steel
door
Structure

2.6.3 Design Principle


 General

Develop a complete set of architectural documents, but not be limited to, all
necessary specifications to construct the buildings.

The building will be designed and constructed to house the stair and
equipment safely, economically and functionally. The final design of building
will use the highest standards of professional architectural design to create an
aesthetically pleasing and functional facility,

 Codes and Standards

perform the design and engineering of the facilities in accordance with


international Codes and Standards and engineering practices, as a minimum,
with the following:

14
Myat Mi Ba Company Limited

 Owner specifications and standards provided within tender documents.


 National codes and regulations as listed within these documents.

 Local regulations as applicable.


 International Codes and Standards to terminal and tire fighting system.
Such as API,
 NFPA, ASME, etc.

2.6.4 Structure style and building material

The buildings in general are single storey with reinforced concrete frame
structure or steel structure system.

The general description of constructor, materials used in the protect are as


follow:

Exterior Walls first class bricks having standard size quality, dimensions
tolerances, etc.

Interior Walls: first class bricks having standard size, quality, dimensions,
tolerances, etc.

roof: reinforced concrete slab roofing will be used for the frame structure
buildings, Corrugated GI Sheet (CGI) Roofing or Corrugated Asbestos
Cement (AC) Sheet Roofing will be used for the light steel sheds as specified.

Interior and Exterior wall finish, steel structure and relevant steel items
coating: both interior and exterior walls, false ceiling, steel structure and other
miscellaneous steel items will be painted as specified.

2.7 Structural

15
Myat Mi Ba Company Limited

2.7.1 SCOPE OF WORK


The scope of structural work include: LPG tank foundation, equipment
foundation, pipe sleeper, pipe rack, pit, foundations for lighting pole,
crossover/access platform , etc.

2.7.2 STURCTURAL STYLE SELECTION


The pre-stress high strength concrete (PHC) pile raft type foundations with
ring beam will be recommended to use in the project, diameter of pile is
400mm and the range of pile length is about 30~40m. The material for the
bottom layer of inside the reinforced concrete ring beam for the diesel tank
foundation/ gasoline tank foundation/fire water tank foundation will be
compacted sand or sand mixed gravel. The finial compacted sand depth shall
be verified according the finial top elevation of the tank foundations: the top
layer is 100mm thickness bitumen sand.

LPG tank foundation are 12 independent foundations connected with


apron piece and there are PHC piles under independent foundations.

Office building and substation are reinforcement concrete structure, with PHD
pile foundation. The foundations guard house are concrete independent
foundations.

Steel structure will be recommended to use air compressor room, compressor


room, LPG pump shed, LPG loading bay shed and generator shed. The
foundations are reinforcement concrete foundations.

The pipe sleeper foundation and pit are reinforcement concrete structure.

Foundations of equipment with dynamic load or heavy load are PHC pile
foundation.

The crossover/access platforms, operating platforms and pipe rack are steel
structure

2.7.3 MATERIAL
All concrete shall be mixed concrete & works shall be in accordance with ACI
318M-08 "building code requirements for reinforced concrete". The minimum
concrete strength as determined by 28-days cylinder test to ASTM
C192/C192M, and Grades of Concrete as follows:

16
Myat Mi Ba Company Limited

Types of Minimum Max. size Maximum Minimum Application


concrete or design of water / cementiti
Nominal Cylinder aggregate cement ous ratio
grade of strength (mm) ratio in Kg/m3
concrete (28 days)
in N/mm2**
C40 32 20 0.40 380 General
Foundations,
Substructure,
Anchor blocks
C30 24 20 0.40 380 Beam, Slab,
Colum

C15 12 10 0.50 250 Leveling


concrete

 Reinforcing steel bars for general concrete work shall be high-yield


deformed bars conforming to BSI BS 4449 Grade 460 or ASTM A615
Grade 60.
 Structural steel shall be in accordance with BSI BS EN 10025 Grade
S275 or equivalent or ASTM A992/A992M.

2.7.4 CODE
 Standard Test Methods for Cylindrical Compressive Strength of
Concrete General Requirements for Steel Sheet Metallic-Coated by the
Hot Dip Process ASTM A924)
 Minimum Design Loads for Buildings and other Structures (ASCE 07-10)
 Building Code Requirements for structural Concrete (ACI 318-08)
 Foundations for dynamic equipment (ACI 351.3R-04)
 Building Code Requirements for Masonry Structures (ACI 530-08)
 Standard Specification for Deformed and Plain Carbon-Steel Bars for
 Concrete Reinforcement (ASTM A615)

2.7.5 Basic Design Data


Peak ground acceleration was 0.2 g and earthquake intensity was (7) in
Mercalli

17
Myat Mi Ba Company Limited

(MM) Scale.

2.7.6 PROBLEM SPECIFICATION


 There is no axial load capacity bearing of PHC pile.
 Foundation style may be changed after the detail geological exploration
report arrived.
 Ground treatment may be changed after department reviewed.

2.8 Fire Protection System & Water Supply and Drainage

2.8.1 Codes and Standards


The fire protection systems and equipment shall be designed in accordance
with the applicable codes and standards.

NFPA 10 Standard for Portable Fire Extinguishers

NFPA 11 Standard for Low-, Medium-, and High-Expansion Foam

NFPA 15 Standard for Water Spray Fixed Systems for Fire Protection

NFPA 20 Standard for the Installation or Stationary Pumps for Fire Protection

NFPA 22 Standard for Water Tanks for Private Fire Protection

NFPA 24 Standard for the Installation of Private Fire Service Mains and Their
Appurtenances

NFPA 30 Flammable and Combustible Liquids code

API RP2030 Application of Water Spray Systems for Fire Protection in the
Petroleum Industry

API 2510 Design and Construction of LPG Installations

2.8.2 Water Source


According to the fire-water demand, the supposed flow rate for fire water
refilling is not less than 200m3/h, the refilling water source is depended on
the municipal water supply system nearby, and the deep bore well water
supply system in the Terminal will be the backup

18
Myat Mi Ba Company Limited

2.8.3 Firewater Demand


It is supposed that there only one fire in the same time in the Terminal.

According API 2510 and API 2030, the whole surface area of the burning LPG
Sphere tank will be cooling with the application rate 10.2 L/min.m 2 and 4 hours
control time. The biggest volume of the firewater is occurred in the LPG-502
burning, in this situation, the whole LPG Sphere shell of VS-502 need to be
cooling and half of the each adjacent tank's area or VS-501 need to be
cooling.

2.8.4 Fire Water Tank


There will be built 1 No. of new fire water tank with the net volume of 6000
cubic meter.

2.8.5 Fire Water Pump


Based on the calculation, there will install 3 No. (2 working and 1 standby)

Diesel Engine Driven Firewater Pumps, with the capacity of 2000 GPM @
1.2MPa. The firewater pump should be UL / FM approved.

* Detail calculation will be given to confirm require flow rate for the pump

There will install 1 No of Motor Driven Jockey Pumps with capacity 60


m3/hr@1.2MPa

2.8.6 Firewater Network


The firewater piping will be around the dike area, loading area and down
loading area. Piping shall be aboveground installing, when crossing the road.

The aboveground firewater piping shall be carbon steel with external epoxy
coating.

The block valve shall be UL/ FM Approved butterfly valve with post indictor.
There are not more than 5 sets of fire hydrant between two block valves.

All the high point shall be equipped with vent valve, and the low point shall be
equipped with drain valve.

19
Myat Mi Ba Company Limited

2.8.7 Fire Hydrants


The fire hydrants will be installed on the firewater pipe network, and the
distance between fire hydrants shall not exceed 60 meters The fire hydrant
shall have two (2) 2 1/2” (65mm) valves NH thread couplings and one (1)4”
NH valve pumper connection. All two outlets are to be fitted with a cap and
retaining chain.

The hose boxes (cabinets) shall be located near to the tire hydrant and be self
standing type, and the material of the boxes shall be steel with red color.

-2 off 30 meter lengths of 65 mm hose with 65 mm NH couplings

-2 off adjustable nozzle with inlet NH coupling

- 2 on universal coupling spanners

The hose shall be for three-layer type, first layer shall be synthetic (nitrile)
rubber hose, second layer shall be Jacket which made from woven fiber, third
(outside) layer shall be synthetic (nitrile) rubber cobber. It shall be red in
Color.

2.8.8 Tank Cooling and Extinguish Equipment

The oil tank shell and the root shall be equipped with the firewater cooling
system. The UL/FM Approved open type spray nozzle shall be installed on
the firewater cooling ring pipe. And the control valve for firewater cooling
piping will using the UL / FM Approved deluge valve, the deluge valve shall be
equipped with solenoid valve to open / close the deluge valve from the control
room.

The UL / FM Approved foam chamber will installed at the top of the oil tank
shell to extinguish the tank tire. The control valve for the foam solution piping
will be the motor driven butterfly valve to open / close the deluge valve from
the control room.

The LPG tank shall be equipped with firewater cooling ring pipe, and the UL /
FM Approved open type spray nozzle shall be installed. The control valve will

20
Myat Mi Ba Company Limited

be UL / FM Approved deluge valve which equipped with solenoid valve to


open / close the deluge valve from the control room.

2.8.9 Firefighting for Pump Shelter and Loading Bays

The foam and firewater spray system will be installed for the oil pump shelter
and the oil loading bays.

The firewater spray system will be installed for the LPG pump shelter, LPG
loading bays and LPG Cylinder Filling Area.

The UL / FM Approved deluge valve will be used control firewater system and
the motor driven butterfly valve will be used control foam system.

2.8.10 Fire Extinguisher

Portable 5 kg CO2 chemical fire extinguishers shall be located inside the


builds, pump shelters, loading bays and etc.

Portable 5 kg CO2 fire extinguishers shall be located inside the substations,


control room, instrument room and etc.

Portable 5kg CO2 chemical fire extinguishers shall be located at process


equipment area

2.8.11 Jetty Firefighting System

There may be install 2 Nos. of monitor tower with fire water monitors located
on the two sides of the jetty. Each of the monitor towers will be double
platforms, the lower platform will install the fire water monitor and the upper

21
Myat Mi Ba Company Limited

platform will install the foam monitor. The flow rate of the monitor shall be
100L/S@ 7Bar.

The fire hydrants and the fire extinguisher will be the supplement equipment
for the fire fighting equipment.

If the tanker or the jetty loading and unloading facilities catching a biggest fire,
the 2 No. of firewater monitors will used to extinguishing the fire.

2.8.12 Water Supply System

The water source will be the municipal water supply system nearby, and the
deep bore well water supply system In the Terminal will be the backup water
source.

The water supply system including municipal water supply pipe, and deep
bore well with pumps, hydrocyclone desander, potable water tank, water
pumps, UV Disinfector and so on.

The water source for the tank farm is introduced from municipal water supply
system or deep bore well by pump (200m3/hr), then goes through the
hydrocyclone desander to remove large particles, And then, one part will go to
refilling the firewater tank, another part will go to the portable water system
and stored in the potable water tank, then the portable water pump will
pumping to control building, guard house, and other consumption points.

There will be install some emergency eyewash and showers in the product
pump shelter, LPG pump shelter, loading bays and etc.

2.8.13 Sanitary Drain System

22
Myat Mi Ba Company Limited

The sanitary sewer system is a closed system designed to collect all sanitary
waste from washbasin, water closet, urinal, shower and etc. in the building in
the terminal.

The sanitary waste water will collect via gravity through the underground
manhole, chambers, piping and transferred to the septic tank for pretreatment.
After the septic tank, the sanitary water will go to the small sanitary sewage
treatment package located near the building. The treated water will discharge
to sea by the rain ditch.

2.8.14 Oily Water System

The oily water system is mainly including oily water catch basins, manholes,
valve pits, underground piping, oily water collection pit, CPI oily water
treatment package, low grade oil tank and etc.

The oily water system is to deal with the potential oil contaminated water,
such as the rain water from the oil tank farm, ground flushing water from the
product pump shelter, loading bays, flushing water from the oil tank, etc.

The initial 10 minutes for the potential oil contaminated rain water in the oil
tank farm will be collected to the CPI oily water treatment package to separate
the oil and the water by gravity. After separating, the oily water is divided into
water and oil. The water will be discharged into the sea with uncontaminated
water. The oil will be collected to the low grade oil tank and transferred to the
nearby for treat.

2.9 Control and Instrumentation

2.9.1 Scope of Work

Scope will include supply of all instruments, equipment and accessories,


preparation of detailed engineering drawings, installation, inspection, testing,
pre-commissioning and commissioning of all systems:

23
Myat Mi Ba Company Limited

 BPCS (Basic Process Control System)


 (IPS) Instrumented Protective System
 Fire Alarm System
 Local Area Network for communication
 Auto Tank Gauging System
 Tank Overfill Protection
 Jetty and Gantry Loading Metering System
 Local Instruments include temperature, pressure, flow, level instruments
etc.
 Junction Boxes, cable trays etc.
 Power. control, earthing and data cables including accessories
 Installation accessories
 Communicate with the third parties
 Weight bridge system

2.9.2 General

The Terminal Automation control System provides monitoring and control of


the terminal from the control room situated inside facility office building. All
systems are computers based on Visual display unit for Terminal Operator /
Engineer interface.

 Monitor and control of Field instrumentation.


 Monitor and control of bitumen and HFO transfer pumps.
 Interfacing Tank-gauging System and data acquisition.
 Monitor and communication with batch controller

The management and control system has three levels:

Level 0: Field instrument and local control

Level 1: PLC and remote control

Level 2: computer control and management system

The management and control system will achieve the function as following:

 Tank inventory management


 Loading management
 Process control
 Fire and safety management

24
Myat Mi Ba Company Limited

2.9.3 BPCS (Basic Process Control System)


The main control PLC (dual redundant) will carry out all data acquisition and
process, analysis management and display in the terminal. BPCS is
composed of following several parts:

 Operator workstation
 Engineering station
 Marshalling Panel, Power supply
 Licensed software, Licensed Key, Network Connectors
 Main control PLC
 Others

The main functions of the control system are to control all dedicated
equipment in such a proper and safe operation. In addition the Control System
shall communicate with loading batch controller, Tank Gauging System, fire
alarm system and other third parties.

2.9.4 IPS (Instrumented Protective System)

The PLC of Instrumented Protective System is SIL 2 Compliant and dual


redundant. IPS mainly includes the following devices.

 Operator workstation
 Marshalling Panel, Power supply
 Licensed software, Licensed Key
 Network Connectors
 Others Scope of Work

Scope will include supply or all instruments, equipment and accessories,


preparation of detailed engineering drawings, installation, inspection, testing,
pre-commissioning and commissioning of all systems:

 BPCS (Basic Process Control System)


 (IPS) Instrumented Protective System
 Fire Alarm System
 Local Area Network for communication

25
Myat Mi Ba Company Limited

 Auto Tank Gauging System


 Tank Overfill Protection
 Local Instruments include temperature, pressure, flow, level instruments
etc.
 Junction Boxes, cable trays etc.
 Power. control, earthing and data cables including accessories
 Installation accessories
 Communicate with the third parties

2.9.5 Technical Description

 General

The Terminal Automation control System provides monitoring and control of


the terminal from the control room situated inside facility office building. All
systems are computers based on Visual display unit for Terminal Operator /
Engineer interface.

 Monitor and control of Field instrumentation.


 Monitor and control of bitumen and HFO transfer pumps.
 Interfacing Tank-gauging System and data acquisition.
 Monitor and communication with batch controller

The management and control system has three levels:

Level 0: Field instrument and local control

Level 1: PLC and remote control

Level 2: computer control and management system

The management and control system will achieve the function as following:

 Tank inventory management


 Loading management
 Process control
 Fire and safety management
 Control System
 BPCS (Basic Process Control System)

26
Myat Mi Ba Company Limited

The main control PLC (dual redundant) will carry out all data acquisition and
process, analysis management and display in the terminal. BPCS is
composed of following several parts:

 Operator workstation
 Engineering station
 Marshalling Panel, Power supply
 Licensed software, Licensed Key, Network Connectors
 Main control PLC
 Others

The main functions of the control system are to control all dedicated
equipment in such a proper and safe operation. In addition the Control System
shall communicate with loading batch controller, Tank Gauging System, fire
alarm system and other third parties.

 IPS (Instrumented Protective System)

The PLC of Instrumented Protective System is SIL 2 Compliant and dual


redundant. IPS mainly includes the following devices.

 Operator workstation
 Marshalling Panel, Power supply
 Licensed software, Licensed Key
 Network Connectors
 Others

The signals of tuning fork type level switches in all tanks, explosion proof gas
detectors, emergency shutdown valves and smoke and heat detectors in the
important room such as control room, cabinet room, etc. are uploaded to the
IPS (Instrumented protective System).

 Auto Tank Gauging System

27
Myat Mi Ba Company Limited

Auto Tank Gauging System (ATG) System includes Radar Type Level Gauge.
Remote Display Unit, Pressure transmitter, Temperature sensing probe with
water

bottom sensor, Field Control unit, Tank Management System, Licensed


software, operator workstation etc. The Tank gauges shall provide
measurements of level, destiny and temperature.

The field instruments in tank farm shall be connected to Inventory


Management station of Tank management system (TMS) which ls installed In
the control room.

With the Radar Transmitters the following equipment will be provided for all
tanks:

 Multipoint temperature sensors Pt-100 of length adequate to the height


of the tanks
 High precision Pressure Transmitter, which Is connected directly to the
Radar head, Radar Transmitter will calculate density observed and mass
continuously.
 Water detectors at the bottom of the tanks. These detectors will be
integrated into the temperature sensor
 Local display to install at the base of the tanks for data monitoring of
level temperature and density.

 Batch Controller Metering System

Batch Controller Metering System mainly includes temperature compensation


(RTDs), pressure transmitter, ticket printers and Explosion Proof Batch
Controller. All signals of this system shall be uploaded to the BPCS.

The loading point has the following equipment

 A batch controller.
 A grounding monitor.
 Emergency Stop Pushbutton.
 One metering system composed by flowmeter, and flow control valve.
 One top loading arm and an overfilling level switch on the arm.

One level overfill protection switch shall be set on loading arm for each Day.
When the level switch alarms, the batch controller will make the control value
closed automatically to avoid oil overfilling.

28
Myat Mi Ba Company Limited

Batch controllers shall interface to operation station in control room. Batch


controller is suitable to interface with the following permissive:

 Overfill protection input and interlock


 Ground hog protection input & interlock
 Start & Stop & interlock

 Fire Alarm System

In the important room in the building, such as control room, cabinet room, etc.
smoke and heat detectors will be set. And the alarm information will be sent to
IPS PLC.

2.9.6 Local Instruments Selection

 Principles of selection of Instruments and material

Stability, reliability, high performance / price, meeting the accuracy


requirements, meeting the requirements of circumstance and process are the
principles of selection of instruments.

Instruments, the important factor of the system operation, are the key of
process data acquisition and carrying out commands from computer control
system. So the selected instruments must be able to meet the necessary
accuracy, pressure rate, and temperature and explosion proof requirements.
Generally, instruments with transmitter signal will be electrical instrument.

 Temperature measuring instruments

Bimetallic thermometer is used to display temperature locally Bimetallic


thermometer accuracy will be ±1% full span.

Accuracy of temperature transmitters will be ±0.5% full span. And accuracy of


the temperature transmitters used for custody transfer metering will be ±0.2%
full span.

29
Myat Mi Ba Company Limited

 Pressure instruments

Pressure gauge is used to display pressure locally, the accuracy will be ±1%
full span. And Accuracy of pressure transmitters will be ±0 075% full span.

 Level measurement

The solution for level measurement of liquid fuels is based on the high
precision radar technology level gauging. The installed accuracy will be better
than ± 2 mm.

The solution for level measurement of other tanks adopts servo liquid meter or
other types.

 Turbine flowmeter

The Truck loading system will be metered by Turbine flow meter. The
accuracy will be better than ±0.5%.

The signals of all flow meters and interrelate pressure and temperature
transmitters will upload to BPCS PLC.

 Switch type instruments

Switch type instruments will output dry contact, contact rating will be not less
than 24VDC, 1A. They include tuning fork type level switch.

 Control valve

Control valve will be used to control the pressure, temperature and/or oil flow
in nitrogen cleaning system and fuel loading pipeline.

 Safety Instruments

Safety instruments include Flame Detectors, inflammable gas detector, smoke


and heat detectors and Manual Call Points for manual shutdown and alarm.

30
Myat Mi Ba Company Limited

2.9.7 Others

 Power Supply

An electrical cabinet of voltage stabilized, 24VDC and 220VAC will be


considered. The stabilized voltage will be produced In UPS and will be used to
power instruments, control system and equipments.

 Grounding System

The grounding system Includes safety earth and signal earth, the grounding
system will be designed by electrical department. The resistance of
combination grounding will be according to the requirement but less than 4Ω.

 Cable Laying

The cable will be selected as per the output signals of the instruments and
control equipments. If the output signal is analogue signal, copper core
polyvinyl chloride insulated and sheathed and copper wire braid shielded
control cables will be selected. If the output signal is digital signal, copper core
polyvinyl chloride insulated and sheathed control cables will be selected. If the
signal is communication protocol signal, communication cable will be selected.

2.10 Electrical

2.10.1 Scope of Work

The electrical scope or work includes power supply system, power distribution
system, lighting system, lightning protection, anti-electrostatic and earthing
systems.

External overhead transmission power line, relevant switchgear, protection


and measuring equipment etc. (33kV) is not in the scope of work.

31
Myat Mi Ba Company Limited

2.10.2 Power supply and distribution system

One 33kV power supply will be fed from local power grid. Due to the
unreliability of local power grid, four 0.4kV diesel generator sets shall be
provided. One 500kW generator sets, as standby power source, will be
designed to supply 50% power in case of main power failure. This generator
set will be provided as emergency power source of important.

The UPS system will be provided to ensure the continuity and reliability of
power for important load of control system, instrumentation,
telecommunication and so on. The battery type of UPS is VRLA type and the
required autonomy time is 2 hours.

A substation will be set up in the station. Electrical equipments are indoor


layout, which comprise 33kV switchgear. 2000kVA oil-type transformer, the
integrated automatic protect device, DC power device, low-voltage switchgear
and MCC panel, etc.

One generator sets will be set up in generator shelter

2.10.3 Lighting
The minimum maintained illumination shall be according to the related IEC
standard.

High mast lights and street lights are adopted for the outdoor lighting. The
outdoor lighting shall be controlled by photo-electric cell with manual override
control.

Emergency and accident lighting shall be installed in important area where


hazard is likely to happen if normal lighting system failure, for example:
generator shelter, substation, office building, tank farm areas, control room
and pump station, etc. The emergency lighting fixtures shall be incorporated
with a self-contained battery pack.

Lighting in explosive and fire hazard area shall be according to related


provisions in IEC 60079 (Electrical apparatus for explosive gas atmospheres).

2.10.4 Lighting protection and earthing system

32
Myat Mi Ba Company Limited

Earthing system shall consist of electrical working grounding, equipment


protection grounding, anti-electrostatic grounding of equipment and pipeline,
instrumentation and telecommunication working grounding and protection
grounding, lightning protection grounding system. The earthing system shall
be TN-S system.

The earthing system is designed to form a combination earthing system to


handle the grounding of electrical working, electrical equipment protection,
anti-electrostatic, instrumentation and telecommunication working and
protection, lightning protection. The earthing resistance of earthing system
shall be not more than 40hm.

The earthing network will comprise horizontal earth electrode, vertical earth
electrode and subsidiary branch earthing cable. Horizontal earth electrode
shall be galvanized flat steal. Vertical earth electrode shall be galvanized
angle steel.

2.10.5 Cable laid


Copper core insulated cables shall be used for power distribution. Cables
inside building shall be laid in cable trench or buried laying in steel conduit.
Cables outside building shall be armored and directly buried underground or
installed above ground in hot-dipped galvanized cable ladders or trays.

Copper core insulated wires for lighting circuits in building shall be laid in
flame retardant PVC conduits or steel conduits in the wall or ceiling. Flame
retardant copper core insulated wires for lighting circuit shall be laid in steel
conduits along the wall in explosive and fire hazardous area.

2.11 Telecommunication

2.11.1 General
The document defines the minimum technical requirements for the
telecommunication systems design.

The design of the telecommunication system shall be carried out in


accordance with ITB Telecommunication requirements and international
codes and standards.

33
Myat Mi Ba Company Limited

The CCTV System and general wiring system (network and voice) in
Myanmar Petroleum Terminal & Storage Project (Thilawa) is in the scope of
our work, other area is out the scope of our work.

2.11.2 Closed Circuit Television (CCTV System)


CCTV cameras & monitoring system shall be provided to ensure the safety
and security . CCTV system is deployed at perimeter to cover whole fence
area to prevent intrusion & Also process CCTV to ensure safety in critical area
spares for future expansion will be considered.

The basic architecture shall consist of 1080p IP cameras, video servers,


network switch and video management processor. A server capable of storing
video images of all cameras shall be installed in the telecom cabinet. The
images shall be stored in with capacity sufficient for minimum 14 days
recording.

Heating boxes and sunshades shall be provided wherever required.


Explosion- proof cameras which are used in hazardous area. The cameras
shall be pole mounted . Outdoor equipment shall be IP65 according to IEC
60529 where required.

2.11.3 general wiring system


General wiring system provide the service of network and voice for Office
Building.

2.12 Anti-corrosion

2.12.1 Piping Above Ground


Normal temperature (T ≤ 120°C)

1st Coat Epoxy Zinc Rich 60 microns DFT


2nd Coat Micaceous Iron Oxide 140 microns DFT
Epoxy

34
Myat Mi Ba Company Limited

3rd Coat Aliphatic Polyurethane 60 microns DFT

Total dry film thickness (DFT) 260 microns minimum

2.12.2 PIPING Under Ground


Normal temperature (50°C)

1st Coat Solvent free liquid epoxy 300 microns DFT


Total dry film thickness (DFT) 300 microns minimum

Corrosion Outer tape wrap with min thickness 1mm 55% overlaps.

2.12.3 STORAGE LPG TANKS EXTERNAL COATINGS


Application Surface paint DFT µm/coat
prep
Sa 2 1/2 Primer Epoxy Zinc 60
Temp. up to 100*C Rich
Not insulated Inter coat Epoxy MIO 140
surface intercoat
Top coat Aliphatic 60
Polyurethane

2.13 Air conditioning &Ventilation

2.13.1 Air conditioning System

The office building, duty room will be air conditioned by split Air Conditioning
for continuous running operation to maintain the temperature & humidity
inside shelters at all the time with reference to the changing of outside
weather condition.

The control room and UPS room shall be equipped with one 100% back-up
split AC unit.

35
Myat Mi Ba Company Limited

2.13.2 Ventilation System

Ventilation in occupied spaces shall be provided natural by operable windows,


where possible. Sanitary rooms, showers, locker rooms and other rooms with
smell or humidity sources shall have mechanical exhaust to the outside.
Makeup air for the exhaust shall be provided by door grilles, wall grilles and
operable windows.

Rooms with temperature control by ventilation (no mechanical cooling) shall


have mechanical exhaust with air flow sized according to the space heat gains
and required indoor temperature. Fresh air shall be supplied through the
louvers from the outside.

Rooms with special ventilation requirements like Battery Charging roam, Fire-
Fighting room, Inert Gas Storage room etc. shall be ventilated according to
the specific functional, safety and emergency requirements.

Special attention shall be paid to spaces with explosion risk, All HVAC
equipment for such spaces shall be in explosion proof design.

36
Myat Mi Ba Company Limited

3 Standards and Rules

All design, construction, installation works shall comply and be carried out in
accordance with the latest editions of the relevant Standards, Codes, Rules,
Regulations and Laws. (NOTE: In EPC stage, same standards list below can
be replaced by equivalent international standard after approving by
EMPLOYER),

Standards NO. Standards Name


Process
API Spec.5L Specification for Line Pipe
API std.610 Centrifugal Pumps for Petroleum, Heavy Duty
Chemical, and Gas Industry Services
API 6D API 6D, Specification for Pipeline Valves
API 6FA Specification for fire test for valves
API 607 Testing for valves-fire type-testing requirements
API 598 Valve inspection and testing
API 520 Sizing, Selection, and Installation of Pressure-
Relieving Devices in Refineries
API 521 Pressure-relieving and Depressuring Systems
ASME B16.5 Pipe flange and flange fittings
ASME B16.9 Factory-made wrought buttwelding fillings
ASME B31.3 Process Piping
ANSI/ASME 36.10 Welded and Seamless Wrought Steel Pipe
Mechanical
API 650 Welded tanks for oil storage
API 2000 Venting atmospheric and low-pressure storage
tanks
ASME BPV Code Materials
Section II
ASME BPV Code Rules for construction of pressure vessels
Section VII, Div.1
ASME BPV Code Welding and Brazing Qualifications
Section IX
ASME BPV Code Nondestructive examination
Section V
ASME B 16.5 Pipe Flanges and flanged fittings
Structural
BS 8110 Structural use of concrete

37
Myat Mi Ba Company Limited

EN 206 Concrete
BS 4027 Suflate-resisting Portland cement
EN-197 Specification for Portland cement
UBC Uniform building code
BS 8004 Code of Practice for Foundations
EN 1991-1 Loading for Building
BS 5950 Structural Use or Steelwork in Building
EN 1992 Design of Concrete Structure
BS 5606 Guide to accuracy in building
Air conditioning & Ventilation
ASHRAE American Society of Heating, Refrigeration and Air
Conditioning Engineers
Control and Instrumentation
API MPMS Manual of Petroleum Measurement Standards
ISA 5.1 Instrumentation Symbols & Identification
ISA 5.2 Binary Logic Diagrams for Process Operations
ISA S 18.1 Specifications and Guides for the use of General
Purpose
Annunciators
ISA S 71.01 Environmental Conditions for Process
Measurement and Control Systems
ISA S 71.04 Environmental Conditions for Process
Measurement and Control Systems: Airborne
Contaminants
ISA 84.01 Application of Safety Instrumented System for
Process Industries
ISA 91.01 Identification of Emergency Shutdown System and
Controls that are critical to maintaining safety
ISA RP 55.1 Hardware Testing of Digital Process Computers
ISA 9241/3 Standard for monitor ergonomics
ISO 3511 Process measurement control function and
instrumentation -
symbolic representation.
IEC 60364 Wiring Recommendation for the Electrical and
Electronic Equipment
IEC 61511 Functional Safety of Safety Instrumented Systems
for the
Process Sector
IEC 60529 Ingress Protection

38
Myat Mi Ba Company Limited

IEC 61000 Electromagnetic Compatibility


IEC 61508 Functional Safety of
Electrical/Electronic/Programmable Electronic
Safety Related System
IEC 61131 Programmable Controllers
IEC 801 Part 2 Electromagnetic Compatibility for measurements
and control
IEC 801 Part 3&4 Equipment industrial process

IEC 60079 Code of practice for selection, installation and


maintenance of
Electrical apparatus for use in potentially explosive
atmospheres
API RP 550 Installation for refinery instruments and control
systems
API MPMS 3-1A Standard practice for Manual Gauging or
Petroleum and
Petroleum products in stationary tanks
API MPMS 3-1B Standard Practice for Level Measurement of Liquid
Hydrocarbons in stationary Tanks by Automatic
Tank Gauging
API MPMS 3-3 Standard Practice for Level Measurement of Liquid
Hydrocarbons in stationary Pressurized storage
Tanks by Automatic Tank Gauging
API MPMS 7-4 Static Temperature Determination Using fixed
Automatic Tank Thermometer
DIN V VDE 19250 Fundamental Safety Aspects to be Considered for
Measurement and control Protective Equipment
EN 50081 European Harmonized Generic Standard for
Electro-Magnetic Emissions
EN 50082 European Harmonized Generic Standard for
Electro-Magnetic Immunity
EN 55022 Radio Interference Specification for Limits and
Methods of Measurement or Radio Interference
Characteristics of IT equipment
MIL-HDBK-217D Reliability Predictions of Electronic Equipment
NFPA 70 National Electrical Code
Fire Protection Systems & Water Supply and Drainage
NFPA 10 Portable Fire Extinguishers
NFPA 15 Standard for Water Spray Fixed Systems for Fire
Protection
NFPA 20 Installation of Centrifugal Fire Pumps
NFPA 22 Standard for Water Tanks for Private Fire

39
Myat Mi Ba Company Limited

Protection
NFPA 24 Standard for the Installation of Private Fire
Service Mains and
Their Appurtenances
Electricity
API RP 505 Recommended Practice for Classification of
Locations for Electrical Installations at Petroleum
Facilities classified as Class I, Zone 0. Zone 1,
and Zone 2
API RP 540 Electrical Installation in Petroleum Processing
Plants
IEC 60034 Rotating Electrical Machines
IEC 60076 Power Transformers
IEC 60079 Electrical Apparatus for Explosive Gas
Atmospheres
IEC 60099 Lightning Arresters
IEC 60255 Electrical Relays
IEC 60287 Calculation of the Continuous Current Rating of
Cables

IEC 60364 Low voltage Electrical Installations


IEC 60439 Low Voltage Switchgear and Control gear Assemblies
IEC 60598 Luminaries
IEC 60664 Insulation Co-ordination for Equipment Within Low Voltage
Systems
IEC 60694 Common Specifications for High Voltage Switchgear and
Controlgear Standards

IEC 60726 Dry-Type Transformers


IEC 60909 Short Circuit Calculations in Three Phase A.C. System
IEC 60947 Low Voltage Switchgear and Controlgear
IEC 62271 High Voltage Switchgear and Controlgear
IEC 62305 Protection Against lightning
Anti-corrosion
BS EN ISO Paints & Varnishes — Corrosion protection of steel
12944 structures by protective paint systems

40
Myat Mi Ba Company Limited

ISO 8501- Preparation of steel substrates before application of paints


General and
Title related products
ISO 8502- Preparation of steel substrates before application of paints
General and
Title related products - Tests for the assessment of surface
cleanliness
ISO 8504- Preparation of steel substrates before application of paints
General and
Title related products - Surface preparation methods
Plot Plan
NFPA 30 Flammable and Combustible Liquids Code
BS 6031 Code of practice for earthworks
ASCE 77 Design and Construction of Urban Stormwater Management
Systems
AASHTO Guide for design of pavement structures

41
Myat Mi Ba Company Limited

4 Engineering Deliverables

MMB will carry out our design work strictly according to the Tender & Contract
Specifications. And deliver our detailed design documents in time according to
the stated codes. The planned detailed design documents to deliver are listed
in the following datasheet.

4.1 Detail Drawings


No TITLE
.
Process Flow Diagram for LPG Tank Area
Process Flow Diagram for LPG Pump Station
Process Flow Diagram for LPG Truck Loading Bay
Process Flow Diagram for LPG Bottling system

Piping Plan & Section for Tank LPG-501 Area


Piping Plan & Section for Tank LPG-502 Area
Piping Plan & Section for Tank LPG-503 Area
Piping Plan & Section for Tank LPG-504 Area
Piping Plan for LPG Pump Shelter
Piping Plan for Truck Loading Bay

Piping Plan for Jetty Area


Piping Plan For Air compressor System
Piping Plan For compressor System
Overall Piping Plan
Overall Piping Plan (out of tank farm)
General Plot Plan
General Layout for Pipeline and Cables / Underground Service
Site Preparation and Grading
Layout
Earthwork Volume Calculation

42
Myat Mi Ba Company Limited

Roads and paving layout


Storm water Drainage System Layout
Road and paving Details
Storm water Drainage System Details
Bund Wall Details
Containment Wall Details
Mechanical
Drawings for 3,300 m3 LPG Sphere Storage Tank
Drawings for 6,000 m3 Fire Water Pond
Architectural
The plan, elevation, section drawing for Guard House
The plan, elevation, section drawing for Office Building
The plan, elevation, section drawing for Air Compressor Building
The plan, elevation, section drawing for Compressor Workshop
The plan, elevation, section drawing for Diesel Generator Shed
The plan, elevation, section drawing for Transformer Substation
The plan, elevation, section drawing for Pump Shed
The plan, elevation, section drawing for Truck Loading Shed
Structural
DRAWING FOR AIR COMPRESSOR ROOM
DRAWING FOR COMPRESSOR ROOM
DRAWING FOR LPG PUMP SHED
DRAWING FOR LPG LOADING BAY SHED
DRAWING FOR GENERATOR SHED
DRAWING FOR OFFICE BUILDING
DRAWING FOR GUARD HOUSE
FOUNDATION FOR LPG-501
FOUNDATION FOR LPG-502
FOUNDATION FOR LPG-503
FOUNDATION FOR LPG-504

43
Myat Mi Ba Company Limited

FOUNDATION FOR FIRE WATER TANK


TECHNICAL REQUIEMENTS OF PILES TEST
DRAWING FOR PIPE SUPPORT 0F TANK FARM (1)
DRAWING FOR PIPE SUPPORT 0F TANK FARM (2)
DRAWING FOR FIRE FIGHTING PIPE SUPPORT 0F TANK FARM
(1)
DRAWING FOR FIRE FIGHTING PIPE SUPPORT 0F TANK FARM
(2)
DRAWING FOR PIPE FRAME ON JETTY
DRAWING FOR PIPE SUPPORT OUT 0F TANK FARM (1)
DRAWING FOR PIPE SUPPORT OUT 0F TANK FARM (2)
FOUNDATION FOR STEEL POLE
DRAWING FOR CABLE TRAY SUPPORT OUT OF BUILDINGS
DRAWING FOR STEEL PLATFORM AND LADDER IN TANK
FARM
FOUNDATION FOR STREET LIGHTING
FOUNDATION FOR HIGH-MAST LIGHTING
DRAWING FOR VALVE PIT
DRAWING FOR MANHOLE
Water Supply and Drainage & Fire Protection System
Piping installation for fire water tank
Piping installation for fire water pump room
Piping installation for jetty elevated fire monitor
Piping installation for potable water skid
Piping plan for water supply and drainage network
Piping plan for oily water network
Piping plan for firefighting system
Fire extinguisher arrangement
Firefighting installation for product pump shelter
Firefighting installation for product pump loading bay
Firefighting installation for LPG pump shelter
Firefighting installation for LPG loading bay

44
Myat Mi Ba Company Limited

Firefighting installation for LPG-501


Firefighting installation for LPG-502
Firefighting installation for LPG-503
Firefighting installation for LPG-504
Water supply and drainage for office building
Water supply and drainage for office guard house
Control and Instrumentation
Instrument & Automation Legends and Symbols
System configuration diagram
Process and instrument diagram
Firefighting process and instrument diagram
Tank Area cable laying drawing
Pump Shelter cable laying drawing
Truck Loading Bay cable laying drawing
Instrument installation Diagrams
Wiring diagram
Control Room Layout and cable laying drawing
Fire Alarm System Diagram
Fire Fighting instruments and Cable Layout Drawing
Logic diagram
Cause and effect matrix
I/O list
Equipment list
Material list
Cable list
Electricity
Office Building
Lighting single line diagram for Office Building
Small power single line diagram for Office Building
Lighting plan for Office Building

45
Myat Mi Ba Company Limited

Power and earthing plan for Office Building


Lighting protection layout for Office Building
Guard House
Lighting single line diagram for Guard House
Small power single line diagram for Guard House
Lighting plan for Guard House
Power and earthing plan for Guard House
Lighting protection layout for Guard House
Substation
Main single line diagram for Substation
Lighting single line diagram for Substation
Small power single line diagram for Substation
Equipment layout for Substation
Lighting plan for Substation
Power and earthing plan for Substation
Lighting protection layout for Substation
Generator Shelter
Lighting single line diagram for Generator Shelter
Small power single line diagram for Generator Shelter
Equipment layout for Generator Shelter
Lighting plan for Generator Shelter
Power and earthing plan for Generator Shelter
Lighting protection layout for Generator Shelter
Fire Fighting Pump Station
Lighting single line diagram for Fire Fighting Pump Station
Small power single line diagram for Fire Fighting Pump Station
Pump Station
Lighting single line diagram for Pump Station
Small power single line diagram for Pump Station
Lighting plan for Pump Station

46
Myat Mi Ba Company Limited

Power and earthing plan for Pump Station


Lighting protection layout for Pump Station
Air Compressor Station
Lighting single line diagram for Air Compressor Station
Small power single line diagram for Air Compressor Station
Lighting plan for Air Compressor Station
Power and earthing plan for Air Compressor Station
Lighting protection layout for Air Compressor Station
Overall Plant
Cable layout for overall plant
Earthing layout for overall plant
Air conditioning & Ventilation
Office Building Ventilation and Air-conditioning Plan
Transformer Substation Ventilation and Air-conditioning Plan

4.2 Specifications, Data sheets

No TITLE
.
Specification for Centrifugal Pump
Specification for Gate and Ball and Check Valve
Specification for Truck Loading Arm (Top)
Specification for Marine Loading / Unloading Hose
Specification for Compressor Air System
Specification for Compressor System
Data Sheet for Centrifugal Pump
Data Sheet for Gate Valve
Data Sheet for Ball Valve

47
Myat Mi Ba Company Limited

Data Sheet for Pressure / Thermal Safety Valve


Data Sheet for Marine Loading / Unloading Arm
Data Sheet for Compressor Air System
Data Sheet for Sump oil pump
Data Sheet for Portable pumps
Mechanical
Specification for Storage Tank
Specification for Tank Plate
Specification for Pressure Vessel
Data Sheet for fire extinguisher
Control and Instrumentation
Specification of Pressure Gauge
Specification of Pressure Transmitter
Specification of Temperature Transmitter
Specification of Bimetallic thermometer
Specification of Radar Level Transmitter
Specification of Level switch
Specification of control panel (including electric devices)
Specification of Tank Farm Computer-Based Control System
Specification of Flame and Gas System
Data Sheet of Pressure Gauge
Data Sheet for Tank Plate
Data Sheet for Tank Anti-Corrosion
Water Supply and Drainage & Fire Protection System
Specification for jockey pump
Specification for fire water pump controller
Specification for jetty elevated fire water monitor
Data Sheet for jockey pump
Data Sheet for fire water pump controller
Data Sheet for jetty elevated fire water monitor

48
Myat Mi Ba Company Limited

Data Sheet for fire hydrant


Data Sheet for fire water monitor
Data Sheet for firefighting valve
Data Sheet of Pressure Transmitter

Data Sheet of Temperature Transmitter


Data Sheet of Bimetallic thermometer
Data Sheet of Radar Level Transmitter
Data Sheet of Level switch
Data Sheet of control panel (including electric devices)
Data Sheet of Tank Farm Computer-Based Control System
Data Sheet of Flame and Gas System
Electricity
Specification for Low Voltage Switchgear and MCC
Specification for High Voltage Switchgear and MCC
Specification for Generator
Specification for Transformer
Specification for Integrated Automatic Protect System
Specification for AC UPS
Specification for DC Power Device
Specification for Power and Control Cable
Data Sheet for Low Voltage Switchgear and MCC
Data Sheet for High Voltage Switchgear and MCC
Data Sheet for Generator
Data Sheet for Transformer
Data Sheet for Integrated Automatic Protect System
Data Sheet for AC UPS
Data Sheet for DC Power Device
Data Sheet for Power and Control Cable
Anti-corrosion
Specification for painting and coating

49
Myat Mi Ba Company Limited

4.3 Study Reports

No TITLE
Calculation for Pumps Sizing
Calculation for Pressure / Thermal Relief Valves
Calculation for Pipe Size
Calculation for Pipe Wall Thickness
Report of Basic Design
Stress Analysis Report for Tank Area
Stress Analysis Report for Pump Station
Process Operation Principle
CALCULATION FOR PILE
CALCULATION OF FOUNDATION FOR LPG-501
CALCULATION OF FOUNDATION FOR LPG-502
CALCULATION OF FOUNDATION FOR LPG-503
CALCULATION OF FOUNDATION FOR LPG-504
CALCULATION OF OFFICE BUILDING
CALCULATION OF COMPRESSOR ROOM
CALCULATION OF GENERATOR SHED
CALCULATION OF LPG PUMP SHED
CALCULATION OF PIPE SUPPORT OUT 0F TANK FARM
Calculation report for 3,300 m3 LPG Bullet Storage Tank
Calculation report for fire fighting system

4.4 Software
The system/software which the CONTRACTOR proposes to use for detailed
design, CAD is as the following table.

No Item Software
A Engineering Software

50
Myat Mi Ba Company Limited

1 Process
2 Process
3 Structure
4 Mechanical

5 Mechanical
6 Electricity
7 Instrumentation and
Control
B Drafting Software
1 Process AutoCAD Ver 2010 Office 2007
2 Mechanical AutoCAD Ver 2010 Office 2007
3 Civil AutoCAD Ver 2010 Office 2007
4 Electricity AutoCAD Ver 2010 Office 2007
5 Instrumentation and AutoCAD Ver 2010 Office 2007
Control
6 Water Engineering AutoCAD Ver 2010 Office 2007
7 Telecommunication AutoCAD Ver 2010 Office 2007
8 Plot Plan and Piping AutoCAD Ver 2010 Plant Office 2007
Design
System Ver 6.3
9 Cathodic Protection AutoCAD Ver 2010 Office 2007
10 Air-conditioning & AutoCAD Ver 2010 Office 2007
Ventilation
C Management Software
1 Photoshop Ver 6.0 Office 2007

The short description for professional system/software of the abovementioned


system/software is as followings.

4.5 Plan and Procedures for Review and Approval


Documentation

Before the official submission of drawings, and documents such as


specifications, datasheets, project documents and vendor documents, etc. the
aforementioned drawings and documents will he internally checked, reviewed

51
Myat Mi Ba Company Limited

and approved in accordance with the MMB’s internal quality control and
administration system and will be signed by related designer, checker and
approver. The drawings and documents will be in the Employer required
numbering system, size and format. The drawings and documents will be
submitted to Employer for comments as per the MMB’s document
management system which is in accordance with Employer’s document
management requirements. MMB will submit the documents within certain
working days which required by the tender & contract specifications.

MMB hereby suggest it is better for the Employer to assign operation director
and design specialists to work together with MMB in MMB office so as to
shorten design documentation submittal and approval time. And the submitted
design documents shall be returned by the Employer within five (5) days upon
receipt time of the same.

52