Wilmont's Pharmacy Gantt Chart
Wilmont's Pharmacy Gantt Chart
WORK
WBS TASK LEAD START END DURATION % DONE S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
DAYS
1 Initiating
1.1 Development of scope & Plan - 40 100% 0
1.2 Engage Stakeholders - 5 60% 0
1.3 Create WBS - 4 100% 0
1.4 Contract - 4 75% 0
2 Planning
2.1 Project Team - 10 100%
2.2 Cost Estimation / Project Plan - 10 90% 0
2.3 Approvals - 2 50% 0
3 Construction
3.1 Kick Off Meeting - 4 100% 0
3.2 Validate User Requirement - 3 10% 0
3.3 Programming System Design - 3 10% 0
3.4 Programming Interface Design - 6 10% 0
3.5 Project Status Report - 2 20% 0
3.6 Interface Flight Operation 10 20%
3.7 Interface Online Order Entry 10 20%
3.8 Interface communications 10 20%
3.9 Information Security 15 20%
3.10 Hardware/Software System Integration 20 20%
4 Testing
4.1 Software Testing 4 20%
4.2 Order Entry Log 2 30%
4.3 Delivery Confirmation Log 3 40%
4.4 System Integration Log 2 10%
4.5 Project Status Report 2 40%
5 User Training
5.1 Verify User Requirements 2 5%
5.2 Establish end user communication 3 5%
5.3 User Manual 3 5%
5.4 Final User Training 6 0%
5.5 Project Status Report 2 0%
5.6 Initiate First Flight 1 0%
6 Close Out