Professional Documents
Culture Documents
Sippican Case Review
Sippican Case Review
Inferences
1. Based of the profitability analysis, Valves have the highest GPM with 41%, followed by Pumps with a GPM of 18%. Flow con
2. Comparing the GPM and the CPM for the product mix, it is overserved that both flow meters and pumps incurr heavy overh
3. It can be observed from the resource utilization table, that machines are utilised to only 75%, and receving and production i
At present scenario, Sippican can achieve its production with 47 machines. They should consider to decrease the no of machin
4. With 10% increase in the Selling Price of Flow Controllers there weren't and affect in the demand. This may be due to the in
Sippican should consider to increase the selling price of flow controllers to $152 (for 35% GPM), or at least to $99 to stay at br
5. The flow controllers incurr 67% of the total engineers expense.
Sippican should consider to reduce the number of its engineers working with flow controllers.
They should also consider to incentivise the orders of flow controllers. Customers ordering with larger lot or shipment size can
As this will reduce the OH costs for FCs, as larger order size means lower setup times and aslo fewer shipment packages.
6. The Flow Controllers are incurring almost 2.5 times of setup time than the machine run time.
Sippican should consider to run the production for Flow controllers for longer duration.
This will reduce the setup costs for flow controllers and increase profitability.
FC Valves Pumps FC
$35,871 33.5% 55.8% 10.7%
$92,912 2.9% 17.6% 79.4%
$10,174 5.8% 29.0% 65.2%
$52,000 6.7% 26.7% 66.7%
$64,235 11.8% 29.4% 58.8%
$255,192
$64
mps with a GPM of 18%. Flow controllers have a negative GPM of -4%.
ers and pumps incurr heavy overhead costs which reduces their profitability by a large margin.
5%, and receving and production is utilised till 83%.
ider to decrease the no of machines, or else increase its production depending on market demand.
emand. This may be due to the intricacies involved in producing flow meters.
M), or at least to $99 to stay at break even for the flow controllers.
FC
$ 35,871
$ 10,174
$ 92,912
$ 64,235
$ 52,000
$ 255,192
$ 64
Valves Pumps
Direct Labor Cost $12.35 $16.25
Direct Material Cost $16 $20
New OH Cost $18 $21
Standard Unit Cost $ 46.35 $ 57.25
Target GPM (%) 0.35 0.35
New Target Selling Price $ 71.31 $ 88.08
Valves Pumps
Direct Labor Cost $12.35 $16.25
Direct Material Cost $16.00 $20.00
Mfg. OH (@185%) $22.85 $30.06
Standard Unit Costs $51.20 $66.31
Target Selling price $78.77 $102.02
Planned Gross Margin (%) 35% 35%
Actual Selling Price $79.00 $70.00
Actual Gross Margin $27.80 $3.69
Actual Gross Margin (%) 35% 5%
1.25 hrs/run
hrs/packa
0.83 ge
0.13 hrs/item
FC
$13
$22
$64
$ 99.00
0.35
$ 152.31
FC
$13.00
$22.00
$24.05
$59.05
$90.85
35%
$95.00
$35.95
38%