Back-Filling Begind Bridge Abutment

You might also like

Download as pdf
Download as pdf
You are on page 1of 1
KCI-Gauff-Chodai-Soosung-LASA JV SASEC II Project Implementation Consultants Head Office: 7, Daerung Technotown 15,401, Simin-daero, Dongangu, Anyang: Gyeonggi-do, Korea Dhaka Office: House No27, Road No.1, Block G, Niketan, Gulshan 1, Dhaka. Bangladesh Tel, 9856598 9856599. ‘Email: galbiolee@amaitcom Our reference: SASEt -2/PICITL/WC-6T012/202007,3 Date: 23 January 2020 To The Contractor's Representative Work Package: 06, 07,08,09,10,11,12 Subject: Baek-filling Behind Bridge Abutment Dear Sir, It is known that vehicular traffic generate undue settlement on finish road behind bridge abutment. To limit this settlement, the embankment fill behind selected backfill material as shown in the abutment drawing, shall be done with sand of FM not less than 0.8 complying clause 2.5.3.6 of the specification. The sand layer below ISG, shall be compacted as per above mentioned clause. To facilitate proper compaction, the sand bed may be around 15m long or as directed by the Engineer. We, therefore, request you to follow above mentioned instruction and then submit a detailed method statement on this matter. Yours sincerely, /SASEC Road Connectivity Project! LEE Sang-Koo Team Leader, PIC SASEC Road Connectivity Project-2 Copy to: 1. The Project Director (ACE, RHD), SASEC Road Connectivity Project-2 2. Additional Project Director-1(SE, BBA),2,3(SE, RHD), SASEC Road Connectivity Project-2 3. Project Manager-2(EE, BBA),3,4,5,6,7,8 (EE, RHD), SASEC Road Connectivity Project-2 4, Resident Engineer-6,7,8,9,10,11,12, PIC Field Office 5. Project Manager, Contractor Representative, Field Office. 6. Office Copy. Ghee {In association with BCL Associates Limited, BETS Consulting Services Ltd, Development Technical Consultants Pvt, Lid. and Phitkoe! International Inc.

You might also like