QSC5-DD

Rotary Screw Air Compressor

Operating Instructions

This manual contains important safety information and should be made available to
all personnel who operate and/or maintain this product. Carefully read this manual
before attempting to operate or perform maintenance on this equipment.

Manual No. 65105-1A

July 2006 Edition


Table of Contents

Section I - General Information


Safety Alert Symbols............................................................................................................1
Safety Precautions................................................................................................................2
Spare Parts Ordering Information........................................................................................3
Serial/Model Identification...................................................................................................3
Standard Warranty................................................................................................................4
Section II - Description
Proper Usage........................................................................................................................5
Qualified Personnel..............................................................................................................5
General Safety Instructions...................................................................................................6
Drive . .................................................................................................................................7
Air Path.................................................................................................................................7
Fluid . .................................................................................................................................7
Cooling.................................................................................................................................7
Flow Diagram.......................................................................................................................8
Section III - Installation
Transporting & Installation Location....................................................................................9
Setup . .................................................................................................................................9
Ventilation..........................................................................................................................10
Connecting to the Compressor..........................................................................................10
Electrical Connections........................................................................................................11
Section IV - Operating Procedures
Prepare for Start-up............................................................................................................12
Check Fluid Level...............................................................................................................12
Start-up Lubrication of the Compressor.............................................................................12
Switch on Compressed Air Generation..............................................................................13
Compressor Operation Checklist.......................................................................................13
Section V - Servicing
Maintenance Schedule.......................................................................................................14
Preparing for Service..........................................................................................................15
Check Fluid Level/Refill Fluid.............................................................................................15
Check for Leaks..................................................................................................................16
Check the Compressor Temperature.................................................................................16
Check for Condensate........................................................................................................16
Check for Cooler Fouling...................................................................................................17
Replace Fluid and Fluid Filter.............................................................................................17
Replace Air/Fluid Separator...............................................................................................18
Replace Air Filter................................................................................................................18
Check Pressure Relief Valve...............................................................................................18
Check Drive Coupling........................................................................................................19
Lubrication of the Electric Motor........................................................................................19
Completing Service............................................................................................................19
Appendix A - Technical Data
Technical Data....................................................................................................................20
Section I - General Information

• Safety Alert Symbols


• Safety Precautions
• Spare Parts Ordering Information
• Serial/Model Identification
• Standard Warranty

Safety Alert Symbols

IMPORTANT!
Throughout this manual we have identified key hazards. The following symbols
identify the level of hazard seriousness:

Danger! Warning!
This symbol identifies immediate This symbol identifies hazards or unsafe
hazards which will result in severe practices which could result in personal
personal injury, death or substantial injury, death or substantial property
property damage. damage.

Danger! Caution!
This symbol identifies life threatening Identifies hazards or unsafe practices
electrical voltage levels which will result which could result in minor personal
in severe personal injury or death. All injury or property damage.
electrical work must be performed by
a qualified electrician.

Notice!
Caution!
Identifies important installation,
This symbol identifies hot surfaces operation or maintenance information
which could result in personal injury or which is not hazard related.
property damage.

Quincy Compressor-QSC-5DD™ 
Section I - General Information

Safety Precautions

Read this manual and follow all instructions • Never assume it is safe to work on the
prior to installing or operating the compressor because it is not operating.
compressor. Many installations have automatic start/
stop controls and the compressor may
This manual contains information required
start at any time.
for safe, trouble free operation of the
Quincy QSC5-DD rotary screw compressor. • This compressor is designed for use in
Damage incurred due to improper usage the compression of normal atmospheric
may not fall under the conditions of air only. No other gases, vapors or
warranty. fumes should be exposed to the
For this reason, please keep this manual compressor intake, nor processed
where all users have free access to it at all through the compressor.
times.
• Relieve all pressure internal to the
The QSC5-DD was developed, compressor prior to servicing. Do not
manufactured, tested, and documented in depend on check valves to hold system
state-of-the-art technology and considering pressure.
all current safety standards.
Under normal circumstances, no danger • A properly sized pressure relief valve
for personnel or property will result if all must be installed in the discharge
stipulations of this manual are complied piping ahead (upstream) of any shutoff
with and if the transport, assembly, service valve (block valve), heat exchanger,
handling is performed according to the orifice or any potential blockage
regulations. point. Failure to install a pressure
relief valve could result in the rupturing
Listed below are some, but not all, safety or explosion of some compressor
precautions that must be observed with component.
compressors and compressed air systems.
• Do not change the pressure setting of
the pressure relief valve, restrict the
function of the pressure relief valve, or
Warning! replace the pressure relief valve with
a plug. Over pressurization of system
Failure to follow any of these precautions or compressor components can occur,
may result in severe personal injury, resulting in death, severe personal
death, property damage and/or injury or property damage.
compressor damage.
• Never use plastic pipe, rubber hose,
or soldered joints in any part of the
• Air from this compressor will cause compressed air system. Failure to
severe injury or death if used for ensure system compatibility with
breathing or food processing. Air compressor piping is dangerous.
used for these processes must
meet OSHA 29 CFR 1910.134 or • Never use a flammable or toxic solvent
FDA21XDE178.3570 regulations. for cleaning the air filter or any parts.

• Disconnect and lockout all power • Do not remove any guards or attempt
supplies to the compressor plus any to service any compressor part while
remote controllers prior to servicing the the compressor is operating.
unit.

 Quincy Compressor-QSC-5DD™
Section I - General Information

• Do not operate the compressor at Notice!


pressures in excess of its rating.

• Observe control panel displays daily These instructions, precautions


to ensure compressor is operating and descriptions cover standard
properly. Quincy manufactured QSC5-DD air
compressors. As a service to our
• Follow all maintenance procedures and customers, we often modify or construct
check all safety devices on schedule. packages to customer specifications.
This manual may not be appropriate
• Never disconnect or tamper with the in those cases.
high air temperature (HAT) sensors.

• Compressed air is dangerous, do not


play with it.
Notice!
• Use the correct fluid at all times. Every effort has been taken to ensure
complete and correct instructions have
• Do not rely on the discharge air line been included in this manual, however,
check valve. possible product updates and changes
may have occurred since this printing.
• Do not override any safety or shutdown Quincy Compressor ® reserves the
devices. right to change specifications without
incurring any obligation for equipment
previously or subsequently sold. Not
responsible for typographical errors.


Spare Parts Ordering Information Serial/Model Identification

Quincy Compressor maintains replacement Reference to the machine MODEL, SERIAL


parts for Quincy compressors and NUMBER and DATE OF ORIGINAL START-
accessories. A repair parts list is shipped UP must be made in all communication
with all new machines. Order parts from relative to parts orders. A model/serial
your Authorized Quincy distributor. Use number decal is located on the reservoir
only genuine Quincy replacement parts. tank.
Failure to do so may void warranty.

Quincy Compressor-QSC-5DD™ 
Section I - General Information

Standard Warranty
QSC5-DD Rotary Screw Air Compressor
Seller warrants products of its own manufacture This warranty shall not apply and Seller shall not
against defects in workmanship and materials be responsible nor liable for:
under normal use and service, as follows: (a) Consequential, collateral or special losses
Packaged Compressors (except airends) or damages;
– Twelve (12) months from date of installation (b) Equipment conditions caused by fair wear
or eighteen (18) months from date of shipment and tear, abnormal conditions of use,
from the factory, whichever occurs first. Package accident, neglect or misuse of equipment,
warranty does not include labor or travel. improper storage or damages resulting
Airends on packaged Compressor – Twenty- from shipment;
four (24) months from date of installation. (c) Deviation from operating instructions,
Limited warranty for thirty-six (36) months, specifications or other special terms of
immediately to proceed expiration of the initial sales;
twenty-four month warranty, to cover airend (d) Labor charges, loss or damage resulting
rotors and airend housing. Airend warranty does from improper operation, maintenance
not include labor or travel. or repairs made by person(s) other than
Seller or Seller’s authorized service
Motors on packaged Compressor – Standard station;
motor warranty is twelve (12) months. Motor (e) Improper application of product.
warranty based on this proposal is for sixty (60)
months from date of installation. Motor warranty In no event shall Seller be liable for any claims,
to cover the motor assembly, pursuant to whether arising from breach of contract or
operational guidelines and terms and conditions warranty claims of negligence or negligent
previously stated in this proposal. Motor manufacture, in excess of the purchase price of
warranty does not include labor or travel. the equipment.

Parts – Ninety (90) days from date of distributor This warranty will be valid only if the user
sale or one (1) year from date of shipment from maintains the compressor package and airend
factory. per the prescribed instructions in this Operating
Instructions manual. Any failure to adhere
With respect to products not manufactured by to the maintenance schedule and/or use of
Seller, Seller will, if practical, pass along the only genuine Quincy replacement parts will
warranty of the original manufacturer. Warranty immediately void the factory warranty. It is
claims associated with the structural integrity of incumbent on the user to provide complete and
the baseplate or collateral damages resulting accurate records of maintenance and verifiable
from the design of the baseplate in the target proof of purchase and use of genuine Quincy
application will not be considered under this compressor repair and replacement parts.
warranty.
Under no circumstances shall Quincy have any
Notice of alleged defect must be given to Seller, liability for liquidated damages or for collateral,
in writing, with all identifying details including consequential or special damages or for loss
serial number, model number, equipment type of profits, or for actual losses or for loss of
and date of purchase, within thirty (30) days production or progress of construction, whether
of discovery of defect during the warranty resulting from delays in delivery or performance,
period. Distributor start-up documentation with breach of warranty, negligent manufacture or
serial number must be provided for warranty otherwise.
consideration.
At the time of shipment of the equipment from
Seller’s sole obligation on this warranty shall the factory, Quincy will comply with the various
be, at its option, to repair, replace or refund the laws and regulations concerning occupational
purchase price of any product or part thereof health and safety and pollution. However, in the
which proves to be defective. If requested by installation and operation of the equipment and
Seller, such product or part thereof must be other matters over which Seller has no control,
promptly returned to Seller, freight collect for Quincy assumes no responsibility for compliance
inspection. with those laws and regulations, whether by the
Seller warrants factory repaired or replaced way of indemnity, warranty or otherwise.
parts of its own manufacture against defects in THIS WARRANTY IS THE SOLE WARRANTY
material and workmanship under normal use and OF SELLER AND ANY OTHER WARRANTIES,
service for ninety (90) days or for the remainder EXPRESS, IMPLIED IN LAW OR IMPLIED
of the warranty on the product being repaired, IN FACT, INCLUDING ANY WARRANTIES
whichever is longer. OF MERCHANTABILITY AND FITNESS FOR
PARTICULAR USE, ARE HEREBY SPECIFICALLY
EXCLUDED.

 Quincy Compressor-QSC-5DD™
Section II - Description

• Proper Usage
• Qualified Personnel
• General Safety Instructions
• Drive
• Air Path
• Fluid
• Cooling
• Flow Diagram

Proper Usage

The QSC5-DD is designed exclusively The generated compressed air may


for the generation of compressed air and not be used for human respiration. If
for operation in an environment without the compressed air is to be used for
explosion risk. pharmaceutical or sanitary purposes, or in
Any other utilization is regarded as not in in production plants where it will come into
compliance with the design purpose. direct contact with food, it must undergo
further treatment.
The manufacturer/vendor is not liable for
damage incurred if the QSC5-DD is not
used according to its design purpose.


Qualified Personnel

This manual is directed at qualified • based on many years of activity in


personnel who will transport, install, a comparable field, have the same
operate or service the QSC5-DD. Those state of knowledge as someone with
individuals should read this entire manual, professional training.
paying special attention to the section(s)
relevant to their duties. Activities not described in this manual
must be performed by authorized technical
Qualified personnel are individuals who: personnel.
• upon the basis of their professional
training, knowledge and experience
as well as their understanding of the
Warning!
relevant norms can assess the work
to be performed with regard to all Disregarding the warnings in this manual
possible dangers, or or those affixed to the compressor
can lead to serious personal injury or
property damage.

Quincy Compressor-QSC-5DD™ 
Section II - Description

General Safety Instructions

Notice!
Warning!
Use only factory spare parts and
Retrofitting or modifications on the recommended fluids when servicing
QSC5-DD may reduce its level of safety. the QSC5-DD.
The results could be serious personal, Quincy recommends keeping a set of
material or environmental damage. service parts (parts subject to wear) on
Retrofitting or modifications on the hand to ensure compressor availability.
QSC5-DD with equipment components Contact Quincy customer service for
from third party manufacturers must first assistance with ordering the correct
be approved by the manufacturer. parts.

Danger! Caution!
Unless otherwise instructed, all Damage to the compressor may result
installation, service or repair work in environmental damage.
must be performed on a switched-off,
sufficiently cooled and pressure-free Before initial start-up, the compressor
compressor. The compressor must must be correctly installed according
be secured against being accidentally to Section III.
started during service. Follow all lock-
out, tag-out procedures.
If measuring or testing work is required
Notice!
on the electrical components while
the compressor is in operation, it Dispose of all used or defective
must be performed by a licenced materials properly.
electrician observing all relevant safety This is especially true for components/
regulations. materials containing compressor fluid.
Condensation containing fluid may not
enter the sewage system.
Contact Quincy sales for an appropriate
Caution! fluid/water separator for condensation
processing.
Never direct compressed air streams
towards persons. When working with
compressed air, always wear protective
safety glasses.
Notice!
Compressed air receivers require
regular technical inspections.
Notify the responsible technical
inspection authority of the
commissioning of the compressor.
They will inspect the compressor and
provide a receiver test book.

 Quincy Compressor-QSC-5DD™
Section II - Description

Drive

An electric drive motor drives the


compressor through a flexible drop out
type coupling.


Air Path

In the reservoir, compressed air is compressor through the compressed air


separated 98% from the fluid and the connection.
downstream air/fluid separator removes The inlet valve opens shortly after the
the remaining fluid from the compressed compressor has started up for generating
air. The air then flows via the minimum compressed air. It closes when the
pressure check valve into the compressed compressor changes to off-load operation
air aftercooler and is cooled to 10 to and/or comes to a stop and unloads via
15°C (50 to 59°F) above the ambient the relief valve.
temperature before it leaves the


Fluid

Fluid is circulated through the airend and Fluid leaves the airend with the
has the following functions: compressed air as a hot fluid return
• heat removal of the temperature air mixture. It is separated from the
increase caused by the compression compressed air by an air/fluid separator
process in the separator tank. Once separated, it
flows into the fluid cooler. A temperature
• sealing lubrication of the rotors to each regulator mixes the cooled fluid with the
other and to the housing with a fluid fluid cooler-bypass hot fluid as defined by
film the set point temperature. Finally, a fluid
filter cleans the fluid before it is returned to
• bearing lubrication the airend.
• noise dampening An additional heater can be installed in
the separator tank, if desired, to prevent
condensation damage in cold or damp
compressor environments.

Cooling

The compressed air aftercooler is cooled


by a built-in cooling fan.
The electric motor is always cooled by its
own fan.

Quincy Compressor-QSC-5DD™ 
Section II - Description

Flow Diagram

 Quincy Compressor-QSC-5DD™
Section III - Installation

• Transporting & Installation Location


• Setup
• Ventilation
• Connecting to the Compressor
• Electrical Connections

Transporting & Installation Location

The compressor should be stored in a dry, Always transport the compressor in its
room above 1.7°C (35°F). normal operating orientation in a pressure-
free state. Tilting or laying the compressor
Notice! down is not allowed.
Use a fork-lift truck for transport. For short
Observe all local regulations and
transportation distances, a palette lifting
other requirements pertaining to the
trolley may be used.
professional use of tools, lifting and
transport equipment, as well as the
valid standards and regulations for
accident prevention.


Setup

Install the QSC5-DD in a location with the Space requirements and compressor
following environmental conditions: weights are dependent on the compressor
• maximum height above sea level: type purchased. See Appendix A -
1000 meters (3281 feet) Technical Data for dimensions and weights.
Always maintain the minimal clearance
• ambient temperature: to walls or other objects, so compressor
-5 to 45°C (23 to 113°F) service can be performed without
hindrance.
• ambient conditions: cool, dry, dust free

Warning!
Open flame/fire or welding work in
the vicinity of the compressor are
forbidden.

Quincy Compressor-QSC-5DD™ 
Section III - Installation

Ventilation

Air is used for compression as well as for • The temperature of the cooling air
compressor cooling. must be between -5 and 45°C (23 and
113°F).
The ventilation must fulfill the following
criteria:
• Supply sufficient cooling air amounts as Warning!
defined in Appendix A - Technical Data.
Ensure that the supply air contains no
• Remove exhaust air in order to prevent
dangerous explosive gas mixtures,
heating up the compressor site.
steam, dust or aggressive pollutants.
• The cooling air must be cool, dry and
dust-free.


Connecting to the Compressor

Install a shut-off valve at the input of the


compressed air system. Warning!
Connect the compressor to the
compressed air system with flexible During load switching in the compressed
compressed air hose. Maximum air system, the hose can move suddenly
recommended length of hose: 1.5 meters and with great force. Therefore, the
(5 feet). hose must be adequately anchored or
fixed.

10 Quincy Compressor-QSC-5DD™
Section III - Installation

Electrical Connections

The unit is provided for connection to


The supply cables should be professionally
a three-phase supply system. Properly
installed. Ensure that the installation
dimensioned safety equipment (to protect
cannot endanger individuals or property.
personnel and equipment) must be
Take into account the necessary cable
installed in the power supply lines.
diameters, strain relief, and maximum
All the relevant data for the connections allowed cable lengths.
can be found in Appendix A - Technical
Connect the compressor according to the
Data or on the nameplate of the
circuit diagram provided in the electrical
compressor.
enclosure of the compressor.

Danger! Warning!
Only licenced electricians may connect
Before switching on the generation of
the compressor to the electrical supply
compressed air, initial start-up must be
network.
correctly performed.

Before making connections according to


Test for correct function of all safety
the compressor nameplate, verify that
devices (protective grounding, protective
the available supply network is adequate.
switch, etc.).
Voltage deviations greater than 10% are
not allowed. Lock the electrical enclosure after the
connection work is completed.

Quincy Compressor-QSC-5DD™ 11
Section IV - Operating Procedures

• Prepare for Start-up


• Check Fluid Level
• Start-up Lubrication of the
Compressor
• Switch on Compressed Air
Generation
• Compressor Operation Checklist

Prepare for Start-up Check Fluid Level

1. Ensure that when the main 1. Ensure that escaping fluid can be
compressor switch is switched off, no collected.
inadvertent switching on can occur. 2. Check the fluid level on the sight-
2. Ensure that the compressor glass (compressor fluid should
is correctly connected to the completely fill the sight-glass).
compressed air system and that when Loosen the filling screw. Do not lose
the shut-off valve on the pressure the seal ring. With new compressors,
side is closed, inadvertent opening the fluid level should be at the lower
cannot occur. edge of the filler neck.
3. If required, top off fluid level (see
Section V - Servicing, Check Fluid
Level/Refill Fluid).


Start-up Lubrication of the
Compressor

If the compressor is not operated for an 3. Finally, tighten the filler screw of the
extended period of time, i.e.: between inlet valve.
delivery and start-up or during a company If no extra fluid is available (only fluid of the
shutdown, there may no longer be any same variety may be used), the fluid can be
fluid in the rotor chamber of the airend. taken from the fluid drain.
This fluid is absolutely necessary for
bearing and rotor lubrication in the start-up If the compressor operates only very
phase. irregularly or is shut down weeks on end,
it should run an hour in the off-load mode
1. Before switching on the compressor, once a week in order to avoid corrosion
add approximately 0.2 liter (6.76 oz.) damage caused by standing condensation.
of fluid at the filler screw of the inlet
valve.
2. Rotate the airend by hand in the
correct direction of rotation until the
noticeable resistance dwindles and
the fluid passes through the airend.

12 Quincy Compressor-QSC-5DD™
Section IV - Operating Procedures

Switch on Compressed Air Generation

1. Before switching on the compressor, 3. Switch on the main switch.


ensure that no one can be 4. Ensure that no tools or loose objects
endangered by doing so. are lying on or in the compressor.
2. Carefully open the shut-off The line pressure will slowly rise if the
valve between the compressed compressed air consumption is less than
air connector and the system the quantity delivered by the compressor.
compressed air receiver. The
compressor is now connected to the
system.


Compressor Operation Checklist

Following start-up, perform the following should be between 75 and 100°C


checks to ensure that the compressor is (167 and 212°F); at 100°C (212°F) a
operating properly: warning is issued, at 110°C (230°F)
1. Check all fluid and air piping for the compressor automatically shuts
leaks. down.

2. Check the fluid level of the 4. Re-tighten all electrical connections


compressors at between 10 and 20 after one week.
minutes of operation. If the fluid 5. Perform service according to Section
level is low, top off as defined in V - Servicing, Maintenance Schedule.
Section V - Servicing, Check Fluid 6. Check the standard operation of
Level/Fluid Refill. the functions performed weekly
3. Check the compressor temperature. according to Section V - Servicing,
The compressor temperature Maintenance Schedule.

Quincy Compressor-QSC-5DD™ 13
Section V - Servicing

• Maintenance Schedule
• Preparing for Service
• Check Fluid Level/Refill Fluid
• Check for Leaks
• Check the Compressor Temperature
• Check for Condensate
• Check for Cooler Fouling
• Replace Fluid and Fluid Filter
• Replace Air/Fluid Separator
• Replace Air Filter
• Check Pressure Relief Valve
• Check Drive Coupling
• Lubrication of the Electric Motor
• Completing Service

Maintenance Schedule

After the After the Every 2000


first 100 first 500 operating
See operating operating hours or
Service Activity Page hours hours Once a week once a year

Check fluid level 15 ü ü


Check for leaks 16 ü ü
Check compressor temperature 16 ü ü
Check for condensate 16 ü ü
Check for cooler fouling 17 ü ü
Replace fluid and fluid filter 17 ü ü
Replace air/fluid separator 18 ü
Replace air filter 18 ü
Check pressure relief valve 18 ü
Check drive coupling 19 ü
Lubrication of motor 19 ü
General compressor service n/a ü

14 Quincy Compressor-QSC-5DD™
Section V - Servicing

Preparing for Service

1. Switch off compressed air generation.


Wait until the compressor has Warning!
been switched off after a run-on or
ventilation phase.
Hot surfaces, hot fluid. Ensure that
2. Switch the main compressor switch no one can be burned or scalded.
off and perform lock-out tagout Particularly note dangerous situations
procedure to ensure that it cannot be which can arise from the release of hot
turned on by mistake or intentionally. fluid vapor.
3. Ensure that the pressure side shut-off
valve is closed and cannot be opened
Notice! accidentally or intentionally.
4. Verify that there is no pressure in the
Use Genuine Quincy replacement parts system.
only.
5. Ensure that when working on the
fluid circulation, escaping fluid is
collected.

Check Fluid Level/Refill Fluid

Prepare the compressor for service as 2. Use an appropriate funnel for filling.
outlined above. Fill to the filling rim of the fitting.
Check the fluid level when the compressor
has been shut down for a minimum of 30
minutes to ensure that the fluid has settled
after the running phase.
The fluid level is okay if the sightglass is full
of fluid.
If the sightglass is not full of fluid, top off
the fluid as follows:
1. Unscrew the fluid fill screw (retain the
gasket ring).

Caution! 3. Correctly seat the seal and screw the


fitting screw closed.
Mixing different types of compressor
fluid can cause compressor damage. 4. Perform the steps under Completing
Compressor fluids must not be mixed. Service (page 19) to put the
Use only original fluid. compressor back into service.

Quincy Compressor-QSC-5DD™ 15
Section V - Servicing

Check for Leaks Check the Compressor Temperature

1. Prepare the compressor for service as The compressor temperature should be


outlined on page 15. between 75°C and 100°C (167 and 212°F).
2. Check all piping and the bottom
of the compressor for fluid rests. If Caution!
there is still fluid in the compressor,
the cause should be found and the Too high or too low compressor
fluid removed. temperature can cause compressor
3. Perform the steps under Completing damage.
Service (page 19) to put the
compressor back into service.


Check for Condensate

The absorption capacity of water humidity Since water is heavier than compressor
in the air falls with increasing pressure and fluid, after an extended shutdown (i.e.:
rises with increasing temperature. over the weekend) the condensate collects
Sufficiently high compressor temperature in the bottom of the separator tank. It can
guarantees that the intake air humidity be drained off by the discharge drain.
does not precipitate as condensation. Perform the following service only when
Frequent switching on and off of the the compressor has been turned off at
compressor can result in the compressor least overnight.
not achieving the required operating 1. Prepare the compressor for service as
temperature. outlined on page 15.
2. Open the drain and carefully observe
Caution! the escaping liquid. Close the drain
again as soon as fluid appears.
Condensation in the compressor fluid 3. Check the fluid level as instructed on
can cause compressor damage. If you page 15.
determine that there is condensation
in the separator tank, contact Quincy 4. Perform the steps under Completing
service immediately. Service (page 19) to put the
compressor back into service.
Condensation damages are not covered
by the warranty.

16 Quincy Compressor-QSC-5DD™
Section V - Servicing

Check for Cooler Fouling

1. Prepare the compressor for service as blowing it out using compressed air
outlined on page 15. (the dirt particles should be blown
outside).
2. Check the fluid cooler and the
aftercooler from the inside and 3. Perform the steps under Completing
outside. If you determine there is Service (page 19) to put the
any fouling, it can be removed by compressor back into service.


Replace Fluid and Fluid Filter

Replace the fluid only when the old fluid is


still warm. Cold fluid, because of its higher Caution!
viscosity, does not flow as well.
Mixing different types of compressor
Warning! fluid can cause compressor damage.
Compressor fluids must not be mixed.
Hot surfaces, hot fluid. Ensure, that Use only original fluid.
no one can be burned or scalded.
Particularly note dangerous situations
4. Use an appropriate funnel for filling.
which can arise from the release of hot
Fill to the filling rim of the fitting.
fluid steam.
5. Verify that the seal is correctly seated
and screw the fitting screw closed.
1. Prepare the compressor for service as
6. Loosen the fluid filter with a strap
outlined on page 15.
wrench and remove possible seal
2. Unscrew the filler screw (don’t rests from the fluid filter housing.
misplace the gasket ring).
7. Lightly oil the new fluid filter seal.
3. Open the fluid drain, allow the fluid
8. Screw the new fluid filter to the stop
to drain into an appropriate vessel
and tighten another half revolution by
and close the drain.
hand.
9. Test the fluid filter for leakage at
operating temperature.
10. Perform the steps under Completing
Service (page 19) to put the
compressor back into service.

Quincy Compressor-QSC-5DD™ 17
Section V - Servicing

Replace Air/Fluid Separator

1. Prepare the compressor for service as 3. Lightly oil the new separator seal.
outlined on page 15. 4. Screw the new air/fluid separator in
2. Loosen the air/fluid separator using a to the stop. Tighten the separator
strap wrench. Remove possible seal another half revolution by hand.
rests from the separator housing. 5. Test the air/fluid separator for
leakage at operating temperature.
6. Perform the steps under Completing
Service (page 19) to put the
compressor back into service.


Replace Air Filter

1. Prepare the compressor for service as 2. Remove the old air filter.
outlined on page 15. 3. Install the new air filter.
4. Perform the steps under Completing
Caution! Service (page 19) to put the
compressor back into service.
The compressor must not be operated
without an air filter. Dirt and dust
entering the intake can cause damage
to the compressor.


Check Pressure Relief Valve

1. Prepare the compressor for service as 5. If the adequate functionality of the


outlined on page 15. old pressure relief valves can no
2. Remove the pressure relief valve and longer be guaranteed, install a new
remove any residue at the threaded pressure relief valve.
connection. 6. Perform the steps under Completing
3. Check the pressure relief valve using Service (page 19) to put the
an appropriate apparatus. compressor back into service.

4. If it is still working correctly, add


sealing tape to the connecting thread
of the valve and reinstall it.

18 Quincy Compressor-QSC-5DD™
Section V - Servicing

Check Drive Coupling

1. Prepare the compressor for service as 4. Mount the cam ring on the coupling
outlined on page 15. half and manually test for radial play
2. Manually test to see if the coupling again.
has radial play. 5. Perform the steps under Completing
3. If so, loosen the cam ring of the Service (page 19) to put the
coupling, push it back, and replace compressor back into service.
the coupling element.


Lubrication of the Electric Motor

1. Prepare the compressor for service as Notice!


outlined on page 15.
2. The bearing lubrication period of If there are no grease nipples on the
2000 hours for the electric motor electric motor, then it is equipped
must be observed. with capsulated permanently greased
bearings. These motor bearings must
3. Carry out the required lubrication
be replaced when they are worn out.
with a grease gun.

4. Perform the steps under Completing


Service on page 19 put the
compressor back into service.

Completing Service

1. Open the stopcock slowly on the 6. Used filter elements, compressor


pressure side. fluid, seals, excess condensate
2. Switch the main compressor switch and cleaning materials should be
on. considered hazardous waste and
disposed of in an environmentally
3. Ensure that no tools or loose objects friendly way.
are lying on or in the system.
4. Check all fluid and air piping for
leaks. Notice!
5. Check all new filter elements
and newly mounted pressurized Maintenance services not performed
components for leaks at operating degrade the service life reliability of the
temperature. system. Damages caused by improper
usage or lack of maintenance are not
covered by the warranty.

Quincy Compressor-QSC-5DD™ 19
Appendix A - Technical Data

QSC5-DD Technical Data: Units 50Hz


Maximum Operating Pressure barg (psig) 8.6 (125)
Volume Flow (at maximum pressure) l/min (cfm) 311.5 (11)
Ambient Temperature °C (°F) -5 to +45 (+23 to +113)
Compressed Air Temperature °C (°F) 33 (91.4)
(at Ta=20°C (68°F))
Acceleration (horizontal/vertical) g <1.5
Voltage V 400/3~
Motor Power kW (hp) 5.5 (7.4)
Motor Speed rpm 2925
Motor Efficiency % 88.5
Power Motor Shaft (including fan) kW 5.79
Motor protection/ISO IP 40°C (104°F)/F
Total Power Consumption kW 6.55
Fan Power Consumption kW 0.16
Cooling Air Flow m³/h (cfm) 1100 (647.4)
Compressor Speed rpm 2925
Sound Level (@1 meter) dB(A) 72
Pressure Relief Valve setting barg (psig) 10.3 (149.4)
Connection G 1/2“
Dimensions (no frame) mm (inches) 940 x 480 x 470 (37 x 18.9 x 18.5)
Weight kg (lbs) 168 (370.4)
Reservoir Capacity l (gallons) 6.1 (1.6)

20 Quincy Compressor-QSC-5DD™
Standard Terms and Conditions

Quincy Compressor and Ortman Fluid Power Divisions


TITLE & LIEN RIGHTS: The equipment shall remain personal property, regardless of how affixed to any
realty or structure. Until the price (including any notes given therefore) of the equipment has been fully
paid in cash, Seller shall, in the event of Buyer’s default, have the right to repossess such equipment.
PATENT INFRINGMENT: If properly notified and given an opportunity to do so with friendly assistance,
Seller will defend Buyer and the ultimate user of the equipment from any actual or alleged infringement of
any published United States patent by the equipment or any part thereof furnished pursuant hereto (other
than parts of special design, construction, or manufacture specified by and originating with Buyer), and will
pay all damages and costs awarded by competent court in any suit thus defended or of which it may have
had notice and opportunity to defend as aforesaid.
STANDARD WARRANTY: Seller warrants that products of its own manufacture will be free from defects
in workmanship and materials under normal use and service for the period specified in the product
instruction manual. Warranty for service parts will be ninety (90) days from date of factory shipment.
Electric Motors, gasoline and diesel engines, electrical apparatus and all other accessories, components
and parts not manufactured by Seller are warranted only to the extent of the original manufacturer’s
warranty.
Notice of the alleged defect must be given to the Seller, in writing with all identifying details including
serial number, type of equipment and date of purchase within thirty (30) days of the discovery of the same
during the warranty period.
Seller’s sole obligation on this warranty shall be, at its option, to repair or replace or refund the purchase
price of any product or part thereof which proves to be defective. If requested by Seller, such product or
part thereof must be promptly returned to seller, freight prepaid, for inspection.
Seller warrants repaired or replaced parts of its own manufacture against defects in materials and
workmanship under normal use and service for ninety (90) days or for the remainder of the warranty on the
product being repaired.
This warranty shall not apply and Seller shall not be responsible or liable for:
(a) Consequential, collateral or special losses or damages;
(b) Equipment conditions caused by fair wear and tear, abnormal conditions of use, accident, neglect
or misuse of equipment, improper storage or damage resulting during shipping;
(c) Deviation from operating instructions, specifications or other special terms of sale;
(d) Labor charges, loss or damage resulting from improper operation, maintenance or repairs made by
person(s) other than Seller or Seller’s authorized service station.
In no event shall Seller be liable for any claims whether arising from breach of contract or warranty or
claims of negligence or negligent manufacture in excess of the purchase price.
THIS WARRANTY IS THE SOLE WARRANTY OF SELLERS AND ANY OTHER WARRANTIES,
WHETHER EXPRESS OR IMPLIED IN LAW OR IMPLIED IN FACT, INCLUDING ANY WARRANTIES OF
MERCHANTABILITY AND FITNESS FOR PARTICULAR USE ARE HEREBY SPECIFICALLY EXCLUDED.
LIABILITY LIMITATIONS: Under no circumstances shall the Seller have any liability for liquidated damages
or for collateral, consequential or special damages or for loss of profits, or for actual losses or for loss of
production or progress of construction, whether resulting from delays in delivery or performance, breach of
warranty, negligent manufacture or otherwise.
ENVIROMENTAL AND OSHA REQUIREMENTS: At the time of shipment of the equipment from the
factory, Quincy Compressor/Ortman Fluid Power will comply with the various Federal, State and local laws
and regulations concerning occupational health and safety and pollution. However, in the installation and
operation of the equipment and other matters over which the seller has no control, the Seller assumes no
responsibility for compliance with those laws and regulations, whether by the way of indemnity, warranty or
otherwise.

Quincy Compressor-QSC-5DD™ 21
Standard Terms and Conditions

Quincy Compressor and Ortman Fluid Power Divisions


LEGAL EFFECT: Except as expressly otherwise agreed to in writing by an authorized representative of
Seller, the following terms and conditions shall apply to and form a part of this order and any additional
and/or different terms of Buyer’s purchase order or other form of acceptance are rejected in advance and
shall not become a part of this order.
The rights of Buyer hereunder shall be neither assignable nor transferable except with the written consent
of Seller.
This order may not be canceled or altered except with the written consent of Seller and upon terms which
will indemnify Seller against all loss occasioned thereby. All additional costs incurred by Seller due to
changes in design or specifications, modification of this order or revision of product must be paid for by
Buyer.
In addition to the rights and remedies conferred upon Seller by this order, Seller shall have all rights and
remedies conferred at law and in equity and shall not be required to proceed with the performance of this
order if Buyer is in default in the performance of such order or of any other contract or order with seller.
TERMS OF PAYMENT: Unless otherwise specified in the order acknowledgment, the terms of payment shall
be net cash within thirty (30) days after shipment. These terms shall apply to partial as well as complete
shipments. If any proceeding be initiated by or against Buyer under any bankruptcy or insolvency law, or
in the judgment of Seller the financial condition of Buyer, at the time the equipment is ready for shipment,
does not justify the terms of payment specified, Seller reserves the right to require full payment in cash
prior to making shipment. If such payment is not received within fifteen (15) days after notification of
readiness for shipment, Seller may cancel the order as to any unshipped item and require payment of its
reasonable cancellation charges.
If Buyer delays shipment, payments based on date of shipment shall become due as of the date when
ready for shipment. If Buyer delays completion of manufacture, Seller may elect to require payment
according to percentage of completion. Equipment held for Buyer shall be at Buyer’s risk and storage
charges may be applied at the discretion of Seller.
Accounts past due shall bare interest at the highest rate lawful to contract for but if there is no limit set
by law, such interest shall be eighteen percent (18%). Buyer shall pay all cost and expenses, including
reasonable attorney’s fees, incurred in collecting the same, and no claim, except claims within Seller’s
warranty of material or workmanship, as stated below, will be recognized unless delivered in writing to
Seller within thirty (30) days after date of shipment.
TAXES: All prices exclude present and future sales, use, occupation, license, excise, and other taxes
in respect of manufacture, sales or delivery, all of which shall be paid by Buyer unless included in the
purchase price at the proper rate or a proper exemption certificate is furnished.
ACCEPTANCE: All offers to purchase, quotations and contracts of sales are subject to final acceptance by
an authorized representative at Seller’s plant.
DELIVERY: Except as otherwise specified in this quotation, delivery will be F. O. B. point of shipment.
In the absence of exact shipping instruction, Seller will use its discretion regarding best means of insured
shipment. No liability will be accepted by Seller for so doing. All transportation charges are at Buyer’s
expense. Time of delivery is an estimate only and is based upon the receipt of all information and
necessary approvals. The shipping schedule shall not be construed to limit seller in making commitments
for materials or in fabricating articles under this order in accordance with Seller’s normal and reasonable
production schedules.
Seller shall in no event be liable for delays caused by fires, acts of God, strikes, labor difficulties, acts of
governmental or military authorities, delays in transportation or procuring materials, or causes of any kind
beyond Seller’s control. No provision for liquidated damages for any cause shall apply under this order.
Buyer shall accept delivery within thirty (30) days after receipt of notification of readiness for shipment.
Claims for shortages will be deemed to have been waived if not made in writing within ten (10) days after
the receipt of the material in respect of which any such shortage is claimed. Seller is not responsible for
loss or damage in transit after having received “In Good Order” receipt from the carrier. All claims for loss
or damage in transit should be made to the carrier.

22 Quincy Compressor-QSC-5DD™
Notes

____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________

Quincy Compressor-QSC-5DD™ 23
Notes

____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________

24 Quincy Compressor-QSC-5DD™
Quincy Compressor Products: 217.222.7700
E-mail: info@quincycompressor.com © 2006 Quincy Compressor, an EnPro Industries company
Website: www.quincycompressor.com All Rights Reserved. Litho in U.S.A.

You might also like