Preliminary Estimate for Geotechnical Investigation for Reach-1A---(Bore holes considered @ 100m C/c Spacing)

( Based On Monarch Surveyors Contract Pune Metro)

Monarch Monarch
Surveyors Pune Surveyors Pune
S.No Item Unit Qty Rate 01-09-
Rate with 15% Amount(in Rs) Amount(in Remarks
2017(28.35% Crores)
higher than Escalation for
estimated rate) 3-years

Mobilization & demobilization of boring rigs ( Calyx/Hydraulic type at work site


including setting up at site and removing away from the site on completion of
1
work including loading, unloading etc complete.
Nos. 15.00 ₹ 15,402.00 ₹ 17,712.30 ₹ 231,030 ₹ 0.02
Note: Internal shifting of machines will not be considered as Mobilization.

a) Vertical boring 150mm dia. through all kinds of soil and weathered /soft & hard
rock having RQD <=50% with adequate/ suitable equipment for a depth measured
below existing ground upto a depth of 20mts.

1) Total Length of Reach-1A in Phase-2----18,678m.


b) Collecting undisturbed soil samples in 100mm dia, 450 mm long thin walled tube
2) Considering Bore Holes to be drilled at 100m Spacing,
2 sampler at every 3.00 m interval or at change of strata whichever occurs earlier RMT 1,870.00 ₹ 3,016.23 ₹ 3,468.66 ₹ 5,640,341 ₹ 0.56 3) Total No. of Bore holes to be drilled--(18678/100)=187 Nos.
and sealing the container. Conducting standard penetration test as per IS213-1932
at 3 m interval or at change of strata and collecting disturbed samples, packaging 4) Average Depth of Bore hole considered to be drilled = 15m
& labelling the same. (Weighted Average of Borehole Depths of Reach-1A as per DPR of
Phase-2 is 13.13m + 10% Extra).
c) Conducting Laboratory test on collected samples as per list enclosed as 5)Based on the Borelog details of DPR of Phase-2, We have
Annexure-1. considered
* First 10m depth out of 15m Bore Length Per Bore hole for Item
a) Vertical boring 150mm dia with double tube swindle core barrel, diamond No.2 of this BOQ.
drilling bits with to take out core samples through hard rock having RQD> 50% with
adequate suitable equipment for a depth measured below existing ground upto a * Next 5m depth out of 15m Bore Length per Bore hole for
depth of 40mts. Item No.3 of this BOQ.
6)Quantity for Item No.2= (187 x 10) =1870m

b) Collecting un-disturbed soil samples in 100mm dia, 450 mm long thin-walled 7)Quantity for Item No.3= (187 x 5) =935m
tube sampler at every 3.00 m interval or at change of strata whichever occurs
3 earlier & sealing the container. Conducting standard penetration test as per IS: RMT 935.00 ₹ 5,134.00 ₹ 5,904.10 ₹ 4,800,290 ₹ 0.48
213-1962 at 3 m interval change or at change of strata and collecting the disturbed
sample, packaging and labelling the same.

c) Conducting Laboratory test on collected samples as per list enclosed as


Annexure-1.

Note: Borehole shall be terminated after drilling to a depth of 5m in hard rock


strata having RQD>=75% or as directed by Engineer-in-charge.

Breaking of concrete pavement (if necessary, for drilling of holes in concrete


4 surface). Sq.Mt 100.00 ₹ 3,465.45 ₹ 3,985.27 ₹ 346,545 ₹ 0.03

5 Restoration of road surface to its original position on completion of drilling work Nos. 150.00 ₹ 4,107.20 ₹ 4,723.28 ₹ 616,080 ₹ 0.06
including cleaning of site etc.. complete

Total Amount ₹ 11,634,286 ₹ 1.16 Crores


Average Bore Hole Depth for Geotechnical Investigation
of Reach-1A as per DPR of Phase-2
Diff in
Chainage Bore Hole Weighted Average
S.No Bore Hole No. Chainage Depth(m) BoreHole Depth

Xi Hi ∑XiHi ∑XiHi/∑Xi
0 20200 0
1 C-4/1 20260 650 10.5 6825
2 C-4/2 20850 650 12 7800
3 C-4/2(A) 21500 1038 12 12456
4 C-4/3 22538 1012 16 16192
5 C-4/4 23550 900 10.5 9450
6 C-4/5 24450 1050 13.5 14175
7 C-4/6 25500 1000 7.5 7500
8 C-4/7 26500 850 10.5 8925
9 C-4/8 27350 1150 7.5 8625
10 C-4/9 28500 775 12 9300
11 C-4/10 29275 800 10.5 8400
12 C-4/11 30075 1210 15 18150 13.18
13 C-4/12 31285 1140 9 10260
14 C-4/13 32425 1055 12 12660
15 C-4/14 33480 280 10.5 2940
16 C-4/15 33760 630 10.5 6615
17 C-4/16 34390 725 10.5 7612.5
18 C-4/17 35115 518 30 15540
19 C-4/17(A) 35633 292 21 6132
20 C-4/18 35925 1525 25.5 38887.5
21 C-4/19 37450 1030 12 12360
22 C-4/20 38480 488 13.5 6588
23 38968

∑Xi= 18,768 ∑XiHi= 247,393

Weighted Average Bore Hole Depth for Geotechnical Investigation


of Reach-1 A as per DPR of Phase-2= 13.18m
Preliminary Estimate for Geotechnical Investigation of all 4-reaches of Phase-2 (43.791Km)----50% Locations
Amount(in
S.No Item Unit Qty Rate Amount(in Rs) Crores) Remarks

Drilling through hydraulic machine of 100/150mm * Total Length of all reaches in Phase-2----43.791 KM
1 dia borehole using NX size diamond bits, RMT 4,380.00 ₹ 2,880.00 ₹ 12,614,400 ₹ 1.26 *Assuming Bore Holes to be drilled at 25m Spacing,
conducting standard penetration tests alternate at Total No. of Bore holes to be drilled--(43,791/25)=1751 Nos.
an internal of 1.5 to 2mtr depth, collecting UDS,SPT *50% of Total Bore Hole Locations =(1751/2)=876 Nos.
alternatively, conducting necessary laboratory
tests like grain size analysis, liquid limit, plastic * Average Depth of Bore hole considered to be drilled = 20m
limit, water content, field density, specific gravity, (Weighted Average of Avg.Borehole Depths of all Reaches +
shear & consolidation parameters for soil strata 10% Extra---Based on DPR of Phase-2).
Nx<100
* Assuming 5m depth boring for Nx< 100, Total Drilling
Length=(5*876)=4380m.

*Assuming 15m depth boring for Nx> 100, Total Drilling


Length=(15*876)=13,140m.
Drilling through hydraulic machine of 100/150mm
dia borehole using NX size diamond bits, * Rate is Considered from Latest Variation of Manish Nagar
2 RMT 13,140.00 ₹ 4,320.00 ₹ 56,764,800 ₹ 5.68 Contract + 20% Profit.
conducting standard penetration tests alternate at
an Internal of 1.5 to 2mtr depth, collecting UDS,SPT
alternatively, conducting necessary laboratory
tests like grain size analysis, liquid limit, plastic
limit, water content, field density, specific gravity,
shear & consolidation parameters for soil strata,
Nx >100-----(In all kinds of Rocks)

Total Amount ₹ 69,379,200 ₹ 6.94 Crores