Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 5

SEMESTER PROJECT

Prepare project work schedule using MS-Project.

Report the Gantt chart and convert in to pdf format


Report Network diagram with the critical activity (pdf format)
Assign resources to activities and then level the over allocation
resources. (pdf format)
 Report Material resources (by month)
 Report Equipment resources (by month)
 Report Manpower resources (by month)
On cost of project analysis cash flow or (Report cash flow
analysis) (pdf format)
And if need Report all necessary data form Ms- project

N.B: Assume all reasonable required raw data and estimate the unit price of the individual
items.
: Calculate the activity duration based on the work quantity and the crew output given.
: Assume all non-working days entirely for the project and create your own base calendar.
: Every 30 days there is General meeting for the project.

 Project submitted date: a day after your final exam!!


SEMESTER PROJECT

Group - 1
XYZ Water Supply Project
1. General item
No. Description Unit Quantity
1 General item    
Mobilization of man power, equipment, machinery and all
1.1 No. 1
required materials to the site
Provide survey control points and setting out work for
1.2 Ls 1.0
construction
Fabricated and erect metallic project sign boards for the project
1.3 Ls 1
identification
Pipeline testing and commissioning for the whole work,
including all necessary works such as transportation and use of Ls
1.4 water, pipe fittings, disposing of used water 1  
Prepare and provide as built drawings of all works constructed
1.5 under this contract as per the specification and to the Ls 1
satisfaction of engineer
1.6 Demobilization Ls 1

2. Distribution Network
No Description Unit Qty.  
1 Trench excavation & back filling
1.1 Depth up to 0.8m*0.6m trench excavation in normal soil m3 1121.98  
1.2 Ditto 1.1 but soft rock m3 198.00  
1.3 back fill and compaction by native soil m3 1121.98  
SUPPLY AND LAY HDPE PE 100 PN 10 PIPES
2 including compression fittings at joints  
2.1 OD 40 mm m 793.10  
2.2 OD 50 mm m 780.20  
2.3 OD 63 mm m 174.21  
2.4 OD 75 mm m 437.45  
3 Supply and Installation of Medium Class GI Pipe  
3.1 DN 25 mm m 840.00  
Provide and construct reinforced concrete (C-20) valve
3.2
Chamber with dimension of as shown in the drawing . No. 7.00  
SEMESTER PROJECT

3. Construct 50 m3 Service reservoir

No. Description Unit Quantity


1 Earth Work  
2
1.1 Site clearing up to a depth of 20 cm m 55.4  
3
1.2 Bulk Excavation of Normal soil not exceeding a depth of 100cm m 43  
1.3 Cart away the excavated materials 50m away m3 42.83  
Back fill with selected material compact at each 20cm layer with
1.4 optimum moisture content m3 11.25  
1.5 25cm thick Hard core filling with hard basaltic stone m2 32.15  
2 Concrete Work  
5cm thick C-10 lean concrete under the base slab of service
2.1 reservoir m2 32.15  
2.2 C-30 reinforced concrete for floor slab of reservoir m3 4.53  
Ditto to item 2.2 above but 20cm thick circular reinforced
2.3 concrete wall & top beam m3 2.11  
2.4 Ditto to item 2.2 above but 15cm thick Roof slab C-25 m3 4.53  
2.5 Provide and fix zigba or steel Form work  
2.5.1 a) In base slab m3 4.02  
2.5.2 b) In wall & top tie beam m3 85.91  
2.5.3 c) In top slab m3 22.64  
2.6 Reinforcement bar  
2.6.1 a) For base slab (Dia 8mm & 10mm) kg 380  
2.6.2 b) For wall & top tie beam (Dia 10mm & 12mm) kg 275  
2.6.3 c) For top slab (Dia 12mm) kg 578  
3 Finishing Work  
30 mm thick water tight smooth cement screed sloping towards
3.1 the slump for floor slab (1:2) m2 19.63  
Provide and apply 3 coats of plaster to internal walls, columns
3.2 and external wall surface m2 37.68  
Semi-dressed stone pavement around the water reservoir having
3.3 70cm wide with (1:3) mix ratio m2 15.61  
4 Pipes and fittings and ladder installation  
4.1 Supply and install of Inlet Pipe with 37.5mm GI pipe No 1  
4.2 Supply and install of outlet Pipe with 100mm GI pipe No 1  
4.3 Supply and install of overflow Pipe with 100mm GI pipe No 1  
5 Fence Work  
Supply and erect fence of 6 lines of barbed wire 200mm and
400mm spacing the bottom 4 and upper 2 lines, respectively, with
cross diagonal on angle iron poles, embedded in concrete around
5.1 the pole to depth of 50cm ml 50  
5.2 4000mmX2000mm Gate No 1  
SEMESTER PROJECT

4. Generator and Pump House

Item Description Unit Qty


A Sub Structure  
1 Earth work  
1.1 Clearing and removal of top soil to average depth of 25cm m2 50  
1.2 Bulk Excavation in ordinary soil m3 50.00  
1.3 Ditto 1.2 in Soft Rock excavation m3 25.00  
1.4 Cart away the excavated material note less than 500m m3 20.00  
1.5 Selected material fill m3 42.00
2 Masonry Work  
2.1 Stone masonry with cement mortar 1:4 ratio m3 7.68  
2
2.2 25cm thick hard -core filling m 50  
3 Concrete works  
3.1 5cm thick C-10 lean concrete above the hard core m3 6.40  
3.2 C-25 reinforced concrete for floor, column & top tie beam m3 9.5  
B Super Structure  
4 HCB walling  
2
4.1 Class "B" 20cm thick HCB wall m 112.8  
 4.2 Class "B" 15cm thick HCB wall m2 15.4  
4.3 Plastering of the internal & external wall m2 243.6  
Apply three coat of synthetic enamel paint to plastered Vertical
4.4 surfaces, beams and columns and wall m2 243.6  
5 Roofing  
5.1 Gauge 28 corrugated iron sheet Roof cover m2 49.08  
6 Door and window  
6.1 Door size 1200 x 2500mm with Sheet Metal Thickness 1mm pcs 2  
6.2 Door size 1200 x 2500mm Sheet Metal Thickness 1mm pcs 2  
7 Truss work  
7.1 8cm diam. Vertical & Diagonal Eucalyptus truss. m 61  
7.2 10cm diam eucalyptus for lower & upper chord. m 69  
7.3 50*70mm eucalyptus purlin m 50  
8 Fence Work  
Supply and erect fence of 6 lines of barbed wire 200mm and
400mm spacing the bottom 4 and upper 2 lines, respectively,
with cross diagonal on angle iron poles, embedded in concrete
8.1 around the pole to depth of 50cm ml 70  
8.2 4000mmX2000mm Gate No 1  

5. Electro mechanical Works


Item Description Unit Qty
1 Electro mechanical works
SEMESTER PROJECT
supply and installation of submersible pump with Q=2.7 lit/s,
1.1 1
H=125m, pump motor power <=9.2kw. set
Supply and installation of diesel generator set, with prime
1.2 1
power =30 kva, 3 phase, 400V, 50hz, 1500 RPM set

You might also like