Prepare Project Work Schedule Using MS-Project
Prepare Project Work Schedule Using MS-Project
N.B: Assume all reasonable required raw data and estimate the unit price of the individual
items.
: Calculate the activity duration based on the work quantity and the crew output given.
: Assume all non-working days entirely for the project and create your own base calendar.
: Every 30 days there is General meeting for the project.
Group - 1
XYZ Water Supply Project
1. General item
No. Description Unit Quantity
1 General item
Mobilization of man power, equipment, machinery and all
1.1 No. 1
required materials to the site
Provide survey control points and setting out work for
1.2 Ls 1.0
construction
Fabricated and erect metallic project sign boards for the project
1.3 Ls 1
identification
Pipeline testing and commissioning for the whole work,
including all necessary works such as transportation and use of Ls
1.4 water, pipe fittings, disposing of used water 1
Prepare and provide as built drawings of all works constructed
1.5 under this contract as per the specification and to the Ls 1
satisfaction of engineer
1.6 Demobilization Ls 1
2. Distribution Network
No Description Unit Qty.
1 Trench excavation & back filling
1.1 Depth up to 0.8m*0.6m trench excavation in normal soil m3 1121.98
1.2 Ditto 1.1 but soft rock m3 198.00
1.3 back fill and compaction by native soil m3 1121.98
SUPPLY AND LAY HDPE PE 100 PN 10 PIPES
2 including compression fittings at joints
2.1 OD 40 mm m 793.10
2.2 OD 50 mm m 780.20
2.3 OD 63 mm m 174.21
2.4 OD 75 mm m 437.45
3 Supply and Installation of Medium Class GI Pipe
3.1 DN 25 mm m 840.00
Provide and construct reinforced concrete (C-20) valve
3.2
Chamber with dimension of as shown in the drawing . No. 7.00
SEMESTER PROJECT