ACTIVITY SEQUENCING
GROUP- 7
COUSE NAME AND ID- 2020F-T1 EPM 1143 - PROJECT RESOURCE
STUDENT DETAILS: NAVNEET KAUR (C07941180), NISHA NISHA (C0784734), NAVPREET KAUR SANDHU
(C0784719), NAVDEEP SINGH (C0775876), NAVJOT SINGH (C0780719)
#GROUP ASSIGNMENT1: ACTIVITY SEQUENCING
The restaurant is going to be opened on Chandigarh highway road near Sunny enclave sector 125, Mohali, Punjab (140301).
India is a diverse country and people often visit restaurants with their families to spend quality time with each other. Constructing a restaurant in
expected budget of ($272,000) near major developing cities with modern in and outlook designs. Also, supplying organically produced food will
not only make customers healthy but force them to pay for good quality which in turn help the owner to generate maximum income after this
6month project.
As the restaurant is providing organic food which will impact consumers in terms of good health benefits and escalate their satisfaction levels.
Hence, purpose is to build this restaurant from a small scale to a positive brand in an estimated time of 5 years.
Based on this selected project “Building the restaurant” we are going to continue this assignment further. This is a construction project therefore;
1. Activity lists (at least 20) will be created which will be performed to build the restaurant.
1
#GROUP ASSIGNMENT1: ACTIVITY SEQUENCING
3. Define activity Dependencies: How the activities are co-related to each other.
4. Drawing Network diagram - Precedence Diagramming Method (PDM): To show the sequence between all the activities and
ACTIVITY LIST:
A Finalise Drawings. Building a restaurant will need some prior architectural drawing. Hence, this activity will
should be submitted to local environmental health department to get permit for production
D Marking Footprint To construct the restaurant, various measurements will be taken which will tell how much
2
#GROUP ASSIGNMENT1: ACTIVITY SEQUENCING
requirements.
F Excavation at construction site As per architectural/ engineering specification this activity needs removal of extra soil to
G Purchasing building material. Placing order for raw material such as bricks, stones, cement with their accepted delivered
contractor will be hired which will further provide us trained labour. Contractor will look
further all construction activities on his behalf in decided time for project.
I Giving Information to contractor The hired contractor will be informed about the architectural drawings that will help
restaurant’s building.
L Roof framing In this structure of roof will be framed as per engineering and architectural requirements.
M Plumbing It is the activity to install drainage system such as installing pipes in walls.
N Electrical installation Fitting of electrical wires to use any electronic appliances in restaurant.
3
#GROUP ASSIGNMENT1: ACTIVITY SEQUENCING
O Making list of other supplies Preparing list of various materials such as infrastructure, tables and chairs that should be
procured.
P Finding the supplier Making sure to select the potential supplier in the market that can give quality of supplied
material.
Q Accepting/ Testing the procured materials. The supplied materials should be tested to reduce infrastructural defect.
R Developing the interiors It will not only to complete and finalise the interiors and exteriors as per architectural/
painting
S Landscaping It is the activity to fascinate the building of restaurant by adding features such as adding
garden, plants and trees to the final architectural design, design public and private areas. It
4
#GROUP ASSIGNMENT1: ACTIVITY SEQUENCING
B A 9
C B 5
D A, C (F S) 1
E D 2
F E, A (FS) 3
G A 2
H D 3
I H 1
J F, G, H, I (FS) 13
K J 55
L K 1
M L 12
N M 15
O G 1
P O 2
Q P 1
R Q, N(FS) 25
S R 8
T S 3
5
#GROUP ASSIGNMENT1: ACTIVITY SEQUENCING
U T 1
END U 0
ACTIVI PREDECES
DRAWING NETWORK DIAGRAM - PRECEDENCE DIAGRAMMING METHOD (PDM)
TY SOR
START -
Note: 1) If A (Finalize drawing) will finish, then D (Mark footprints) will start.
A START
2) If A (Finalize Drawing) will finish, then F (Excavation at site) will start
B A
3) If G (Purchasing Building Material), H (Hiring the contractor), I (Giving information to contractor) will C B
E D
4) If N (Electrical installation) will finish, then R (Developing the interiors) will Start
F E, A (FS)
G A
H D
I H
J F, G, H, I
(FS)
K J
L K
C
M L
B 5 D
9
N M 1
O G
S
F
P O
S
F
START
Q
A P
O 3
R Q, N(FS)
S R G
P
T S 2 O
2
1
U T
6
END U
#GROUP ASSIGNMENT1: ACTIVITY SEQUENCING
NUMBER OF PATHS AND CALCULATING THE LONGEST PATH FROM PDM DIAGRAM
There are total 7 paths as shown below:
PATH 1: A+B+C+D+H+I+J+K+L+M+N+R+S+T+U+END= 3+9+5+1+3+1+13+55+1+12+15+25+8+3+1+0=155 Days
PATH 2: A+B+C+D+H+J+K+L+M+N+R+S+T+U+END= 3+9+5+1+3+13+55+1+12+15+25+8+3+1+0 =154 Days
PATH 3: A+B+C+D+E+F+J+K+L+M+N+R+S+T+U+END=3+9+5+1+2+3+13+55+1+12+15+25+8+3+1+0=139 Days
PATH 5: A+D+E+F+J+K+L+M+N+R+S+T+U+END=3+1+2+3+13+55+1+12+15+25+8+1+0= 142 Days
PATH 6: A+F+J+K+L+M+N+R+S+T+U+END=3+1+13+55+1+12+15+25+8+3+1+0= 137 Days
PATH 7: A+G+J+K+L+M+N+R+S+T+U+END= 3+2+13+55+1+12+15+25+8+3+1+0= 140 Days
The longest path in our network diagram is path1with duration of 155 days.
The shortest path is path6 with duration of 137 days.