Professional Documents
Culture Documents
Losses of Prestress
Losses of Prestress
Losses of Prestress
1
Introduction
Losses
Time
Immediate
dependent
Elastic Anchorge
Friction Creep Shrinkage Relaxation
Shortening slip
Sr. Pre-tensioning Sr. Post-tensioning
No. No.
5 Friction
6 Anchorage slip
Loss due to Elastic deformation of concrete
Pre-tensioned members
αc = Es/Ec
Cable 4 = 0
PL
∆=
AE s
Loss of stress due to anchorage slip =(P/A) = (Es∆/L)
Since the loss of stress is caused by a definite total
amount of shortening, the percentage loss is higher
for short members than for long ones.
A concrete beam is post tensioned by a cable
carrying an initial stress of 1200N/mm2. The slip at
the jacking end was observed to be 8mm. The
modulus of elasticity of steel is 210 kN/mm2.
Estimate the percentage loss of stress due to
anchorage slip if the length of the beam is (a) 10m
and (b) 50m.
For a 10 m long beam,
Loss of stress = (210 ×103 ×8)/(10×1000) = 168 MPa
Percentage loss of stress = (168/1200) ×100 = 14%
Px = P0 e (µα + kx)
where
e − ( µα + kx )
= 1 − (µα + kx )
∴ Px = P0 [1 − (µα + kx )]
P0 − Px
Loss of stress =
As
(P0 − Px ) = P0 − P0 [1 − (µα + kx )]
= P0 (µα + kx )
P0 − Px P0 (µα + kx )
∴ Loss of stress = =
As As
The value of µ and k given below may be adopted for
calculating the friction losses (IS 1343 – 2012):
Friction losses can be reduced by several methods,
such as
1. Overtensioning the tendons by an amount equal to
the maximum frictional loss, and
2. Jacking the tendons from both ends of the beam,
generally adopted when the tendons are long or
when the angles of bending are large.
Total losses allowed for in Design
• It is normal practice in the design of prestressed concrete
members to assume the total loss of stress as a
percentage of the initial stress and provide for this in the
design computations.
• Since the loss of prestress depends on several factors,
such as
• the properties of concrete and steel,
• method of curing,
• degrees of prestress and
• the method of prestressing, it is difficult to generalize
the exact amount of the total loss of prestress.
Typical values of the total losses of stress that could be
encountered under normal conditions of work are
outlined as below:
Pretensioning Post-tensioning
Elastic shortening and 4 1
bending of concrete
Creep of concrete 6 5
Shrinkage of concrete 7 6
Creep in steel 8 8
Total 25 20
A post-tensioned cable of a beam 10 m long is
initially tensioned to a stress of 1000N/mm2 at one
end. If the tendons are curved so that the slope is 1
in 15 at each end with an area of 600 mm2.
Calculate the loss of prestress due to friction given
the following data:
Coefficient of friction between duct and cable = 0.55
Friction coefficient for wave effect = 0.0015/m
During anchoring, if there is a slip of 3mm at the
jacking end, calculate the final force in the cable and
the percentage loss of prestress due to friction and
slip.
Cumulative angle between tangents to the cable at
supports = 1/15 ×2 = 2/15
= 15.13%
Px = P0 [1 − (µα + kx )]
Solving P0 = 290kN
0.5(250 + 290)
fs = = 540 MPa
500
Relaxation loss = 4% = (4/100) × 540 = 21.6 N/mm2