Professional Documents
Culture Documents
Widening and Reconstruction (KM 368.000 To 399.000) Pkg-I: Projet - Name
Widening and Reconstruction (KM 368.000 To 399.000) Pkg-I: Projet - Name
49
Activity ID Activity Name Unit Total Balance Original Start Finish 2020 2021
Quantity Quantity Duration February March April May June July August September October November December January February March April May June July August September October
W5 W6 W7 W8 W9 W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W1 W2 W3 W4 W5 W6 W7 W8 W9 W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W
Widening and reconstruction new 17m 20-Feb-20 28-Sep-21 28-Sep-21, Widening and reconstruction new
A. Widening of Existing 2 Lane Alignment 13m 20-Feb-20 20-Jun-21 20-Jun-21, A. Widening of Existing 2 Lane Alignment
A1000 (1) Earthwork up to Subgrade kM 26.6 0.254 9m 20-Feb-20 20-Feb-21 (1) Earthwork up to Subgrade
A1040 (5) Wearing Coat(BC) kM 26.6 18.135 8m 20-Oct-20 20-Jun-21 (5) Wearing Coat(BC)
B. Reconstruction / New 2- Lane realignment/ bypass (Flexible Pavement) 5m 20-Jan-21 20-Jun-21 20-Jun-21, B. Reconstruction / New 2- Lane realignment/ bypass (Flexible Pavement)
A1060 (1) Earthwork up to Subgrade kM 1.825 0.325 2m 20-Jan-21 20-Mar-21 (1) Earthwork up to Subgrade
A1100 (5) Wearing Coat(BC) kM 1.825 0.125 5m 20-Jan-21 20-Jun-21 (5) Wearing Coat(BC)
C. Re- Construction & New Culverts on existing road 13m 20-Apr-20 14-Aug-21 14-Aug-21, C. Re- Construction & New Culverts on existing road
A1110 (1)Culverts (Length < 6m) Nos 150 45 13m 20-Apr-20 14-Aug-21 (1)Culverts (Length < 6m)
ACHIEVED TARGETED
A. 1 - Widening & repair of Minor Bridges (Length > 6m and < 60m) 0m 20-Feb-20 20-Feb-20 20-Feb-20, A. 1 - Widening & repair of Minor Bridges (Length > 6m and < 60m)
MILESTONE MILESTONE
A1120 Minor Bridge 0m 20-Feb-20 20-Feb-20 Minor Bridge
III(Mar-21) IV(Sep-21)
A. 2 - New Minor Bridges (Length > 6m and < 60m) 15m 20-Feb-20 14-Aug-21 14-Aug-21, A. 2 - New Minor Bridges (Length > 6m and < 60m)
A1130 (1) Foundation + Sub- Structure R/m 150 60 15m 20-Feb-20 14-Aug-21 (1) Foundation + Sub- Structure
A. 2 - New Major Bridges & Viadect 16m 20-Feb-20 15-Sep-21 15-Sep-21, A. 2 - New Major Bridges & Viadect
A1170 (1) Foundation 0m 20-Feb-20 20-Feb-20 (1) Foundation
A1190 (3) Super Structure (Including Bearings) 0m 20-Feb-20 20-Feb-20 (3) Super Structure (Including Bearings)
A1200 (4) Wearing Coat including expansion 0m 20-Feb-20 20-Feb-20 (4) Wearing Coat including expansion joints
joints
A1210 (5) Miscellaneous Items like hand rails, 0m 20-Feb-20 20-Feb-20 (5) Miscellaneous Items like hand rails, crash barriers, road markings etc.
crash barriers, road markings etc.
A1250 (i) Road Side Drain kM 30.30 17.394 13m 20-Apr-20 14-Aug-21 (i) Road Side Drain
A1260 (ii). Road sign, markings, km stones, kM 0 0 0m 20-Feb-20 20-Feb-20 (ii). Road sign, markings, km stones, safety devices,
safety devices,
A1270 (a). Utility Duct kM 28.725 1.654 8m 20-Apr-20 20-Mar-21 (a). Utility Duct
A1280 (b). W- Beam Crash Barrier kM 17.209 11.426 9m 20-Dec-20 15-Sep-21 (b). W- Beam Crash Barrier
A1310 (b). Truck lay- byes Nos 1 1 1m 20-May-21 20-Jun-21 (b). Truck lay- byes
A1320 (c). Rest Areas Nos 1 1 1m 20-May-21 20-Jun-21 (c). Rest Areas
A1340 (e). Junction, Scenic overlook Nos 11 11 5m 20-Jan-21 20-Jun-21 (e). Junction, Scenic overlook
(v). Protecction work 14m 20-May-20 28-Sep-21 28-Sep-21, (v). Protecction work
A1350 (a). RCC Retaining Wall / Breast Wall R/m 8756 1872 9m 20-May-20 01-May-21 (a). RCC Retaining Wall / Breast Wall
A1360 (b). Reinforcement Earth Wall R/m 379 160 5m 01-May-21 28-Sep-21 (b). Reinforcement Earth Wall
Actual Level of Effort Remaining Work Baseline Milestone Page 1 of 1 TASK filter: All Activities
Actual Work Critical Remaining Work Milestone © Oracle Corporation
WORK PROGRAMME
PHYSICAL PROGRESS
Project Name : - Widening and Reconstruction of Exisiting Intermediate (2-Lane to 2 Lane with Paved Shoulder) Configuration from ExisitingNational Highway-07 (Old NH-58) from Lameri to Karanprayag at Km 368.000 to km. 399.000 (Excluding Km. 379.100 to Km 380.275) in the State of Uttarakhand an Engineering, Procurement and
Construction (EPC) Contract
Milestone-(III) ORAGINAL(June-2020)
(a). RCC Retaining Wall / Breast Wall R/M 8756 6884 1872 0 0 0 1000 1000 0 0 0 1000 1000 1256 1000 1000 1000 500 0 0 8756 6884
(b). Reinforcement Earth Wall R/M 379 219 160 0 0 0 0 0 0 0 0 0 0 0 0 0 0 100 50 50 100 79 379 219.00
Project Name : - Widening and Reconstruction of Exisiting Intermediate (2-Lane to 2 Lane with Paved Shoulder) Configuration from ExisitingNational Highway-07 (Old NH-58) from Lameri to Karanprayag at Km 368.000 to km. 399.000 (Excluding Km. 379.100 to Km 380.275) in the State of Uttarakhand an Engineering, Procurement and Construction (EPC) Contract
BO
As per Agreement Quantities Total Length Balance
Q
Up to date Balance to
Ite Descriptions Total Total
Achieved
m Unit BOQ Amount BOQ Rate be Achieved Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 Jul-21 Aug-21 Sep-21 Amount to be Cumulativ
Upto 30th apr- Achieved e Amount
No 21 J= H - I
A B C D E F G 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 01 to 23='24 25= F-24
(1) Earthwork up to Subgrade Km. 101830694.2 3828221.587 10.09 0.10 0.77 0.77 0.77 0.77 0.77 0.00 0.00 0.00 1.15 1.15 1.19 1.15 1.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.18 20.27
(2) GSB -WMM Km. 131520461.8 4944378.265 13.06 0.09 0.00 0.00 1.48 1.48 1.48 0.00 0.00 0.00 1.48 1.48 1.01 1.48 1.48 1.76 0.00 0.00 0.00 0.00 0.00 0.00 13.15 26.21
(3) DBM Km. 144455477.6 5430657.051 13.51 0.93 0.00 0.00 1.63 1.63 1.63 0.00 0.00 0.00 1.63 1.63 1.49 1.63 1.09 2.09 0.00 0.00 0.00 0.00 0.00 0.00 14.45 27.96
(5) Wearing Coat (BC) Km. 98618643.34 3707467.795 3.14 6.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.56 0.56 0.21 1.85 3.71 0.74 0.37 0.37 0.37 0.37 0.74 0.00 8.73 11.87
B. Reconstruction / New 2- Lane realignment/ bypass (Flexible Pavement)
(1) Earthwork up to Subgrade Km. 10243837.95 5613061.892 0.84 0.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.27 0.59 0.17 0.00 0.00 0.00 0.00 0.00 0.00 1.02 1.87
(2) GSB -WMM Km. 8854842.976 4851968.754 0.73 0.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.22 0.23 0.44 0.00 0.00 0.00 0.00 0.00 0.00 0.89 1.61
(3) DBM Km. 36113869.39 19788421.58 2.97 0.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.89 0.94 1.78 0.00 0.00 0.00 0.00 0.00 0.00 3.61 6.58
(5) Wearing Coat (BC) Km. 18230559.07 9989347.434 0.12 1.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.45 0.45 0.45 0.20 0.27 0.00 0.00 0.00 0.00 1.82 1.95
C. Re- Construction & New Culverts on existing road.
Work Programme
FINANCIAL AMOUNTING ( S-CURVE)
Number Month 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21
Up to date
Month Achieved Upto Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 Jul-21 Aug-21 Sep-21
30th apr-21
Monthly Schedule (Cr.) 111.975 1.52 1.52 9.03 10.20 10.16 10.16 10.16 10.16 12.19 9.51 11.79 16.87 19.83 17.07 10.89 8.39 9.00 5.82 5.33 1.88
Cum Schedule (Cr.) 111.975 1.52 3.05 12.08 22.28 32.45 32.45 32.45 32.45 44.64 54.15 65.93 82.81 102.63 119.70 130.58 138.97 147.97 153.79 159.12 160.99
250.00
Cumulative - - % Monthly Target- %
111.97
10
Cumulative - Amt. Cr. Monthly Target- Amt. Cr.
200.00
159.12
147.97 153.79
138.97
150.00 119.70 160.99
130.58
111.97 102.63
82.81
100.00
65.93
54.15
44.64
32.45 32.45 32.45
50.00 22.28 32.45
12.08
16.87 19.83 17.07
3.05 10.20 10.16 10.16 10.16 10.16 12.19 9.51 11.79 10.89
9.03 8.39 9.00 5.82 5.33
1.52 1.52 1.88
0.00 1.52
Up to date Achieved Upto 30th
Feb-20
apr-21 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 Jul-21 Aug-21 Sep-21
Monthly Target-
Amt. Cr.
111.97 1.52 1.52 9.03 10.20 10.16 10.16 10.16 10.16 12.19 9.51 11.79 16.87 19.83 17.07 10.89 8.39 9.00 5.82 5.33 1.88
Cumulative - Amt.
Cr.
111.97 1.52 3.05 12.08 22.28 32.45 32.45 32.45 32.45 44.64 54.15 65.93 82.81 102.63 119.70 130.58 138.97 147.97 153.79 159.12 160.99
Monthly Target- % 69.55% 0.95% 0.95% 5.61% 6.34% 6.31% 6.31% 6.31% 6.31% 7.57% 5.91% 7.32% 10.48% 12.32% 10.60% 6.76% 5.21% 5.59% 3.62% 3.31% 1.17%
Cumulative - - % 0.00% 0.95% 1.89% 7.50% 13.84% 20.15% 20.15% 20.15% 20.15% 27.72% 33.63% 40.95% 51.43% 63.75% 74.35% 81.11% 86.32% 91.91% 95.53% 98.83% 100.00%