Job Safety Analysis Sheet

Job Description: Rebar bending, Cutting, Loading & Offloading, Rebar &
Form works, Concrete Pouring, Vehicle & Equipment Maintenance, Chemical
handling, Office maintenance JSA Ref. No. EF 1931-O&G-JSA01
Equipment’s: M crane, Bending & cutting machine, F, L Trailer , Boom Truck, (REV-0,22.02.2020)
Service Truck, Diesel Tanker, W, B, Skid loader, D.G, Pick-up

Work Area / Equipment:


KOC
Facility: NEW NEW GATHERING CENTRE GC-32 Permit No.
Emergency-160
GC-32 AREA- TSF O&G Date:
90030980 (PIL)

Personal Protective Equipment & Tools: Hard Hat, Safety Shoes, Safety Goggles/Face shield, Hand Gloves, Overall with
reflective stripes, Hand tools & Power tools
Sequence of
Potential Hazards Precautions
Basic Job Steps

 Project HSE Induction and EOD training other job related


Non-compliance with KOC awareness training.
HSE Procedures  Permit to Work and Excavation Notification controls in place.
(Confined Space Permit for all excavations >1.2m).
 Pre-task TBT relevant to job hazards for every activity daily.
 Project Trainings & Safety induction / Visitor induction shall be
attended
Inexperienced / New  Ensure Heavy equipment operators, riggers and flagman
Employees / Visitors completed third party competency training.
 Only trained and competent personnel are allowed to perform
the activities.
Pre - work
 Ensure all equipment are inspected and certified as per KOC.
Equipment Failures
SA.013 Temporary Mobile Equipment Procedure.

 Ensure driver of the vehicle have completed Defensive Drive


Training by the Contractor.
Non-defensive Driving  Strictly follow Company driving procedures, Kuwait Ministry of
Interior Traffic Regulations.
 Comply with Company Safe Driving procedure HSEMS-SA-016
 Seat belts worn at all times by all personnel.

 Do not drive in Foggy/ Dusty/ rainy weather condition in case


Getting lost in the field
of poor visibility.
(Fog / Sand / Rains)
 Provide rain coat to personnel in case of rains.
 Locate UG services using a calibrated metal detector.
 Prepare scan report for underground services
 Identify the services found and provide barriers and markers.
Damage to AG/UG services  Isolate services as needed through authorized permit.
 Expose manually the UG services.
 Confine work within the boundary of the approved worksite.

Unauthorized access of  Install adequate number of warning signs & lights.


worksite  Conduct Toolbox Talk.
Survey & Scanning

Blocked access to  Ensure the approach to emergency equipment is not blocked


emergency equipment tools and equipment’s.

 Ensure that all electrical power tools used for cutting timber /
formwork is properly inspected, all safety devices / guards are
Rebar and Fire and Explosion operational and in place; the equipment is used in a safe
Shuttering works manner by an experienced operator.
 All electrical cables, plugs, sockets, earthling is properly
inspected and fit for purpose.
Page 1 of 5
 Ensure that rebar is correctly stored, segregated and
barricaded at all times.
 Ensure that “off cuts” (rebar or timber) are not left underfoot
Exposure to Extreme to cause a hazard. Collect and dispose off in the waste skip.
Weather  All rebar protrusions are properly capped, to avoid puncture
wounds, and where necessary identified with warning tape to
minimize trip or other hazards.

Formwork inadequately
 Formwork correctly braced and supported to take concrete
supported to take the
load without collapsing.
pressure of concrete.

Timber and nails during


 Remove nails as soon as possible, and dispose off timber /
removal of formworks /
formwork which cannot be re-used in the skip.
shuttering.

 Ensure the work place is maintained clear of debris, waste and


Personnel injury
other rubbish and make the place clean and tidy.

 Workers must wear safety harness and tie to secure lifeline /


anchorage point at all times as necessary.
 Worker to remove shuttering materials from a safe distance.
 De-shuttering to be done part by part (or) section by section.
De-Shuttering Activity Falling of objects &  Materials to be removed from the area as and when it is
personnel from heights getting accumulated.
 Wood and other shuttering materials to be removed
immediately after de-shuttering.
 De-nailing has to be done immediately after de-shuttering of
wooden materials.

 Ensure driver of the vehicle have completed Defensive Drive


Training by the Contractor.
Unsafe Driving  Strictly follow Company driving procedures, Kuwait Ministry of
Interior Traffic Regulations.
 Comply with Company Safe Driving procedure HSEMS-SA-016
 Seat belts worn at all times by all personnel.

 Do not drive in Foggy/ Dusty/ rainy weather condition in case


Getting lost in the field of poor visibility.
(Fog / Sand / Rains) Ensure only travel at designated routes or areas certified as
cleared with EOD.

 Be cautious about the trap point on the concrete mixer.


Trap hands/fingers Ensure access way for equipment’s are clear of pedestrian of
Concrete Pouring work crews.
using truck mixer
 Ensure loose items and clothing is secured.
Rotating equipment
Rotating parts of the equipment’s shall be properly guarded.

 Ensure face shield, disposable coverall and gumboots for the


person assigned for concrete activities.
Splash Concrete
 Wear appropriate PPE.
SDS of concrete to be attached with Permit to Work.

 Flagman should be assigned to control and monitor equipment


and manpower movement during the work.
Collision of Equipment to
 Provide adequate warning signage as required.
personnel
Ensure emergency first aid facilities are available with the
team and presence of qualified first aider at all times whilst
works is ongoing.

Page 2 of 5
 Do not position the equipment close to the trench /
excavation, overhead power lines.
 Ensure ground is stable and properly compacted as required for
Positioning of crane on
positioning of crane.
unstable ground
 Ensure crane outriggers pad of adequate size and thickness.
 Ensure 360 lifting radius of the crane are properly barricaded
with posted warning signs.

 Ensure all Cranes are inspected with necessary authorized 3rd


party inspection certificates and color coded.
 Do not overload the lifting capacity of the crane as per
manufacturer standards under any circumstances
 Do not exceed 75% of the rated capacity of the crane for any
Mechanical failure lifting and shifting works.
 Do not override any inbuilt safety devices or take short cut
during the lifting operations.
 Ensure duly accomplished specific lifting plan as per the load
about to be lifted.
 Ensure daily equipment inspection checklist done by operator
prior to starting the work.

 All worn lifting tools / tackles and those who don’t have 3rd
party certification must be removed from site.
Lifting tackles and sling
 All lifting tools and tackles must be free from grease and oils.
failure during the
 Ensure all lifting gears and shackles are inspected with
operation
necessary authorized 3rd party inspection certificates, good
condition and color coded.

 Ensure signal man or rigger is visible with fluorescent vest to


the crane operator during every phase of lifting activity and all
are 3rd party trained.
Lifting and Rigging
 Do not attempt any lifting operation on an extreme weather
Poor visibility condition i.e., heavy sandstorm, strong wind, thick fog, rain,
lightning etc.
 Ensure wind speed has been checked prior to starting of the
lifting.
 Ensure availability of anemometer during lifting operation.

 Do not stand below or near the suspended load.


 Close supervision by a competent rigging supervisor during the
lifting operations.
 Ensure proper positioning of body parts during slinging avoid
exposing in the line of fire.
Personnel injury  Ensure emergency first aid facilities are available with the
team and presence of qualified first aider at all times whilst
works is ongoing.
 In case of medical emergency call KOC Emergency number
#160.

 Conduct regular visual inspection of all lifting gears and


mechanism of crane prior to start any lifting operation by a
competent rigging supervisor/foreman.
Damage of equipment
 Provide adequately strong and long tag lines at both ends of
the load.

 Conduct survey prior to start any lifting operation inside


confined space by a competent rigging supervisor/foreman.
 Ensure gas test done prior to enter crane inside confined space
 The working ground must be compacted and free from
Crane positioning inside
loose/wet soil.
confined space
 Provide proper and safe access to enter crane inside confined
space.
 Only trained personnel shall be deployed
 Close supervision shall be provided
Page 3 of 5
Remove any clutter in work area. Practice good
housekeeping prior to starting any work. Clean up
Trip, slip, fall--Fire and or
spills and remove any combustible or flammable
explosion
materials. Note location of nearest fire extinguisher/s
and fire blanket/s.
Exposure to Grease,
Vehicle Maintenance oil/petrol products Do not get engine oil, grease on your skin or clothing -
may have toxic effects. -- remove clothing and wash skin immediately. Practice
Improper good housekeeping, clean up any spills. Follow
disposal of waste oil and government guidelines for the recycling of waste oil,
filter will have grease and filter.--
environmental impact
 All tools shall be kept free of mushroom heads
 Goggles should be worn to protect the eyes
Flying chips of metal  Wear gloves
Use of hand tools  Use Chisel holder
and power tools  Never use a screwdriver in place of a chisel
 Replace all cracked or busted wooden handles, to prevent
Hand cuts or abrasions pinching of hands
Never use tape or glues to repair broken wooden handles
 Tool box talks must be carried out and all crew will be briefed
with the job hazards
 All trip hazards from the area shall be cleared-off
 Not to climb or stand on the running facilities while doing
Slip trip & Fall photography.
 In case of work at high elevations proper Work at height
restrictions shall be complied
 Proper caution while working on platforms and deep trench
edges
 Personnel shall be trained and experienced in usage of the
equipment.
Photo Snap Shots  Competent supervision must be ensured
Improper Handling of  Batteries and other accessories shall be properly installed prior
Equipment /Camera to
Enter in the site.
 Keep the Camera switch off when not in use
 Not to keep the camera unattended at site

 Regular visual inspections shall be carried out prior to use the


Fire & Explosion
camera at hazardous and restricted areas.
 Photographer should aware of the areas restricted for
Non Compliance with Site photography and required permissions shall be obtained.
Safety Rules  Only authorized and approved personnel shall use the camera
for photography.
 Ensure the work place is maintained clear of debris, waste and
Personnel Injury due to
other rubbish and make the place clean and tidy.
poor housekeeping
Post Work  Close the trench, backfill & compact the area.
Trenches left open for
 Close the permit after making the site clean & tidy.
extended period
Had barricade / signage in English/Arabic.

 Drink water frequently to avoid dehydration (during both


summer and winter)
 Working schedules to avoid hottest times of day, with regular
Heat Stress / Extreme Cold rest/rehydration breaks (10-15mins/hr)
 Ensure emergency first aid facilities are available with the
team and presence of qualified first aider at all times whilst
works is ongoing.
Additional Hazards  In case of medical emergency call KOC Emergency number
#160.

 Do not touch any company assets without proper authorization.


 In case of strange objects are found, immediately stop the
Un-identified Objects
activity, evacuate all personnel from the work location and
exposure
inform Company representative or call KOC safety / EOD as
appropriate at 160

Page 4 of 5
 Awareness training on dangerous and poisonous animals
Biological hazards, animal
 Do not feed stray animals / wild life. Ensure buddy system is
bites
implemented.
JSA Done By Controlling Team: MP-III, TEAM-XI
Name:
Permit Applicant /
Controlling Team /
KOC No. Signature:
Asset Owner

Name: Controlling Team: MP-III, TEAM-XI


JSA Reviewed By
Permit Issuer
KOC No. Signature:

Page 5 of 5