Professional Documents
Culture Documents
Example On Schedule Compression: DR - Sawsan Hamzeh
Example On Schedule Compression: DR - Sawsan Hamzeh
Dr.Sawsan Hamzeh
Example
Dr.Sawsan Hamzeh
example
activity IPA Duration (days ) cost (unit currency )
F C 4 4 500 500
G D,F 7 5 700 1000
Dr.Sawsan Hamzeh
example
5,12
B
7
6,13 13,19 19,25
E H
0,5 5,13 6
25
6
A C
5
13,19 19,25 PF
8
0,5 5,13 25
13,17 17,24
F G
5,16 4 7
D
11 14,18 18,25
7,18
Dr.Sawsan Hamzeh
solution
This simple project has five paths they are listed next
,along with their length in days :
Dr.Sawsan Hamzeh
solution
Dr.Sawsan Hamzeh
solution
Dr.Sawsan Hamzeh
solution
Dr.Sawsan Hamzeh
solution
Dr.Sawsan Hamzeh
solution
Dr.Sawsan Hamzeh
solution
Days cut -- 1 1 1 1 1 1 1
Project duration 25 24 23 22 21 20 19 18
(days)
Increased cost -- 40 50 100 140 165 225 270
day
Direct cost 4,950 4,990 5,040 5,140 5,280 5,445 5,670 5.940
(currency)
Indirect costs 3,000 2,880 2,760 2,640 2,520 2,400 2,280 2,160
(currency)
Total cost 7,950 7,870 7,800 7,780 7,800 7,845 7,950 8,100
(currency)
Dr.Sawsan Hamzeh