Professional Documents
Culture Documents
Appeal Report Draft - For Discussion
Appeal Report Draft - For Discussion
L A K E V I C T O RI A N O RT H W A T E R CE N T R AL R I F T V A L L E Y W AT E R W O R K S
W O R K S DE V E L O P M E N T A G E N C Y D E V E L O P ME N T A G E N C Y
CO N S U L TA NC Y S ER VI C ES F O R D E S IG N R E VI E W A ND
CO N S T RU C T IO N S UP ER V IS IO N O F MA LA B A W AT E R S U P P LY AN D
S AN I TA T IO N P R O J EC T
DR AF T NE M A AP P EA L P AP ER
PREPARED BY
1. Back ground Information on NEMA Application
The Environmental Impact Assessment for Malaba sanitation project was done and submitted to
NEMA in September 2019, the request for further public participation through adverts were
received in October 2019 and successfully advertised between December to January 2020 in the
local dailies, local radio and the Kenya Gazette and the same evidences submitted to NEMA.
The NEMA review process took a very long time and the 1st review comments were received on 17th
November 2020 which were adequately addressed and responses shared with NEMA on 14 th
January 2021. The advance copy of the second review comments were send to the agency on 4th
May 2021.
In the second review, the authority raised pertinent issues as shown below
i) The proposed site for the wastewater treatment plant extends into a wetland which is an
environmentally sensitive area.
ii) The wastewater treatment plant is located within two rivers i.e., Malakisi and Komiria rivers
that join downstream into Transboundary River Malaba draining into Lake Kyoga in
Uganda. River Malaba is a shared resource between Kenya and Uganda and there is No
evidence of consultation and/or notification with the Uganda Authorities in line with the
guidelines on shared resources in East Africa.
iii) A comprehensive risk assessment and analysis of alternatives of the project and its
associated facilities and amenities had not been undertaken to inform the project location
and have the appropriate environmental and social safeguards.
iv) Precautionary principle: the project has potential public health risks, transboundary
resource use conflicts and other uncertainties due to its scale and nature in relation to
adjacent environmentally sensitive area.
This paper therefore has been prepared for submission to the authority for reconsideration for the
issuance of an EIA license under the provision of Emca 1999
The following key Aspects of project design were considered and can be discussed briefly as follows
The composition of the liquid waste depends on its source. The three main sources are
• Residential,
• Commercial, And
Stormwater is also a source of liquid waste and an allowance of 15 % of infiltration of ground water
and storm drain has been allowed in this design. Liquid waste from domestic sources can be classified
as blackwater, which contains excreta, and greywater. Liquid waste from commercial areas is broadly
similar to wastewater from residential areas they mainly consist of Fats and oil and minor quantities
chemicals from restaurants, hospitals, offices, schools and cafes around the town and its environs.
The characteristics of industrial wastewaters depend on the type of industry. Some industrial
wastewaters are hazardous. The characteristics of wastewaters can be described in physical, chemical
and biological terms.
Physical characteristics include the number of suspended solids, the temperature and odour.
The quantity of organic matter in liquid waste is an important measure of its polluting potential. If
discharged into a river or lake, organic matter exerts an oxygen demand which can reduce the
availability of oxygen for fish and other aquatic organisms.
Organic matter is measured in terms of biochemical oxygen demand or chemical oxygen demand.
Industrial wastes in towns produces liquid wastes are such as waste food, textiles and tanneries
chemicals and solid wastes etc. In Most cases Industries produce polluting liquid wastes that should
be treated before being discharged into the environment
Shown below is the schematic layout of the proposed sewerage pipelines and layout with their flows.
The total discharge for phase one is 4000m3/day
The figure above shows the main trunk sewer and interconnection of sewer networks as was designed
The following treatment process were considered in the selection of appropriate wastewater
treatment methods;
• Design temperature, which is the mean air temperature in the coolest month has been taken
as 23oC;
• Net evaporation, which is the mean evaporation in the coolest month has been taken as
5mm/day;
• Wastewater flow assumed to include no seepage (infiltration) water since there is no collection
pipe work;
• The works have been designed based on the peak dry weather flow (PDWF), obtained from
multiplying the average dry weather flow (ADWF) by a peak factor of 1.4;
• Ponds have been specified to be located at least 500 m downwind from any residential area,
to create required buffer zone;
• Ponds have also been specified not to be located within 2 km of any airport/airstrip;
• Vehicular access to the ponds has been considered to form part of the works (access roads).
• The soil at the proposed site has been observed to be clayish in property and stabilization may
be necessary as specified to be sufficiently stable with minimum seepage to minimize
compaction.
Primary treatment
Inlet chamber
The design of inlet chamber has been based on the following criteria:
Screen’s chamber
Grit chamber
The design of grit chamber has been based on the following criteria:
The design of the sullage channel has been based on the following criteria:
Distribution chamber
The design of the flow distribution chamber has been based on the following criteria:
Secondary treatment
The waste stabilization ponds have been designed to achieve effluent standards of un-restricted
irrigation i.e. <15 mg/l BOD5 and <100 FC/100 ml.
a. Length to breadth ratio of 1:1 for the equivalent trapezoidal section have been adopted in this
design for the anaerobic ponds;
b. Three number of anaerobic ponds in parallel have been considered to allow for maintenance;
c. Assumed liquid depth of pond is 3m;
d. Assumed free board depth or depth of bund for trapezoidal section is 0.5m;
e. The ponds have been sized to receive BOD of up to 330g BOD/m3/day according to the
volumetric loading criteria shown in the following table and design temperature of 23oC;
The loadings and the corresponding percentage BOD removal adopted are shown in the Table below:
Table 5-2: Volumetric loadings and percentage BOD removal
• Anaerobic pond volume design was based on BOD of the raw wastewater, mean wastewater flow
and volumetric organic loading rate as related by the following formula:
V=Li Q /λ v
Where:
Li=influent BOD
(g/m3); Q=flow
(m3/day); V=pond
volume (m3);
λ v=volumetric organic loading rate (g/m3.day).
• Using the removal efficiency (E) estimated from the table above, the effluent
concentration (BODeff) of the anaerobic pond was calculated from the following
equation:
Where:
E=removal efficiency;
• Length to breath ratio of 1:3 have been adopted for the rectangular and equivalent
trapezoidal section for the facultative ponds in this design with orientation that optimizes on
wind induced mixing of the pond content;
• Three number facultative ponds in parallel have been considered to allow for maintenance;
• Assumed liquid depth of pond is 1.5m;
• Assumed free board depth or depth of bund for trapezoidal section is 0.5m;
• The ponds have been sized to receive BOD of up to 311 kg BOD/ha d;
• The facultative ponds have been assumed to have 80 % BOD removal;
• The surface BOD loading rate on the facultative ponds at the specified design temperature
was obtained from the following equation:
s=350x (1.107–0.002xT)T-25, where T is the mean temperature in the coolest month (0C)
The facultative pond area was calculated by using the following equation:
Af=10LiQ/λs
Where:
formula: t=AfH/Qavg
Where:
Q=average flow
(m3/day);
Therefore, t=2AfH/(Qi+Qe)
Mass balance of flow used in the design was given as follows:
If infiltration is negligible:
Q effluent=Qinfluent-0.001Afe
Where:
t=2AfH/(Qi-0.001Afe)
a) The above evaporation rate has been taken as 5mm/day in the design of facultative
ponds;
b) A minimum detention time of 5 days has been adopted in the design to minimise
hydraulic short circuiting and to prevent algal washout.
• Length to breath ratio of 1:2 have been adopted for the rectangular and equivalent
trapezoidal section for the maturation ponds in this design;
• The ponds have been designed for a minimum retention period of 3 days;
• Two series of two number of maturation ponds each in parallel have been considered to allow
for maintenance;
• Assumed liquid depth of pond is 1.2m;
• Assumed free board depth or depth of bund for trapezoidal section is 0.5m;
• It has been assumed that maturation pond will remove 25 % of BOD after removal by
anaerobic and facultative ponds;
• The method of Mara is represented by the following first-order kinetic model in a completely-
mixed reactor, has been adopted for the design of maturation ponds for faecal coliform removal:
Ne/Ni=1/[1+kTθ]n
Where:
For a series of anaerobic, facultative and maturation ponds the equation becomes:
Ne= Ni
n]
Where:
T=temperature (oC);
KT20=2.6.
The following three sets of conditions were considered to ensure that the maturation ponds are
designed satisfactorily:
θf>θm;
λsm1(BOD)≤0.75λsf(BOD)
Where:
Maximum BOD loading in the first maturation pond was assumed to be 75% of that of the preceding
facultative pond.
Where:
R=percentage removal;
The inlet chamber has been designed for a detention time of 10 sec.
One large inlet chamber with size 1.7m x 1.7m x1.0m and a liquid depth of 0.45m has been proposed
The coarse screen chamber has been designed for a flow through velocity of 0.6m/sec.
One coarse screen chamber with size 3.0m x 1.0 m x0.8m and a liquid depth of 0.30m has been
proposed.
(iii) Coarse screens
The coarse screens have been designed for a flow velocity (velocity a head of screen) of 0.6m/sec.
The proposed coarse screen details are as shown in the Table below:
The sullage channel has been designed for a flow through velocity of 0.6m/sec.
One sullage channel with size 3.71m x 1.0m x0.8m and a liquid depth of 0.3m has been proposed.
The distribution chamber has been designed for a detention time of 30 sec.
The distribution chamber with size 1.4m x 1.4m x3m has been proposed.
Anaerobic ponds
The anaerobic ponds have been designed to meet the following parameters;
The proposed size for the design of the anaerobic ponds for the drainage area is given in the table below:
Table 6-4: Proposed anaerobic pond size
Year No. Ponds Liquid depth (m) Pond top size (m) Free board (m)
2040 3 3 30 x 30 0.5
The above sizes have been obtained by computing dimensions of the equivalent trapezoidal shape
anaerobic ponds with side slopes 1 in 3.
Treated sewage from anaerobic ponds will be transmitted to the facultative ponds for further treatment.
Facultative ponds
The facultative ponds have been designed to meet for the following;
The proposed sizes for the design of the facultative ponds are given in the table below:
Year No. Ponds Liquid depth (m) Pond top size (m) Free board (M)
The tabulated sizes are for trapezoidal shape facultative ponds with side slopes 1 in 3 proposed with
required stability measures.
Treated sewage from facultative ponds will be transmitted to the maturation ponds for further treatment.
Maturation ponds
The maturation ponds have been designed to meet for the following criteria;
The proposed size for the design of the facultative ponds for the drainage area is given in the table below:
Year No. Ponds Liquid depth (m) Pond top size (m) Free board (m)
The tabulated sizes are for trapezoidal shape maturation ponds with side slopes 1 in 3 proposed with
required stability measures.
Treated sewage from maturation ponds will be transmitted to the constructed wetlands for further
polishing/treatment.
Regular monitoring of the quality of the treated sewage from maturation ponds through the constructed
wetlands will be done before the effluent discharge to nearby drainage system, used for irrigation and
or other preferred approved purposes.
Sludge drying beds
All sludge from the waste stabilisation ponds, together with any additional sludge that will be delivered
directly to the treatment plant, will undergo treatment by drying in sludge drying beds before disposal.
The table below shows the computations of the size of the proposed sludge drying beds.
. Table 1-3: Expected standard treated sewage characteristics from waste stabilization ponds which has
been achieved through considering all parameters are show in the table below
The designed components of the Waster stabilization Ponds to achieve the required standards can be
summarized as below
(i) Inlet chamber
The inlet chamber has been designed for a detention time of 10 sec.
One large inlet chamber with size 1.7m x 1.7m x1.0m and a liquid depth of 0.45m has
been proposed.
(ii) Coarse screen chamber
The coarse screen chamber has been designed for a flow through velocity of 0.6m/sec.
One coarse screen chamber with size 3.0m x 1.0 m x0.8m and a liquid depth of 0.30m
has been proposed.
(iii) Coarse screens
The coarse screens have been designed for a flow velocity (velocity a head of screen) of
0.6m/sec.
The proposed coarse screen details are as shown in the Table below:
(iv) Grit chamber
Minimum Size of Grit particle 0.15mm
Specific Gravity of Grit 2.65
Size of Grit Chamber 10.2 m x 1mx 1.5m
(v) Sullage channel with parshall flume
The sullage channel has been designed for a flow through velocity of 0.6m/sec.
One sullage channel with size 3.71m x 1.0m x0.8m and a liquid depth of 0.3m has been
proposed.
(vi) Distribution chamber
The distribution chamber has been designed for a detention time of 30 sec. A distribution
chamber of size 1.4m x 1.4m x3m has been proposed.
(vii) Anaerobic ponds
The anaerobic ponds have been designed to meet the following parameters;
Minimum temperature 23C;
Evaporation rate 5.00 mm/day;
Design organic load (inlet) 330g BOD/m3.day;
Design retention time 1.36 days;
Liquid depth in pond 3 m;
BOD removal 66 %.
(viii) Facultative ponds
The facultative ponds have been designed to meet for the following;
• Minimum temperature 23 0C;
• Evaporation rate 5.00mm/day;
• Design organic load (inlet) 311 g BOD/m3.day or kg/Ha-day;
• Design retention time 7.47 days;
• Liquid depth in pond 1.5 m;
• BOD removal 80 %.
(ix) Maturation ponds
The maturation ponds have been designed to meet for the following criteria;
• Minimum temperature 23 0C;
• Evaporation rate 5.00mm/day;
• Minimum design retention time 3 days;
• Designed retention time 3.5 days;
• Liquid depth in pond 1.2 m;
• BOD removal 25 %.
. Table 1-3: Expected standard treated sewage characteristics from waste stabilization ponds for key
parameters
The other parameters are as shown in the table below and to which the waste treatment plant has
been designed to achieve
A laboratory has been constructed at the pond site to monitor quality of the treated sewage from
maturation ponds before the effluent discharge to nearby river
(i) Sludge drying beds
All sludge from the waste stabilisation ponds, together with any additional sludge that will be delivered
directly to the treatment plant, will undergo treatment by drying in sludge drying beds before disposal.
Layout plan of Sewerage Treatment Plant fig 1
The goal of design review was to confirm site suitability for the Employers consideration for purchase
and development. Cost-related factors included land purchase, potential excavation and fill
requirements, which were found to be within the budget during design review stage of the project.
Below are some of the factors generally considered when selecting a site for WWTP and adopted in
many places of the in world.
i. Land-Use
In the Land-use Map, different areas of Malaba have been assigned varied existing and proposed uses.
Areas earmarked for residential, industries, agriculture, forests and social amenities are considered
less suitable for the location of a Wastewater Treatment Plant (WWTP). On the other hand, public
utility or undeveloped Agricultural Land located away from the sensitive residential areas are
preferred.
The distance from the WWTP site to the final receiving environment such as the river and ocean, is
an important consideration in site selection. Preference is given to the sites that require shorter lengths
of Outfall Sewers. When confirming the selected site the outfall distance was approximately 200m
which is within the range.
An ideal WWTP site should be located on a low-lying area of the sewerage system for gravity
conveyance. Otherwise, pumping stations become necessary thereby increasing both capital cost and
the operation and maintenance requirements of the sewerage system. The design for sewer network
reticulation were placed at an elevation able to collect waste from a wider project area, allow also for
future extension. The sewer networks from various high points converges in to a single trunk line
which convey the wastes to a lowest pond of the town where the site for treatment plant was located
The slope at an ideal site should permit the gravity flow within the WWTP without requiring excessive
excavations for the structures. Slopes less than 1:20 are preferred. While confirming an initial survey
this condition was established and the slopes for this site found acceptable as per the required design
standards
v. Geological Conditions
A site with low water table and whose soils are impermeable is considered ideal with respect to
geological considerations. For instance, silt or clay soils are suitable for pond construction.
More often, the geological formation within an area is fairly similar. For instance, all the candidate
sites in Malaba comprise of a mixture of well drained, deep, dark red to reddish brown, friable, sandy
clay loam to sandy clay, with top soil of loamy sand and well drained, very deep, yellowish red, very
friable, fine sandy loam to fine sandy clay loam. These soils are suitable for WWTP (Waste Stabilization
Ponds) construction.
Proximity to infrastructural systems such as roads, electricity and portable water is sought for while
siting for a WWTP location. It reduces cost of construction and operation & maintenance requirements
of the WWTP. Sites that are closer to existing infrastructure are preferred. With these site accesses is
made possible by an existing murrum road which easily allows vehicles and truck to reach the site
while carrying out routine maintenance.
Treated wastewater can be reused for beneficial purposes such as agricultural irrigation, industrial
processes, ground water recharge, etc. Proximity to the potential re-use application and relative
elevation difference (for gravity conveyance) is preferred in siting of WWTP. For instance,
downstream arable land would make a WWTP site ideal for agricultural irrigation.
viii. Land Acquisition
In most places because of the topography and the long-time benefit of a gravity scheme the land
selected can be in private land which requires acquisition.
The following have been considered to further maintain the quality and the required standards
• The sides slopes of all the ponds have been lined with reinforced concrete class 20
• Double layer of Polyvine 35 have provided at the base of each pond to contain seepage bottom to
guarantee the quality of ground water
• Dykes are to be constructed in the space between the rivers and the sewerage pond this is to
guarantee that if flooding may occur in the future as a result of climate change the pond area will
not be flooded
• Trees to form a beaver zone are to be planted around the pond to control and maintain a good
ambience and control odour
• Proper landing scaping and planting of specialized grass will be done at the pond area to mitigate
on soil erosion especially of the loose soil around the pond
Through a letter Ref: NEMA/EIA/5/2/1643 addressed to Central Rift valley the Environmental agency
raised for issues that can be summarized below and we prepared brief responses in the meantime as
we prepare a proper appeal as earlier advised.
2. The wastewater treatment plant is located within two rivers i.e., The site is located on Lat :0°37'31"N
Malakisi and Komiria rivers that join downstream into and Long :34°13'12"E where river
Transboundary River Malaba draining into Lake Kyoga in Malakisi joins Malaba river and not
Uganda. River Malaba is a shared resource between Kenya and where komiria Joins Malakisi which is
Uganda and there is No evidence of consultation and/or located and these should be reviewed.
notification with the Uganda Authorities in line with the
guidelines on shared resources in East Africa.
3. A comprehensive risk assessment and analysis of alternatives of The feasibility study was adequately under
the project and its associated facilities and amenities had not and submitted to NEMA
been undertaken to inform the project location and have the
appropriate environmental and social safeguards.
4. Precautionary principle: the project has potential public health • No Health risk is posed to the public
risks, transboundary resource use conflicts and other since the ponds have a lining on
uncertainties due to its scale and nature in relation to adjacent both the walls and Lining at the beds
environmentally sensitive area. to mitigate against infiltration of
waste water into the underground
Baseline Situation
As part of baseline water quality assurance at EIA stage and as provided by water quality regulations,
2006 (legal notice no. 121) EMCA 1999 Cap 387. The surface water quality analysis including both
bacteriological and physiochemical analysis of the receiving Rivers Malakisi and Malaba was carried
/ will be out at the proposed river outfall points. The objective was to assess the baseline Biological
Oxygen Demand (BoD5) and other physiochemical parameters including Chemical Oxygen Demand
(CoD), pH, Conductivity and Total Dissolved Solids (TDS) and Total Suspended Solids (TSS) of the
rivers before establishment of the WWTP.
The results of water sampling are summarized table below. Detailed laboratory report is given / will
be in Appendix of this paper.
*Adopted effluent disinfection method is the Waste Stabilization Ponds (WSPs) comprising of
Screening + Anaerobic Ponds +Facultative Ponds + Maturation Ponds
Other water pollution related mitigation measures adopted by the project design are
associated with the parameters listed below
• Lining of Waste Water Stabilization ponds beds to mitigate against infiltration of waste water
into the underground water aquifers
• Construction of dykes around the Waste Water Stabilization ponds to protect the ponds for
risks associated with flooding.
• Channeling Treated effluent downstream the existing water intake to Uganda side to reduce
pollution risks
• Hydrological assessments were done to determine the level of flood impact at the proposed
site
2. Impacts on Soils
• Adopted mitigation measures above will also mitigate against potential pollution of soil resources
from pollution agents related to raw sewerage contamination
3. Cumulative Impacts
Adverse cumulative impacts to downstream biophysical and social economic setting was will be
analyzed during the ESIA in two folds; (i) downstream cumulative impacts on biodiversity triggered
by likelihood of contamination of the Malaba River by raw sewerage in the event of overflows during
floods and blockages, And (ii) Pollution risks to downstream water users triggered by likelihood of
contamination of the Malaba River by raw sewerage in the event of overflows during floods and
blockages.
Baseline Situation
Therefore, in order to map available biodiversity within the Malaba River and present an inventory
aquatic fauna and terrestrial fauna who depend on Malaba river basin. Finding from the biodiversity
survey was as listed in Table below
Two-day report writing meeting at Busia to be 10 (CRV, LVN, Consultant and Busia
submitted to NET County)
Type and source of effluent The effluent will be from Wastewater Treatment Plants. The Wastewater
Treatment Plant will be treating Domestic, Institutional, commercial and
Industrial wastewater.
Domestic,
Institutional,
Commercial and Wastewater
Receiving River
Industrial Treatment Plant
Wastewater
Design of Effluent treatment The proposed Wastewater Treatment Plants are Wastewater
plant