Professional Documents
Culture Documents
Specifications Section 1 General
Specifications Section 1 General
1
Class " A " - 1:2:4 - for footings, columns, slabs, beams
Class " B " - 1:2 1/2:5 - for concrete floor on fill and other concrete works
Class " C " - 1:2 - for plastering and mortar
Class " D " - 1:5 - for CHB mortar
2
Ground floor concrete slab with 4" minimum thickness shall be rough finished
(exterior along shower area and concrete benches).
3.8 Inspection
No pouring of concrete shall be done unless the bearing surfaces has been
inspected and approved by the Owner, and the Authority to proceed has been
received by the Contractor.
3.9 Drainage System @ Site
Provide, construct and maintain for the duration of the work, drainage system of
the site approved and or as directed by the supervising Architect or Engineer.
3.10 READY MIXED CONCRETE
All ready mixed concrete shall conform with the requirements of ASTM C-94, placed
in forms within one hour after adding water or not more than ½ hours if a
retarder is used. It shall be kept constantly agitated during the transit period.
Pouring of concrete should not be started until after the forms and reinforcement
for the whole unit are properly laid and installed, cleaned, inspected and
approved.
Construction joints shall be rough-in and clean thoroughly before any pouring
starts. Wet and slush surface with cement mortar.
Section 4 CARPENTRY AND JOINERY WORKS
The work to be done under this Item consist of furnishing all required materials,
fabricated woodwork, tools, equipment and labor and performing all operations
necessary for the satisfactory completion of all carpentry and joinery works in
strict accord with applicable drawings, details and these Specifications.
Section 5 TILE WORKS
Toilet walls unless specified shall be waistcoat with white/colored 8” x 8”
glazed tiles or chlorinated paint of any brand, at 2.0 m. high. All glazed tiles
shall be laid on concrete mortar, 1/8" apart. Toilet floors shall be laid with
unglazed tiles or chlorinated paint of any brand whichever is available. Care
must be fitted properly around the plumbing fixtures and trench drains. Tiles
must be soaked in water before installation.
Section 6 TINSMITHRY
Rib type or Tile span roffing gauge 26 by DN Steel Corporation to be used shall
nailed and secured to the purlins. Purlins shall be spaced to fit length of
corrugated sheets 0.60mm x 1.090 mts. X LS. Provide Ventilator hood 0.60mm x 1.20
mts. x 2.44 mts and end flashing 0.60mm x 0.915 mts. X 2.44 mts. Use 0.60mm x
1.20 mts. x 2.44 mts. Gutter. It shall be provided with at least 3/4" per foot of
pitch to downspouts. Downspouts shall be provided with sufficient G.I. straps to
the walls. Catch basin connected to drainage shall be provided below each
downspout. All joints shall be welded with rod #6013.
Section 7 HARDWARE
Provide and install all rough hardware necessary for the completion of the work
including nails, spikes, WI straps, bolts, etc., and all finishing hardware
herein specified. All works shall be done in workmanlike manner. All doors shall
be provided with door lock set. Where the exact types of hardware specified are
not adoptable to the finishing, shape or size of members requiring the hardware,
suitable types having as applicable the same operation and quality as the
corresponding individual types specified shall be furnished.
Section 8 ELECTRICAL WORKS
8.1 General
All electrical equipment installations covered by main construction shall be in
accordance with the latest edition of the Philippine Electrical Engineering Code
and must conform to the provision of the National Building Code and Fire Code.
8.2 Wiring Methods
a. All wiring that run through CHB walls and concrete floorings shall be in PVC
conduits. All parts of the installations shall be put in proper places at such
stages in the progress of constructions as to permit cabinets, pull boxes and
other outlet boxes to be mounted on flush. All conduits to be run in the most
direct line possible and entirely concealed.
b. Conduits shall be continuous from outlets to outlets; and from outlets to pull
boxes in such manner that the conduit system shall be electrically continuous
from the service entrance to an outlet.
c. All conduit system shall be completed before the wiring is started.
8.3 The number of ceiling, convenience outlets and others shall have been shown in the
electrical plans and layout including their location and site.
3
Use white switches and convenience outlets on painted surface and brown on varnish
surfaces. No wire smaller than #8 AWG shall be used.
8.4 The main switches and distribution panel should be located inside the unit in an
easily accessible location.
Section 9 PLUMBING WORKS
9.1 General
All plumbing works and installations shall be done in accordance with the latest
edition of the Plumbing Code and must conform to the Provisions of the National
Building Code.
9.2 Piping
a. Water piping shall consist of standard galvanized steel pipe with galvanize
iron fittings, which shall have a minimum of 1” , 3/4” and 1/2" in diameter.
b. Sanitary piping and fittings buried in the ground shall be the pvc pipe moldex
or neltex brand as approved by the Master Plumber or Sanitary Engineer.
c. Exposed vent pipe shall be 2" diameter and shall be of PVC Pipe.
9.3 Fixtures
The following fixtures shall be provided:
a. American Standard Under-counter Lavatory (optional only)
(Ovalyn including P-Trap/Strainer)
b. Single hole Lavatory Faucet w/ one supply pipe (Sannix)
c. American Standard Water Closet w/ Sloan Flushometer (Clarisse)
d. Urinal w/ Sloan Flushometer (Eco Washbrook)
e. Stainless curtain Rod 1” diam x 1.5m
f. Stainless towel rod ¾” diam x 0.60m
g. Soap Holder (Symphony)
Section 10 PAINTING WORKS
10.1 Preparation of Surfaces
Prior to paint applications, all surfaces shall be dry clean, smooth and properly
prepared to receive finish.
10.2 Concrete Masonry and other plaster surfaces shall be coated with a solution of
one-kilo zinc sulfate crystal per gallon of water and be allowed to dry
thoroughly. Brush all excess crystal deposit after surfaces dried before priming
coat paint is applied. Before painting, remove all dust and loose mortar by
sweeping and brushing with a stiff fiber or wire brush.
10.3 Painting Schedules
All painting shall be done in two coatings and shall not be done continuously at
the same time.
All exterior and interior areas or surfaces to be painted shall be done as
directed or specified by the Engineer/Architect during progress of construction.
All Painting materials that will be use shall be of BOYSEN brand.
All colors shall be in accordance with samples or color code approved by the
owner with the advice of the Architect/Engineer in charge of the project.
Section 11 TILE WORKS
11.1 Toilet walls unless specified shall be 8” x 8” non skid floor tiles and 8” x
12”glazed wall tiles or of any approved brand, at 1.50 m. high. All glazed tiles
shall be laid on concrete mortar, 1/8" apart. Toilet wall tiles shall be mixed with
tile adhesive and grout. Care must be fitted properly around the plumbing fixtures
and trench drains. Tiles must be soaked in water before installation.