Professional Documents
Culture Documents
TYNDP Cost-Benefit Analysis: From Assessment Indicators To Investment Decisions
TYNDP Cost-Benefit Analysis: From Assessment Indicators To Investment Decisions
TYNDP Cost-Benefit Analysis: From Assessment Indicators To Investment Decisions
TYNDP 2018
TYNDP Cost-
Benefit Analysis
from assessment
indicators
to investment
decisions
Final version after public consultation and
ACER opinion - October 2019
— Executive Report – Contains the key insights of the whole TYNDP package
through its two-year cycle.
— Regional Reports – Based on the four projects of common interest (PCI) regions,
the reports focus on the regional challenges of the energy transition.
— Communication – These reports communicate how we have interacted with our
stakeholders and improved the TYNDP package from 2016 to 2018.
— Technical – These reports give a deeper insight into the technical subjects,
including how we use our data, and the technical challenges of energy transition.
Executive
summary
The energy system and energy market of the TYNDP 2018 – TYNDP CBA from assessment indicators to investment decisions
future are being built today by its participants.
The investment decisions in the energy sector
today should re lect a compromise between
cost effectiveness and technical feasibility.
1
ENTSO-E is striving to outline the main parameters that Overall the TYNDP 2018 showed a decline in the
should facilitate the investment decision process and benefits of its projects as compared to the
provide consistent interpretation of the assessment predecessors. This is caused by both Scenario
results that are being produced in the TYNDP. assumptions, that have changed significantly for
TYNDP 2018 compared to TYNDP 2016 and
While the current report highlights the differences methodologies that have been improved and
between the current TYNDP 2018 CBA results increased in complexity for the new release of this
compared to TYNDP 2016, it is worth acknowledging TYNDP.
that the CBA methodology applies a multi-criteria
analysis, as many of the indicators cannot be In summary, the following parameters which influence
monetized. Such non-monetized indicators (security of the TYNDP CBA indicators:
supply, flexibility, stability etc.) should not be
underestimated as they are expected to play an — Climatic conditions
increasingly significant role in the future of the energy — RES installed capacities
transition in Europe and worldwide. — Fossil fuel installed capacities
— Fuel and CO2 prices
The system needs analyses performed by ENTSOE for — Transfer capacities
the TYNDP 2018 showed the necessity for the — Uncertainty ranges.
construction of transmission projects, even with
reduced monetized benefits during the CBA phase.
Therefore, whilst this insight report concentrates on the
overall comparison of the monetarised CBA analysis
results between the TYNDP 2016 and 2018 and the
reasons for this, the impact on the each individual
transmission project CBA must consider the totality of
the monetized and non-monetized indicators for any
given project.
Figure 1.1 Drivers for change for 3 main monetarized CBA Indicators
Transfer capacities
Switch in
RES generation generation
merit order
Installed capacities
for RES
2
Section 2
Introduction to the
TYNDP Cost Benefit
Analysis
The TYNDP CBA is conducted every 2 years by ENTSO-E and acts as reliable basis to
define the benefits of potential candidate projects for the Projects of Common Interest
(PCI) list and other electricity infrastructure within the ENTSO-E area. ENTSO-E
improves with each TYNDP the quality of data used for the studies, the processes used
to assess projects and to study other aspects of the expected future electricity system
and the communication of results.
This insight report provides an overview of the TYNDP 2018 CBA results evolution as
well as answers the question why TYNDP 2018 CBA results differ compared to the
results of previous TYNDP 2016.
Project benefits as
result of the scenarios
Figure 3.1: Relationship between project socio-economic welfare and price differences at the borders –
TOOT and PINT
0.20
R² = 0.92101
0.18
0.16
0.14
Average SEW/MW
0.12
0.10
0.08
0.06
0.04
0.02
0.00
0.00 5.00 10.00 15.00 20.00 25.00
Average price difference (€)
30.00
R² = 0.72797
20.00
Average SEW/MW
15.00
10.00
5.00
0.00
0.00 50.00 100.00 150.00 200.00 250.00 300.00 350.00 400.00 450.00
Average price difference (€)
5
The benefits of a project, independent of the type of
project, depend on the electricity system as a whole.
Information on, but not limited to, thermal and
renewable generation systems (generation capacities
and placement), consumption amounts and location,
the interconnectivity of market nodes and both fuel
prices and emission costs play an important role. All
these factors are part of the description of the
expected future electricity system – the TYNDP2018
scenarios.
Differences between
TYNDP16 and TYNDP18
project indicators
As concluded in the previous chapter, improvements to the methodology used
as part of the CBA 2.1 methodology and change in the scenarios in the scope of
TYNDP 2018 when compared to TYNDP 2016 have led to considerable changes
in the CBA results for the TYNDP projects.
These effects are caused by multiple reasons, with factors interacting with each
other. We have identified the main trends and drivers.
Figure 4.1: Comparison of average between all TYNDP 2016 and all TYNDP 2018 total ΔSEW for
selected projects
2000 200%
1500 150%
1000 100%
M€/year
500 50%
0 0%
-500 50%
-1000 -100%
RG BS RG NS RG CCE RG CSE RG CCS RG CSW ENTSO-E
Average
2
Selected projects for comparison were such that do not vary for more than 50% in delta NTC parameter and have not changed substantially in terms of network topology
between TYNDP 2016 and TYNDP 2018.
8
Figure 4.2: 2 TYNDP 2018 Reference Network Composition
IN PERMITTING3
UNDER CONSTRUCTION
COMMISSIONED
NETWORK OF TODAY
Overall, the evolution of the interconnectivity (sum network compared to 2030 CBA reference network in
of the import and export Net Transfer Capacities) for TYNDP 2016 are summarized in the Figure 4 3 below.
the market areas in the TYNDP 2018 CBA reference
Figure 4.3: Change of Import and Export NTC sum in TYNDP 2018 CBA network compared to TYNDP 2016
2030 network
y Redu
acit cin
g cap gc
ap
sin GB ES FR ac
rea DE 5000 CY ity MW
c NO RS
In
NL 4000 LV
MK 3000 HU
BE 1000 HR
0
BG AT
-1000
SE -2000 LUg
GR -3000 LT
DKe SK
NI SI
FI BA
DKw EE
PT CH
PL IT
LUf RO Import NTC change
LUb IS CZ ME Export NTC change
In TYNDP 2018 ”In permitting” project status is refered to planned projects able to prove by a written acknowledgement by a competent body
3
that application to the permitting phase has started (similar to the pre-application phase defined for PCIs defined in TEN-E).
9
It may be derived from Figure 4.3, that despite
a more restricted reference network in TYNDP 2018
as compared to TYNDP 2016, for some areas the
status of some transmission infrastructure had evolved
by the time of the project collection phase for TYNDP
2018, to increase the cross border or even cross
boundary capacity, e.g. for ‘boundary 2’ which is
strongly affected, (see more details in NSOG insight
report).
Figure 4.4: NGC/Marginal cost per generation technology – DE market node – Scenario 2025 BEST
Figure 4.5: NGC/Marginal cost per generation technology – DE market node – Scenario 2030 V2
5000
4500
4000
3500
3000
M€/year
2500
2000
1500
1000
500
0
2025 BEST 2030 ST
Marginal cost difference amplifier effect caused by is leading to volatility of the marginal cost in one market
increased wind generation area against the other thus causing the upward trend
As it has already been concluded, benefits of for the transmission infrastructure benefits in terms
transmission projects are driven by the generation cost of Socio-Economic Welfare.
differences between market areas. The uncorrelated
wind infeed from the RES generation distributed Increased volumes of wind generation amplify
around ENTSO-E based on the economic feasibility this effect.
0 100 200 300 400 500 600 700 800 900 1000
GWh
V4 V3 2030ST 2030DG 2030EUCO 2025BEST V2 V1
12
4.2
Changing ΔRES and ΔCO2 indicators
The ΔRES indicator has shown in overall a decreasing
trend at the ENTSO-E perimeter in TYNDP 2018.
Figure 4.8: Comparison of average between all TYNDP 2016 and all TYNDP 2018 total ΔRES and ΔCO2
for selected projects
14000 500%
12000
400%
10000
8000 300%
6000
200%
MWh/year
4000
100%
2000
0 0%
-2000
-100%
-4000
-6000 -200%
RG BS RG NS RG CCE RG CSE RG CCS RG CSW ENTSO-E
Average
5000 800%
0 0%
-1000
-200%
-2000
-400%
-3000
-600%
-4000
-5000 -800%
RG BS RG NS RG CCE RG CSE RG CCS RG CSW ENTSO-E
Average
1400
1200
1000
800
GWh
600
400
200
0
2020 V1 V2 V3 V4 2025 2030 2030 2030
EP BEST ST DG EUCO
Solar Wind
800
700
600
500
GWh
400
300
200
100
0
2020 V1 V2 V3 V4 2025 2030 2030 2030
EP BEST ST DG EUCO
700
600
500
400
GWh
300
100
0
2020 V1 V2 V3 V4 2025 2030 2030 2030
EP BEST ST DG EUCO
6000
TYNDP 2018 TYNDP 2018
5000
4000
3000
2000
1000
0
FLH
-1000
-2000
-3000
-4000
-5000
-6000
1982 1984 2007 2011
Figure 4.11 shows the variation of the full load hours in Switch to gas before coal merit order for the
comparison to the average of 4 Climatic Years (1982, Scenarios after 2025 horizon
1984, 2007, 2011) for different RES technologies as According to the TYNDP 2018 Scenario Storylines,
represented in Pan-European Climate Data Base reaching the RES penetration targets after 2025
(PECD) in ENTSO-E. requires more flexible low carbon technologies to
be built. In this regard the gas generation plays a
Overall, it can be seen in Figure 4.11 that the TYNDP significant role. Gas fired technologies in turn placed
2016's climatic assumptions lie between the in a large scale in the middle of the merit order scale,
3 climatic year conditions used in TYNDP 2018 limiting the variation of the CO2 emission factors from
in terms of full load hours of the different RES hour to hour, thus leading to lower CO2 emission
technologies. In the TYNDP 2018 calculations the variation.
weighted average of 3 Climatic Condition (1982,
1984, 2007) were used, which as a result show lower More optimized use of hydro generation
full load hours for the ENTSO-E region. The ΔCO2 results have partially dropped in the TYNDP
4.4
Lower uncertainty ranges due
to improved market modelling
Most of the CBA indicators of the project assessments The reason for such evolution, despite the fact the
are based on results of market studies, carried out results themselves have changed, is the fact that in
with fundamental market models (i.e. software tools TYNDP 2018 more sophisticated error checking
that try to simulate the electricity system as close methods were used ensuring higher precision. Also,
to the reality as possible). Even if the complexity the fact that 3 market modelling software tools were
of the market simulations has been increased in used.
TYNDP2018 (several climate years, multiple tools for
every assessment, results-comparison and outlier-
identification processes) – the confidence of the
market model results has increased noticeably in
TYNDP2018.
150 100%
80%
100
60%
40%
50
20%
M€/year
0 0%
-20%
-50
-40%
-60%
-100
-80%
-150 -100%
RG BS RG NS RG CCE RG CSE RG CCS RG CSW ENTSO-E
Average
1500 60%
1000 40%
500 20%
0 00%
MWh/year
-500 -20%
-1000 -40%
-1500 -60%
-2000 -80%
-2500 -100%
-3000 -120%
RG BS RG NS RG CCE RG CSE RG CCS RG CSW ENTSO-E
Average
1000 45%
30%
500
15%
0 0%
-15%
ktonnes/year
-500
-30%
-45%
-1000
-60%
-90%
-2000
-105%
-2500 -120%
RG BS RG NS RG CCE RG CSE RG CCS RG CSW ENTSO-E
Average