Hub material shell is “weld able steel casting” En8 to be used
according to mechanical property. 2no’s Hub to be machined. Keep some material in ID for maching after spoke welding (due to huge spoke welding pipe may get distortion in shape). All spokes to be welded as per degree on Hub OD. Spokes material shall be pressed or rolled as per drawing. Seating curve to be cut as per drawing and bevel to be prepared. Place it on Hub OD as per angularity back held all three spokes on OD of the HUB. Check the degree as per drawing and make root run check DP test and complete full weld. Re-machine ID of Hub ( if necessary) and joint to pipe shaft (OD 273).
First middle hub as per drawing root DP test to be carried out. If DP
test found ok, complete the weld. Use MIG wire (SG2)/flux cored wire 71T1 or E7018 electrode for hub to pipe welding. If material thickness more than 18mm a pre-heat of 100°C (212°F) in order to prevent cracking. Use low H2 welding consumables to avoid unacceptable hardening and cold cracking. Post weld heat treatment may be required to meet hardness limitations, if any specified. All spokes to be weld before welding the HUB on pipe shaft. Before welding the spokes with Hub end pipe shaft dummy to be weld to avoid distortion of shaft ID.
WELDING SEQUENCE FOR HUB WITH SHAFT:
First insert the middle hub.
Second insert bottom hub. Third insert top flange.
WELDING PROCEDURE FOR TOP FLANGE & SHAFT:
Pre machine the top flange except mouting hole.
Keep material on register dia on top flange face. Fix the Top Flange on drive end without face out with respect to pipe axis. Weld stiffener plate on pipe ID for centering and lefting the Top flange welding with pipe shaft and machining to be done before hub and spokes welding pipe shaft otherwise machining will be complicated.