TIME MANAGEMENT PLAN

Time Management Plan


Deliverables Sequence Activities Duration Precedence Critical Path
Project
management 1 Sign Contract 10 days ---- 10 days
  2 Create house map 21 days 1 21 days
Landscaping 3 Lay walk way 15 days 2 15 days
  4 Setup Lawn 7 days ----  
Foundation 5 Dig land 30 days 3 30 days
  6 Lay Foundation 20 days 1,2  
Architecture 7 Install Pillars and beams 40 days 5 40 days
  8 Construct Walls 75 days 3,7 75 days
  9 Roofing 30 days 7  
Mechanical work 10 Sanitary Fitting 15 days 2,6  
  11 Water Fitting 15 days 5  
  12 Gas Fitting 14 days 5  
  13 Water Pumps 10 days 11  
  14 Rain Pipes 7 days 11,13,5  
Electrical Work 15 Earthing 30 days 5  
  16 Electric Wiring 15 days 15  
  17 Installing electric meter 10 days ----  
Interior finishing 18 Installing tiles 25 days 3,8 25 days
  19 Woodwork 10 days 6,8,9  
  20 Painting 14 days 18 14 days
  21 Furniture 3 days 19,20  
  22 Install Lights, AC, Fans 2 days 17  
Exterior finishing 23 Brick Work 7 days ----  
  24 Wood work 5 days 3  
  25 Windows 7 days ----  
  26 Plastering 4 days 20 4 days
  27 Painting 3 days 26 3 days
Testing Architechural
Final Inspection 28 Work 2 days 2  
Testing Mechanical
  29 Work 1 days 2  
  30 Testing Elecrical Work 2 days 16  
  31 Testing Smart appliances 1 days 16  
Total     450 days   254 days

NETWORK DIAGRAM
TOTAL ACTIVITIES PATHS
TOTAL ACTIVITIES PATHS
No. of paths Paths Days
1 start+1+2+3+5+7+9+end 146
2 start+17+22+end 12
3 start+1+2+28+end 31
4 start+1+2+29+end 32
5 start+1+2+3+24+end 51
6 start+1+2+3+5+11+13+14+end 108
7 start+1+2+3+5+12+end 90
8 start+1+2+3+5+14+end 83
9 start+1+2+3+8+18+20+21+end 72
10 start+1+2+3+8+18+20+26+27+end 117
11 start+4+end 7
12 start+23+end 7
13 start+25+end 7
14 start+1+2+10+end 46
15 start+1+2+6+10+end 66
16 start+1+6+10+end 45
17 start+1+6+19+end 40
18 start+1+2+6+19+21+end 64
19 start+1+2+3+18+20+26+27+end 109
20 start+1+2+3+18+20+21+end 68
21 start+1+2+3+8+19+end 134
22 start+1+2+3+5+15+16+31+end 92
23 start+1+2+3+5+15+16+30+end 93
24 start+1+2+3+5+7+8+18+20+26+27+end 254
25 start+1+2+3+5+7+8+18+20+21+end 233
26 start+1+2+3+5+7+9++19+21+end 159
27 start+1+2+3+5+7++8+19+21+end 204

Critical path activities duration= 254 days.