Professional Documents
Culture Documents
Constrprt4 10 06
Constrprt4 10 06
Constrprt4 10 06
Pre-Construction Report
Section 5.36
Item 59.27
Prepared for:
Demicco Brothers Construction, Inc.
1580 Stillwell Ave
Bronx, NY 10461
Prepared By:
18 Pierson Place
Glen Ridge, NJ 07028
(646) 529 2577(Phone) (973) 337 2871 (Fax)
Project HWK-472W Reconstruction of Flushing Ave and Area
Pre-Construction Report April 10, 2006
Table of Contents
Table of Contents…………………………………………………………… i
1.0 Executive Summary……………………………………………………… 1-4
2.0 Description of Contractors’ Proposed Methods ………………………… 5-8
3.0 Building Condition Survey Requirements ……………………………… 9
4.0 Definition of “Radius of Influence” ……………………………………… 10-11
5.0 Anticipated Vibration Levels……………………………………………… 12-13
6.0 Recommended Allowable Vibration Levels……………………………… 14-15
7.0 Description of Recommended Vibration Monitoring Program………… 16-17
8.0 Settlement and Settlement Monitoring…………………………………… 18-19
Appendices
i
Project HWK-472W Reconstruction of Flushing Ave and Area
Pre-Construction Report April 10, 2006
Newmark Engineering, P.C. has been retained by Demicco Brothers Construction, Inc. to
prepare a preconstruction report and monitor and summarize the effect of construction
activities on structures within the influence line of work to be performed so as to ensure
that the Contractor’s operation will not create or aggravate any hazardous conditions, in
accordance with the requirements identified in Project ID HWK-472W, Section 5.35,
pages A5-13 through A5-16. Also included in this report is an analysis of underpinning
requirements in accordance with special note entitled “Shoring, Bracing, Underpinning,
Protection and Maintenance of Buildings and/or Structures”, pages A4-304 to A4-306.
For purposed of construction, the project has been broken into four phases as follows:
Phase I: a) Flushing Ave between N. Portland Ave and Franklin
b) N. Portland Ave between Park Ave and Flushing Ave
Phase II: a) Flushing Ave between Cypress Ave and Humboldt Street
b) Flushing Ave between Humboldt Street and Broadway
Phase III: a) Humboldt Street Between Flushing Ave and Varet
b) Flushing Ave between Broadway and Franklin
Phase IV: a) Flushing Ave between N. Portland and Flatbush Ave Ext.
b) Gold Street between Nassau Street and Sand Street
c) Sand Street Between Gold Street and Jay Street
¾ Identify and document the Contractor’s proposed construction activities that may
cause damage.
1
Project HWK-472W Reconstruction of Flushing Ave and Area
Pre-Construction Report April 10, 2006
On 3/31/06, Newmark Engineering, P.C. visited the site, interviewed contractor’s project
manager, reviewed the overall construction plans in the field and photographed the
exterior of existing buildings within the project limits.
Based on a detailed review of the project plans, contractor’s means and field conditions;
and review of a pre-construction building survey performed at 398-414 Flushing Avenue
(attached herewith to this report), quantitative analysis of existing building structure, we
have concluded that proposed watermain and sewer construction activities at the
intersection of Franklin Ave and Flushing Avenue, as indicated on contract drawings,
will result in potentially dangerous movement and settlement of this particular structure,
and would therefore create a life-safety hazard. In accordance with the referenced
building condition survey there is substantial structural distress in the west façade and
load-bearing wall contiguous to the proposed construction activities, which has
compromised the ability of this building to accommodate additional loads and strains that
would be effectively imposed by removal of groundwater, loss of lateral support and
construction-induced vibrations immediately adjacent to this building.
2
Project HWK-472W Reconstruction of Flushing Ave and Area
Pre-Construction Report April 10, 2006
general shear failure of the foundation wall. Because of the poor condition of the west
wall of this building and foregoing quantitative analysis, any underpinning performed
would need to consist of “top down” methods (i.e. methods working from existing grade
that do not require placement of support devices in pre-excavated pits) such as bored-in
secant pile wall, grout column and/or bored-in offset piles connected to existing
foundation wall.
We recommend that allowable peak particle velocity (PPV) for this project be established
at a level of 1.0in/sec for the project corridor, with the exception of the building located
at 398-414 Flushing Ave, where vibration levels exceeding 0.25 in/sec could easily cause
damage of an already fragile structure. Continuous vibration and crack monitoring at
multiple locations will be required when performing any construction work within 100
feet of this building. Anticipated vibrations levels within the corridor shall remain within
these allowable threshold levels so as to preclude structural damage.
3
Project HWK-472W Reconstruction of Flushing Ave and Area
Pre-Construction Report April 10, 2006
4
Project HWK-472W Reconstruction of Flushing Ave and Area
Pre-Construction Report April 10, 2006
5
Project HWK-472W Reconstruction of Flushing Ave and Area
Pre-Construction Report April 10, 2006
possible solution would be to connect the proposed 48” x 72” Tee connection
between existing and proposed water main and install new 48” trunk main over
existing 72” sewer using shallow cover protection rather than casing inside of the
existing 72” water main, eliminating the need for deep excavation support and
eliminating vibratory sheeting and deep de-watering. Vibration monitoring,
including provision for multiple seismographs and vibrating-wire transducer (i.e.
crack displacement sensors) to monitor real-time movement of existing major
building cracks is recommended for all construction activities to occur within 100
feet of the building at 398-414 Flushing Ave.
2.3 Stage 3 – Reconstruction of Sewers: Sewer reconstruction within this stage will
generally be installed in 8-12’ deep open trenches located above the water table
and beyond the radius of influence of existing structures, with the exception of the
24” RCP called to be installed in a combined trench with existing 72” water main
contiguous with the fragile west foundation wall of the building structure located
at 398-414 Flushing Ave (SE Corner of Franklin). Typically sewer reconstruction
will be installed in sheeted trenches using sliding rail sheeting, tight timber
sheeting or trench boxes. During this phase, removal of some groundwater may be
necessary, generally, depth of groundwater removal will be less than 2’. At 398
Flushing Ave underpinning of existing foundation would be required prior to
excavation activities, so as to prevent creation of a life-safety hazard caused by
removal lateral and overburden restraint provided by fill immediately adjacent to
the existing foundation wall. Design computations, attached herewith as
Appendix “B”, indicate that 10-12’ deep excavation immediately adjacent to this
structure will result in a 2.5 tsf reduction in bearing capacity, which comprises
62% of the presumptive bearing capacity of 4.0tsf of the fully stressed 8-65
material that the building is founded on. These computations indicate that
excavation for 24” sewer at this location a 10-12’ deep excavation adjacent to
existing wall would not be safe, and can cause a general shear failure and
subsequent collapse of the wall. Because of the poor condition of the west wall of
this building, underpinning would need to consist of “top down” methods (i.e.
methods that do not require pre-placement of support devices in excavated pits)
such as bored-in secant pile wall, grout column and/or bored-in offset piles
6
Project HWK-472W Reconstruction of Flushing Ave and Area
Pre-Construction Report April 10, 2006
2.5 Stage 5 – Construction of Curbs and Sidewalks: Curb and sidewalk removal
operations will be accomplished using pavement sawcutters and pneumatic
hammers to initially rubbelize existing sidewalk, and hydraulic excavator with
bucket to complete curb and sidewalk excavation. Demolition activities for curb
and sidewalk may occur within 10’ of existing buildings and could potentially
cause vibration levels above safe threshold levels. Also, portable pneumatic
vibrators may be used to proof roll subgrade, these also could cause vibration
levels above safe thresholds immediately adjacent to existing buildings. As a
result, vibration monitoring and control are recommended during curb and
sidewalk removal and subgrade compaction activities at locations deemed
sensitive to vibrations and directed by NYCDDC Resident Engineer.
7
Project HWK-472W Reconstruction of Flushing Ave and Area
Pre-Construction Report April 10, 2006
8
Project HWK-472W Reconstruction of Flushing Ave and Area
Pre-Construction Report April 10, 2006
Survey of the building at 413 Flushing Ave will be included in future revision Pre-
Construction report if required:
9
Project HWK-472W Reconstruction of Flushing Ave and Area
Pre-Construction Report April 10, 2006
4.1 De-Watering Operations: Within limits of Stage IV, between Gold Street and N.
Portland, the contractor proposes to remove groundwater from trenches using
open pumping or well-points beyond trenches. Proposed sheeting may not be fully
watertight, therefore it is anticipated that some lowering of the groundwater table
outside the sheeted trench limits can occur. An empirical relationship developed
by Sichart provides a Ro as a function of drawdown:
Soil types encountered within this phase consist predominantly of fine, loose sand
with silts(SM). According to Powers, permeability for this soil type will range
from 10 to 50 microns per seconds, because of relatively low N values 50 microns
per second is assumed. Based on the foregoing, the radius of influence will vary
as a function of drawdown in accordance with:
Ro = 21.2 (H-h)
Building lines are located approximately minimum 30’ from proposed trench
lines. Therefore if drawdown is under 1.5’ depth, de-watering will not
substantially impact existing buildings. According to plans, drawdown of greater
than 1.5’ depth will be required during installation of 48” Trunk Water Main
along Flushing Ave/Nassau Street between No. Portland and Gold Streets.
However, the exact position of water table may vary and this should be verified in
the field by Resident Engineer during excavation.
10
Project HWK-472W Reconstruction of Flushing Ave and Area
Pre-Construction Report April 10, 2006
11
Project HWK-472W Reconstruction of Flushing Ave and Area
Pre-Construction Report April 10, 2006
The following table summarizes the anticipated construction activities likely to generate
significant vibrations by stage, along with the expected range of vibration levels (peak
particle velocity or PPV) at the adjacent building lines (i.e. receptor sites):
Note that these levels will vary depending upon actual equipment used, precise location
of water table, and variations in density and type of geological profile between
construction activity and building line.
See Appendix “A” for a copy of a graph published by ASCE Journal of Geotechnical
Engineering which plots ranges of PPV expected at various distances for a variety of
construction activities. This graph was used to develop the expected PPV ranges in Table
1.0 above, however, values were not merely “picked” off the chart; engineering judgment
12
Project HWK-472W Reconstruction of Flushing Ave and Area
Pre-Construction Report April 10, 2006
and experience were used in combination with the published graph to establish the
predicted PPV ranges.
13
Project HWK-472W Reconstruction of Flushing Ave and Area
Pre-Construction Report April 10, 2006
A considerable amount of research has been done to correlate vibrations from single
events such as dynamite blasts with architectural and structural damage. The US Bureau
of Mines (USBM) and other researchers have established a safe vibration level as one
which a peak particle velocity of 2in/sec in any one of three mutually perpendicular
components is not exceeded by the ground motion at the structure of concerns. This is so
stated in USBM RI-8507.
However, according to USBM 8507, the allowable vibration levels for ground motions
below 40hz will be less than 2in/sec, and for ground motions below 12hz allowable
vibration levels are 0.75 in/sec. Construction-induced vibrations typically result in ground
motions that typically range from 6 to 40hz.
Potential for damage to existing buildings will depend upon the type of construction, age,
and natural frequency of the structure. The amount of vibration a given structure can
safely withstand depends upon its ability to safely accommodate additional strains
imposed by construction vibrations. The existing buildings within the project corridor
consist primarily of one to four story masonry buildings, there is considerable variation in
the age, type and use of the existing buildings, with newly constructed buildings (which
may have more ductility and ability to absorb strain) intermingled with older one to three
story “brownstone” type masonry structures and older industrial use buildings that may
be more “brittle” and have a limited ability to safely accommodate additional strains.
Based on the foregoing, it is recommended that PPV for this project be set to a reasonable
level of 1.0in/sec for the project corridor, with the exception of the building located at
398-414 Flushing Ave, where vibration levels exceeding 0.25 in/sec could easily cause
14
Project HWK-472W Reconstruction of Flushing Ave and Area
Pre-Construction Report April 10, 2006
damage of an already fragile structure, therefore the allowable vibration threshold for
activities within 100 feet of this location will be 0.25 in/sec. Allowable vibration levels
can be increased to account for ambient or background vibration levels due to traffic and
other sources. Specialized construction means and methods will be required to keep
vibration levels within safe limits when working in the vicinity of this building.
As can be seen from Table 1, with the exception of certain construction activities
occurring closer than 10’ from existing building lines anticipated vibrations levels should
remain within allowable threshold levels to preclude structural damage. Construction
activities occurring closer than 10’ from existing building lines as specified herein should
be monitored and Resident Engineer should direct contractor to use alternative means of
construction whenever potentially damaging vibration levels are reached immediately
adjacent to existing buildings.
15
Project HWK-472W Reconstruction of Flushing Ave and Area
Pre-Construction Report April 10, 2006
Benchmark Monitoring
Spot Monitoring
“Spot” vibration monitoring should also be deployed at any location where individual
building owners express concern regarding “annoyance” vibration levels. The protocol
16
Project HWK-472W Reconstruction of Flushing Ave and Area
Pre-Construction Report April 10, 2006
Continuous Monitoring
17
Project HWK-472W Reconstruction of Flushing Ave and Area
Pre-Construction Report April 10, 2006
seconds period and perform a detailed “event” plot further analyzing vibration if a
preset PPV is exceeded. Event trigger will be set to 0.5 in/second (i.e. 50% of
threshold level). If desired, audible alarms can be provided that can be set for 85%
of allowable threshold level.
• Continuous recording seismographs will be left in place for the duration of the
day and will be removed from the site at the end of the day.
• A report of results will be printed in the field and provided to the Resident
Engineer, construction superintendent and Contractor’s project manager.
18
Project HWK-472W Reconstruction of Flushing Ave and Area
Pre-Construction Report April 10, 2006
De-watering and trenching activities will occur primarily 25’ away from existing
buildings, with the exception of critical location at Franklin/Flushing noted herein. The
increase in effective stress imposed by open pumping up to 5 feet inside of tight sheeting
should not cause any appreciable settlement of surrounding buildings located 25’ feet
from pumping location, however these buildings should be monitored for settlement as a
safety precaution (see Section 4.1). Twenty-five feet 25’ deep excavation including 15’
deep de-watering would be required for construction of jacking and receiving pits at the
intersection of Flushing Avenue and Franklin Street, if this element is built according to
original design. Design for excavation protection system and de-watering at this location,
if required, would be submitted under a separate transmittal, however, if deep excavation
19
Project HWK-472W Reconstruction of Flushing Ave and Area
Pre-Construction Report April 10, 2006
at this location is retained in the design, we will both monitor and mitigate potential
settlement of surrounding building structures due to dewatering for these deep pits.
Settlement monitoring will be required for each of the two building structures located
adjacent to critical activity identified in section 9.0 of this report, in addition to the
buildings located along Flushing Ave/Nassau Street Between No. Portland and Gold
Street or other locations where more than 1.5 feet of drawdown of water table is
anticipated or encountered.
20
Appendix A
Appendix B
Appendix C
Appendix D