ONE PAGER BRIEF KTMD STAGE-01

The Contract for “Construction of Civil Work along with Design, Supply,
Installation, Testing and Commissioning of Hydraulic Steel, Mechanical and
Electrical Works” was signed between WAPDA and FWO-DESCON JV on 07-Jun-
2016 and The Engineer gave notice on 14-Jun-2016 for commencement of the
works, within 28-days of receiving the Engineer notice which becomes 12-Jul-
2016, accordingly Contractor JV mobilized at Site of the Project on 12-Jul-2016.

Salient Features
1 CA Cost 12006 Mn
2 Consultant MMP-PES JV
3 Date of 12 Jul 2016
commencement
4 Date of completion Apr-2024
5 Total Power Generation 83.9 MW
capacity
6 Stage-01 Power 18.4 MW
Generation Capacity
7 Stage-1 irrigation 16300 Acres
capacity
8 Stage-2 Power 65.5 MW
Generation Capacity
9 Stage-2 irrigation 376000 Acres
capacity
10 Stage-2 status Under Planning
stage