Inspection and Test Plan For HVAC Cladding Works: 0-WD860-CA250-00312 0
Inspection and Test Plan For HVAC Cladding Works: 0-WD860-CA250-00312 0
0-WD860-CA250-00312
Inspection and Test Plan for HVAC Cladding Works Rev. No. 0
Page 1 of 2
Inspection Mode
Item Verifying
Activity Reference Documents Acceptance Criteria VPCI AES Frequency Remarks
No. GTC Documents
Site QC
1.0 Preparation
1.1 Review of IFC Drawing IFC Drawing As per Project specification H R R R 100%
0-WD-010-MZ731-00110 WP for Random Packing List Note 2
1.2 Material Check As per Project specification H R R R
warehousing and receiving
WP for Cladding of Pipeworks Inspection *Note 1
1.3 Visual Insulation Check As per Project specification H R R R 100%
and DuctWorks Request
2.0 Cladding Fabrication for Ductworks and Pipeworks
Confirm Dimension WP for Cladding of Pipeworks Inspection
2.1 Approved IFC Drawing H SW SW V Random
Verification and DuctWorks Request
2.2 Item Marking IFC Drawing Approved IFC Drawing H SW SW V Random -
Visual Inspection of WP for Cladding of Pipeworks Inspection
2.3 Approved IFC Drawing H SW SW V Random
workmanship and DuctWorks Request
3.0 Installation of Cladding
Inspection
3.1 Pipe/Duct Spacing Check IFC Drawing As per Project specification H V V V Random
Checklist
Cladding for Duct & Pipe WP for Cladding of Pipeworks Visual Inspection Status, No Inspection
3.2 H SW SW V Random
Condition and DuctWorks Severe Defects / Damage Checklist
Check Groove & Bend WP for Cladding of Pipeworks Visual Inspection Status, No Inspection
3.3 H SW SW V Random
properly installed and DuctWorks Severe Defects / Damage Checklist
Confirm Hanger & support Inspection
3.4 IFC Drawing Visual Inspection Status H SW SW V Random
bracing properly installed Checklist
Visual Inspection of cladding IFC Drawing , WP for Cladding Inspection
3.5 No severe defects / damage H SW SW V 100%
workmanship of pipeworks and ductworks Checklist
*Note: 1. Pipeworks and Ductworks already inspected and accepted. H Hold Point
Note 2 : Material check should be done with material controller of VPCI W Witness Point
LEGEND SW Spot Witness
R Review
V Surveillance
Masinloc Power Plant Expansion Project Doc. No. 0-WD860-CA250-00312
Inspection and Test Plan for HVAC Cladding Works Rev. No. 0
Page 2 of 2
Inspection Mode
Item Verifying
Activity Reference Documents Acceptance Criteria VPCI AES Frequency Remarks
No. GTC Documents
Site QC
Note: 1. Pipeworks and Ductworks already inspected and accepted. H Hold Point
Note 2 : Material check should be done with material controller of VPCI W Witness Point
LEGEND SW Spot Witness
R Review
V Surveillance
Masinloc Power Plant Expansion Project Doc. No. 0-WD800-CA250-00302
Inspection and Test Plan for Plumbing Work Rev. No. A
Page 4 of 4
Inspection Mode
Item Verifying
Activity Reference Documents Acceptance Criteria VPCI AES Frequency Remarks
No. GTC Documents
Site QC
7.0 Repair