Detailed Estimate for Pump Room 3mx3m

Measurements
S.No Detail of work(Description) No Quantity Total Unit Remarks
Length Breath Height/Depth
Total Length of center Line 14.2
1 Excavation
Excavation for Foundation 1 12.575 1.2 1.3 19.617 19.617 m3
2 Cement Concrete
Cement Concrete in foundation 1 12.575 1.2 0.2 3.018 3.018 m3
3 Brick work in foundation & Plinth 4- Brick work in Cement mor
1st Step 1 12.575 0.9 0.5 5.65875
2nd Step 1 12.575 0.6 0.5 3.7725
3rd Stept upto Plinth 1 12.575 0.45 0.45 2.5464375 11.9776875 m3
4 Brick work in Superstructure 1 12.575 0.23 3.1 8.965975
Deduction for
Opening for Door -1 1.2 0.23 2.1 -0.5796 Door Size= 1.2x2.1
Opening for Window W -4 0.9 0.23 1.37 -1.13436 7.252015 m3 Window 0.9x1.37
5 RCC M20 Grade 1:1.5:3
Slab 1 3.46 3.46 0.15 1.79574
Lintel 4 1.2 0.6 0.05 0.144 1.93974 m3
6 Re-bar confirming grade Fe415/500
10mm @ 150mm c/c -Along Breadth 23 3.23 45.1252533333
10mm @ 150mm c/c -Along Length 23 3.23 45.1252533333 90.2505066667 kg
7 Flooring
Earth Filling 20cm Thk 1 3 3 0.2 1.8 1.8 m3
Sand Filling 15cm Thk 1 3 3 0.15 1.35 1.35 m3
PCC 1:4:8 10cm Thk 1 3 3 0.1 0.9 0.9 m3
8 Plastering
Internal Walls 4 3 3.1 37.2
External Walls 4 3 3 3.25 39
Window around 1 4.54 0.23 1.0442
Opening for Door -1 1.2 2.1 -2.52
Opening for Window W -4 0.9 1.37 -4.932 69.7922 m2
9 White washing
Internal Walls 4 3 3.1 37.2
External Walls 4 3 3 3.25 39
Window around 1 4.54 0.23 1.0442
Opening for Door -1 1.2 2.1 -2.52
Opening for Window W -4 0.9 1.37 -4.932 69.7922 m2
10 Brick work in steps
1st step 1 1.2 0.75 0.15 0.135
2nd step 1 1.2 0.5 0.15 0.09
3rd step 1 1.2 0.25 0.15 0.045 0.27 m3
1- Excavation in Foundation
2- Cement Concrete in Foundation
3- Brick work in cement mortar (1:4)
in foundation & Plinth
4- Brick work in Cement mortor (1:6) in superstructure
5- 2.5 cm thick DPC