NAME OF WORK: ESTIMATE FOR CONSTRUCTION OF A RESIDENTIAL BUILDING PILE

FOUNDATION

ABSTRACT
OWNER: Mr. 575,000
SL.
QTY DESCRIPTION OF ITEM OF WORK Rate Per Amount
No
A Foundation
Earth work excavation for foundation in
1 4748.69 ordinary soil including initial lead and lift etc. 11.50 Cft 54,610
complete.
Collection and supply of M.sand filling for
2 1638.40 foundation and basement in layers of 15cm 49.00 Cft 80,281
thick including all labour charges etc.complete

Plain cement concrete 1:5:10 mix using 40mm


3 1638.40 size HBBG metal including cost of all materials 112.00 Cft 183,500
and all labour charges etc complete

Reinforced cement concrete 1:2:4 mix using 20


4 268.94 mm ISS gauge HBBG metal including cost of all 187.00 Cft 50,292
materials and all labour charges etc complete,

Centering and shuttering arrangements for RCC


5 444.00 works including cost of all materials and . and 50.00 Sft 22,200
all labour charges etc.complete
Supplying cutting ,bending &tying in position
6 537.89 Steel rods including cost of binding wire &all 70.00 Kg 37,652
labour charges etc complete
Wall plastetring in cm 1:5 mix (inner and outer)
7 2943.79 including cost of all materials and all labour 25.00 Sft 73,595
charges etc. complete
8 1471.90 Basement filling Gravel 17.00 Cft 25,022

9 264.00 Pile Erection 70.00 Rft 18,480

Subtotal - Ground Floor 545,633

60 L.S Provision made for petty supervision charges L S 25,000

61 L.S Provision made for unforseen expences L S 4,367

TOTAL 575,000