Professional Documents
Culture Documents
MS Format-Tata Projects Hosur
MS Format-Tata Projects Hosur
MS Format-Tata Projects Hosur
TPL/UI-670050/QMD/MS/
URBAN INFRASTRUCTURE
Record of Revisions
INDEX
PAGE
S. No. CONTENT REMARKS
NUMBER
Index
1 3-7
Objective
2 7
Scope
3 8
Reference code & documents
4 8-10
Materials Required
5 11
Tools and machinery required
6 12-13
Safety PPE Requirement
Roles, Responsibilities & Authorities like as
7 13-14
project manager, safety officer, QC person etc.
8 14
Power and light requirement
9 14
Unloading and storage of material.
10 15
General preparation to start work
11 16-17
Work sequence/Procedure in details step by step
1. Objective
1) Fill: 80mm dia nozzle has been provided to unload the product from the tanker to the
installed aboveground tank. The product flows through pumping.
2) Man Hole : We have been provided to carry out maintenance of the main AG tank on
the top of tank and also 600mm dia man hole arranged with 1 mtr height from the bottom
plate.
3) Spare Nozzle: (80mm)This is for future use of any other purpose.
4) Air Vent: (50mm) This acts as breather to the main tank and ensures that the tank are
depressurized at all times.
5) Dip: (50mm) An aluminum dip rod has provide to monitor the level of fuel maintained
6) Suction: (80mm) This discharges the product from the main tank to the DG day tank by
pumps.
The main tank are installed on the RCC mat raft and sealed with a concrete slab. It is earthed
safely within the pit connected to the earthling boss provided in the tank.
1 No Working 225 LPM Geared pump with 5 HP FLP Motor & 1 No standby 225 LPM Geared
pump with 5 HP Motor.
1 No Working 125 LPM Geared pump with 3 HP FLP Motor & 1 No standby 125 LPM Geared
pump with 3 HP Motor installed consisting with Ball valves, strainers at inlet and NRV’s, Ball
valves and pressure gauges at outlet line to pump the fuel from the AG tanks to intermediate
tank. These pumps will be operated automatically and manually by the HSD control panel.
b.4 Piping:
Fill Line:Fill line is 80NB containing with unloading pumps and FLP motors, flow meter, ball
valves, strainers has been fixed in the fill line.
Delivery Line: 50NB pipe used from tank suction nozzle to master day tank,
Gravity Flow Line: 40NB pipe used from master day tank to day tanks
Ball valves, pumps Non Return valves are fixed in the delivery line which is inside the pump
hose.
Level Switches provided in master day tank. The Level Switch is calibrated to Low and High
Levels. The Level Switch operates pumps to fill the master day tank at low level and shut off
pumps at high level.
A) 4 Core X 1.5 Sq.MM copper armored cable usedfrom level instruments etc. to Control
panel, operation and emergency stop switch,
B) 4 Core X 2.5 Sq.MM copper armored cable used fromtransfer pumps to Control panel
C) From level switch in master day tank to Control Panel
D) From level indicator in main A/G tank to Control Panel.
From tanker unloading to main A/G tank operation we will provide 5HP Flameproof DOL
starter (1W+1S) and for Transfer pumps we will provide flameproof emergency stop switched
(Push button) operation of the diesel system. This works on AUTO and MANUAL Mode. Main
control panel will be installed near DG room area.
TATA PROJECTS LIMITED
TPL/UI-670050/QMD/MS/
URBAN INFRASTRUCTURE
1). 80 mm dia digital flow meter installed in inlet line with by-pass arrangement for measuring
inlet flow to A/G tanks.
2). 50 mm dia in pumps delivery line with by-pass arrangement for measuring out flow from
UG tanks.
Emergency Stop push button installed near the pumps to shut off the total system during
emergency.
It is advised that once the product is received at site the following steps are taken:
1) Lock the truck tyre from rolling by providing solid vedge under the tyres.
2) Connect the earthing clamps to the tank till the discharge of HSD is complete.
3) Allow 10 to 15 minutes for the product to settle down before unloading from the tanker.
4) Check for water in diesel using hydrometer.
5) Connect hose pipe to the decanting line and open the valve. Do not disturb till the process
is completed and the truck is decanted fully and completely.
6) During unloading the hose connecting the road tanker to the fill line of the main tank
should be properly coupled so as prevent spillage.
7) Unload compartment by compartment.
E USING DIESEL FROM MAIN TANK:
7) When diesel in the DG day tank reaches High Level flow automatically stops and pump
switches off.
8) If the motor is being used for the first time, it needs to be primed with the product to be
handled, keeping all valves in open condition.
9) Subsequently no priming is required.
F BEFORE PUMPING:
1) Self priming pumps must have the suction and delivery valves open.
2) Check the direction of rotation of the pump.
G NORMAL OPERATION:
AUTO MODE:
AUTO: REMOTE
A) Control Panel:
In case of any emergency, stop Button on the Remote Panel should be pressed to cut off power
supply for pump operation. It can be released by turning it in clockwise direction.
I SAFETY FEATURES:
1) Non Return Valves ensure that the product does not return to the main tank.
2) Level Switches calibrated in the FAIL – SAFE Mode to ensure no diesel overflow in case of
power failure.
3) Strainers ensure that diesel is free of foreign matter.
2. SCOPE
This method statement provides the details methodology for carrying out HSD
Vertical
Storage Tank Fabrication which covers different activities like Handling of material,
it’s storage, preservation, Cutting ,Forming, fit up, welding , NDT, Painting
This statement also consider the safe working Methodology to meet zero accidents.
2.1 ACTIVITIES
2.6 Cleaning
2.7 Painting
2.8 Final Inspection
TATA PROJECTS LIMITED
TPL/UI-670050/QMD/MS/
URBAN INFRASTRUCTURE
3. REFERENCES:
5.10 D’ shackles.
5.12 Elcometer
Do not allow the presence of any fire, flame or naked light near the space
where pain is carried out.
All metal parts of spray booths, exhaust ducts, or any conductive body
coming into Paint circuits, shall be earthed
Spark free, flameproof electrical equipment and wiring shall be used in the
area where Painting is performed
Safety kick off meeting given to all personnel involve in fabrication process.
When unloading Workers operating the crane should have been trained in
its safe use and safe slinging techniques
DOCUMENTATION
1 Mr.Jitender Singh
(Project Manager) Cell No: 9346387816
5 Mr. SukhdebBiswakarma
(Site Engineer) Cell No: 9556044523
6 Mr.Ayush Jain
(Supervisor) Cell No: 7231904040
7 Mr.Shiva Kumar
(Safety cum Quality Engineer) Cell No: 7708841435
11 Mr. PramodYadav
(Welder)
TATA PROJECTS LIMITED
TPL/UI-670050/QMD/MS/
URBAN INFRASTRUCTURE
13 Mr. BrijeshYadav
(Rigger/ Gascutter) Cell No: 7311160819
14 Mr. Hridyanandpal
(Rigger)
15 Mr. DhanajayYadav
(Welder)
Select and use lifting equipment and lifting accessories (tackle) which are suitable for
the task. In particular, do not exceed their safe working load.
A safe exclusion zone should be established around the working area, vehicle and
lifting equipment prior to commencing the operation.
Safety kick off meeting given to all personnel involve in fabrication process.
When unloading Workers operating the crane should have been trained in its safe use
and safe slinging techniques
Must have PPEs, welding goggles, or welding mask, safety footwear, long sleeved
overalls, apron if required, protective headgear.
Must have appropriate tools and equipment for task (ensure equipment in good
condition and safe to use), portable local exhaust ventilation (LEV) if required.
10.1 MATERIAL
10.1 All materials shall be procured with MTC and stored properly
10.3 The Material test certificates for Raw materials including Welding consumables
certificates and Paint batch certificates shall be reviewed and approved by
QA/QC.
10.4 The raw materials shall be taken up for fabrication only after the QC clearance.
To the greatest extent possible, all the materials shall be prepared in the machines.
After preparation, all the components shall be identified with its mark number / code
number.
The cutting plan shall be prepared before commencement of fabrication work for all
the raw material.
10.1.4 Straightening
All steel material shall be free from bends or twists and if noted shall be
corrected by the mechanical Means.
10.1.4 Cutting
To the greatest extent possible the materials shall be cut by oxy acetylene machines.
The Cut edges shall be free from defects.
10.1.6 Holes
To the greatest extent possible the holes shall be drilled by drilling machine
Drilled holes shall be free from burrs.
Forming Process:
The plate shall be bend to the required dimension by bending machine. Any cracked
developed at bend portal shall be visual checked.
TATA PROJECTS LIMITED
TPL/UI-670050/QMD/MS/
URBAN INFRASTRUCTURE
The components shall be fitted for welding as per the requirements of relevant IS
code
Proper Root Gap, Root face, bevel angle shall be maintained as per approved WPS.
Both side of the fit up joint shall be cleaned. There should not be any debris,
grease, and rust at the adjacent of Fit up joint
The root gap and welding edges shall not exceed the limits of relevant IS code
The edges or surfaces of parts to be joined by welding shall be clean and free
from contaminations like moisture, slag, oil, grease, paint, scale, rust etc.
11.2 Electrodes
All the welding consumables shall be stored clean and in a dry place.
All the welding consumables shall be suitably selected which will match the
mechanical properties of the base material reputed make-ESAB, ADOR, D&H
Electrode shall be used for welding work
11.3 Welding
All welding shall be carried out as per relevant IS code and approved WPS
The sequence of welding shall be selected to ensure that the components assembled
by welding are free from distortion and large residual stresses are not developed.
Welds shall be made in flat position wherever practical.
The ends of butt welds shall have full throat thickness. This shall be obtained on all
main butt welds by the use of runoff and run on pieces adequately secured on either
side of main plates. Additional metal remaining after the removal of extension pieces
shall be removed by grinding or by gas cutting.
TATA PROJECTS LIMITED
TPL/UI-670050/QMD/MS/
URBAN INFRASTRUCTURE
Temporary supports shall be removed by grinding without damaging the base metal
and the damaged areas shall be ground smooth and flush. Temporary supports shall
be removed only by grinding.
After complete weld jointing the final dimension to be ensured to comply with client
approved drawing.. The report of the same shall be prepared
11.7 INSPECTION:-
The weld reinforcement of butt-welds & Fillet joints shall be within the requirements
Visual inspection shall be carried out on the assemblies before releasing for Surface
cleaning and painting
Inspection and Test shall be carried out as per the submitted Inspection and Test
Plan.
Pressure Gauges
Gauges shall be installed for each test. One placed in the highest part and the other in
the lowest part of the Test System. All Pressure Gauges shall be duly calibrated from
NABL laboratory
The Pressure Test will then be performed in accordance with the project specifications.
The client witness and approve the Test.
All welds and Non Destructive Testing shall have been completed.
Hydro test diagram showing test limits with blinds and manifold and vents and
drains location shall be prepared and attached in this procedure.
Vent shall be open during filling so that all air is vented prior to applying pressure to the
system.
Test medium shall be sweet water for hydro test and with valid laboratory analysis
during the test.
The circuit shall be vented during filling and before any pressure is applied. The filling
of the System shall to be at lowest point.
Pneumatic test sequence shall be in stepwise such that initially 50% of the Test
pressure has to be pressurized and then check for preliminary Check shall be done.
Then onwards test pressure shall be increased in Steps no greater than one-fifth of test
pressure shall be increased and finally 100% have to be pressurized and check for
leaks.
The test pressure shall be reached gradually and be maintained constant, for the time
enough to enable a visible inspection of the circuit, a time not less than 30 minutes or
the time required by the inspector.
All welds and flanged connections shall be visually inspected to ascertain possible
leakage.
13.5 Provision of drain cock in each storage tank with lock and seal
13.7 Whether any leakages observed in HSD valves, joints and pipelines & what action
taken by HSE in- charge.
13.8 Whether ground availability of HSD oil is measured by dip reading in each shift and
recorded while handing over and taking over
13.9 Whether calibration of storage tank is done after cleaning in case of physical
deformation of the tank is noticed
13.15 Number of fire extinguishers, location & due date for testing/refilling.