Method Statement For Construction of Bored Cast In-Situ Piles Using Mechanical Rotary Rig
Method Statement For Construction of Bored Cast In-Situ Piles Using Mechanical Rotary Rig
1.1 Scope
To document a suitable methodology for construction of bored cast in-situ piles using
mechanical rotary rig in accordance with the requirements of the specifications and
drawings.
1.2 References
Contract Agreement
Indian Railway Bridge Manual
1.4 Equipment
Total Station / Leveling Instrument
Measuring Tape
Winch with engine
Pile driving tools & accessories (bailer, chiseler, tremmie pipe etc.).
Tripod & monkey
Mechanical Rotary Rig
Generator
Welding machine
Bar Cutting/Bar Bending Machine
Batching Plant
Transit Mixer
Concrete Pump
1.5 Methodology
1.5.1 Setting Out
The location of the pile shall be set out with respect to the control points (co-
ordinates) and shall be got checked by Employer’s Representative.
Guide points / reference points (minimum 3 points) shall be fixed at the
suitable location outside the casing for future reference while executing the pile
Signature
Name &
Designation
Prepared by Reviewed by Approved by
METHOD STATEMENT FOR CONSTRUCTION OF
BORED CAST IN-SITU PILES USING MECHANICAL
ROTARY RIG
Rev. No 0 Method Statement No. Page No. 2
and these reference points shall be guarded and ensured that these reference
points are not disturbed during piling.
Truck shall be positioned on the pile in such a manner that the center of the rig is in
line with the center of the pile.
Each pile shall be identified with a reference number. The convenience of
installation may be taken into account while scheduling the sequence of piling in a
group.
Piles shall be installed as accurately vertical as possible. The permissible limits for
deviation with respect to position and (inclination) alignment shall confirm to
specifications.
1.5.2 Boring
1.5.2.1 Installation of Permanent MS liners
Permanent MS Liners of specified thickness painted from outside with coal tar epoxy
shall be provided for piles up to point of refusal or scour depth as applicable.
The diameter of liners shall be such as to give the necessary finished diameter of
the concrete pile.
Pilot hole of approximately 1 to 2m deep shall be made at the pile location. First liner
of 1.5m length shall be installed in this pilot hole and shall be checked for verticality
and position with reference to reference points. This liner shall be driven up to
working platform level using monkey/chisel/bailer.
Second piece of the liner shall be placed on the first liner and the horizontal joint
shall be fully welded and the driving shall be done using monkey/chisel/bailer. It
shall be ensured that 1m boring is available below the liner tip of second liner. For
the purpose of installation of liners boring shall be done using chisel and bailer.
In the same manner third piece of liner shall be driven ensuring that more than 1m
bore is available below it. Now boring shall be advanced up to the bottom of already
driven liners.
During liner driving the verticality of the bore shall be constantly checked .
This liner driving process shall be continued till the refusal.
Signature
Name &
Designation
Prepared by Reviewed by Approved by
METHOD STATEMENT FOR CONSTRUCTION OF
BORED CAST IN-SITU PILES USING MECHANICAL
ROTARY RIG
Rev. No 0 Method Statement No. Page No. 3
Signature
Name &
Designation
Prepared by Reviewed by Approved by
METHOD STATEMENT FOR CONSTRUCTION OF
BORED CAST IN-SITU PILES USING MECHANICAL
ROTARY RIG
Rev. No 0 Method Statement No. Page No. 4
1.5.5 Concreting
Permit for pouring concrete shall be obtained from the Employer’s Representative.
The reinforcement cage shall be lowered in to the pile bore with the help of tripod
and winch or tower crane.
Immediately after the lowering of reinforcement cage, tremmie pipes of 250 mm
with funnel at top shall be lowered into pile.
Flushing shall be carried out by flushing fresh drilling mud through tremmie pipe to
clean the pile bore.
Provide a gap/clearance of minimum 300 mm between the tremmie pipe bottom and
the pile tip level.
The volume of first pour of concrete shall be calculated such that the concrete
flows in single go and seals the bottom of the tremmie pipe so that the subsequent
pour shall be in dry (capacity of funnel shall also be selected based on the same) and
a minimum of 600 mm depth of concrete is to be built up inside the pile bottom.
Initially a lid shall be provided at the funnel bottom and the concrete of first batch
(calculated volume) shall be poured, the lid shall be removed so that the concrete
shall flow into the tremmie pipe and shall reach the pile bottom.
During concreting it shall be ensured that the bottom of the tremmie pipe is always
embedded in the concrete of minimum 600 mm.
During the course of concreting, if tremmie is with drawn out of concrete either
accidentally or to remove a choke in the tremmie, the method given in the following
manner as per sub para 10 of para 415 of IRS Bridge Manual which is reproduced as
under –
“In case of withdrawal of tremie out of the concrete either accidentally or
to remove a choke in the tremie, the tremie may be reintroduced in the following
manner to prevent impregnation of laitance or scum lying on top of the concrete
deposited in the bore. The tremie shall be gently lowered on to the old concrete with
very little penetration initially. A vermuculite plug should be introduce in the tremie.
Signature
Name &
Designation
Prepared by Reviewed by Approved by
METHOD STATEMENT FOR CONSTRUCTION OF
BORED CAST IN-SITU PILES USING MECHANICAL
ROTARY RIG
Rev. No 0 Method Statement No. Page No. 5
Fresh concrete of slump between 150 mm and 175 mm should be filled in the tremie
which will push the plug forward and will emerge out of the tremie displacing the
laitance/scum. The tremie will be pushed further in steps making fresh concrete
sweep away the laitance/scum in its way. When tremie is buried by about 60 to 100
cm,concreting may be resumed.”
Initially a vermiculate ball plug shall be introduced in the tremmie, fresh concrete of
slump between 150 mm to 180 mm is filled in the tremmie which shall go on pushing
the plug forward and emerge out of the tremmie. After this the tremmie is pushed
further in steps making fresh concrete displace the lean concrete.
When the tremmie is buried about 0.6 m to 1.0 m in the concrete then the
concreting is resumed/continued.
Concreting by tremmie shall continue to allow the initial pours of concrete mixed
with Bentonite slurry, sludge and cut spoils from the bore over flows and the
consistency and quality of the over flowing concrete is comparable to that of
designed mix.
It shall be ensured that the volume of concrete poured is at least equal to the
theoretically computed volume of the pile being cast.
The top of concrete in pile as cast shall be above the cut-off-level as shown in
drawings (maximum) to remove all laitance and week concrete and ensure good
concrete at cut-off-level, for proper embedment into the pile cap.
Concrete shall be built up to the cut off level and shall be confirmed by sounding
chain.
Measurements shall be recorded.
1.6 Quality Control
Quality control of all the materials shall be done as per the frequency specified in
the approved Quality Assurance Plan.
1.7Safety
Work site shall be barricaded.
All the personnel in the module shall be wearing the personal safety gear like safety
gloves, safety hats and shoes during the operations.
Minimum number of persons shall be present during the works and unauthorized
persons shall not be allowed.
The work site shall be cleaned from loose material, cut rebar from the site at regular
intervals.
Signature
Name &
Designation
Prepared by Reviewed by Approved by