CALCULAR EL VOLUMEN DE EXCAVACION DE

ZANJAS
COTAS DE FONDO DEL BUZON 6
LONGITUD DE TUBERIA DE 8 "
LIBRETA DE NIVELACION: COLECTOR 0-9      
VISTA
ESTACIO PUNT VISTA ALTURA DE ADELANT DISTANCI OBSERVACION
N O ATRÁS COTA INSTRUMENTO E A (m ) ES
A 0 1.65 110.00 111.65   0.00 BUZON 0
  1   110.35   1.3 10.00  
  2   110.65   1 20.00  
  3   109.85   1.8 30.00  
  4   110.25   1.4 40.00  
  B   110.35   1.3  
B B 1.00 110.35 111.35      
  5   109.55   1.8 50.00  
  6   109.75   1.6 60.00  
  7   109.95   1.4 70.00  
  8   109.45   1.9 80.00  
  9   109.75   1.6 87.00 BUZON 9
PERFIL LONGITUDINAL

107.00
106.00
105.00
104.00
103.00
101.00 BUZON 0 rasante m 0 4= 1.75 %
100.00 m5-9=2.1 %
99.00 rasante
98.00
97.00 mtub= 1.7 % BUZON 9
96.00
95.00
94.00 mtub=2.3%
PUNTOS 0 1 2 3 4 5 6 7 8 9
COTA TERRENO 100.00 101.00 99.50 100.50 98.00 99.50 95.00 99.80 94.70 96.00
PROGRESIVA 1 20.00 40.00 60.00 80.00 100.00 120.00 140.00 160.00 180.00
PROGRE - ACUM 1 1+ 20.00 1+40.00 1+60.00 1+80.00 1+100.00 1+120.00 1+140.00 1+160.00 1+180.00
COTA TAPA 100.00 98.60 96.50
COTA FONDO 98.80 97.10 94.80
ALTURA DE BUZON1.20 1.50 1.70