Professional Documents
Culture Documents
Vendor System Audit Report (Final) - Technico Ind., Bawal (T043)
Vendor System Audit Report (Final) - Technico Ind., Bawal (T043)
Part Number:
Subject: Vendor System Audit
Part Name: Door Hinges, Brake Pedal Assy
Major audit observations are as follow:
1) RPN should be calculated for each Potential cause of failure mode, however at present it is calculated for failure mode.
2) Process audit was not carried out for during IFM of YJC MC - Hinge Assy, Front door.
3) In the 4M monitoring sheet, recording of all the breakdowns were not evident, same to be ensured.
4) Same practical Evaluation sheet is used to asses Skill level 3 (Can solve problems) and skill level 4 (Can train others), however no
assessment parameters for judgment of "Can train others" is evaluated.
5) Brake Pedal Assy, YCA not found covered in Product audit plan (2020~21), same to be included. On further investigation it was found that
Product audit was not conducted for Brake Pedal Assy., YCA in 2019~20.
6) Standardization of documents was not ensured against In-house CAPA analysis done for "Gauge out" concern reported in Jun-20.
7) n the PM check sheet of tool, Female body door hinge YP8, against the check point of strip guide size (Spec: 73.3±0.05 mm), actual was
recorded as 73.8 mm & 73.7 mm in PM check sheet and was judged as "OK.
8) Adherence of defined work instructions at shop floor to be improved.
○ △ ×
1 18 / 24 6 2 0
2 9 / 15 3 2 0
3 12 / 18 4 2 0
4 15 / 18 5 1 0
5 6 / 18 2 4 0
6 9 / 15 3 2 0
7 12 / 21 4 3 0
8 6 / 21 2 5 0
9 12 / 18 4 2 0
10 6 / 15 2 3 0
11 9 / 15 3 2 0
12 12 / 18 4 2 0
13 12 / 12 4 0 0
14 9/ 9 3 0 0
Total
(MSIL)
147 / 237 49 30 0
Pre decided negative marking (if
Improvement Submission Date 1-Feb-21 Last Audit Rating 72%
any)
Regarding management
2
/implementation by
production preparation Do you implement follow-up to control the schedule and progress
plan/report (master plan)
①
of production preparation items?
○
Defect prevention on the 1) In the past trouble study record of YJC MC (Door hinge) dated Mar'19, Only one customer complaint
3
stage of process design was considered. However, there are 5 more MSIL customer complaint reported between Oct'17 &
by using FMEA/Matrix Do you consider following items and reflect them to the processes Mar'19 on Door Hinge, but same was not evident in the Past Trouble Data bank study report.
diagram and standards beforehand? Also, internal complaints and supplier complaints should be included in data bank.
① -Troubles in the past; -Defect items expected; △ It is required to consider all sources of defect during past trouble study. Further, format should be
-Defect items unable to capture at customer; revised to include defect applicability and implementation status as column requirements.
-Defect items difficult to repair;
1) As per the procedure, periodic review of PFMEA to be carried out once in a year. Currently, periodic
review is not evident. It is required to prepare PFMEA review plan and carry out periodic review as per
procedure.
Do you review and improve FMEA or Matrix diagrams when any 2) Gap observed in the preparation of new model PFMEA w.r.t AIAG guidelines. Ex: In the PFMEA of
② △ YNC brake pedal, at process no.345-Robot MIG welding, RPN is calculated for failure mode (i.e., RPN
critical issue occurs after SOP?
for weld penetration NG is calculated as100) but it is required to prepare RPN for each potential cause
(like welding parameter variation, welding tip ID more etc.).
Product/process
4
evaluation at the quality Do you prevent defects by quality improving activities of cross-
①
function team to evaluate quality performance?
○
evaluation meeting in
each trial
Do you define condition to start mass production and then check
②
on the product line prior to SOP? ○
2. Regulation for
Regulation for 1
initial production control Do you define following items related to initial production control
initial by standards ?
production -controlled parts; -controlled items; -inspection method;
control ①
-initial production control period;
○
-a person who announce start/end of initial production control;
-finish condition;
1) Verified the initial flow control record of YJC MC - Hinge Assy, Front door and following improvements
are required.
a) Stricter check of in process parameter are not evident. (only 100% check carried out on final Assy
part). It is required to identify the critical parameter at each station and do stricter check.
How do you define items required special control during initial b) All the termination condition mentioned in the procedure are not evident in the termination check
② production control? Do you set stricter inspection methods than △ sheet. Ex: Termination condition like internal PPM, closure status of process audit observation etc. are
the ordinal inspection? not mentioned in termination check sheet.
2) As per procedure, process audit are to be carried out, same was not conducted during IFM of YJC
MC - Hinge Assy, Front door.
2
Implementation of initial
Do you pick up issues and improve them during initial production
production control ① ○
control?
During IFM carried out for YJC MC-Hinge Assy, Front Door, process capability are studied for 3 months
but monitoring & taking action in case of negative trend is not evident. Ex: CPK values of parameter 28.6
mm for month1, month2 & month3 are 1.81, 1.78 & 1.68 Cpk respectively.
Do you control process capability and defect rate during initial Similarly, for parameter 71 mm, CPK values are 2.03, 1.86 & 1.73 for month1, month2 & month3
②
production control?
△ respectively.
i.e., CPK values are deteriorated for both the parameters. However, corrective actions are not evident.
Further, in such cases, IFM should have been extended but was not ensured.
3. Definition and
Changing 1
implementation of Do you define unexpected change (unusual) and planned change
management changing management
①
clearly?
○
1) In the 4M monitoring sheet, recording of all the breakdowns were not evident. Ex: Breakdown
reported in machine # YLM-38 for "main pump not work" dated 17.8.20 & in the machine # DHL05 for
Do you record product quality check results to ensure batch code machine not working dated 18.8.20 were not recorded in 4M monitoring sheet.
③ △
traceability?
1) Currently, for the machine breakdowns in which retro check to be done and in which retro checks are
not to be done are defined w.r.t shop wise (Weld shop, press shop & Assy shop). Further, some of new
breakdowns (not in 4M guidelines) are reported in weld shop and press shop and no retro check was
carried out.
Ex: (a) On 6th Jul'20, Clamping cylinder not working reported in machine # RM5 (weld shop)
Do you retroactively check about product quality when
④ △ (b) On 29th Jul'20, Air pipe leak reported in machine # RM4 (weld shop)
unexpected change occurs?
(c) On 14th Aug'20, air pressure pipe broken reported in machine # DHL03.
Further, it is required to update new breakdowns in 4M guidelines after necessary validations and
accordingly actions to be taken.
4. Procedure to make
Standards 1
process control Do you make process control standards for all products which is
management standards(QA process ①
shipped to SMC / MSIL? ○
charts)
1) In the control plan of YCA Brake pedal, at process no. 800, bush & spacer Assy with arm and
Do you mention followings on process control standards required greasing in boss, details of Pokayoke is not evident. (During Shop Floor audit it was found that
to each process? Pokayoke was available w.r.t air pressure/ proper greasing etc.). It is required to add Pokayoke details in
③ -quality confirmation method; -regulations; △ control plan.
-standards (operation instruction/items to be focused on);
-boundary samples; -parameter chart; -Pokayoke
5. Education/ training Operator trainings Planned vs Attended is not evident. As of now all operators are given training as per
Education and 1
procedure annual training calendar, however there is no system evident in which plan vs actual is captured as
training Do you clarify the department in charge of promoting quality verified for "Quality abnormality handling/ Red Bin handling" training conducted multiple times in past,
① education, implement education based on annual plan? △ however many operators such as Mr. Lakhan, etc. were not found covered Also Re-training to be
Are records of education kept? planned for the members whose training is not conducted.
New Operator training mechanism was verified, following concerns should be focused-
a) Acceptance criteria along with Target vs Actual for "Tact time" and "Quality defects" parameter
should be recorded in practical evaluation sheet for skill level evaluation, presently scoring of 5 was
given on all days as evident for New Operator Dharmender (DOJ- 23/Jun/20), but basis of giving 5 score
is not evident.
b) Same practical Evaluation sheet is used to asses Skill level 3 (Can solve problems) and skill level 4
(Can train others), however no assessment parameters for judgment of "Can train others" is evaluated.
Same to be included while upgrading the operator from skill level 3 to skill level 4.
Do you define and implement the skill evaluation of operator to
c) Skill matrix was not found to be updated for operator Dharmender, DOJ as 23-Jun-20, Operator
② determine whether operator can work without surveillance?(e.g. △
acceptable revel/evaluation frequency/evaluation method) achieved "skill level 1" on 27-Jun-20 and "skill level 2" on 30-Aug-20, however till present skill matrix was
not updated for Operator Dharmender. Skill matrix Updation frequency is defined as once every quarter
however same should be amended in such a manner so that such changes are captured at the earliest.
2) New Operator training procedure should be revised to include timelines, Passing criteria and
Evaluation mechanism for each skill level upgradation i.e. Skill level 2,3 and 4, presently same is defined
only for Dojo training mechanism.
Education for 1) Training should be identified for all associates, presently in TNI-2020~21, no training was identified for
2
managers/Inspectors/ many staff members e.g., Mr. Gaurav Vijay, Mr. Hari Prasad, Mr. Padam Chandra Jain, etc., it is
Special operators recommended to plan at least one management / behavioural/ technical training, etc. for all associates in
Do you implement planned education to supervisors for skill the entire year.
①
improvement ? △
'2) TNI should be adequately identified. For ISO:26000 training, As per TNI, Mr. Saurabh Malhotra
requires the training, who is also identified as a trainer for the same.
6. 1) Brake Pedal Assy, YCA not found covered in Product audit plan (2020~21), same to be included. On
Quality audit 1
Activity to keep/improve Do you conduct internal quality audit periodically? further investigation it was found that Product audit was not conducted for Brake Pedal Assy., YCA in
and process production quality 2019~20, procedure not adhered.
verification
① following are standardized:, -auditor team; -audit frequency; -audit △
timing; -audit method; -audit check sheet; 2) Timelines for CAPA against NC closure should be established in Process audit procedure, same is
not defined.
Management, quality
2
evaluation and instruction Do you collect supplier failure information, determine supplier
for suppliers ① grade according to quality level and conduct audit and instruction ○
periodically?
For outsourcing any production, do you instruct them clearly 1. As observed during Gemba audit, agreement of inspection for child parts supplied by various sub
② about function and important control items of products at the △ suppliers are not available. Same to be defined and implemented.
meeting ?
IFC, NPD requirements should be communicated to Sub-suppliers, presently same is not shared to sub-
Do you make suppliers to conduct initial production control and suppliers.
④
decide department in charge of conduct?
△
Prevention of recurrence 1) Wrong data is presented to management during review, As per Pareto shown to management,
2
"Gauge Out" concern was reported as top most defect and top most contributing part was Door Hinge,
・Customer claims YP8 RUL in Jun-20. However, analysis was done for Rear Upper Female part-YJC which is not even
・In process failure considered in "Gauge out" defect contributing part pareto, methodology to be improved.
・Suppliers failure Do you prevent recurrence of issues by analysing cause of 2) QPIS was raised to M/s Micro turn for "Length Short issue" reported in YHB-Boss part on 30-Jul-20
① occurring defect based on process investigation result such as 5- △ and closed on 10-Aug-20. Further on 17-Aug-20 again QPIS was raised for Length Short issue and
why analysis? same CAPA sheet was re-submitted by changing the dates. Such practices to be strictly avoided and
analysis should be strengthened at Tier-2 to avoid repetitive concerns.
1) Standardization of documents was not ensured against In-house CAPA analysis done for "Gauge out"
concern in Door Hinge YP8, reported in Jun-20, Actions were taken as "Coil spring guide provided",
however PFMEA was not updated for the same.
Do you reflect corrective action to improvement of process control 2) 'PFMEA was not found updated for "Part mix-up" as cause of failure for Hole Miss concern, as verified
②
and review of standards?
△
in Extension, Front Fender Upper Bracket, L Part, reported as customer complaint from MSIL on
25.07.2020
1) Effectiveness of the action implementation is not adequately judged for Supplier concerns, QPIS was
raised to M/s Micro turn on 30-Jul-20 for "Length Short issue" in YHB-Boss Part, and CAPA was closed
on 10-Aug-20, while same problem was reported on 17-Aug-20 in YHB-Boss, however effectiveness
was judged as "OK" for next two months.
After corrective action are taken, do you conduct on-site check-up 2) As per defined procedure, Effectiveness of an action implemented is judged for next three months,
③
and evaluate the effectiveness?
△
however same was not ensured for "Gauge out" concern reported in Rear Upper Female-YJC part in
Jun-20, same to be ensured as per defined procedure, similar case was also evident in Jul-20 and Aug-
20 gauge out concerns reported in different parts.
Horizontal deployment of action column was left blank in CAPA sheet filled for In-house rejection
Do you cascade information of corrective action to similar parts analysis done in Jun-20 for "Gauge Out" concern reported in YJC-Rear Upper Female, same should be
④
and processes? △
filled so that action can be implemented in other applicable area
9. Location of production 1) At the material receiving area, some of the bins (containing child parts) were kept directly on floors. It
5S 1
site Do you keep store material, work-in-process, finished products, is required to keep bins only on pallets to avoid transfer of floor dust into bins.
management ① inventory and container at appropriate storage prevented from △
dust, rust, scratch, deformation and rainwater?
1. Temporary storage of material on workplace to be avoided. As observed during Gemba audit, at Brkt
③ Do you forbid operators to put temporary storage on work place? △ Floor console box ctr (YHB) punching station, operator was found keeping parts on the press machine
bed along with pre-processed material. Same can lead to mixing of material.
10. Maintenance of 1) During preventive maintenance, recording of actual values of parameters was not evident. Ex: In the
Equipment/ 1
equipment's , jigs and PM check sheet of press machine # NP40 dated 18.5.20, tension of V-belt, current of motor are
Inspection tools measured and mentioned as "OK" instead of recording actual values.
equipment's Also, in the PM check sheet of plating rectifier # REC 03 dated 02.08.2020, judgment criteria is not
management evident for checkpoints. It is to be added.
Do you conduct daily/regularly check of production equipment's,
① △ 2) In the PM check sheet of tool, Female body door hinge YP8, against the check point of strip guide
dies and jigs? Are records of maintenance kept? size (Spec: 73.3±0.05 mm), actual was recorded as 73.8 mm & 73.7 mm in PM check sheet dated -27th
Aug & 5th Sep'20 respectively and was judged as "OK", however recorded value is out of spec.
1) PM check sheet of Spin Riveting machine was verified, one of the check point was mentioned as
"check the working of Pokayoke" and method was mentioned as "visually" against the same, observation
was mentioned as "found OK". But details of Pokayoke, method to check (like set the parameter to out of
spec. values) & judgment criteria (machine shall give alarm/ stop) is not mentioned. It is required to
Do you confirm regularly the function of Pokayoke, automated review the PM check sheet and same to be updated accordingly.
② △
stop and alarm? Are records of maintenance kept? - Similarly, in the PM check sheet of progressive press PLNP07, checkpoint & checking method of inbuilt
Pokayoke (oil level sensor) was not evident. It is required to add Pokayoke details for the same.
Maintenance of 1. As observed during Gemba audit, gauge validation for Brkt Floor console box ctr (YHB) is found
2
inspection equipment's Do you calibrate regularly inspection equipment's and put the overdue (expired on 12/8/20). Monitoring of gauges and fixture for timely validation to be strengthened.
①
expire date on them?
△
11. Implementation of
Implementatio 1 Do you use easy expression (visualizer, onomatopoeia ,etc.) for
standards
n of standards ① operation instructions? So that operator can easily understand ○
process and critical points.
Checking method should be defined against each check point in Robot MIG-03 daily start-up machine,
presently same is not defined.
Is it possible to judge OK/NG specifically by each check sheet (of
⑤
daily equipment check, quality control report, etc.) you use?
△
Non-confirming parts 1. Area for keeping non confirming parts to be separated and properly identified. As observed during
2 Do you control identification of non-confirming parts and parts on
management Gemba audit, rejection material and material storage for plating is kept together without any identification
①
hold. Do you store them separately?
△
or separation of the locations.
Do you keep the repair history when repairing & using Maru A
③ ○
items?
PLANNING
VENDOR CODE T043
TOTAL 0
AUDIT DATE 30.09.2020 & 01.10.2020
RECEIVING DATE
VERIFICATION
VERIFICATION
AUDIT PART NAME
1) As per the procedure, periodic review of PFMEA to be carried out once in a year. Currently, periodic review is not 1. Model Wise PFMEA Review Plan to be develop and same to be followed.
evident. It is required to prepare PFMEA review plan and carry out periodic review as per procedure.
2) Gap observed in the preparation of new model PFMEA w.r.t AIAG guidelines. Ex: In the PFMEA of YNC brake
1) PFMEA Review plan is shared wherein review frequency of each
pedal, at process no.345-Robot MIG welding, RPN is calculated for failure mode (i.e., RPN for weld penetration NG is 2. Potential Cause wise RPN to be calculated and PFMEA for YNC Brake Pedal to be PFMEA is covered with once/year frequency. (Closed) 1. Closed
1 3.2 calculated as100) but it is required to prepare RPN for each potential cause (like welding parameter variation, welding revised and retraining to be given for the PFMEA. 1
tip ID more etc.). 2) Updated PFMEA with individual RPN for each occurrence rating 2. Open
to be shared, presently same is not shared.
1) Verified the initial flow control record of YJC MC - Hinge assy, Front door and following improvements are required.
a) Stricter check of in process parameter are not evident. (only 100% check carried out on final assy part). It is required
to identify the critical parameter at each station and do stricter check.
b) All the termination condition mentioned in the procedure are not evident in the termination check sheet. Ex:
Termination condition like internal PPM, closure status of process audit observation etc. are not mentioned in 1a) Trainining on IFC awareness regarding " Stricter check of In-
termination check sheet. Process parametere and IFC termination condition" should be given
to team and shared as evidence. 1a,1B)
2) As per procedure, process audit are to be carried out, same was not conducted during IFM of YJC MC - Hinge Assy, 1 & 2. Procedure/ Rule/Checksheet to be reviewed wrt Termination Condition and same 1b) Filled termination sheet to be shared, kindly ensure all
Front door. to be followed in the under-developing projects. Open
2 1.2 termination paramatetes are deined. 2
2) For the same, kinldy ensure in IFC training sheet, "Process 2) Open
Audits to be ensured during IFC tenure" and ve given to team to
follow the same.
1) In the control plan of YCA Brake pedal, at process no. 800, bush & spacer assy with arm and greasing in boss,
details of pokayoke is not evident. (During Shop Floor audit it was found that pokayoke was available w.r.t air pressure/ Updated control plan is not shared, Kinldy attach the updated
proper greasing etc.). It is required to add pokayoke details in control plan. Control Plan to be review for the Poka-Yoke availablity and Control Method to be
4 1.3
mentioned in the YCA Brake Pedal similarly. control plan at Process-800 wherein poka-yoke refrence has been Open 1
added to the same.
Operator trainings Planned vs Attended is not evident. As of now all operators are given training as per annual training
calendar, however there is no system evident in which plan vs actual is captured as verified for "Quality abnormality (i) Training Skill matrix is attached, kinldy share annual training
handling/ Red Bin handling" training conducted multiple times in past, however many operators such as Mr. Lakhan,
etc. were not found covered Also Re-training to be planned for the members whose training is not conducted. calendar wherein all operator names should be mentioned to track
Plan for the Operator trainings to be develop and same to be incorporate with the the plan vs actual for each operator.
5 1.1 procedure for the re-training of the leftover operators considering their process wise
(ii) Training Procedure to be updated regarding requirement of Re-
Open 1
topics.
training incase any training or an individual is not able to attend the
training.
New Operator training mechanism was verified, following concerns should be focused-
a) Acceptance criteria along with Target vs Actual for "Takt time" and "Quality defects" parameter should be recorded
in practical evaluation sheet for skill level evaluation, presently scoring of 5 was given on all days as evident for New
Operator Dharmender (DOJ- 23/Jun/20), but basis of giving 5 score is not evident. a. Operator Observance sheet and Practical OJT sheet are two
b) Same practical Evaluation sheet is used to asses Skill level 3 (Can solve problems) and skill level 4 (Can train separate documents, kinldy share the Practical OJT sheet for the
others), however no assessment parameters for judgment of "Can train others" is evaluated. Same to be included while same, also kindly ensure to share a filled practical OJT sheet to
upgrading the operator from skill level 3 to skill level 4. 1a. Observance Sheet to be reviewed and revised as per evaluation criteria.
make Takt time and quality defect target vs actual monitoring a. Open
c) Skill matrix was not found to be updated for operator Dharmender, DOJ as 23-Jun-20, Operator achieved "skill level
1" on 27-Jun-20 and "skill level 2" on 30-Aug-20, however till present skill matrix was not updated for Operator 1b. Level Wise Skill Level criteria to be reviewed and revised for the L-1, 2, 3 & 4. evident. b. Open
Dharmender. Skill matrix udation frequency is defined as once every quarter however same should be amended in b. No Skill assesment sheet (Practical OJT) is shared for L-4 & L-3. c. Open
5 1.2 such a manner so that such changes are captured at the earliest. 1c. Skill Updation frequency to be revised in the format and same to be link with the
c. Training Procedure to be updated regarding skill matrix updation
1
2) New Operator training procedure should be revised to include timelines, Passing criteria and Evaluation mechanism procedure.
for each skill level upgradation i.e. Skill level 2,3 and 4, presently same is defined only for Dojo training mechanism. frequency, It is recommended to revise the skill matrix as soon as 2. Partially
the operator skill level is upgraded. Closed
2. Procedure for new operator evaluation criteria to be revised in the existing procedure.
2. Training Procedure is updated with L-2, L-3, L-4, Timelines for
skill upgradation, etc., however Passing criteria for skill level-3 is
not defined, same to be added to manual.
1) Training should be identified for all associates, presently in TNI-2020~21, no training was identified for many staff
members e.g., Mr. Gaurav Vijay, Mr. Hari Prasad, Mr. Padam Chandra Jain, etc., it is recommended to plan at least 1) TNI is updated with missing names i.e. Mr. Gaurav Vijay, Hari
one management / behavioral/ technical training, etc. for all associates in the entire year. 1. TNI for the staff level needs to be revised for all the employee and methodology of Prasad, Mr. Padam Chandra, etc. 1. Closed
'2) TNI should be adequately identified. For ISO:26000 training, As per TNI, Mr. Saurabh Malhotra requires the training, considering atleast one training of every staff.
5 2..1
who is also identified as a trainer for the same.
1
2. Awareness wrt updating and TNI to be given to the HR executive. 2) Updated Trainers list is not shared wherein Mr. Saurabh 2. Open
malhotra's name has been remove for ISO 26000 trainer.
1) Defect matrix should be prepared and all possible visual defects should be included in the same for carrying out
Poisons Cake test. At present Poisons cake test is carried out 6 times a year with any one (1) random NG part. Number
of NG parts passed during test to be increased and should be driven from defined defect matrix to cover all possible
defects within defined periodic frequency, same needs to be updated in procedure.
2) Poisons cake test procedure to be revised to reconfirm the part quality for already verified lots incase an inspector 1. Defect Matrix wrt internal defects and external (Customer) defects to be developed 1) Defect Matrix is not shared, same to be shared, kinldy ensure all
fails in poisons cake test. and their Coding to be define in it. defects are covered in the same 1. Open
5 2.3 2) Poisons cake test Procedure (TIL/QMS/PRD/20) is revised with 1
2. Poison Cake Test Rule to be revised considering "Containment action against Fail condition of Re-inspection of parts incase inspector fails in the 2. Closed
Inspector". poisons cake test along with training.
1. Product Audit Plan to be reviewed for considering all the MSIL parts in it.
1) Brake Pedal Assy, YCA not found covered in Product audit plan (2020~21), same to be included. On further 1. No Evidence shared, Updated Product audit plan to be shared
investigation it was found that Product audit was not conducted for Brake Pedal Assy., YCA in 2019~20, procedure not 2. Procedure for the Product Audit needs to be revised considering " Action against NC where Brake Pedal Assy (YCA) should be ensured, also review by 1. Open
6 1.1 adhered. closure" with the given time duration. HOD should be evident on Audit Plan. 2
2) Timelines for CAPA against NC closure should be established in Process audit procedure, same is not defined.
2. Open
2. Updated Timeline is not evident, Evidence attached is not clear.
Process audit Judgment was given for 3 voltage parameter out of 4 Voltage parameters (Boss / Plate / Switch / Stroke Awareness on VSA 6.3 process Audit has been given, evidence
Awareness to be given to the Process Auditor for the mentioning the specific
6 2.2 Sensor), as verified for YHB Brake Assy Weld (MIG) process, audit conducted on 29.08.20, same to be ensured
parameters details in the report and control plan as well for parameter cross-check. attached.
Closed
against parameters mentioned in control plan.
1. No action evidence were taken against certain audit observations such as "Statistical Technique and gauging", etc. 1. No Training evidence was shared wherein team was given 1. Open
concern raised during new supplier selection audit conducted for M/s CSR Forging on 23/Oct/2019. Also, timelines for Procedure for the Selection New Supplier to be update considering Criteria against training for adequately filling audit observations.
7 1.1
countermeasure evidences collected against audit observation should be defined in procedure. Action Plan for not achieving the score, IFC and other requirements. 2. New Supplier selection audit check sheet is not shared with
2
2. New Supplier selection audit check sheet to be revised to include check points for IFC.
updated IFC check point. 2. open
As observed during Gemba audit, agreement of inspection for child parts supplied by various sub suppliers are not Incoming/Receiving Inspection Plan wrt parameters define to revise and same to be Inspection standard for suppliers is not shared, same to be shared
7 2.2
available. Same to be defined and implemented. followed for other BOP's as well. as evidene.
Open 1
Supplier End Training Plan to be conduct for the IFC, 4M, Why-Why Analysis, QPIS
and other requirements.
7 2.4 IFC, NPD requirements should be communicated to Sub-suppliers, presently same is not shared to sub-suppliers. Supplier Quality Manual is not shared. Open 1
Supplier Quality Manual to be develop for the same.
In-house rejection analysis procedure should be revised to include Daily rejection analysis criteria on the basis of Daily rejection criteria is addreesed with analysis being done for
8 1.2
volume of rejection in a day and criticality of defect.
Procedure to be revised considering Inhouse rejection handling on daily basis.
top-2 high defects.
Closed
1) Wrong data is presented to management during review, As per Pareto shown to management, "Gauge Out" concern 1. Training evidence to be shared wherein team has to be given
was reported as top most defect and top most contributing part was Door Hinge, YP8 RUL in Jun-20. However, analysis
was done for Rear Upper Female part-YJC which is not even considered in "Gauge out" defect contributing part pareto, trainig about following of CAPA criteria as er defined procedure, 1. Open
methodology to be improved. Awareness to be given to the concern team for the proper analysis of the CAPA and same to be shared.
8 2.1
2) QPIS was raised to M/s Micro turn for "Length Short issue" reported in YHB-Boss part on 30-Jul-20 and closed on same to be demostrate to the management. 1
10-Aug-20. Further on 17-Aug-20 again QPIS was raised for Length Short issue and same CAPA sheet was re-
2. Root Cauae analysis, Whhy-Why and CAPA analysis training 2. Closed
submitted by changing the dates. Such practices to be strictly avoided and analysis should be strengthened at Tier-2 to
avoid repetitive concerns. has been given to Mr. Ramesh Yadav
1) Standardization of documents was not ensured against In-house CAPA analysis done for "Gauge out" concern in
1. Awareness to be given to the concern team for the proper analysis of the CAPA and 1. Updated PFMEA is not shared. 1. Open
Door Hinge YP8, reported in Jun-20, Actions were taken as "Coil spring guide provided", however PFMEA was not
same to be demostrate to the management.
8 2.2 updated for the same.
2. Updated PFMEA for Hole miss problem in extension, Front
2
2) 'PFMEA was not found updated for "Part mix-up" as cause of failure for Hole Miss concern, as verified in Extension,
Front Fender Upper Bracket, L Part, reported as customer complaint from MSIL on 25.07.2020
2. Documents updation wrt CAPA to be reviewed and update.
Fender Upper Bracket, L Part, was not found. 2. Open
1) Effectiveness of the action implementation is not adequately judged for Supplier concerns, QPIS was raised to M/s
Micro turn on 30-Jul-20 for "Length Short issue" in YHB-Boss Part, and CAPA was closed on 10-Aug-20, while same 1. Supplier End Training Plan to be conduct for the IFC, 4M, Why-Why Analysis, QPIS 1. SQA team to be given training regarding CAPA and adequate
problem was reported on 17-Aug-20 in YHB-Boss, however effectiveness was judged as "OK" for next two months. and other requirements. closure, also supplier training records are not evident. 1. Open
8 2.3 2) As per defined procedure, Effectiveness of an action implemented is judged for next three months, however same 2
was not ensured for "Gauge out" concern reported in Rear Upper Female-YJC part in Jun-20, same to be ensured as 2. QPIS closure is only being done by HOD-SQ after completing the three months lot 2. Closure of QPIS will be done after three month effectiveness
per defined procedure, similar case was also evident in Jul-20 and Aug-20 gauge out concerns reported in different verification.
2. Open
parts. check to be defined in procedure.
Horizontal deployment of action column was left blank in CAPA sheet filled for In-house rejection analysis done in Jun-
Awareness to be given to the concern team for the proper analysis of the CAPA and CAPA training record is evident for Mr. Ramesh Yadav about root
8 2.4 20 for "Gauge Out" concern reported in YJC-Rear Upper Female, same should be filled so that action can be
Horizontal Deployment activities cause, 5-Why and CAPA.
Closed
implemented in other applicable area
1) PM checksheet of Spin Rivetting machine was verified, one of the check point was mentioned as "check the working 1. SPIN Rivetting PM check sheet was foun revised with "Check the
of pokayoke" and method was mentioned as "visually" against the same, observation was mentioned as "found OK". dressing of the poka-yoke" and same is visually confirmed, same
But details of pokayoke, method to check (like set the parameter to out of spec. values) & judgment criteria (machine Partially
PM Checksheet to reviwed and revised wrt parameters and other process to be define condition was also evident for other check point of the same
10 1.2 shall give alarm/ stop) is not mentioned. It is required to review the PM checksheet and same to be updated
for Poka-Yoke. machine. Cloesd
accordingly.
- Similarly, in the PM checksheet of progressive press PLNP07, checkpoint & checking method of inbuilt pokayoke (oil However, PM check sheet of PLNP07 is still not updated and
level sensor) was not evident. It is required to add pokayoke details for the same. shared.
As observed during Gemba audit, gauge validation for Brkt Floor console box ctr (YHB) is found overdue (expired on System to be develop for the gauge due date alert fom the inprocess inspector to the
10 2.1
12/8/20). Monitoring of gauges and fixture for timely validation to be strengthened. standard room analyst 10 days before the due date. NO Supporting evidence found Open 1
Checking method should be defined against each check point in Robot MIG-03 daily start-up machine, presently same Checksheet for the Daily Startup Machine to be revised and checking method to be
11 1.5
is not defined. revised. NO Supporting evidence found Open 1
1. Adherence of work standards at receipt inspection stage to be strengthened. As observed during Gemba audit,
following observations made:
a. For child part screw nut (JSN0001) supplied by M/s Auto International, in the PDI report submitted by supplier,
specification for dim. 19.8 is mentioned as -0.1, however, for same dimension, Technico receipt inspection standard Not Considered in Action Plan File, Evidence of the same to be
12 1.3
has spec defined as 19.8+0.1. Also, details of heat no. supplied by vendor in SRV no. 4574 dated 9/1/21 are not shared
Open 1
mentioned in the material test certificate provided along with the lot. However, receipt inspector has mentioned the
report as verified and accepted.
b. Sample size verified in case of material receipt inspection after plating is not mentioned in the report.
Physical stock vs system stock was found to mismatch, As verified for Part Pin Door Hinge, As per SAP data, stock
Identification for the "USE ME FIRST " to be define at BOP stoarge and "ARROW"
12 1.1 was received on 18.09.20, 25.09.20 and 29.09.20. During shop floor audit, lot received on 29.09.20 was not available
marking to be provided for it. Use Me first tags are now used for adequate FIFO control Closed
though previous two lots were still found available, FIFO mechanism to be stregthenend.
Area for keeping non confirming parts to be separated and properly identified. As observed during Gemba audit,
Separate Location for the Non-conforming parts to be define away from OK/WIP parts. Rejection material area is identified with rejection tag and all
12 1.1 rejection material and material storage for plating is kept together without any identification or separation of the
Non-conforming parts to be kept with proper identifications. material kept separately
Closed
locations.
Total Observations
Closed; 9
Partial
Closed; 9; 22%
Partially Closed; 2; 5%