Project Proposal: Rationale / Approach
Project Proposal: Rationale / Approach
Project Proposal: Rationale / Approach
Project Title: Pao Pao High School Stakeholders as Leaders: Leading School to
Better Teaching and Learning by Building a Complete School Learning Facilities
and Productive Library Renovation
Project Site: Pao-Pao High School Brgy. Sinawal General Santos City.
Proponent: LGU (Local Government Unit), DepEd Gensan, Barangay/Purok
Officials, Parents, Teachers and Students
Project Duration/Date: 2nd week of June-September
RATIONALE / APPROACH
The expected outcomes for this project is to provide learning materials such
as books, set of computers and complete school facilities as soon as possible in
order to build development and improvement to the school in order for them to
provide a nice climate environment and a good quality education to students
OBJECTIVES:
PROJECT DESCRIPTION/DEPLOYMENT:
First, recruiting volunteers in the project. Second, the project team will raise
money or budget to the local government or any sponsor that will help achieve
the objectives of the project. After finding sponsors, that will be the moment that
the project team will going to buy the materials needed in making the project. The
school has many classrooms so instead of making library in each classrooms,
the project team develop a plan to renovate the school library to make it more
attractive to the students in the campus. Then, with the help of the local
government, providing more computers in their computer lab will be a great help
to them because the school doesn't have enough computers.
BUDGET:
Materials/Equipment Break-down Amount
Books 100pcs. x ₽150.00 ₽15,500.00
Computers 10 set x ₽12,000.00 ₽120,000.00
Chairs 15pcs x ₽150.00 ₽2,250.00
Long Table 3 pcs x ₽450.00 ₽1,350.00
Cement 15 sacks x ₽220.00 ₽3,300.00
Paint 5 cans x ₽850.00 ₽4,250.00
Paint Brush 8 pcs x ₽30.00 ₽240.00
Woods/Lumber 6pcs x ₽70.00 ₽420,00
Hammer 2pcs x ₽150.00 ₽300.00
Nail 2 bags x ₽135.00 ₽270.00
Aluminum & Steel 8pcs. x ₽350.00 ₽2,800.00
Hollow Blocks 300pcs x ₽5.00. ₽1,500.00
Sand 2 loads x ₽850.00 ₽1,700.00
Construction Workers 4 person x ₽2,500.00 ₽10,000.00
Electric Wires Installation of electricity ₽15,000.00
Meals of participants and 50 pax x ₽150.00 ₽7,500.00
volunteers
TOTAL: ₽186,380.00
GANTT CHART
Activities June (2nd- Last week of July August September
3rd week) June
Submission .
and
Presentation
of Proposal
Coordination .
meeting with
the barangay
Conduct pre- .
test/ training
needs
assessment
Organizational .
meeting/
orientation of
volunteers
Implementatio .
n of project
Post activity .
visitation/
Monitoring/
Evaluation
Submission of .
documentatio
n report
Presentation .
of evaluation
report to the
barangay
Prepared By:
LOPEZ, Krysthal Kate L.
BORAQUIT, Queenie S.
LANON, Jhon Fernan A
GAYRAMARA, John Albert
MATULLANO, Keanu