Transition Chart for PEPSI

DEPARTMENT ACTIVITY
Customer Project Awarding
FAST-PEPSI Kick-off Meeting (Schedule of turn-over: Stock and Materials
FAST Kick-off Meeting
FAST Finalize Transition Plan/Schedule of Activities
FAST Creation of SOPs/Gis/Forms
FAST * Inbound/Issuance
FAST * VAS Process
FAST * Inventory
FAST * Outbound/Dispatch
FAST * Quality Assurance
FAST Presentation of Transition Update/ SOPs/Gis
FAST Update based on discussed Meeting
FAST-Site Head RCA for Transition Budget
Customer Contract Release / NTP
FAST-Customer Contract Processing (Signature)
Support Alabang Branch request
FAST HR Sourcing Candidates / Call Outs / Pooling
FAST HR Online Job Posting (Indeed & Facebook)
FAST-BD/Site Head Ocular of Site (VAS Area)
FAST-BD/Site Head Prepare VAS Layout
FAST-BD/Site Head Present final VAS Layout
FAST-BD/Site Head Prepare VAS area based on approved layout
FAST HR NPA / Contract Signing / Uniform / ID Issuance
FAST HR Delivery of Uniforms & PPEs
FAST PROCU RCE: Equipment (Matrix)
FAST PROCU RO: Office/Cleaning Supplies/Operations Supplies (Polybags)
FAST HR NPA/Contract Preparation
FAST HR Online Examination for Supervisory Level
FAST HR Pre-Employments Requirements / Health Permit Process
FAST HR Checking of Medical Result & Pre-Employment Requirements / Health Permit
FAST HR Orientation
FAST HR Final Interview
FAST HR Uniforms / PPE'S / I.D. Preparation
FAST HR Biometrics Enrollment
FAST HR HRIS Encoding
FAST PROCU Delivery of Equipment
FAST PROCU Delivery of Office Supplies
FAST PROCU Delivery of Unprinted Polybags/Labels
FAST PROCU Delivery of Printed Polybags
FAST HR Deployment
FAST Go Live
FAST Training / Nesting
PSI
START DATE END DATE DURATION
Mar - 16 - 2020 Mar - 17 - 2020 1
Mar - 17 - 2020 Mar - 17 - 2020 1
Mar - 17 - 2020 Mar - 18 - 2020 1
Mar - 17 - 2020 Mar - 18 - 2020 1
Mar - 18 - 2020 Mar - 23 - 2020 5

Mar - 23 - 2020 Mar - 24 - 2020 1


Mar - 24 - 2020 Mar - 25 - 2020 1
Mar - 17 - 2020 Mar - 18 - 2020 1
Mar - 18 - 2020 Mar - 27 - 2020 9
Mar - 27 - 2020 Apr - 06 - 2020 10
Mar - 27 - 2020 Mar - 29 - 2020 2
Mar - 17 - 2020 Mar - 20 - 2020 3
Mar - 17 - 2020 Mar - 18 - 2020 1
Mar - 17 - 2020 Mar - 18 - 2020 1
Mar - 18 - 2020 Mar - 20 - 2020 2
Mar - 20 - 2020 Mar - 25 - 2020 5
Mar - 25 - 2020 Mar - 27 - 2020 2
Mar - 18 - 2020 Mar - 25 - 2020 7
Mar - 18 - 2020 Mar - 23 - 2020 5
Mar - 18 - 2020 Mar - 19 - 2020 1
Mar - 18 - 2020 Mar - 19 - 2020 1
Mar - 23 - 2020 Mar - 25 - 2020 2
Mar - 23 - 2020 Mar - 25 - 2020 2
Mar - 23 - 2020 Mar - 25 - 2020 2
Mar - 23 - 2020 Mar - 25 - 2020 2
Mar - 25 - 2020 Mar - 26 - 2020 1
Mar - 25 - 2020 Mar - 26 - 2020 1
Mar - 20 - 2020 Mar - 26 - 2020 6
Mar - 26 - 2020 Mar - 30 - 2020 4
Mar - 30 - 2020 Mar - 31 - 2020 1
Mar - 16 - 2020 Mar - 27 - 2020 11
Mar - 16 - 2020 Mar - 27 - 2020 11
Mar - 18 - 2020 Mar - 29 - 2020 11
Mar - 18 - 2020 May - 17 - 2020 60
Mar - 28 - 2020 Mar - 28 - 2020
Mar - 28 - 2020 Mar - 28 - 2020
Mar - 28 - 2020 Apr - 18 - 2020 21
Column1

Machine can be deployed based on April 1, 2020 Go Live.

2 months lead-time for the preparation of printed materials