CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT

LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: 01 October 2018 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL WORK DONE Work In Remaining Percent


Sr. No DESCRIPTION UNIT QTY Till Previous Progress Work Completion REMARKS
Day (Today)

1 BUS PARKING AREA


Total Area of Depot M2 55,384.00
1 Excavation M3 42,054.91 42054.91 0.00 100% Completed
2 Gravel Material M3 31,386.73 30462 924.73 97% in Progress
3 Sub Base M3 15,611.22 14668 943.22 94% in Progress
4 Agreegate Base M3 15,611.22 13400 2,211.22 86% in Progress
5 Lean Concrete M3 5,206.34 3,356.00 1,850.34 64% in Progress
6 Rigid Pavement M3 15,619.02 6460 216.00 8,943.02 41% in Progress

2 BOUNDARY WALL
Total Boundary Wall Length M 1,128.35 -
1 Excavation M3 680.30 666.00 14.30 98% in Progress
2 Gravel Material M3 184.45 180.00 4.45 98% in Progress
3 Common Filling M3 418.26 411.00 7.26 98% in Progress
4 PCC Footing M3 185.42 180.00 5.42 97% in Progress
5 RCC in Foundation, Class- A1 M3 91.50 86.45 5.05 94% in Progress
6 RCC in Super Structure, Class- A1 M3 292.32 265.16 27.16 91% in Progress
7 Reinforcement Ton 51.41 50.08 1.33 97% in Progress
8 Brick Work M3 594.89 540.57 54.33 91% in Progress

Page 1 of 4
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: 01 October 2018 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL WORK DONE Work In Remaining Percent


Sr. No DESCRIPTION UNIT QTY Till Previous Progress Work Completion REMARKS
Day (Today)
9 Pointing M2 2,764.77 2,425.57 37.74 301.46 88% in Progress
10 Plastering M2 2,764.77 1,380.47 113.22 1,271.08 50% in Progress

3 WORKSHOP
Total Covered Area M2 4,369.15 -

1 Excavation M3 4,813.63 4,813.63 - 100% Completed

2 Gravel Material M3 1,266.75 1,266.75 - 100% Completed

3 Anti Termite M2 1,800.00 1,800.00 - 100% Completed

4 PCC Footing & Flooring M3 427.00 166.00 261.00 39% Completed

5 RCC In Foundation M3 1,356.96 1,356.96 - 100% Completed

6 RCC in Super Structure M3 1,837.55 73.00 1,764.55 4% in Progress


7 Reinforcement Ton 682.11 194.81 487.30 29% in Progress
8 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 3,402.10 3,402.10 - 100% Completed
9 Sand Filling M3 3,796.13 2,741.00 1,055.13 72% in Progress
10 Brick masonary Ratio 1:4 (225mm thick) M3 874.38 - 874.38 0% -

Page 2 of 4
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: 01 October 2018 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL WORK DONE Work In Remaining Percent


Sr. No DESCRIPTION UNIT QTY Till Previous Progress Work Completion REMARKS
Day (Today)

4 PARK & RIDE


Total Covered Area M2 15,547.18 -
Hold By PDA on 10 July
1 Excavation M3 15,302.72 3,150.00 12,152.72 21%
2018 In meeting

5 OFFICE BUILDING
Total Covered Area M2 5,210.43 -

1 Excavation M3 3,857.08 3,857.08 - 100% Completed

2 Gravel Material M3 1,215.00 1,215.00 - 100% Completed

3 PCC Footing M3 145.45 145.45 - 100% Completed

4 RCC in Foundation M3 3,393.98 1,444.00 3.00 1,946.98 43% in Progress

5 RCC in Super Structure M3 1,812.83 - 1,812.83 0% in Progress


RCC in Super Structure Auditorium & Shear
6 walls M3 89.22 4.18 1.50 83.54 5% in Progress

7 Reinforcement Ton 795.29 156.00 639.29 20% in Progress

8 Brick masonary Ratio 1:4 (225mm thick) M3 1,127.25 - 1,127.25 0% -


9 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 2,387.00 1,600.00 787.00 67% in Progress

Page 3 of 4
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: 01 October 2018 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04

TOTAL WORK DONE Work In Remaining Percent


Sr. No DESCRIPTION UNIT QTY Till Previous Progress Work Completion REMARKS
Day (Today)
6 DRAIN NO. 07
Total Length M 625.00 -

1 Excavation M3 350.00 326.00 24.00 93% in Progress

2 Gravel Material M3 321.07 283.00 38.07 88% in Progress

3 Lean Concrete M3 103.84 87.00 16.84 84% in Progress

4 RCC of Drain Bed, Walls & Slab M3 632.00 468.70 163.30 74% in Progress
5 Reinforcement Ton 60.77 50.17 10.60 83% in Progress
7 Rest Area's (Male & Female)
Total Covered Area M2 1,230.00 -

1 Excavation M3 1,886.04 1,886.04 - 100% Completed

2 Gravel Material M3 377.21 377.21 - 100% Completed

3 PCC Footing & Flooring M3 144.00 60.50 3.00 80.50 42% Completed

4 RCC in Foundation M3 452.25 442.00 10.25 98% in Progress

5 RCC in Super Structure M3 585.94 - 585.94 0% -


6 Reinforcement Ton 166.11 32.36 133.75 19% in Progress
8 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 558.48 550.00 8.48 98% in Progress
9 Sand Filling M3 880.15 615.00 265.15 70% in Progress

Contractor: Consultant:
ANHUI-CALSON JV MM PAKISTAN.