Professional Documents
Culture Documents
Department of Civil Engineering Project Report: St. Joseph Polytechnic
Department of Civil Engineering Project Report: St. Joseph Polytechnic
Joseph Polytechnic
THIRUMAYAM-622 507
Submitted By
REG.NO NAME
29109999 P.MANIKANDAN
29110000 R.MANIKANDAN
29110001 V.MEYYAPPAN
29110002 M.MOOVENTHAN
29110003 K.MURUGANANTHAM
29110004 N.MUTHUKUMAR
Guided by
Thiru. M.PAUL DCE., BE.,
Lecturer in civil Engineering
THIRUMAYAM-622 507
Community hall
St. Joseph Polytechnic
BONAFIDE CERTIFICATE
NAME: REG.NO:
Community hall
St. Joseph Polytechnic
Community hall
St. Joseph Polytechnic
Community hall
St. Joseph Polytechnic
Community hall
St. Joseph Polytechnic
ACKNOWLEDGEMENT
Community hall
St. Joseph Polytechnic
……Project Team
Community hall
St. Joseph Polytechnic
SYNPOSIS
We are the final year students surveyed the area and proposed to
take up a project for con struction of community hall to public in a large
scale here the people live in and around the area can be utilized. This hall
which will be most helpful to perform their functions with a great manner.
Community hall
St. Joseph Polytechnic
REPORT WRITING
Community hall
St. Joseph Polytechnic
Plastering is done with CM 1:5 country wood paneled doors and doors
windows and ventilators are proposed.
As per IS 456-2000, M20 grade concrete and Fe415 grade steel re used.
Drawings are made with the help of AutoCAD software and Estimation is
done with the help of Microsoft Excel software as per the current schedule
of rates 2010-2011.
Community hall
St. Joseph Polytechnic
SPECIFICATION
R.C.C roof slab 1:2:4 mix using 20mm jelly at the size of
150mm thick for ground floor properly the reinforcement of main bar and
distribution bars are designed and provided.
Wall Plastering:
Inner and outer walls in 1:3 with 12mm thick and the edges
of the joining such as jelly finished with cm 1:2mix.
Ceiling Plastering:
Floor Finish:
Community hall
St. Joseph Polytechnic
Flooring:
White Washing:
Community hall
St. Joseph Polytechnic
DESIGN LINTEL:
Data:
Use M20, and Fe 415
Wall thick = 230mm
Brick = 20 KN/m
D = 110 + 30 = 149
= 150mm
Effective Span-:
Height of equiltereal
Triangle = 0.866X L
= 0.866X1.6= 1.3866m
Height of wall above
the lintel = 3-(2.1+0.15) =0.75 m
Since the height of wall above the lintel is less than 0.866XL
the total weight of the rectangular portion of the masonry above the lintel is
consider in the design of lintel
Load:
Community hall
St. Joseph Polytechnic
= 3.278 KN/M
Mu = WI2
8
= (10.125 x 1.6192)
8
=
6
3.276 x 10 KN/m
Area Of Steel:-
Mu = 0.87 x fy x Ast x d (1 -Ast.fy)
bd.fck
Ast = 80.56 mm
Spacing:
Provide 2 Nos. # 10mm dia bars of 300 mm C/c
Community hall
St. Joseph Polytechnic
S = 50 x 100 = 27.47
182
S = 5 x 119 = 595
= 100 x 100
230x 126
= 0.345%
= 142.5 N/mm2
M.F = 2.0
Community hall
St. Joseph Polytechnic
B.VX M.F
= 1600/92x26) = 30.77<126 mm
Result:
Size of lintel = 230X150mm
Tension reinforcement = 2Nos 10mm# Fe 415
Community hall
St. Joseph Polytechnic
Effective span:-
Effective span of flight =2.25+0.9= 3.15m
Loads:-
Consider one meter width
Community hall
St. Joseph Polytechnic
d = 96.87mm
= 150-15-5 =130>96.87mm
Area of steel :-
Main reinforcement
Solving
Ast = 611.95 mm2
Provided 8nos 0f 10mm dia in each flight as main reinforcement
Distributers
Ast (minimum) = 0.12% bd
= 0.12% 1000x150
= 180mm2
Spacing of 8mm # bars
S = ast x1000
Ast
= (50.27 /180) 1000
=219mm
Say270mm c/c
Provide 8mm# @ 270mmc/c
Community hall
St. Joseph Polytechnic
= 0.2N/mm2
Minimum value permissible value = 0.28N/mm2
Hence safe,
= 628 x 100
900x 130
= 0.537%
Fs = 0.58 Fy Ast (required)
Ast ( provided)
= 0.58x 415x (611.5/628)
= 210 N/mm2
M.F = 1.53
= 3150/20x1.53) = 102.87<126 mm
Result:-
Community hall
St. Joseph Polytechnic
Data:
Room Size = 3.90 x 9.15m
Community hall
St. Joseph Polytechnic
Loads:
Weathering course = 1.25 KN/m2
Self weight = 1 x 0.15 x 25 = 3.75 KN/m2
Imposed load (5/3.90) = 1.28 KN/m2
6.28 KN/m2
Factored load = 6.28 x 1.5 = 9.42 KN/m2
Depth Required:
d = √ Mu/Qub = √19.12 x 106/(2.76 x 1000) = 83.23mm
Eff.depth provided = 130mm > 83.23mm
Main Reinforcement:
Mu = 0.87fy Ast[d- fy Ast/fck b]
19.12 x 106 = 0.87 x 415 Ast [130 - 415 Ast/(20 x 1000)]
19.12 x 106 = 46936.5 Ast – 7.49 Ast2
Community hall
St. Joseph Polytechnic
Distributers:
Area = 180mm2
Spacing = ast/Ast x 1000 = 50/180 x 1000 = 277 say 250mm
Provide for 8mm dia @ 250mm C/C
Community hall
St. Joseph Polytechnic
d=√ Mu/Qub
D = 550
Main Reinforcement:
Community hall
St. Joseph Polytechnic
Ast = 1162.30mm2
Shear Reinforcement :
d = 0.505/2 = 0.25
Vu = w l/2.w (0.25+0.505)
τc = 0.59
τc > τv No Shear Reinforcement in necessary only provided nominal
shear reinforcement.
Community hall
St. Joseph Polytechnic
Community hall
St. Joseph Polytechnic
Loads:
Size of Footing :
w = 49.19KN
Area = 49.19 / 120 = 0.41m2
Ratio of B to L = 300/350 = 0.86
0.86 L x L = 0.41
0.86L2 = 0.41
L2 = 0.41/0.86
L = 0.70m
Provide L = 1m
B = 0.70m
Size of Foundation = 1 x 0.70m
Net upward pressure = Po=49.19 / (1 x 10.70) = 70.27 KN/m2
Design of Section :
Bending moment M1 about section X.X
M1 = P0B/8 (L-a)2
= 70.27 x 0.70/8 (1-0.35)2
= 4.00 x 106 N/mm2
Community hall
St. Joseph Polytechnic
τv = Vu/Bd = 49.19(0.325-0.001d2)/0.70d
= 0.144 N/mm2
Allowable Shear Stress:
τc is given by
Community hall
St. Joseph Polytechnic
Community hall
St. Joseph Polytechnic
Community hall
St. Joseph Polytechnic
Community hall
St. Joseph Polytechnic
Community hall
St. Joseph Polytechnic
Minimum reinforcement:
For fe 250 grade steel,
Astmin = 0.15 % as total bD
= 0.15 / 100 (1000 x 75)
= 112.5 mm2.
Spanning of main reinforcement:-
Area of 8mmφ bar ast = π d2/4.
= 50.26 mm2.
i) Spacing of main reinforcement = ast / Astmin x 1000
Community hall
St. Joseph Polytechnic
Community hall
St. Joseph Polytechnic
Community hall
St. Joseph Polytechnic
Effective depth :
Mu = wl2/8 = 9234.375 x 5.112/8 = 30.14KNm
d = √ Mu / Q.b = √30.15 x 10 6/2.759 x 230 =217.98 Sq 220mm
Overall Depth (D) = 220 + 25 + 8 + 20 / 2 = 263mm
Community hall
St. Joseph Polytechnic
Steel reinforcement:
Mu = 0.87fyAst [d- fyAst/fck b]
31.55 x 106 = 0.87 x 415Ast [332-415Ast / (20 x 230)]
82.59Ast2 – 119868.6 Ast +31.55 x 106 = 0
Ast = 285.34mm2
3Nos of 12mm φ rod 339.3 mm2
Shear reinforcement:
d = 0.332/2 = 0.166
Qu = w l/2 = w(0.166+0.332)
= [9234.375 x 5.11 / 2] – [9234.375(0.166+0.332)]
= 23593.83 – 4598.72 =18995.11 N
τc = 0.36+[0.48-0.36/0.25](0.4-0.25)=0.432
Data:
Dimension : 230 x 230mm
Community hall
St. Joseph Polytechnic
Load : 12.368 KN
Self weight of the column = 24 x 0.23 x 0.23 x 6
= 7.6176 KN
Total load on Footing = 19.986 KN.
Ultimate load on Footing = 29.97 KN
= 30.00KN
Grade M20 & Fe415,
Bearing Capacity = 120 KN/m2.
Size of Footing :
A = 33/120 = 0.275 ≈ 0.5m2
Provide Square Footing of 0.75m x 0.75m
Design of Section:
Maximum bending moment act at the face of the column is given by
M = Po B / 8(B-6)2 x 106 Nmm
Net Upward pressure Po = 33 / (0.75 x 0.75) = 58.7 KN/m2.
M = 58.70 x 0.75 /8 (0.75-0.23)2 x 106
= 1.48 x 106 Nmm
d = √M / RB = √1.48 x 106 / 0.875 x 750
= 47.6mm
Provide minimum thickness of 100mm.
Community hall
St. Joseph Polytechnic
τc = F/ (4 bo d)
Where ,
Ks = (0.5 +βc) = (0.5+1) max value is 1
Ks = 1.
Hence Safe.
Design of steel Reinforcement:
Community hall
St. Joseph Polytechnic
Ast = M/σst jd
= 1.48 x 106 / (140 x 0.865 x 100)
= 122.2 mm2
Use 12mm φ bar Aφ = π/4 (12)2 = 113 mm2.
Provide minimum Ast = 0.8% bd.
Development Length:
Ld =58.3φ
Providing cover of 60mm;
Length of the bar available = 1/2[B-b]-60
= ½ [0.75-0.23] x 103 - 60
= 200mm.
Transfer of load at column base:
A2 = 230 x 230 = 52.9 x 103 mm2
A1 = [230+2(2 x 200)]2
= 1.06 x 106
√A1/A2 = 4.47
Adopt maximum value of √ A1/A2 = 2.
Hence permissible shear stress = 0.25 fck √ A1/A2
= 0.25 x 20 x 2
= 10 N/mm2
Actual bearing pressure = 120 x 100 / 230 x 230 =0.22N/mm2.
Hence Safe.
Community hall
St. Joseph Polytechnic
Effective depth :
Mu = wl2/8 = 9234.375 x 5.112/8 = 30.14KNm
d = √ Mu / Q.b = √30.15 x 10 6/2.759 x 230 =217.98 Sq 220mm
Community hall
St. Joseph Polytechnic
Steel reinforcement:
Mu = 0.87fyAst [d- fyAst/fck b]
31.55 x 106 = 0.87 x 415Ast [332-415Ast / (20 x 230)]
82.59Ast2 – 119868.6 Ast +31.55 x 106 = 0
Ast = 285.34mm2
3Nos of 12mm φ rod 339.3 mm2
Shear reinforcement:
d = 0.332/2 = 0.166
Qu = w l/2 = w(0.166+0.332)
= [9234.375 x 5.11 / 2] – [9234.375(0.166+0.332)]
= 23593.83 – 4598.72 =18995.11 N
τc = 0.36+[0.48-0.36/0.25](0.4-0.25)=0.432
Community hall
St. Joseph Polytechnic
d=√ Mu/Qub
D = 550
Main Reinforcement:
Community hall
St. Joseph Polytechnic
Ast = 1162.30mm2
Shear Reinforcement :
d = 0.505/2 = 0.25
Vu = w l/2.w (0.25+0.505)
τc = 0.59
τc > τv No Shear Reinforcement in necessary only provided nominal
shear reinforcement.
Community hall