Professional Documents
Culture Documents
Rock Ford Crossing: Stream Crossing Installation Guide - Page 1 of 4
Rock Ford Crossing: Stream Crossing Installation Guide - Page 1 of 4
Planning
There are many factors to consider when determining the design and
location of the stream crossing. The design of the crossing should be
determined by NRCS staff (rock ford, geocell ford, concrete ford, or
culvert pipe), and will be based on local site conditions. Concerning
location, the ideal crossing should be installed perpendicular to the
direction of the stream flow. They should be located in areas where
streambeds are stable, and where erosion and flooding impacts can be
minimized. Areas to avoid include: abrupt changes in channel slope,
Watering Ramp
turbulent water or overfalls, confluences with tributaries, wetland
areas, shady areas in the stream buffer, or where bridges and culverts
are immediately upstream. All installed crossings should still provide
normal passage of water, fish, and other animals during all seasons.
Trenches for anchoring geotextile fabrics should be excavated along the ends of both approaches (terminal
anchors), as well as along the length of both sides of the crossing (side anchors). Dimensions of the trenches
should be at least 12 inches deep by six inches wide. Figure 2 (below) displays the locations that may be
recommended for geotextile anchor trenches.
Geotextile Fabric Installation. Geotextile fabric meeting the minimum requirements (see construction specifications) is
recommended for installation on the entire crossing surface area. The fabric should be placed in each trench and
the trench should be filled with rock to anchor it in place. The proper folding of the fabric during trenching, as well as
the overlapping of separate fabric rolls, are required to ensure that the stream flows cannot uproot a fabric edge.
This is more important for the side anchors than the terminal anchors. The method used to lay fabric length(s) on
side trenches can vary depending on whether you are using one separate length of fabric (Figure 3) or multiple
lengths of fabric that need to be overlapped (Figure 4).
Surface Materials.
Backfill should be placed around the pipes and thoroughly compacted every nine inches. The recommended fill
depth on top of the culvert pipe is equal to one-half the diameter of the culvert (no less than 24 inches). The fill
should be built up over the culvert such that any stream overflow will cross the road at a point away from the culvert
to protect the structure from erosion. The top of the compacted fill should be covered with geotextile fabric, and
then with six inches of GAB. Riprap or a concrete headwall may be needed on the side slopes to prevent erosion.
Watering Ramps
Watering Ramps are identical in design to a stream crossing, except that they are only located on one side of the
waterbody. These ramps serve as a conservation practice because they limit cattle access to surface waters to a
designated location instead of giving them full access. Similar to crossings, ramps can be constructed of rock,
concrete, or geocell. Care should be taken to ensure that all excavation, trenching, fabric placement, and layering
of surface materials follow the same guidelines as described above.
Before disturbing any land near a stream, investigate if permits should be obtained from the State, the U.S. Fish and
Wildlife Service, and the Army Corps of Engineers. After construction is completed, it is recommended that all
disturbed areas should be vegetated as soon as practical. Each side of the crossing should be fenced so that cattle
will be restricted to the protective crossing surface. Electrified hanging chains along the crossing have proven an
effective way to keep livestock from escaping by traveling upstream or downstream. Ford crossings with free
access by cattle should have minimal shade to reduce cattle loafing time in the stream.
An operation and maintenance plan should be developed and implemented for the life of the practice. The plan
normally recommends inspecting the stream crossing and associated fencing after each major storm event, with
repairs made as needed. During high flows, sediment and deposition may occur on approaches to fords. Excessive
soil or debris deposition should be removed periodically to maintain proper operation of the stream crossing.
Project Information: Funds for this project were provided by the USDA Natural Resources Conservation Service and administered by
the Two Rivers RC&D Council.
Non-Discrimination Statement: The United States Department of Agriculture (USDA) is an equal opportunity provider and employer.