Professional Documents
Culture Documents
Updated Final Ans
Updated Final Ans
Updated Final Ans
Options
2. The net present value of a project is Rs. 9 lakh. If its investment is Rs. 2 lakh and the cost of capital
is 10%, the benefit cost ratio is
Options
5.50
4.50
0.55
0.45
Options
Irreversible
Options
The difference between latest start of preceeding event and earliest finish of suceeding activity
Options
Subtracting the sum of duration of all activities from the sum of duration of all non-critical activities
Options
Options
It is easy to integrate the functions of all concerned departments towards the fulfillment of the project
objectives.
8. If the acceptance of one project is dependent on the acceptance of the other project then they are
said to be
Options
Complementary
Mutually exclusive
Contingent
Economically dependent
9. Value chain analysis is aimed at identifying the activities of the firm that are contributing value to
the firm. Which of the following activities is considered to be a primary activity as per this analysis?
Options
Options
Report to the general manager avoiding both line manager and project manager
11. If two projects A and B are mutually exclusive then selection of one will
Options
None of these
12. Which of the following project appraisal criteria does not assume that the risk of new projects
undertaken by a firm will be same as that of the existing projects?
Options
NPV
BCR
ARR.
Options
Options
-60%
-40%
40%
60%
Options
16. Multiple Choice ( Select 1 out of 4 options, for the question below. )
Options
project management
demand forecasting
all of these
17. A ' dummy activity' in a network diagram
Options
resources
Options
The NPV method if based on the assumption that the intermediate cash inflows are reinvested at a rate
of return equal to the internal rate of return
When the NPV is positive it implies that the project earns an excess return for the equity shareholders
only.
When the IRR is equal to the cost of capital it implies that the intermediate cash inflows are reinvested
at a rate of return equal to the cost of capital
Options
People who give brilliant ideas from their knowlegde and experience can very well manage in getting
their ideas implemented.
People who have great ideas are not necessarlily good implementers.
People who give brilliant ideas will always fail in getting things done.
People who are good at handling things will always possess creative thinking.
20. Which of the following statements is/are/true?
Options
The functional form of organization is not suitable to achieve effective utilzation of resoruces.
Matrix form of organization is not conducive to achieve effective realization of project objectives.
21. Which of the following is/are 'external reasons' for project failure?
Options
Inflation
Labour disputes.
Options
The projects which call for the coordination of different functional areas
Options
The inputs and standards of inputs required for each part of the project.
Options
Will result in resource loss, confusion and lack of confidence among the personnel and ultimaltely
project failure
Is not required because for successful completion of the project the initial plan laid out should be
implemented strictly
Options
The maximum activity of a project will be in the conception and selection stage.
The procurement of materials is undertaken during the planning and secheduling stage.
Options
The concept of crashing an activity is given both in PERT and CPM models
Both PERT and CPM techniques involve drawing network showing relationship between various
activities
27. A certain activity has a budgeted cost of Rs 80,000 and at the time of the periodic progress review it
is estimated that 60 percent of the work has been accomplished at the cost of Rs 52,800. Therefore
cost over-run (under- run) is
Options
9.1%
34%
10%
15%
Options
The duration of the critical path is the longest period in which the project can be completed.
The standard deviation of the duration of the critical path is the sum of the standard deviations of the
durations of the activities on the critical path.
When there is more than one critical path, any one of the paths can be crashed.
29. Which of the following statement is/are true?
Options
Capital rationing exists when funds available for investment are inadequate to undertake all projects
which are otherwise acceptable.
Internal rationing is caused by a choice of hurdle rate higher than the cost of capital.
Options
Should not act supportively, because this may increase the employees demands unreasonably
Should act threateningly which may result in employees conformation to the plans out of fear
Should not bother about the motivational responsibilities because he has got many other aspects to
attend.
Should act supportively because this may bring in confidence among employees that their interests
will be looked after
31. Which of the following might be the reasons for the failure of projects?
Options
Options
Non-availability of equipment in time due to its use by other departments of the organization
Failure to raise required funds on time due to its use by other departments of the organization.
33. Benefit Cost Ratio (BCR) criterion can be considered as superior to net present value because
Options
In case of capital rationing, BCR ranks the projects correctly in the order of decreasingly efficient use
of capital
34. Which of the following is not a risk management tool in capital budgeting?
Options
Coefficient of variance
PERT
Options
Free float is always available for all the activities on critical path
Options
Uniform Annual Equivalent (UAE) can also be referred to as Annual Capital charge.
The UAE (capital costs) increase with the extension of the replacement cycle.
The economic life of an asset refers to the number of years it can be used to produce a certain output
without maintenance.
Options
Equal to zero
Options
There will not exist any conflict in ranking between the two projects
There shall be no Fisherian rate of return applicable for the two projects
That all the appraisal criteria on discounting basis would give each of them the same
39. The internal rate of return can be said to be based on the assumption that the intermediate cash
flows are
Options
Perfectly certain
Highly variable
Options
A project should be viewed as something which contributes to the ability of the organisation.
Options
None of these
Options
It contains the starting and ending date of the project and the events marking completion of the
major tasks in the project, along with their dates of completion.
It contains the details of inputs and standard of inputs required for each part of the project.
43. Which of the following method is most suitable for forecasting the demand for power in the
country?
Options
Delphi Method
Econometric Method
ii. For projects which require the integration of inputs from different
departments.
iii. For companies that are involved in repetitive projects of the same type.
Options
45. Which of the following factors call for the project management?
Options
46. During which stage of the life cycle of project is the level of highest activity?
Options
Evaluation.
47. Which of the following statement/s is/are true?
Options
Two projects are said to be economically independent when cash flows of one project are influenced by
the cash flows of other project.
Two projects are said to be economically dependent when the acceptance or rejection of one project is
influenced by the acceptance (rejection) of the other project.
Two projects are said to be economically dependent when cash flows of one project are influenced by
the cash flows of other projects.
Options
The project is not feasible technically though it can be completed within the stipulated costs
It is feasible technically but it cannot be completed within the stipulated cost and time
If the PV of cash flows are more at the time of the proposal for abandonment than the PV of cash flows
realizable if the project is continued through its life
49. A project requires an initial investment of Rs. 10 crore and provides inflows of Rs.5 crore every year
for five years. The payback period of the project is
Options
5 years
4 years
3 years
2 years
50. A successful project manager should
Options
Have a creative approach to use the resources efficiently and to solve human relation problems
Options
52. ABC Ltd which is going for expansion has made the following time estimate for completion of a
major activity on the critical path. Time in month Optimistic 9 Pessimistic 21 Most likely 15 The
variance of the activity would be ____month
Options
5
53. Projects A and B both involve the same outlay and offer the same IRR, which exceeds the
opportunity cost of capital. The cash flows generated by Project A are larger than those of B but
tend to occur later. Based on this one can conclude that
Options
Options
Commitment to technology.
55. Conflict in the ranking of projects based on different appraisal criteria arises due to.
Options
Options
12.75 days
13.00 days
13.20 days
13.50 days
57. When the cost of capital of a project is equal to its internal rate of return
Options
58. If standard deviations of two projects are same but different means then what is true?
Options
Options
Based on profit
60. Which of the following is/are the informational inputs for project planning?
Options
Statement of work
Project specifications.
Milestone schedule