Construction Management Project Planning and Scheduling
Construction Management Project Planning and Scheduling
EGM 502
Project Planning and Scheduling
Lecture 12
1
Project planning and scheduling
Project planning is the process of identifying all the activities
necessary to successfully complete the project.
Project scheduling is the process of determining the sequential
order of the planned activities, assigning realistic durations to
each activity, and determining the start and finish dates for each
activity.
2
Desired Results of Project Planning And Scheduling
3
Desired Results of Project Planning and Scheduling
4
Key Principles for Planning and Scheduling
1. Begin planning before starting work, rather than after starting work
2. Involve people who will actually do the work in the planning and
scheduling process
3. Include all aspects of the project: scope, budget, schedule, and
quality
4. Build flexibility into the plan, Include allowance for changes and
time for reviews and approvals
5
Key Principles for Planning and Scheduling
5.Remember the schedule is the plan for doing the work, and it will
never be precisely correct
6.Keep the plan simple, eliminate irrelevant details that prevent the
plan from being readable
7.Communicate the plan to all parties; any plan is worthless unless it is
known
6
Responsible Parties
owner
designer
contractor
7
Owner/client Responsibilities
8
Designer
9
Contractor
must develop a schedule for all construction activities in accordance
with the contract documents.
The schedule should include
procurement and delivery of materials to the job
coordination of labor and equipment on the job
interface the work of all subcontractors
The objective of the construction schedule
should be to effectively manage the work to produce the best-quality project for
the owner
10
Characteristics of effective planning
it is based on clearly defined objectives
it is simple
it establishes standards
it is flexible
it is balanced
it uses available resources to the utmost.
11
Techniques for Planning and Scheduling
13
Techniques for Planning and Scheduling
Two general methods
1. The bar chart (sometimes called the Gantt chart)
14
Definition Gantt
The Gantt chart is a simple time-scaled diagram showing timeframes for
activities or areas of work.
The activities are represented by horizontal lines or bars whose length is
proportional to the time involved .
15
General layout
16
Sample of a simple Gantt chat
17
Sample of a Gantt chat
18
Sample of a Gantt chat
19
General uses
The Gantt chart can be used in conjunction with a
network diagram, particularly with respect to large or
complex projects,
used independently for projects of a lesser nature
20
General uses
pre-tender stage to assist the contractor in early planning and
for assessing resource requirements
Post-tender, during the construction phase, the successful
tenderer can utilize the chart for short-term planning and
monitoring and for controlling finance and progress at regular
intervals.
21
General uses
Progress control establishes the following:
work begun but behind schedule
work ahead of schedule
work which has been programmed to start but hasn’t
information upon which to base financial claims.
22
General uses
Gantt charts can be used to establish or derive the following
information:
the number and sequence of activities
the estimated duration of each activity
the estimated duration of the contract
the estimated start time of each activity
the number of trades and specialist areas involved
23
General uses
Gantt charts can be used to establish or derive the following information:
the number of tradespersons employed
the number of semi-skilled and unskilled workers employed
subcontract work involved
other resource requirements and scheduling
estimated person-hours involved in the project, and in each activity
budget information.
24
Advantages Gantt chart
1. Easily understood by most site personnel.
2. Allows a simple and easily read plan of operation to be prepared for site
personnel.
3. Actual performance may be plotted against the plan.
4. Length of bar or line is proportional to time.
5. Readily adaptable to suit a variety of situations.
6. Provides a simple means of communication between personnel involved in a
project.
25
Disadvantages Gantt
1. Activity durations must be known before the chart can be prepared.
2. Does not readily inform of critical relationships/activities.
3. Where floats are not indicated, bottlenecks may result.
4. On large projects, it is difficult to depict the total project on one chart.
5. Does not show interrelated activities.
6. Does not readily lend itself to revision.
26
Layout of a Gantt chart
27
Layout of a Gantt chart
the Number column in which is placed a number for each activity on the network
the Arrow column into which the identity numbers of the activity arrows are
inserted (Sometimes needed)
the Operation column – which is for the main ‘trade headings’ only. These
headings can be obtained from the labour constants sheets issued with each
assignment.
the Section column – which lists each activity used in the network. All the
activities should be recorded adjacent to their associated trade heading.
28
Layout of a Gantt chart
the Plant and Materials columns – which are used to indicate the
major items of materials and plant required for each activity.
duration columns – which occupy the remainder of the chart.
Each of these columns is evenly subdivided – with each
subdivision representing a unit of time, such as a day, week or
month.
29
Critical path network
The critical path network (CPN) is a technique which has been
developed to perform the planning and scheduling function.
A network is essentially a model of the logic and calculation
employed when planning a project.
It displays a series of operations which must be followed in order to
complete a project.
30
Critical path network
33
Advantages of network analysis
It enables closer control of complex projects, since any deviation from
the schedule is quickly noticed.
Critical activities can be highlighted.
It provides a means to test and select alternative solutions before any
particular option is implemented.
It allows for greater detail when planning and scheduling. By dividing
the project into small activities, it assists in the estimation of their
durations, leading to more accurate target dates.
34
Advantages of network analysis
35
Disadvantages
It is a tedious and exacting task if attempted manually. Depending
upon what is required, the number of activities that can be
efficiently handled without the aid of a computer is not very high.
Staff will require special training to prepare and read networks.
36
Disadvantages
The network is generally used only by management staff and
project coordinators and controllers on the project site.
As a rule, subcontractors have no specific interest in the complete
network;
provide a detailed Gantt chart to the subcontractors for their use
it is generally accepted that Gantt charts are easier to read and
understand.
37
Network components
38
Network components
A node represents an event, which is the point at which an activity or group of activities
starts or finishes.
The symbol used to represent a node is a circle.
39
Network components
A milestone is an event selected for its importance in a project.
It may be either the start or finish of an activity and is a useful
means of reporting progress to senior management, as well as for
creating a sense of awareness within the project team.
A different-shaped symbol, such as a hexagon, is often used for the
node concerned, to highlight the event’s importance.
Milestones form a series of goals within the network
40
Basic conventions logic
1. The network flows basically from left to right. The arrowhead on the
activity line indicates the direction of operations for the network.
41
Example:
Set out and prepare the excavations and formwork to a stage where the job is
ready for the pouring of a concrete strip footing.
42
Straight line sequence of activities
43
Alternative sequence including concurrent activities
44
Three fundamentals when scheduling
45
Controlling
Controlling entails monitoring the network to determine
whether it is proceeding as planned.
The actual performance can be compared with the planned
performance.
Problem areas within the work can be detected and remedial
action started to rectify the situation.
46
The critical path
The critical path is the path or paths through a planned sequence of activities of
a network which indicates the shortest possible time in which the project can be
completed.
There is no tolerance allowed along this path, it is critical that each activity be
completed in the specified time.
Any circumstances which create delays, and which cannot be swiftly rectified,
will automatically extend the completion date of the project
47
The critical path
The network shows that there are two paths through the network:
Path 1 involving activities 1–2, 2–4, 4–5
Path 2 involving activities 1–3, 3–4, 4–5.
48
The critical path
Totaling the durations on each path establishes that it requires four days to
complete the activities on Path 1 and three days to complete the activities on
Path 2.
Path 1 is therefore the critical path through this network, as it represents the
shortest time in which the work can be completed – that is, while it’s the path
occupying the longest passage of time, it leads to the earliest possible time by
which all activities can be completed.
49
Examples of establishing the critical path
50
Examples of establishing the critical path
51