Plan Semanal de Perforación y Tronadura

10 al 16 de Mayo
Distrito Centinela

11 de Mayo 2021

Du massen
KPI´S Perforación Esperanza
Lunes Martes Miércoles Jueves Viernes Sábado Domingo
Equipos KPI´s 10-may 11-may 12-may 13-may 14-may 15-may 16-may Total
%Di sp 89% 89% 86% 89% 89% 6% 0% 64%
% Uti l 65% 62% 60% 68% 68% 20% 0% 64%
Rdto 44 44 44 44 44 44 44 44
PE5
Metros 610 581 546 638 638 13 0 3.026
ton/m 151 151 151 151 151 151 151
ton 92.048 87.799 82.421 96.296 96.296 2.010 0 456.871
%Di sp 87% 85% 87% 87% 85% 87% 87% 86%
% Uti l 68% 65% 68% 62% 68% 40% 67% 63%
Rdto 30 30 30 30 30 48 48 35
PE8
Metros 427 396 427 389 414 402 673 3.127
ton/m 71 71 71 71 71 143 143
ton 30.299 28.095 30.299 27.626 29.391 57.436 96.205 299.352
%Di sp 0% 0% 0% 0% 0% 0% 0% 0%
% Uti l 0% 0% 0% 0% 0% 0% 0% #¡DIV/0!
Rdto 32 32 32 32 32 32 32 #¡DIV/0!
PE3
Metros 0 0 0 0 0 0 0 0
ton/m 71 71 71 71 71 71 71
ton 0 0 0 0 0 0 0 0
%Di sp 88% 88% 88% 88% 83% 88% 88% 88%
% Uti l 48% 54% 58% 55% 60% 0% 0% 39%
Rdto 32 32 32 32 32 32 32 32
PE4
Metros 326 367 394 374 381 0 0 1.842
ton/m 71 71 71 71 71 71 71
ton 23.148 26.042 27.971 26.524 27.078 0 0 130.762
%Di sp 7% 91% 91% 91% 91% 91% 91% 79%
% Uti l 56% 50% 58% 44% 58% 58% 50% 53%
Rdto 50 52 55 55 55 55 55 54
PE6
Metros 49 570 699 530 699 699 603 3.849
ton/m 151 151 189 189 189 189 189
ton 7.420 86.024 132.105 100.218 132.105 132.105 113.884 703.860
%Di sp 91% 91% 91% 89% 91% 91% 91% 91%
% Uti l 55% 58% 50% 58% 50% 50% 50% 53%
Rdto 53 53 53 53 53 53 53 53
PE10
Metros 639 674 581 659 581 581 581 4.294
ton/m 189 189 189 189 189 189 189
ton 120.717 127.301 109.742 124.578 109.742 109.742 109.742 811.566
%Di sp 97% 97% 67% 97% 97% 93% 97% 92%
% Uti l 40% 40% 40% 40% 40% 40% 40% 40%
Rdto 28 28 28 28 36 36 36 32
PE25
Metros 260 260 179 260 335 320 335 1.950
m/m 8 8 8 8 8 8 8
Ton 31 31 22 31 40 39 40
%Di sp 97% 93% 97% 97% 97% 93% 97% 96%
% Uti l 55% 55% 55% 55% 55% 55% 55% 55%
Rdto 28 28 28 28 40 35 35 32
PE51
Metros 358 343 358 358 512 428 448 2.804
m/m 8 8 8 8 8 8 8
Ton 43 41 43 43 62 52 54
%Di sp 97% 97% 97% 0% 50% 97% 97% 76%
% Uti l 55% 55% 55% 55% 55% 55% 55% 55%
Rdto 40 28 28 40 40 40 40 36
PE53
Metros 512 358 358 0 264 512 512 2.515
m/m 8 8 8 8 8 8 8
Ton 62 43 45 0 32 62 62
CENTINELA m 2.050 2.587 2.646 2.590 2.713 1.695 1.856 16.137
EECC m 1.130 961 895 618 1.110 1.260 1.294 7.269
TOTAL m 3.180 3.548 3.541 3.208 3.823 2.955 3.150 23.406
Perforación Esperanza
Traslados Camabaja
Fecha Equipo Modelo Ton Origen Destino F07B2248_2264
martes 11 de mayo de 2021 ROC SmartRoc 30 Sulfuro Fase 06 Sulfuro Fase 08
PE08 + ROC
martes 11 de mayo de 2021 PE503 DM45 45 Tesoro Central Fase 10 Tesoro Sur Fase 02 3
miércoles 12 de mayo de 2021 SE07 D75 KS 60 ExPIT Tesoro Central Fase 10 2
jueves 13 de mayo de 2021 ROC SmartRoc 110 Sulfuro Fase 06 Sulfuro Fase 08 Prioridad de Perforación
sábado 15 de mayo de 2021 PE08 DMM3 110 Sulfuro Fase 06 Sulfuro Fase 08
domingo 16 de mayo de 2021 ROC SmartRoc 30 Tesoro Central Fase 10 Sulfuro Fase 07
lunes 17 de mayo de 2021 PE01 DMM3 110 Tesoro Mirador Sulfuro Fase 06 PATIO MANTENCION
lunes 17 de mayo de 2021 ROC SmartRoc 30 Tesoro Central Fase 10 Sulfuro Fase 06 PERFORADORAS PE-05

F06B1784_1800
PE08 + PE04 + 02 ROC 1

6
3

2
1

5
F08B2120
PE05 + PE10 + 01 ROC 1
4
F08B2136
3 PE06 + PE05 + 01 ROC
Tronadura Esperanza
Lunes Ma rtes Mi ércol es Jueves Vi ernes Sá ba do Domi ngo
Fa s e Ba nco Precorte 10-ma y. 11-ma y. 12-ma y. 13-ma y. 14-ma y. 15-ma y. 16-ma y.
F06 1800 PRE 360
F07 2248
F08 2120 PRE 312
F08 2120 PRE 575
F08 2120 PRE 387
F08 2136 331
F08 2136 PRE 301
Tonel a je a trona r [kt] 331 360 0 312 876 0 387

Fa s e 06 Fa s e 07 Fa s e 08 Tota l Sema na
Trona dura s 0 kt 360 kt 0 kt 1.906 kt 2.266 kt
La s tre 0 kt 0 kt 0 kt 1.906 kt 1.906 kt
Mi nera l 0 kt 360 kt 0 kt 0 kt 360 kt

B2248

B2264

B1800

B2120

Lunes
Martes
Miércoles
Jueves
B2136 Viernes
Sábado
Domingo
Ajuste Tronaduras Semanal 10 al 16 May_21
B2248 Pozos:
Prec: Pz
Pozos: Pz
Ton: -- kt (est.)

Tronaduras de
B2264 Pozos:
borde con Prec: Pz
interferencia Pozos: Pz
Ton: -- kt (est.)

B1800 Pozos:
Prec: Pz
Pozos: Pz
B2120 Pozos: Ton: 360 kt (est.)
Prec: Pz
Pozos: Pz
Ton: 575 kt (est.)

B2136 Pozos: Tronaduras de


Prec: -- Pz borde con
Pozos: Pz
Ton: 331 kt (Est.) interferencia

B2120 Pozos:
Prec: Pz
Pozos: Pz
Ton: 387 kt (est.)
Lunes
B2120 Pozos:
Martes
Prec: Pz
Miércoles
Pozos: Pz B2136 Pozos:
Ton: 312 kt (est.) Jueves
Prec: Pz Viernes
Pozos: Pz Sábado
Ton: 301 kt (est.) Domingo
Programa de Perforación Tesoro F10
Lunes Martes Miércoles Jueves Viernes Sábado Domingo
Equipos KPI´s 10-may 11-may 12-may 13-may 14-may 15-may 16-may Total
%Disp 87% 90% 90% 7% 37% 90% 90% 70%
% Util 68% 20% 0% 0% 0% 0% 0% 16%
Rdto 55 55 55 55 55 55 55 55
PE503
Metros 783 237 0 0 0 0 0 1.021
ton/m 98 98 98 98 98 98 98
ton 76.746 23.267 0 0 0 0 0 100.014
%Disp 75% 75% 75% 75% 75% 75% 75% 75%

F10 D-07
% Util
Rdto
0%
44
0%
44
30%
44
57%
44
57%
44
57%
44
57%
44
37%
44
Metros 0 0 238 451 451 451 451 2.043
ton/m 98 98 98 98 98 98 98
ton 0 0 23.285 44.241 44.241 44.241 44.241 200.249
%Disp 97% 93% 97% 97% 93% 97% 97% 96%
% Util 33% 33% 33% 33% 33% 33% 33% 33%
Rdto 44 44 44 44 44 44 44 44
PE49
Metros 338 323 338 338 323 338 338 2.334
ton/m 54 54 54 54 54 54 54
ton 18.230 17.446 18.230 18.230 17.446 18.230 18.230 126.041
CENTINELA m 783 237 0 0 0 0 0 1.021
CONTRATO m 338 323 575 789 775 789 789 4.377
TOTAL m 1.121 560 575 789 775 789 789 5.398

1
Programa de Perforación Tesoro Sur
Lunes Martes Miércoles Jueves Viernes Sábado Domingo
Equipos KPI´s 10-may 11-may 12-may 13-may 14-may 15-may 16-may Total
%Disp 87% 90% 90% 7% 37% 90% 90% 70%
% Util 0% 40% 68% 20% 50% 65% 68% 48%
Rdto 48 48 48 48 48 48 48 48
DM45-503
Metros 0 414 704 15 215 673 704 2.727
ton/m 98 98 98 98 98 98 98
F02 ton
%Disp
0
0%
40.612
0%
69.040
0%
1.507
0%
21.094
0%
65.994
0%
69.040
0%
267.288
0%
% Util 57% 57% 57% 57% 57% 57% 57% #¡DIV/0!
Rdto 44 44 44 44 44 44 44 #¡DIV/0!
SE-D-64
Metros 0 0 0 0 0 0 0 0
ton/m 98 98 98 98 98 98 98
ton 0 0 0 0 0 0 0 0
%Disp 97% 93% 97% 97% 93% 97% 97% 96%
% Util 35% 35% 35% 35% 35% 35% 35% 35%
Rdto 45 45 45 45 40 40 40 43
ROC-550
Metros 366 350 366 366 312 326 326 2.412
ton/m 76 76 76 76 76 76 76
ton 27830 26633 27830 27830 23674 24738 24738 183.274
CENTINELA m 0 414 704 15 215 673 704 2.727
ROCMIN m 366 350 366 366 312 326 326 2.412
TOTAL m 366 765 1.071 382 527 999 1.030 5.139

F02
6

4
1

5
Programa de Perforación Mirador
Lunes Martes Miércoles Jueves Viernes Sábado Domingo
Equipos KPI´s 10-may 11-may 12-may 13-may 14-may 15-may 16-may Total
%Disp 88% 88% 85% 88% 88% 85% 88% 87%
% Util 60% 60% 60% 60% 60% 60% 60% 60%
Rdto 50 50 50 50 50 48 48 49
PE-01
Metros 634 634 615 634 634 590 608 4.347
ton/m 196 196 196 126 126 196 196
ton 124.166 124.166 120.445 79.821 79.821 115.627 119.200 763.248
%Disp 75% 75% 75% 75% 75% 75% 75% 75%
% Util 57% 57% 57% 57% 57% 57% 57% 57%
F04 STA-ELVIRA D-05
Rdto
Metros
48
492
48
492
48
492
48
492
48
492
48
492
48
492
48
3.447
ton/m 126 126 126 126 196 196 196
ton 62.052 62.052 62.052 62.052 96.526 96.526 96.526 537.788
CENTINELA m 634 634 615 634 634 590 608 4.347
EECC m 492 492 492 492 492 492 492 3.447
TOTAL m 1.126 1.126 1.107 1.126 1.126 1.082 1.101 7.794

F04
1

2
4

3
Programa de Tronaduras Tesoro Óxidos
Lunes Ma rtes Mi ércol es Jueves Vi ernes Sá ba do Domi ngo
Fa s e Ba nco Precorte 10-ma y. 11-ma y. 12-ma y. 13-ma y. 14-ma y. 15-ma y. 16-ma y.
F02 2317 165
F02 2325 86 F02 TSUR
F02 2325 81
F02 2325 130
F04 2325 272
F04 2325 248
F04 2332,5 141
F10 2082,5 24
F10 2082,5 PRE 126
F10 2082,5 PRE 196 B2317,5
F10 2082,5 PRE 261
Tonel a je a trona r [kt] 151 86 389 81 327 272 426

Fa s e 02 TSUR Fa s e 04 MIR Fa s e 10 TC Total Sema na


Trona dura s 0 kt 462 kt 661 kt 608 kt 1.730 kt
La s tre 0 kt 297 kt 661 kt 196 kt 1.154 kt
Mi nera l 0 kt 165 kt 0 kt 412 kt 577 kt

F10 TC Lunes
Martes
Miércoles
Jueves
Viernes B2325
B2075 Sábado
Domingo

B2082,5 F04 MIR


B2325

B2340

B2332,5
B2082,5
Protocolo tronaduras Tesoro Sur

• Para tronadura entre los 100 - 200 m, se adiciona en protocolo que no se cortara energía de la línea 23 Kv, pero si se realizará Post tronadura inspecciones y chequeos, por parte
de la mina: Jefe de Turno P&T y por parte de planta: Patricio Gutierrez & Sandra Espinoza
• El horario de las tronaduras comprendidas en zonas entre los 100-200 m y bajo los 100 m, serán a las 14:30 hrs.
• Respecto de las tronaduras que tengan afectación a las áreas críticas, se deben especificar según planificación de extracción. Estas serán incluidas en Plan Semanal de P&T y en
el correo diario de tronadura será enviado a todos los involucrados según lista entregada por Sandra Espinoza.
• Responsables de áreas operativas: instalaciones cercanas y línea eléctrica 23 KV, enviaran el programa mensual de mantenciones, con el fin de tener input en planificación de
tronaduras hacia zona segura.
• Para tronaduras bajo los 100 m, se acuerda que se debe avisar eventos con dos días de anticipación, para que áreas comprometidas puedan tener planes de acción al respecto. Y
además deben estar comprendidas entre los días lunes a jueves de cada semana por los turnos 4x3 encargados de la revisión.
• Se revisará el tema de que si se planifican tronaduras en zona critica bajo los 100 m. está sea la única tronadura del día en rajos Tesoro. También quedó que esta tronadura sea a
las 14:30.
• En temas de suspensión de tronaduras por motivos planta fuerza mayor (quiebre de plan), se deberá enviar un correo formal con la justificación correspondiente antes de las
16:00 hrs del día anterior, copiando en correo: Luis Canales PLANIF. PYT, Carolina Aguilar ING. QAQC, Jorge Nuñez SI PYT, Víctor Ponce ING. PROG. OP. y Gustavo Campillay ING.
PROG. OP.
Programa de Tronaduras ESPERANZA SUR
Miércoles Jueves Viernes Sábado Domingo Lunes Martes Miércoles
Fas e Banco Precorte 12-may. 13-may. 14-may. 15-may. 16-may. 17-may. 18-may. 19-may.
F01 2216 PRE 326
F01 2232 PRE 1.153
F02 2280 286
F02 2296
Tonelaje a tronar [kt] 0 1.153 0 326 0 0 0 286

Fas e 01 Fas e 02 Total Semana


Tronadura 1.479 kt 286 kt 1.765 kt
Las tre 1.479 kt 286 kt 1.765 kt
Mineral 0 kt 0 kt 0 kt

B2296

B2232

B2216

B2328

B2280
Lunes
Martes
Miércoles
Jueves
Viernes
Sábado
Domingo
Tronaduras Rajo OXE
Miércoles Jueves Viernes Sábado Domingo Lunes Martes Miércoles
Fas e Banco obs 12-may. 13-may. 14-may. 15-may. 16-may. 17-may. 18-may. 19-may.
F03 2152 PRE
F03 2152 327
F04 2344 208
F04 2344 700
F04 2344 723
F04 2360 642
Tonelaje a tronar [kt] 642 0 535 0 700 0 723 0
Fas e 03 Fas e 04 Total Semana
Tronadura 327 kt 2.274 kt 2.601 kt
Las tre 0 kt 2.274 kt 2.274 kt
Mineral 327 kt 0 kt 327 kt

B2376

B2360

Lunes
Martes
Miércoles
B2152 Jueves
Viernes
Sábado
Domingo

B2344