Document Control:
CLIENT: ETASET
APROVE BY:
REVISION: A1
Index
2.0 Pre-requisites 5
8.0 Witnessing 7
10.0 Appendix 9
1.0 Introduction.
1.1 The following method statement has been prepared as a guideline. For the
Commissioning of the Dewatering & Foul pumps on the Dubai Metro Red Line project.
This is to be reviewed and agreed by the Design Consultants, M&E Contractor and the
Testing and Commissioning Company that will be performing the procedure. These two
pumps are submersible type.
2.0 Pre-requisites.
2.1 The following pre-requisites must be in place before work can start.
The execution of works will strictly follow the project safety manual.
5.1 Any instrument that requires calibration must have a valid calibration certificate.
And be logged on the Instrument Log Sheet with a copy of the calibration
certificate.
The following test instrumentation & tools will be required to undertake the tests
detailed within this procedure:
• Pressure Gauges*
• Clamp-on Ammeter *
• Hand Tools ( screwdrivers etc)
6.1 The following standards have been referenced when preparing these test
procedures:
7.1 All the pre-commissioning checks should be carried out as per the
Approved pro-forma checklist and all case strictly in line with the manufacturer’s
recommendations.
7.2 Confirm all valves correctly installed and should be made fully open or as
planned for testing (where applicable).
7.3 Confirm discharge pipe-work has been hydrostatically tested and that there is no
evidence of leakage at joints or valves.
7.4 Confirm that the pump is completely submerged and has been vented of all air.
7.5 All electrical connections to equipment should be completed and water tight.
7.6 Note the pumps model and serial number, motor nameplate, the design L/s flow,
and the design head. (If the pump is accessible)
7.7 Verify the impeller size on each pump. By referring to the pump name plate.
7.8 Note the starter data and motor overload protection devices size and ratings.
7.9 Ensure that the discharge pipe-work is free from any blockages or obstructions.
7.10 When this is complete carry out the pump hydronic measurement test.
7.11 Open the pump discharge valve to its full-open position (if applicable.)
7.12 Turn the pump on firstly at the control panel then the local isolator.
7.13 Check that there is a good discharge flow from the pump.
7.14 Record pumps motor amps and voltage in the test sheet.
7.15 Ensure high & low level switches/ floats are operating correctly.
8.0 Witnessing
8.1 Dewatering & Foul pump has been commissioned, and all the relevant paper work
completed. It must be offered to the Commissioning Manager. He/she will organise
a time and date with all relevant parties to witness the system. After the system has
been witnessed the witnessing team or individual will decide to sign off the system
or not depending on the success of the witness.
10.0 Appendix:
10.1 Dewatering Pump Pre-Commissioning Test Sheet
10.2 Foul water Pump Pre-Commissioning Test Sheet
2 Fall from height during May cause death 1. Use of PPE and safety belts
testing 2. Tool talks and trainings to workers
or permanent
2 3 6 1 2 2 Low
disability
R
4 Amperage Y
R-Y
5 Voltage Y-B
B-R
6 Motor Speed RPM
REMARKS :
SIGN.
NAME
DATE
F : 208 : 11 0508
PRE COMMISSIONING CHECKS -FOUL WATER PUMPS
Electrical Checks
1 Panel board installation correct
2 Panel and Switch gears are Cleaned
3 All Connections are frim and Tight on Busbar
4 Starter Over laod are Correct Set /range is Ok
REMARKS :
PERFORMED BY PRIME
DETAILS WITNESSED BY MEP CONTRACTOR APPROVED BY CONSULTANT
TECHNOLOGIES
SIGN.
NAME
DATE
F : 208 : 10 0508
PRE COMMISSIONING CHECKS -DEWATERING PUMPS
Electrical Checks
1 Panel board installation correct
2 Panel and Switch gears are Cleaned
3 All Connections are frim and Tight on Busbar
4 Starter Over laod are Correct Set /range is Ok
REMARKS :
PERFORMED BY PRIME
DETAILS WITNESSED BY MEP CONTRACTOR APPROVED BY CONSULTANT
TECHNOLOGIES
SIGN.
NAME
DATE
F : 208 : 10 0508
PERFORMANCE TEST RECORDS -FOUL WATER PUMP
R
4 Amperage Y
R-Y
5 Voltage Y-B
B-R
6 Motor Speed RPM
REMARKS :
SIGN.
NAME
DATE
F : 208 : 11 0508