Professional Documents
Culture Documents
(A2) MS For Testing and Commissioning of Secondary Chilled Water System
(A2) MS For Testing and Commissioning of Secondary Chilled Water System
Document Control:
CLIENT: ETASET
APROVE BY:
REVISION: A2
Index
2.0 Pre-requisites 5
8.0 Witnessing 8
10.0 Appendix 10
1.0 Introduction.
1.1 The following method statement has been prepared as a guideline. For the
Commissioning of the Secondary Chilled Water Circuit on the Dubai Metro Red Line
project. This is to be reviewed and agreed by the Design Consultants, M&E Contractor
and the Testing and Commissioning Company that will be performing the procedure.
2.0 Pre-requisites.
2.1 The following pre-requisites must be in place before work can start.
5.1 Any instrument that requires calibration must have a valid calibration certificate.
And be logged on the Instrument Log Sheet with a copy of the calibration
certificate.
The following test instrumentation & tools will be required to undertake the tests
detailed within this procedure:
• Pressure Gauges*
• Mercury and fluorocarbon Manometer/ Digital Flow Meter
• Relevant valve charts
• Clamp-on Ammeter *
• Tachometer *
• Hand Tools (Mirror, torch, screwdrivers etc)
6.1 The following standards have been referenced when preparing these test
procedures:
7.1 Confirm CHW system has been pressure tested as per project specifications and
There is no evidence of leakage at joints or valves.
7.2 Pressure gauges and thermometer are installed at correct location.
7.3 Confirm CHW system has been flushed and cleaned.
7.4 All the strainers are cleaned.
7.5 Confirm CHW circuit has been vented of all air.
7.6 All insulation and vapour sealing should be completed.
7.7 Confirm all the AHUS & FCUS cooling coils should be in cooing mode, all the
supply & return valves should be fully open all the by pass valves should be in
closed position.
7.8 Confirm pumps are installed as per manufacturer recommendations and project
specifications.
7.9 Pump impeller is free to rotate.
7.10 Motor terminal wiring is checked.
7.11 Local electrical isolator provided in case of emergency shutdown.
7.12 Direction of volitions correct & checked.
7.13 No excessive vibration and abnormal noise.
7.14 Follow the pre-commissioning check list attached in appendix.
7.16 Measure the main commissioning set and set it to 110% of the design volume.
Either by adjusting the VFD or if no VFD is installed, by regulate the main DRV
to achieve the correct flow.
Note: If the circuit has a stand by pump the volume must also be checked with the
standby pump running and one of the primary pumps isolated. Repeat this for each
standby pump.
Circuit Balancing
7.17 The following procedure will be followed to balance the Secondary Chilled Water
Circuit after the pre-commissioning has been successful.
7.18 Verify all the balancing valves of the CHW circuit are balanced according to
above mentioned circuit balancing procedures.
7.19 Measuring the discharge pressure and the suction pressure. Determine the pump
head by subtracting the suction pressure from discharge pressure.
7.20 Plot the head on the pump curve using the determined shut off head curve and
establish flow. Include the pump curve in report.
7.21 Record the motor Amps, voltage and speed of the motor by tachometer.
7.22 Fill the data in the attached pump commissioning report.
8.0 Witnessing
8.1 After the circuit have been commissioned, and all the relevant paper work
completed. It must be offered to the Commissioning Manager. He/she will organise
a time and date with all relevant parties to witness the system. After the system has
been witnessed the witnessing team or individual will decide to sign off the system
or not depending on the success of the witness.
10.0 Appendix:
10.1 Chilled water circuit Pre-Commissioning Test Sheet
10.2 Pump Pre-Commissioning Test Sheet
Risk Assessment Analysis (Safety & Health) : Testing & Commissioning of Secondary CHW system
Project: Dubai Metro Red Line Project
Secondary CHW Commissioning- Method Statement
Initial Risk Final Risk Residual Risk
POTENTIAL ACCIDENT Rating Risk CONTROL MEASURES / Rating Risk Acceptable
BASIC JOB STEP / ACTIVITY
OR HAZARD Probability x Factor MITIGATION ACTIONS Probability Factor
Severity x Severity
1 Checking electrical motor Hazard of shock, 1. Work area should be demarcated restricting
Connections of the access.
equipments. And electrical faults, 2. Ensure properly trained personnel checking
measuring voltage & the connection.
Amps in starter panel etc causing 3. All safety precautions to be followed.
damage to 2 3 6 2 1 2 Low
materials and/or
manpower.
2 Fall from height during May cause death 1. Use of PPE and safety belts
measuring the flow of 2. Tool talks and trainings to workers
water at the balancing or permanent
valves. 2 3 6 1 2 2 Low
disability
SYSTEM :
10
11
12
13
14
15
Remarks :
SIGN :
NAME :
DATE :
F : 208 : 13 0508
PERFORMANCE TEST RECORDS - PUMPS
TYPE OF SEAL :
MOTOR
SUCTION (kpa)
SHUT-OFF PRESSURE
4 DISCHARGE (kpa)
5 SHUT-OFF HEAD(M)
R
6 Amperage Y
R-Y
7 Voltage Y-B
B-R
8 Motor Speed RPM
REMARKS :
SIGN.
NAME
DATE
F : 208 : 11 0508
PRE COMMISSIONING CHECKS - CHILLED WATER CIRCUIT
SYSTEM :
REMARKS :
PERFORMED BY PRIME
DETAILS WITNESSED BY MEP CONTRACTOR APPROVED BY CONSULTANT
TECHNOLOGIES
SIGN.
NAME
DATE
F : 208 : 10 0508
PRE COMMISSIONING CHECKS - PUMPS
SYSTEM :
Electrical Checks
1 Panel board installation correct
2 Panel and Switch gears are Cleaned
3 All Connections are frim and Tight on Busbar
4 Starter Over laod are Correct Set /range is Ok
REMARKS :
PERFORMED BY PRIME
DETAILS WITNESSED BY MEP CONTRACTOR APPROVED BY CONSULTANT
TECHNOLOGIES
SIGN.
NAME
DATE
F : 208 : 10 0508
PERFORMANCE TEST RECORD - WATER FLUSHING VELOCITY REPORT
SYSTEM :
Final Reading
Design pr. Drop
Sl.no Terminal Ref. Location Valve size in (mm) Design velocity m/s
kpa
Pr.drop Kpa Velocity m/s Turns Open Kv Value
Remarks:
SIGN :
NAME :
DATE :
F : 208 : 12 0508
SYSTRA/PARSONS (The Engineer)
The Engineer’s Office, Union Square, P.O. Box 111081, Dubai, UAE
Tel.: +971 (0) 4 234 0202, Fax: +971 (0) 4 234 0203
ELECTROMECHANICAL EQUIPMENT
Document title Method Statement for Testing and Commissioning of Secondary Chilled Water System
Design Stage
Discipline Electromechanical equipment
Reviewer
Document Project DM001-X-AST-GEM-MT-DCC-1285165
Number
Revision n°/Date A1 of 16 December 2008
Transmittal ID TRANSMIT-025071
Acceptance criteria should be clearly defined in MS/T&C Refer 7.17 +/- 5% WITH 10%
2
documents SPEARD
The test procedure should be submitted in detail before Site Specific test sheets will be
the tests, containing : prepared in the Work Packages.
5 Document details, reference, test record sheet showing the These will be submitted attached to
parameters to be measured/checked, theoretical values the ITR’s. (Covered in the T&C
and acceptable tolerance Plan)
For each equipment A Data sheet to be attached contain :
Type of equipment
Location
Manufacturer
Model No.
6 Refer APPENDIX 10.3
Serial No.
Power (kW)
Power Factor (%)
Starting method
etc
All specialized tools, test equipment and instruments
required to execute Start-up, checkout, and testing of
7 equipment to be provided with sufficient quality and Refer 5.0 EQUIPMENT REQUIRED
accuracy to test and/or measure system performance
within specified tolerances
Contractor must calibrate test equipment and instruments Calibration certificates will be
according to manufacturer’s recommended intervals. submitted attached to the ITR’s
8
Calibration tags must be affixed to the test equipment or within Work Packages. (Covered in
certificates readily available the T&C Plan)
not water