4.4 Subcontractors
١
• Unless otherwise stated in the
Particular Conditions:
(a) the Contractor shall not be required to
obtain consent to suppliers of
Materials, or to a subcontract for which
the Subcontractor is named in the
Contract;
(b) the prior consent of the Engineer shall
be obtained to other proposed
Subcontractors;
Contracts & Specs
Dept. of Civil Eng. ©FIDIC 1999: except underlined text Spring 2008
Hashemite University Dr. M. El-Mashaleh
٣
٢
• The Particular Conditions can indicate a
limit for subcontracting
• For example, the Jordanian Particular
Conditions cape this limit at 33%:
– The maximum size of subcontracting work
is 33% of the “Accepted Contract Amount”
……the Contractor should submit details of
every subcontracted amount along with the
proportion of that amount to the contract
amount. The Engineer should make sure
that the 33% is not exceeded
Contracts & Specs
Dept. of Civil Eng. ©FIDIC 1999: except underlined text Spring 2008
Hashemite University Dr. M. El-Mashaleh
٥
٣
– Require the consent of the Engineer for
suppliers of certain materials:
• …the prior consent of the Engineer shall be
obtained to the suppliers of the following
materials…….
٤
• Unless otherwise stated in the
assignment, the Contractor shall have
no liability to the Employer for the work
carried out by the Subcontractor after
the assignment takes effect
5 - Nominated Subcontractors
٥
5.1 Definition of Nominated
Subcontractors
٦
• The second sentence of Sub-Clause
4.4 [Subcontractors] is still enforced:
٧
• An objection shall be deemed
reasonable if it raises from (among
other things) any of the following
matters, unless the Employer agrees
to indemnify the Contractor against
and from the consequences of the
matter:
(a) there are reasons to believe that the
Subcontractor does not have sufficient
competence, resources, or financial
strength;
Contracts & Specs
Dept. of Civil Eng. ©FIDIC 1999: except underlined text Spring 2008
Hashemite University Dr. M. El-Mashaleh
١٥
٨
(c) the subcontract does not specify that, for
the subcontracted work, the nominated
Subcontractor shall:
٩
5.4 Evidence of Payments
١٠
• Then the Employer may (at his sole
discretion) pay direct to the nominated
Subcontractor, part or all of such
amounts previously certified (less
deductions) as are due to the
nominated Subcontractor and for
which the Contractor has failed to
submit the evidence
• The Contractor shall then repay, to the
Employer, the amount which the
nominated Subcontractor was directly
paid by the Employer