Professional Documents
Culture Documents
BOQ ALOR (Submitted) Final
BOQ ALOR (Submitted) Final
Page 1 of 23
SUMMARY FINAL PRICE
PROJECT : Pekerjaan Sipil & Arsitektur (Paket 1) Status Date : 23-Mar-21
LOCATION : Alor Rev : 1
Page 2 of 23
BILL OF QUANTITIES AND PRICES (FINAL)
PACKAGE OF WORK : POWER GENERATOR BUILDING AND FOUNDATION Status Date 23-Mar-21
LOCATION : ALOR Rev 1
PROJECT NO. :
SUBCONTRAKTOR :
UNIT PRICE TOTAL PRICE
NO DESCRIPTION SPECIFICATION QTY UNIT Equipment & TOTAL PRICE REMARKS
Material ( a ) Labour ( c ) Total (a+b+c) Material Equipment & Tool Labour
Tool ( b )
I. ARCHITECTURAL WORK
1 Brickwall Concrete Block (Vol.3, Page:21, No.:4.4.1.5.1.8) 73.74 M2 38,400.00 16,640.00 72,960.00 128,000.00 2,831,616.00 1,227,033.60 5,380,070.40 9,438,720.00
2 Plaster & Aci (1 :3) 10mm Thk. & lath, Plaster 1PCC : 3 sand tide 147.48 M2 16,800.00 7,280.00 31,920.00 56,000.00 2,477,664.00 1,073,654.40 4,707,561.60 8,258,880.00
3 Exterior wall painting finish Weathershield 73.74 M2 9,300.00 4,030.00 17,670.00 31,000.00 685,782.00 297,172.20 1,302,985.80 2,285,940.00 Delux Weathershield pro
4 Interior wall painting finish Emulsion paint 73.74 M2 25,420.00 620.00 4,960.00 31,000.00 1,874,470.80 45,718.80 365,750.40 2,285,940.00 Delux pentalite
9 Roof Drain UPVC dia.4" W/ BracketStrainer 10.00 Nos 60,000.00 1,500.00 13,500.00 75,000.00 600,000.00 15,000.00 135,000.00 750,000.00
10 Downspot UPVC Pipe dia. 4" W/ BracketStrainer 25.04 M 80,000.00 2,000.00 18,000.00 100,000.00 2,003,200.00 50,080.00 450,720.00 2,504,000.00
Water based, high stregth, coloured
11 Floor Hardener, Dust and Oil Proof type Finish polyurenthane resin floor screed (6-9 mm) suitable 562.50 M2 40,000.00 1,000.00 9,000.00 50,000.00 22,500,000.00 562,500.00 5,062,500.00 28,125,000.00 Epoxy - Sika
flor floors subject to heavy loading, abrasion and
chemical exposure
12 Steel Trowel Finish 45.99 M2 16,000.00 400.00 3,600.00 20,000.00 735,840.00 18,396.00 165,564.00 919,800.00
13 Handrail, 1.0mH Post & Handrail w/ SGP Pipe 1.1/4" (1" for handrail 110.03 M 480,000.00 12,000.00 108,000.00 600,000.00 52,815,410.41 1,320,385.26 11,883,467.34 66,019,263.01
bottom layer)
14 Roof Corrugated double skin insulated Zincalume 0.7mm BMT BlueScope 723.45 M2 371,360.00 9,284.00 83,556.00 464,200.00 268,660,392.00 6,716,509.80 60,448,588.20 335,825,490.00
15 Ridge Capping Flat Zincalume 0.7mm BMT BlueScope 203.28 M1 158,100.00 12,400.00 139,500.00 310,000.00 32,138,568.00 2,520,672.00 28,357,560.00 63,016,800.00
16 Siding Corrugated double skin insulated Zincalume 0.7mm BMT BlueScope 896.09 M2 236,742.00 18,568.00 208,890.00 464,200.00 212,141,326.52 16,638,535.41 187,183,523.40 415,963,385.33 Max. 85 db, 1.0m after wall
17 Gutter Plate Galvalum 0.7mm Thk. BlueScope 52.00 M1 158,100.00 12,400.00 139,500.00 310,000.00 8,221,200.00 644,800.00 7,254,000.00 16,120,000.00
18 Roof Ventilator By Mechanical - Nos - - - -
- - - -
Total I 1,016,863,218.34
II. CONCRETE WORK
1 Concrete Spun Pile dia. 400mm Exclude material concrete spun pile dia. 400mm 60.00 Nos - - - - - - - -
2 Cutting Pile 60.00 Nos - 21,000.00 154,000.00 175,000.00 - 1,260,000.00 9,240,000.00 10,500,000.00
3 Excavation 473.89 M3 - 22,200.00 14,800.00 37,000.00 - 10,520,443.70 7,013,629.14 17,534,072.84
4 Backfill With Compacted 342.56 M3 - 4,320.00 11,680.00 16,000.00 - 1,479,843.08 4,001,057.23 5,480,900.31
5 Disposal 131.34 M3 - 5,000.00 21,000.00 26,000.00 - 656,687.96 2,758,089.42 3,414,777.37
6 Compacted Sub Grade With Compacted 576.62 m2 - 4,320.00 11,680.00 16,000.00 - 2,490,994.76 6,734,911.75 9,225,906.50
7 Plastic Sheet 421.38 m2 11,100.00 150.00 3,750.00 15,000.00 4,677,288.39 63,206.60 1,580,165.00 6,320,659.98
8 Compacted soil fill With Compacted 41.50 M3 12,800.00 800.00 2,400.00 16,000.00 531,224.00 33,201.50 99,604.50 664,030.00
9 Crushed Stone 13.67 M3 442,800.00 10,800.00 86,400.00 540,000.00 6,052,049.78 147,610.97 1,180,887.76 7,380,548.51
10 Lean Concrete Ready Mix Concrete With Cement Type I fc' = 15 12.74 M3 770,800.00 18,800.00 150,400.00 940,000.00 9,817,942.61 239,462.01 1,915,696.12 11,973,100.74
Mpa
11 Concrete fc'25 Sub Structure Ready Mix Concrete With Cement Type I 114.76 M3 984,000.00 24,000.00 192,000.00 1,200,000.00 112,921,380.00 2,754,180.00 22,033,440.00 137,709,000.00
12 Concrete fc'25 Upper Structure Ready Mix Concrete With Cement Type I 93.80 M3 984,000.00 24,000.00 192,000.00 1,200,000.00 92,303,779.46 2,251,311.69 18,010,493.55 112,565,584.70
13 Formwork Use Plywood t = 9 mm, incld frame 577.89 M2 138,600.00 6,600.00 19,800.00 165,000.00 80,095,100.43 3,814,052.40 11,442,157.20 95,351,310.03
SNI 07-2052-2002 BJTP 40 OR ASTM A615 GRADE
14 Deformed Bar dia.10mm 3.61 Ton 11,340,000.00 540,000.00 1,620,000.00 13,500,000.00 40,942,611.98 1,949,648.19 5,848,944.57 48,741,204.74
60 fy = 4000 kg/cm2
SNI 07-2052-2002 BJTP 40 OR ASTM A615 GRADE
15 Deformed Bar dia.13mm 60 fy = 4000 kg/cm2 1.29 Ton 11,340,000.00 540,000.00 1,620,000.00 13,500,000.00 14,590,897.93 694,804.66 2,084,413.99 17,370,116.58
Total II 1,155,745,432.51
III. STEEL WORK
Page 3 of 23
BILL OF QUANTITIES AND PRICES (FINAL)
PACKAGE OF WORK : POWER GENERATOR BUILDING AND FOUNDATION Status Date 23-Mar-21
LOCATION : ALOR Rev 1
PROJECT NO. :
SUBCONTRAKTOR :
UNIT PRICE TOTAL PRICE
NO DESCRIPTION SPECIFICATION QTY UNIT Equipment & TOTAL PRICE REMARKS
Material ( a ) Labour ( c ) Total (a+b+c) Material Equipment & Tool Labour
Tool ( b )
Hot dip galvanized WA 405/1, Hot dip galvanized
1 Steel Grating, 32 Thk 469.82 M2 13,300.00 950.00 4,750.00 19,000.00 6,248,630.52 446,330.75 2,231,653.76 8,926,615.03 Webforge
WA 756/1
Hot dip galvanized WA 405/1, Hot dip galvanized
2 800x250 Stairtreads WA 756/1 135.00 m2 13,300.00 950.00 4,750.00 19,000.00 1,795,500.00 128,250.00 641,250.00 2,565,000.00 Webforge
10 HB-150x150x6.5x9 ASTM A-36 251.54 Kg 26,000.00 2,000.00 9,000.00 37,000.00 6,539,919.75 503,070.75 2,263,818.38 9,306,808.88 Include Fabrication, Sand
Blasting and Instalation
Include Fabrication, Sand
11 HB-200x200x8x12 ASTM A-36 3,099.69 Kg 26,000.00 2,000.00 9,000.00 37,000.00 80,591,893.20 6,199,376.40 27,897,193.80 114,688,463.40
Blasting and Instalation
12 HB-350x350x12x19 ASTM A-36 32,834.77 Kg 26,000.00 2,000.00 9,000.00 37,000.00 853,704,005.70 65,669,538.90 295,512,925.05 1,214,886,469.65 Include Fabrication, Sand
Blasting and Instalation
Include Fabrication, Sand
13 WF-150x75x5x7 ASTM A-36 124.95 Kg 26,000.00 2,000.00 9,000.00 37,000.00 3,248,700.00 249,900.00 1,124,550.00 4,623,150.00
Blasting and Instalation
14 WF-200x100x5.5x8 ASTM A-36 208.67 Kg 26,000.00 2,000.00 9,000.00 37,000.00 5,425,301.70 417,330.90 1,877,989.05 7,720,621.65 Include Fabrication, Sand
Blasting and Instalation
Include Fabrication, Sand
15 WF-250x125x6x9 ASTM A-36 5,330.22 Kg 26,000.00 2,000.00 9,000.00 37,000.00 138,585,720.00 10,660,440.00 47,971,980.00 197,218,140.00
Blasting and Instalation
16 WF-300x150x6.5x9 ASTM A-36 7,629.93 Kg 26,000.00 2,000.00 9,000.00 37,000.00 198,378,180.00 15,259,860.00 68,669,370.00 282,307,410.00 Include Fabrication, Sand
Blasting and Instalation
Include Fabrication, Sand
17 WF-350x175x7x11 ASTM A-36 12,678.88 Kg 26,000.00 2,000.00 9,000.00 37,000.00 329,650,776.00 25,357,752.00 114,109,884.00 469,118,412.00
Blasting and Instalation
18 WF-400x200x8x13 ASTM A-36 9,840.60 Kg 26,000.00 2,000.00 9,000.00 37,000.00 255,855,600.00 19,681,200.00 88,565,400.00 364,102,200.00 Include Fabrication, Sand
Blasting and Instalation
Include Fabrication, Sand
19 WF-450x200x9x14 ASTM A-36 9,633.86 Kg 26,000.00 2,000.00 9,000.00 37,000.00 250,480,230.00 19,267,710.00 86,704,695.00 356,452,635.00
Blasting and Instalation
20 UNP-100x50x5x7.5 ASTM A-36 2,035.35 Kg 26,000.00 2,000.00 9,000.00 37,000.00 52,919,184.50 4,070,706.50 18,318,179.25 75,308,070.25 Include Fabrication, Sand
Blasting and Instalation
Include Fabrication, Sand
21 UNP-150x75x6.5x10 ASTM A-36 967.20 Kg 26,000.00 2,000.00 9,000.00 37,000.00 25,147,200.00 1,934,400.00 8,704,800.00 35,786,400.00 Blasting and Instalation
22 UNP-150x75x9x12.5 ASTM A-36 3,506.58 Kg 26,000.00 2,000.00 9,000.00 37,000.00 91,171,080.00 7,013,160.00 31,559,220.00 129,743,460.00 Include Fabrication, Sand
Blasting and Instalation
Include Fabrication, Sand
23 UNP-180x75x7x11 ASTM A-36 2,073.08 Kg 26,000.00 2,000.00 9,000.00 37,000.00 53,900,137.20 4,146,164.40 18,657,739.80 76,704,041.40 Blasting and Instalation
24 CNP-150x65x20x3.2 ASTM A-36 11,775.29 Kg 26,000.00 2,000.00 9,000.00 37,000.00 306,157,651.80 23,550,588.60 105,977,648.70 435,685,889.10 Include Fabrication, Sand
Blasting and Instalation
Include Fabrication, Sand
25 L-40x40x4 ASTM A-36 400.27 Kg 26,000.00 2,000.00 9,000.00 37,000.00 10,406,995.24 800,538.10 3,602,421.43 14,809,954.76 Blasting and Instalation
26 L-70x70x6 ASTM A-36 96.47 Kg 26,000.00 2,000.00 9,000.00 37,000.00 2,508,105.60 192,931.20 868,190.40 3,569,227.20 Include Fabrication, Sand
Blasting and Instalation
Include Fabrication, Sand
27 L-80x80x8 ASTM A-36 8.11 Kg 26,000.00 2,000.00 9,000.00 37,000.00 210,974.40 16,228.80 73,029.60 300,232.80 Blasting and Instalation
28 L-100x100x7 ASTM A-36 628.94 Kg 26,000.00 2,000.00 9,000.00 37,000.00 16,352,317.80 1,257,870.60 5,660,417.70 23,270,606.10 Include Fabrication, Sand
Blasting and Instalation
Blue colour, PLN vendor list
29 Steel Painting Include sand blasting 3,947.95 m2 11,650.00 890.00 4,460.00 17,000.00 45,993,639.58 3,513,677.19 17,607,865.45 67,115,182.22 Jotun, International Paint
Indonesia or Hempel
30 M8 O.S. Bolt HTB A325, Grade B 304.00 Pcs 11,900.00 850.00 4,250.00 17,000.00 3,617,600.00 258,400.00 1,292,000.00 5,168,000.00
31 M16 O.S. Bolt HTB A325, Grade B 874.00 Pcs 23,800.00 1,700.00 8,500.00 34,000.00 20,801,200.00 1,485,800.00 7,429,000.00 29,716,000.00
32 M16 H.S. Bolt HTB A325, Grade B 868.00 Pcs 23,800.00 1,700.00 8,500.00 34,000.00 20,658,400.00 1,475,600.00 7,378,000.00 29,512,000.00
33 M20 H.S. Bolt HTB A325, Grade B 498.00 Pcs 29,400.00 2,100.00 10,500.00 42,000.00 14,641,200.00 1,045,800.00 5,229,000.00 20,916,000.00
34 M22 H.S. Bolt HTB A325, Grade B 1,376.00 Pcs 32,340.00 2,310.00 11,550.00 46,200.00 44,499,840.00 3,178,560.00 15,892,800.00 63,571,200.00
35 M24 H.S. Bolt HTB A325, Grade B 341.00 Pcs 35,000.00 2,500.00 12,500.00 50,000.00 11,935,000.00 852,500.00 4,262,500.00 17,050,000.00
Page 4 of 23
BILL OF QUANTITIES AND PRICES (FINAL)
PACKAGE OF WORK : POWER GENERATOR BUILDING AND FOUNDATION Status Date 23-Mar-21
LOCATION : ALOR Rev 1
PROJECT NO. :
SUBCONTRAKTOR :
UNIT PRICE TOTAL PRICE
NO DESCRIPTION SPECIFICATION QTY UNIT Equipment & TOTAL PRICE REMARKS
Material ( a ) Labour ( c ) Total (a+b+c) Material Equipment & Tool Labour
Tool ( b )
36 M20 Anchor Bolt ASTM A307, Grade B 5.00 Pcs 115,500.00 8,250.00 41,250.00 165,000.00 577,500.00 41,250.00 206,250.00 825,000.00
37 M24 Anchor Bolt ASTM A307, Grade B 290.00 Pcs 141,400.00 10,100.00 50,500.00 202,000.00 41,006,000.00 2,929,000.00 14,645,000.00 58,580,000.00
Grade SR 24/JIS G 3112, Nut&Washer : Grade B
38 Wind Bracing dia. 16 Round Bar ASTM A307 15.00 Set 256,900.00 18,350.00 91,750.00 367,000.00 3,853,500.00 275,250.00 1,376,250.00 5,505,000.00
Page 5 of 23
BILL OF QUANTITIES AND PRICES (FINAL)
PACKAGE OF WORK : CENTRAL CONTROL BUILDING AND FOUNDATION Status Date 23-Mar-21
LOCATION : ALOR Rev 1
PROJECT NO. :
SUBCONTRAKTOR :
UNIT PRICE TOTAL PRICE
NO DESCRIPTION SPECIFICATION QTY UNIT Equipment & Tool ( TOTAL PRICE REMARKS
Material ( a ) Labour ( c ) Total (a+b+c) Material Equipment & Tool Labour
b)
I. ARCHITECTURAL WORK
1 Brickwall Concrete Block (Vol.3, Page:21, 451.86 M2 36,000.00 15,600.00 68,400.00 120,000.00 16,266,943.80 7,049,008.98 30,907,193.22 54,223,146.00
No.:4.4.1.5.1.8)
2 Plaster & Aci (1 :3) 10mm Thk. & lath, Plaster 1PCC : 3 sand tide 903.72 M2 15,000.00 6,500.00 28,500.00 50,000.00 13,555,786.50 5,874,174.15 25,755,994.35 45,185,955.00
3 Exterior wall painting finish Weathershield 279.12 M2 9,000.00 3,900.00 17,100.00 30,000.00 2,512,073.70 1,088,565.27 4,772,940.03 8,373,579.00 Delux Weathershield pro
4 Interior wall painting finish Emulsion paint 806.42 M2 24,600.00 600.00 4,800.00 30,000.00 19,837,927.08 483,851.88 3,870,815.04 24,192,594.00 Delux pentalite
Page 6 of 23
BILL OF QUANTITIES AND PRICES (FINAL)
PACKAGE OF WORK : CENTRAL CONTROL BUILDING AND FOUNDATION Status Date 23-Mar-21
LOCATION : ALOR Rev 1
PROJECT NO. :
SUBCONTRAKTOR :
UNIT PRICE TOTAL PRICE
NO DESCRIPTION SPECIFICATION QTY UNIT Equipment & Tool ( TOTAL PRICE REMARKS
Material ( a ) Labour ( c ) Total (a+b+c) Material Equipment & Tool Labour
b)
21 Foucet (kran) TOTO, T 23 BQ 13N 2.00 Unit 234,600.00 18,400.00 207,000.00 460,000.00 469,200.00 36,800.00 414,000.00 920,000.00
22 Ceramic Tile Floor (200x200) Un-Gluzed Roman 4.41 M2 66,300.00 5,200.00 58,500.00 130,000.00 292,383.00 22,932.00 257,985.00 573,300.00
23 Ceramic Tile Wall (200x400) Glazed Roman 33.55 M2 86,700.00 6,800.00 76,500.00 170,000.00 2,909,019.09 228,158.36 2,566,781.55 5,703,959.00
24 Ceiling acoustic board 15mm Thk. Mineral fiber board, accoustic mineral board 108.45 M2 56,100.00 4,400.00 49,500.00 110,000.00 6,084,045.00 477,180.00 5,368,275.00 11,929,500.00
15mm Thk. (include accessories)
25 Ceiling GRC board 6mm Thk. w/paint 6mm Thk. (metal furing & C Channel) 73.37 M2 20,400.00 1,600.00 18,000.00 40,000.00 1,496,748.00 117,392.00 1,320,660.00 2,934,800.00
26 Roof Drain UPVC dia.4" W/ BracketStrainer 5.00 Nos 35,700.00 2,800.00 31,500.00 70,000.00 178,500.00 14,000.00 157,500.00 350,000.00
27 Downspot UPVC Pipe dia. 4" W/ BracketStrainer 38.65 M 80,000.00 2,000.00 18,000.00 100,000.00 3,092,000.00 77,300.00 695,700.00 3,865,000.00
29 Waterproofing Membrane Waterproofing Membrane w/ 50mm Mortar 350.35 M2 45,900.00 3,600.00 40,500.00 90,000.00 16,081,065.00 1,261,260.00 14,189,175.00 31,531,500.00
Screed, Chicken mesh dia. 2mm
30 Listplank, 0.65mW 55.10 M 158,100.00 12,400.00 139,500.00 310,000.00 8,711,310.00 683,240.00 7,686,450.00 17,081,000.00
31 Handrail, 1.0mH Post & Handrail w/ SGP Pipe 1.1/4" (1" for 40.27 M 300,900.00 23,600.00 265,500.00 590,000.00 12,117,269.26 950,374.06 10,691,708.17 23,759,351.49
handrail bottom layer) ASTM A-36
- - - - -
Total I 310,424,056.78
II. CONCRETE WORK - - - - -
1 Cutting Pile 15.00 nos - 21,000.00 154,000.00 175,000.00 - 315,000.00 2,310,000.00 2,625,000.00
2 Excavation 316.07 M3 - 2,400.00 27,600.00 30,000.00 - 758,570.40 8,723,559.60 9,482,130.00
3 Backfill With Compacted 316.07 M3 - 1,200.00 8,800.00 10,000.00 - 379,285.20 2,781,424.80 3,160,710.00
4 Compacted Sub Grade 434.83 M3 - 6,000.00 4,000.00 10,000.00 - 2,608,980.00 1,739,320.00 4,348,300.00
5 Plastic Sheet 257.73 M3 7,400.00 100.00 2,500.00 10,000.00 1,907,202.00 25,773.00 644,325.00 2,577,300.00
6 Crushed Stone 10.94 M3 442,800.00 10,800.00 86,400.00 540,000.00 4,842,018.00 118,098.00 944,784.00 5,904,900.00
7 Lean Concrete Ready Mix Concrete With Cement Type I fc' = 9.08 M3 744,000.00 46,500.00 139,500.00 930,000.00 6,752,990.40 422,061.90 1,266,185.70 8,441,238.00
15 Mpa
8 Concrete fc'25 Sub Structure Ready Mix Concrete With Cement Type I 70.88 M3 885,780.00 11,970.00 299,250.00 1,197,000.00 62,779,657.50 848,373.75 21,209,343.75 84,837,375.00
9 Concrete fc'25 Upper Structure Ready Mix Concrete With Cement Type I 200.87 M3 957,600.00 59,850.00 179,550.00 1,197,000.00 192,356,446.94 12,022,277.93 36,066,833.80 240,445,558.67
10 Formwork Use Plywood t = 9 mm, incld frame 1,670.60 M2 131,200.00 3,200.00 25,600.00 160,000.00 219,182,720.00 5,345,920.00 42,767,360.00 267,296,000.00
11 Deformed Bar dia.10mm SNI 07-2052-2002 BJTP 40 OR ASTM A615 6.08 Ton 11,205,600.00 533,600.00 1,600,800.00 13,340,000.00 68,160,548.03 3,245,740.38 9,737,221.15 81,143,509.56
GRADE 60 fy = 4000 kg/cm2
12 Deformed Bar dia.13mm SNI 07-2052-2002 BJTP 40 OR ASTM A615 38.70 Ton 11,205,600.00 533,600.00 1,600,800.00 13,340,000.00 433,656,720.00 20,650,320.00 61,950,960.00 516,258,000.00
GRADE 60 fy = 4000 kg/cm2
13 Deformed Bar dia.16mm SNI 07-2052-2002 BJTP 40 OR ASTM A615 3.90 Ton 11,205,600.00 533,600.00 1,600,800.00 13,340,000.00 43,701,840.00 2,081,040.00 6,243,120.00 52,026,000.00
GRADE 60 fy = 4000 kg/cm2
14 Deformed Bar dia.19mm SNI 07-2052-2002 BJTP 40 OR ASTM A615 19.65 Ton 11,205,600.00 533,600.00 1,600,800.00 13,340,000.00 220,190,040.00 10,485,240.00 31,455,720.00 262,131,000.00
GRADE 60 fy = 4000 kg/cm2
- - - - -
Total II 1,540,677,021.23
III. STEEL WORK - - - - -
- - - - -
Total III -
TOTAL I + II + III 1,851,101,078.02
B PEKERJAAN PERSIAPAN
I. PEKERJAAN PERSIAPAN 1.00 Ls INCLUDE -
GRAND TOTAL 1,851,101,078.02
Page 7 of 23
BILL OF QUANTITIES AND PRICES (FINAL)
PACKAGE OF WORK : WORKSHOP BUILDING AND FOUNDATION Status Date 23-Mar-21
LOCATION : ALOR Rev 1
PROJECT NO. :
SUBCONTRAKTOR :
UNIT PRICE TOTAL PRICE
NO DESCRIPTION SPECIFICATION QTY UNIT Equipment & Tool ( TOTAL PRICE REMARKS
Material ( a ) Labour ( c ) Total (a+b+c) Material Equipment & Tool Labour
b)
I. ARCHITECTURAL WORK - - - - -
1 Brickwall Concrete Block (Vol.3, Page:21, 179.07 M2 37,500.00 16,250.00 71,250.00 125,000.00 6,714,997.31 2,909,832.17 12,758,494.89 22,383,324.38
No.:4.4.1.5.1.8)
2 Plaster & Aci (1 :3) 10mm Thk. & lath, Plaster 1PCC : 3 sand tide 358.13 M2 15,900.00 6,890.00 30,210.00 53,000.00 5,694,317.72 2,467,537.68 10,819,203.67 18,981,059.07
3 Interior wall Vinyl Acetate paint finish Acetate paint finish 400.68 M2 8,940.00 3,874.00 16,986.00 29,800.00 3,582,109.69 1,552,247.53 6,806,008.40 11,940,365.62 Delux pentalite
Page 8 of 23
BILL OF QUANTITIES AND PRICES (FINAL)
PACKAGE OF WORK : WORKSHOP BUILDING AND FOUNDATION Status Date 23-Mar-21
LOCATION : ALOR Rev 1
PROJECT NO. :
SUBCONTRAKTOR :
UNIT PRICE TOTAL PRICE
NO DESCRIPTION SPECIFICATION QTY UNIT Equipment & Tool ( TOTAL PRICE REMARKS
Material ( a ) Labour ( c ) Total (a+b+c) Material Equipment & Tool Labour
b)
Sika "chadure"
Average comsumtive : 3-6kg per m2, depend
on job requipment : light duty = 3 kg/m2,
25 Floor Hardener medium duty = 4-5 kg/m2, heavy duty = 6 90.60 M2 15,300.00 1,200.00 13,500.00 30,000.00 1,386,180.00 108,720.00 1,223,100.00 2,718,000.00
kg/m2. yielding a surface strengthening coat
of approax 2-3 mm THK.
26 Steel Trowel Finish 135.10 M2 9,537.00 748.00 8,415.00 18,700.00 1,288,448.70 101,054.80 1,136,866.50 2,526,370.00
27 Roof Corrugated Zincalume sheet 0.7mm BMT BlueScope 204.61 M2 177,480.00 13,920.00 156,600.00 348,000.00 36,313,543.87 2,848,121.09 32,041,362.24 71,203,027.20
28 Ridge Capping Flat Zincalume 0.7mm BMT BlueScope 12.60 M1 152,388.00 11,952.00 134,460.00 298,800.00 1,920,088.80 150,595.20 1,694,196.00 3,764,880.00
29 Siding Corrugated Zincalume sheet 0.7mm BMT BlueScope 255.90 M2 177,480.00 13,920.00 156,600.00 348,000.00 45,417,132.00 3,562,128.00 40,073,940.00 89,053,200.00
30 Corrugated Translucent Sheet 1.6mm Thk BlueScope 34.00 M2 177,480.00 13,920.00 156,600.00 348,000.00 6,034,320.00 473,280.00 5,324,400.00 11,832,000.00
31 Gutter Steel Sheet Plate (Protected by hot dipped galvaniszed) (Protected by hot dipped galvaniszed) 29.40 M1 179,265.00 14,060.00 158,175.00 351,500.00 5,270,391.00 413,364.00 4,650,345.00 10,334,100.00
32 Flashing 70.27 M1 152,388.00 11,952.00 134,460.00 298,800.00 10,708,975.27 839,919.63 9,449,095.82 20,997,990.72
- - - - -
Total I 384,839,630.98
II. CONCRETE WORK - - - - -
1 Excavation 221.40 M3 - 2,864.00 32,936.00 35,800.00 - 634,089.60 7,292,030.40 7,926,120.00
2 Backfill With Compacted 161.09 M3 - 1,812.00 13,288.00 15,100.00 - 291,902.33 2,140,617.07 2,432,519.40
3 Disposal 60.31 M3 - 5,000.00 21,000.00 26,000.00 - 301,530.00 1,266,426.00 1,567,956.00
4 Compacted Sub Grade 287.92 M2 - 4,077.00 11,023.00 15,100.00 - 1,173,864.11 3,173,780.74 4,347,644.85
5 Plastic Sheet 168.89 M2 10,360.00 140.00 3,500.00 14,000.00 1,749,736.66 23,645.09 591,127.25 2,364,509.00
6 Compacted soil fill 191.93 M3 12,080.00 755.00 2,265.00 15,100.00 2,318,533.73 144,908.36 434,725.07 2,898,167.16
7 Lean Concrete Ready Mix Concrete With Cement Type I fc' = 5.23 M3 722,584.00 17,624.00 140,992.00 881,200.00 3,779,836.90 92,191.14 737,529.15 4,609,557.20
15 Mpa
8 Concrete fc'25 Sub Structure Ready Mix Concrete With Cement Type I 91.60 M3 945,000.00 45,000.00 135,000.00 1,125,000.00 86,562,000.00 4,122,000.00 12,366,000.00 103,050,000.00
9 Formwork Use Plywood t = 9 mm, incld frame 210.73 m2 137,760.00 6,560.00 19,680.00 164,000.00 29,029,544.88 1,382,359.28 4,147,077.84 34,558,982.00
10 Deformed Bar dia.10mm SNI 07-2052-2002 BJTP 40 OR ASTM A615 2.61 Ton 11,025,000.00 525,000.00 1,575,000.00 13,125,000.00 28,764,453.88 1,369,735.90 4,109,207.70 34,243,397.48
GRADE 60 fy = 4000 kg/cm2
SNI 07-2052-2002 BJTP 40 OR ASTM A615
11 Deformed Bar dia.13mm GRADE 60 fy = 4000 kg/cm2 2.70 Ton 11,025,000.00 525,000.00 1,575,000.00 13,125,000.00 29,779,999.70 1,418,095.22 4,254,285.67 35,452,380.60
12 Deformed Bar dia.16mm SNI 07-2052-2002 BJTP 40 OR ASTM A615 4.89 Ton 11,025,000.00 525,000.00 1,575,000.00 13,125,000.00 53,898,406.57 2,566,590.79 7,699,772.37 64,164,769.73
GRADE 60 fy = 4000 kg/cm2
13 Deformed Bar dia.19mm SNI 07-2052-2002 BJTP 40 OR ASTM A615 1.23 Ton 11,025,000.00 525,000.00 1,575,000.00 13,125,000.00 13,546,600.74 645,076.23 1,935,228.68 16,126,905.64
GRADE 60 fy = 4000 kg/cm2
14 Grouting Non Shrink Min Compressive Strength 35 Mpa at 7 Day 0.09 M3 7,329,000.00 349,000.00 1,047,000.00 8,725,000.00 643,119.75 30,624.75 91,874.25 765,618.75
15 Sealant compound Polymeric asphal base, ASTM D3405-97 123.90 M1 41,160.00 1,960.00 5,880.00 49,000.00 5,099,724.00 242,844.00 728,532.00 6,071,100.00
- - - - - SIKA
Total I 320,579,627.80
III. STEEL WORK - - - - -
Include Fabrication, Sand
1 Steel plate 9 Thk. ASTM A-36 2,627.38 Kg 26,000.00 2,000.00 9,000.00 37,000.00 68,311,754.41 5,254,750.34 23,646,376.53 97,212,881.27 Blasting and Instalation
2 Steel plate 16 Thk. ASTM A-36 77.57 Kg 26,000.00 2,000.00 9,000.00 37,000.00 2,016,878.50 155,144.50 698,150.25 2,870,173.25 Include Fabrication, Sand
Blasting and Instalation
Include Fabrication, Sand
3 Steel plate 22 Thk. ASTM A-36 481.89 Kg 26,000.00 2,000.00 9,000.00 37,000.00 12,529,061.55 963,773.97 4,336,982.84 17,829,818.35
Blasting and Instalation
4 Steel plate 25 Thk. ASTM A-36 492.17 Kg 26,000.00 2,000.00 9,000.00 37,000.00 12,796,508.04 984,346.77 4,429,560.47 18,210,415.28 Include Fabrication, Sand
Blasting and Instalation
5 WF-200x100x5.5x8 ASTM A-36 3,144.36 Kg 26,000.00 2,000.00 9,000.00 37,000.00 81,753,423.57 6,288,724.89 28,299,262.01 116,341,410.47 Include Fabrication, Sand
Blasting and Instalation
Include Fabrication, Sand
6 WF-250x125x6x9 ASTM A-36 2,452.93 Kg 26,000.00 2,000.00 9,000.00 37,000.00 63,776,097.84 4,905,853.68 22,076,341.56 90,758,293.08 Blasting and Instalation
7 WF-400x200x8x13 ASTM A-36 7,788.77 Kg 26,000.00 2,000.00 9,000.00 37,000.00 202,507,905.60 15,577,531.20 70,098,890.40 288,184,327.20 Include Fabrication, Sand
Blasting and Instalation
Include Fabrication, Sand
8 UNP-150x75x6.5x10 ASTM A-36 796.27 Kg 26,000.00 2,000.00 9,000.00 37,000.00 20,703,009.60 1,592,539.20 7,166,426.40 29,461,975.20 Blasting and Instalation
9 CNP-150x65x20x3.2 ASTM A-36 3,971.28 Kg 26,000.00 2,000.00 9,000.00 37,000.00 103,253,369.22 7,942,566.86 35,741,550.88 146,937,486.97 Include Fabrication, Sand
Blasting and Instalation
Include Fabrication, Sand
10 L-40x40x4 ASTM A-36 701.47 Kg 26,000.00 2,000.00 9,000.00 37,000.00 18,238,129.00 1,402,933.00 6,313,198.50 25,954,260.50
Blasting and Instalation
Include Fabrication, Sand
11 L-75x75x6 ASTM A-36 355.64 Kg 26,000.00 2,000.00 9,000.00 37,000.00 9,246,649.23 711,280.71 3,200,763.20 13,158,693.14
Blasting and Instalation
Blue colour, PLN vendor list
12 Steel Painting Include sand blasting 876.04 M2 11,650.00 890.00 4,460.00 17,000.00 10,205,862.27 779,675.32 3,907,136.97 14,892,674.56 Jotun, International Paint
Indonesia or Hempel
Page 9 of 23
BILL OF QUANTITIES AND PRICES (FINAL)
PACKAGE OF WORK : WORKSHOP BUILDING AND FOUNDATION Status Date 23-Mar-21
LOCATION : ALOR Rev 1
PROJECT NO. :
SUBCONTRAKTOR :
UNIT PRICE TOTAL PRICE
NO DESCRIPTION SPECIFICATION QTY UNIT Equipment & Tool ( TOTAL PRICE REMARKS
Material ( a ) Labour ( c ) Total (a+b+c) Material Equipment & Tool Labour
b)
13 M8 O.S. Bolt HTB A325, Grade B 173.00 Pcs 11,130.00 795.00 3,975.00 15,900.00 1,925,490.00 137,535.00 687,675.00 2,750,700.00
14 M16 O.S. Bolt HTB A325, Grade B 200.00 Pcs 22,260.00 1,590.00 7,950.00 31,800.00 4,452,000.00 318,000.00 1,590,000.00 6,360,000.00
15 M16 H.S. Bolt HTB A325, Grade B 131.00 Pcs 22,260.00 1,590.00 7,950.00 31,800.00 2,916,060.00 208,290.00 1,041,450.00 4,165,800.00
16 M20 O.S. Bolt HTB A325, Grade B 307.00 Pcs 27,860.00 1,990.00 9,950.00 39,800.00 8,553,020.00 610,930.00 3,054,650.00 12,218,600.00
17 M20 H.S. Bolt HTB A325, Grade B 603.00 Pcs 27,860.00 1,990.00 9,950.00 39,800.00 16,799,580.00 1,199,970.00 5,999,850.00 23,999,400.00
18 M24 Anchor Bolt PJTN=150 L=750 ASTM A307, Grade B 76.00 Pcs 134,540.00 9,610.00 48,050.00 192,200.00 10,225,040.00 730,360.00 3,651,800.00 14,607,200.00
19 M24 Anchor Bolt PJTN=70 L=440 ASTM A307, Grade B 5.00 Pcs 134,540.00 9,610.00 48,050.00 192,200.00 672,700.00 48,050.00 240,250.00 961,000.00
20 Wind Bracing dia. 16 Round Bar Grade SR 24/JIS G 3112, Nut&Washer : Grade 21.00 Set 240,940.00 17,210.00 86,050.00 344,200.00 5,059,740.00 361,410.00 1,807,050.00 7,228,200.00
B ASTM A307
Grade SR 24/JIS G 3112, Nut&Washer : Grade
21 Sagrod, dia. 12 Round Bar B ASTM A307 147.00 Set 120,470.00 8,605.00 43,025.00 172,100.00 17,709,090.00 1,264,935.00 6,324,675.00 25,298,700.00
- - - - -
Total III 959,402,009.27
TOTAL I + II + III 1,664,821,268.05
B PEKERJAAN PERSIAPAN
I. PEKERJAAN PERSIAPAN 1.00 Ls INCLUDE -
GRAND TOTAL 1,664,821,268.05
Page 10 of 23
BILL OF QUANTITIES AND PRICES (FINAL)
PACKAGE OF WORK : WAREHOUSE BUILDING AND FOUNDATION Status Date 23-Mar-21
LOCATION : ALOR Rev 1
PROJECT NO. :
SUBCONTRAKTOR :
UNIT PRICE TOTAL PRICE
NO DESCRIPTION SPECIFICATION QTY UNIT Equipment & Tool ( TOTAL PRICE REMARKS
Material ( a ) b) Labour ( c ) Total (a+b+c) Material Equipment & Tool Labour
I. ARCHITECTURAL WORK - - - - -
Concrete Block (Vol.3, Page:21,
1 Brickwall No.:4.4.1.5.1.8) 173.80 M2 37,500.00 16,250.00 71,250.00 125,000.00 6,517,585.50 2,824,287.05 12,383,412.45 21,725,285.00
2 Plaster & Aci (1 :3) 10mm Thk. & lath, Plaster 1PCC : 3 sand tide 347.60 M2 16,680.00 7,228.00 31,692.00 55,600.00 5,798,044.06 2,512,485.76 11,016,283.72 19,326,813.54
3 Exterior wall painting finish Weathershield 78.75 M2 9,150.00 3,965.00 17,385.00 30,500.00 720,552.71 312,239.51 1,369,050.15 2,401,842.37 Delux Weathershield pro
4 Interior wall painting finish Emulsion paint 268.86 M2 25,010.00 610.00 4,880.00 30,500.00 6,724,079.31 164,001.93 1,312,015.47 8,200,096.72 Delux pentalite
13 Washtafel TOTO, LW 240 CJ 1.00 Unit 929,840.00 23,246.00 209,214.00 1,162,300.00 929,840.00 23,246.00 209,214.00 1,162,300.00
14 Seating Closet TOTO, CW421J/SW420JP 1.00 Unit 1,260,800.00 31,520.00 283,680.00 1,576,000.00 1,260,800.00 31,520.00 283,680.00 1,576,000.00
15 Floor drain TOTO, TX 1BV1 1.00 Unit 76,500.00 6,000.00 67,500.00 150,000.00 76,500.00 6,000.00 67,500.00 150,000.00
16 Foucet (kran) TOTO, T 23 BQ 13N 1.00 Unit 233,580.00 18,320.00 206,100.00 458,000.00 233,580.00 18,320.00 206,100.00 458,000.00
17 Fiberglass Water Tube size 70 x 70 1.00 Unit 209,763.00 16,452.00 185,085.00 411,300.00 209,763.00 16,452.00 185,085.00 411,300.00
18 Ceramic Tile Floor (200x200) Un-Gluzed Roman 3.19 M2 66,300.00 5,200.00 58,500.00 130,000.00 211,579.88 16,594.50 186,688.13 414,862.50
19 Ceramic Tile Wall (200x400) Glazed Roman 18.32 M2 86,700.00 6,800.00 76,500.00 170,000.00 1,588,257.30 124,569.20 1,401,403.50 3,114,230.00
20 Ceramic Tile Wall (200x500) Glazed Roman - M2 86,700.00 6,800.00 76,500.00 170,000.00 - - - -
21 Ceramic Tile Floor (600x600) Glazed Roman 57.85 M2 65,433.00 5,132.00 57,735.00 128,300.00 3,785,299.05 296,886.20 3,339,969.75 7,422,155.00
Gybsum tile x 1200 (metal furing & C
22 Ceiling gybsum board 9mm Thk. Channel) 56.70 M2 47,787.00 3,748.00 42,165.00 93,700.00 2,709,283.97 212,492.86 2,390,544.68 5,312,321.50
23 Ceiling GRC board 6mm Thk. w/paint 6mm Thk. (metal furing & C Channel) 3.19 M2 20,400.00 1,600.00 18,000.00 40,000.00 65,101.50 5,106.00 57,442.50 127,650.00
24 Roof Drain UPVC dia.4" W/ BracketStrainer 6.00 Nos 37,638.00 2,952.00 33,210.00 73,800.00 225,828.00 17,712.00 199,260.00 442,800.00
Page 11 of 23
BILL OF QUANTITIES AND PRICES (FINAL)
PACKAGE OF WORK : WAREHOUSE BUILDING AND FOUNDATION Status Date 23-Mar-21
LOCATION : ALOR Rev 1
PROJECT NO. :
SUBCONTRAKTOR :
UNIT PRICE TOTAL PRICE
NO DESCRIPTION SPECIFICATION QTY UNIT Equipment & Tool ( TOTAL PRICE REMARKS
Material ( a ) b) Labour ( c ) Total (a+b+c) Material Equipment & Tool Labour
25 Downspot UPVC Pipe dia. 4" W/ BracketStrainer 51.75 M 50,235.00 3,940.00 44,325.00 98,500.00 2,599,661.25 203,895.00 2,293,818.75 5,097,375.00
Epoxy "sika"
Water based, high stregth, coloured
26 Floor Hardener, Dust and Oil Proof type Finish polyurenthane resin floor screed (6-9 mm) 59.20 M2 25,092.00 1,968.00 22,140.00 49,200.00 1,485,446.40 116,505.60 1,310,688.00 2,912,640.00
suitable flor floors subject to heavy loading,
abrasion and chemical exposure
Sika "chadure"
Average comsumtive : 3-6kg per m2, depend on
job requipment : light duty = 3 kg/m2, medium
27 Floor Hardener duty = 4-5 kg/m2, heavy duty = 6 kg/m2. yielding 17.13 M2 15,300.00 1,200.00 13,500.00 30,000.00 262,127.25 20,559.00 231,288.75 513,975.00
a surface strengthening coat of approax 2-3 mm
THK.
28 Painting Finish Acrylic emulsion paint 59.89 M2 12,546.00 984.00 11,070.00 24,600.00 751,332.89 58,928.07 662,940.79 1,473,201.75 Dulux pentalite
29 Roof Corrugated Zincalume sheet 0.7mm BMT BlueScope 189.81 M2 153,204.00 12,016.00 135,180.00 300,400.00 29,079,099.71 2,280,713.70 25,658,029.15 57,017,842.56
30 Ridge Capping Flat Zincalume 0.7mm BMT BlueScope 12.60 M1 140,658.00 11,032.00 124,110.00 275,800.00 1,772,290.80 139,003.20 1,563,786.00 3,475,080.00
31 Siding Corrugated Zincalume sheet 0.7mm BMT BlueScope 270.92 M2 153,204.00 12,016.00 135,180.00 300,400.00 41,506,428.94 3,255,406.19 36,623,319.65 81,385,154.78
32 Gutter Steel Sheet Plate Protected by hot dipped galvaniszed 29.40 M1 175,797.00 13,788.00 155,115.00 344,700.00 5,168,431.80 405,367.20 4,560,381.00 10,134,180.00
33 Flashing BlueScope 70.27 M1 140,658.0 11,032.0 124,110.0 275,800.00 9,884,656.56 775,267.18 8,721,755.78 19,381,679.52
34 Listplank Corrugated Metal 0.7 mm BMT BlueScope 36.24 M2 140,658.00 11,032.00 124,110.00 275,800.00 5,097,817.26 399,828.80 4,498,074.05 9,995,720.11
35 Roof Ventilator By Mechanical - Unit - - - - - - - -
- - - - -
Total I 349,047,105.34
II. CONCRETE WORK - - - - -
1 Excavation With Compacted 221.40 M3 - 2,912.00 33,488.00 36,400.00 - 644,716.80 7,414,243.20 8,058,960.00
2 Backfill 161.09 M3 - 1,884.00 13,816.00 15,700.00 - 303,501.10 2,225,674.70 2,529,175.80
3 Disposal 60.31 M3 - 5,000.00 21,000.00 26,000.00 - 301,530.00 1,266,426.00 1,567,956.00
4 Compacted Sub Grade 207.36 M2 - 4,239.00 11,461.00 15,700.00 - 878,999.04 2,376,552.96 3,255,552.00
5 Plastic Sheet 189.85 M2 10,878.00 147.00 3,675.00 14,700.00 2,065,188.30 27,907.95 697,698.75 2,790,795.00
6 Compacted soil fill 16.68 M3 10,878.00 147.00 3,675.00 14,700.00 181,460.81 2,452.17 61,304.33 245,217.32
7 Lean Concrete Ready Mix Concrete With Cement Type I fc' 5.63 M3 740,720.00 46,295.00 138,885.00 925,900.00 4,169,512.88 260,594.56 781,783.67 5,211,891.10
= 15 Mpa
8 Concrete fc'25 Sub Structure Ready Mix Concrete With Cement Type I 66.51 M3 945,600.00 59,100.00 177,300.00 1,182,000.00 62,891,856.00 3,930,741.00 11,792,223.00 78,614,820.00
9 Concrete fc'25 Upper Structure Ready Mix Concrete With Cement Type I 35.40 M3 969,240.00 23,640.00 189,120.00 1,182,000.00 34,314,468.96 836,938.27 6,695,506.14 41,846,913.36
10 Formwork Use Plywood t = 9 mm, incld frame 211.33 M2 133,250.00 3,250.00 26,000.00 162,500.00 28,159,855.75 686,825.75 5,494,606.00 34,341,287.50
SNI 07-2052-2002 BJTP 40 OR ASTM A615
11 Deformed Bar dia.10mm 2.68 Ton 10,880,268.00 518,108.00 1,554,324.00 12,952,700.00 29,206,914.39 1,390,805.45 4,172,416.34 34,770,136.17
GRADE 60 fy = 4000 kg/cm2
SNI 07-2052-2002 BJTP 40 OR ASTM A615
12 Deformed Bar dia.13mm GRADE 60 fy = 4000 kg/cm2 2.90 Ton 10,880,268.00 518,108.00 1,554,324.00 12,952,700.00 31,548,123.16 1,502,291.58 4,506,874.74 37,557,289.48
13 Deformed Bar dia.16mm SNI 07-2052-2002 BJTP 40 OR ASTM A615 5.60 Ton 10,880,268.00 518,108.00 1,554,324.00 12,952,700.00 60,982,251.23 2,903,916.73 8,711,750.18 72,597,918.13
GRADE 60 fy = 4000 kg/cm2
14 Deformed Bar dia.19mm SNI 07-2052-2002 BJTP 40 OR ASTM A615 1.33 Ton 10,880,268.00 518,108.00 1,554,324.00 12,952,700.00 14,417,356.59 686,540.79 2,059,622.37 17,163,519.75
GRADE 60 fy = 4000 kg/cm2
15 Grouting Non Shrink Min Compressive Strength 35 Mpa at 7 Day 0.09 M3 7,032,900.00 334,900.00 1,004,700.00 8,372,500.00 617,136.98 29,387.48 88,162.43 734,686.88
16 Sealant compound Polymeric asphal base, ASTM D3405-97 169.40 M1 41,328.00 1,968.00 5,904.00 49,200.00 7,000,963.20 333,379.20 1,000,137.60 8,334,480.00 Sika
- - - - -
Total I 349,620,598.48
III. STEEL WORK - - - - -
1 Steel plate 9 Thk. ASTM A-36 2,492.64 Kg 26,000.00 2,000.00 9,000.00 37,000.00 64,808,754.91 4,985,288.84 22,433,799.78 92,227,843.52 Include Fabrication, Sand Blasting and
Instalation
Include Fabrication, Sand Blasting and
2 Steel plate 16 Thk. ASTM A-36 77.57 Kg 26,000.00 2,000.00 9,000.00 37,000.00 2,016,878.50 155,144.50 698,150.25 2,870,173.25 Instalation
3 Steel plate 22 Thk. ASTM A-36 481.89 Kg 26,000.00 2,000.00 9,000.00 37,000.00 12,529,061.55 963,773.97 4,336,982.84 17,829,818.35 Include Fabrication, Sand Blasting and
Instalation
4 Steel plate 25 Thk. ASTM A-36 325.46 Kg 26,000.00 2,000.00 9,000.00 37,000.00 8,461,988.45 650,922.19 2,929,149.85 12,042,060.49 Include Fabrication, Sand Blasting and
Instalation
5 WF-200x100x5.5x8 ASTM A-36 3,144.36 Kg 26,000.00 2,000.00 9,000.00 37,000.00 81,753,423.57 6,288,724.89 28,299,262.01 116,341,410.47 Include Fabrication, Sand Blasting and
Instalation
Include Fabrication, Sand Blasting and
6 WF-250x125x6x9 ASTM A-36 2,291.31 Kg 26,000.00 2,000.00 9,000.00 37,000.00 59,574,081.84 4,582,621.68 20,621,797.56 84,778,501.08 Instalation
7 WF-400x200x8x13 ASTM A-36 5,904.36 Kg 26,000.00 2,000.00 9,000.00 37,000.00 153,513,360.00 11,808,720.00 53,139,240.00 218,461,320.00 Include Fabrication, Sand Blasting and
Instalation
Include Fabrication, Sand Blasting and
8 UNP-150x75x6.5x10 ASTM A-36 796.27 Kg 26,000.00 2,000.00 9,000.00 37,000.00 20,703,009.60 1,592,539.20 7,166,426.40 29,461,975.20 Instalation
9 CNP-150x65x20x3.2 ASTM A-36 3,971.28 Kg 26,000.00 2,000.00 9,000.00 37,000.00 103,253,369.22 7,942,566.86 35,741,550.88 146,937,486.97 Include Fabrication, Sand Blasting and
Instalation
Include Fabrication, Sand Blasting and
10 L-40x40x4 ASTM A-36 701.47 Kg 26,000.00 2,000.00 9,000.00 37,000.00 18,238,129.00 1,402,933.00 6,313,198.50 25,954,260.50 Instalation
11 L-75x75x6 ASTM A-36 355.64 Kg 26,000.00 2,000.00 9,000.00 37,000.00 9,246,649.23 711,280.71 3,200,763.20 13,158,693.14 Include Fabrication, Sand Blasting and
Instalation
12 Steel Painting Include sand blasting 876.04 M2 11,650.00 890.00 4,460.00 17,000.00 10,205,862.27 779,675.32 3,907,136.97 14,892,674.56 Blue colour, PLN vendor list Jotun or Hempel
13 M8 O.S. Bolt HTB A325, Grade B 173.00 Pcs 11,900.00 850.00 4,250.00 17,000.00 2,058,700.00 147,050.00 735,250.00 2,941,000.00
14 M16 O.S. Bolt HTB A325, Grade B 200.00 Pcs 20,650.00 1,475.00 7,375.00 29,500.00 4,130,000.00 295,000.00 1,475,000.00 5,900,000.00
15 M16 H.S. Bolt HTB A325, Grade B 131.00 Pcs 20,650.00 1,475.00 7,375.00 29,500.00 2,705,150.00 193,225.00 966,125.00 3,864,500.00
Page 12 of 23
BILL OF QUANTITIES AND PRICES (FINAL)
PACKAGE OF WORK : WAREHOUSE BUILDING AND FOUNDATION Status Date 23-Mar-21
LOCATION : ALOR Rev 1
PROJECT NO. :
SUBCONTRAKTOR :
UNIT PRICE TOTAL PRICE
NO DESCRIPTION SPECIFICATION QTY UNIT Equipment & Tool ( TOTAL PRICE REMARKS
Material ( a ) b) Labour ( c ) Total (a+b+c) Material Equipment & Tool Labour
16 M20 O.S. Bolt HTB A325, Grade B 307.00 Pcs 27,860.00 1,990.00 9,950.00 39,800.00 8,553,020.00 610,930.00 3,054,650.00 12,218,600.00
17 M20 H.S. Bolt HTB A325, Grade B 502.00 Pcs 27,860.00 1,990.00 9,950.00 39,800.00 13,985,720.00 998,980.00 4,994,900.00 19,979,600.00
18 M24 Anchor Bolt PJTN=150 L=750 ASTM A307, Grade B 76.00 Pcs 137,900.00 9,850.00 49,250.00 197,000.00 10,480,400.00 748,600.00 3,743,000.00 14,972,000.00
19 M24 Anchor Bolt PJTN=70 L=440 ASTM A307, Grade B 5.00 Pcs 137,900.00 9,850.00 49,250.00 197,000.00 689,500.00 49,250.00 246,250.00 985,000.00
Grade SR 24/JIS G 3112, Nut&Washer :
20 Wind Bracing dia. 16 Round Bar Grade B ASTM A307 21.00 Set 253,120.00 18,080.00 90,400.00 361,600.00 5,315,520.00 379,680.00 1,898,400.00 7,593,600.00
21 Sagrod, dia. 12 Round Bar Grade SR 24/JIS G 3112, Nut&Washer : 147.00 Set 124,110.00 8,865.00 44,325.00 177,300.00 18,244,170.00 1,303,155.00 6,515,775.00 26,063,100.00
Grade B ASTM A307
- - - - -
Total III 869,473,617.53
TOTAL I + II + III 1,568,141,321.34
B PEKERJAAN PERSIAPAN
I. PEKERJAAN PERSIAPAN 1.00 Ls 42,299,469.97
GRAND TOTAL 1,610,440,791.32
Page 13 of 23
BILL OF QUANTITIES AND PRICES (FINAL)
PACKAGE OF WORK : EXHAUST GAS STACK AND FOUNDATION Status Date 23-Mar-21
LOCATION : ALOR Rev 1
PROJECT NO. :
SUBCONTRAKTOR :
UNIT PRICE TOTAL PRICE
NO DESCRIPTION SPECIFICATION QTY UNIT Material Equipment & Tool Labour UNIT PRICE Material Equipment & Tool Labour TOTAL PRICE REMARKS
I. ARCHITECTURAL WORK - - - - -
- - - - -
Total I -
II. CONCRETE WORK - - - - -
1 Cutting Pile 18.00 nos - 21,000.00 154,000.00 175,000.00 - 378,000.00 2,772,000.00 3,150,000.00
2 Excavation 168.75 m3 - 22,200.00 14,800.00 37,000.00 - 3,746,250.00 2,497,500.00 6,243,750.00
3 Backfill With Compacted 129.13 m3 - 4,212.00 11,388.00 15,600.00 - 543,878.71 1,470,486.89 2,014,365.60
4 Disposal 39.62 m3 - 5,000.00 21,000.00 26,000.00 - 198,120.00 832,104.00 1,030,224.00
5 Compacted Sub Grade 75.00 m2 - 4,212.00 11,388.00 15,600.00 - 315,900.00 854,100.00 1,170,000.00
6 Lean Concrete Ready Mix Concrete With Cement Type I fc' 3.17 m3 743,822.00 18,142.00 145,136.00 907,100.00 2,360,891.03 57,582.71 460,661.66 2,879,135.40
= 15 Mpa
7 Concrete fc'25 Sub Structure Ready Mix Concrete With Cement Type I 43.36 m3 949,560.00 23,160.00 185,280.00 1,158,000.00 41,174,820.72 1,004,263.92 8,034,111.36 50,213,196.00
8 Concrete fc'25 Upper Structure Ready Mix Concrete With Cement Type I 1.73 m3 949,560.00 23,160.00 185,280.00 1,158,000.00 1,640,839.68 40,020.48 320,163.84 2,001,024.00
9 Formwork Use Plywood t = 9 mm, incld frame 90.00 m2 138,600.00 6,600.00 19,800.00 165,000.00 12,474,000.00 594,000.00 1,782,000.00 14,850,000.00
SNI 07-2052-2002 BJTP 40 OR ASTM A615
10 Deformed Bar dia.10mm 1.05 ton 11,340,000.00 540,000.00 1,620,000.00 13,500,000.00 11,935,531.84 568,358.66 1,705,075.98 14,208,966.48
GRADE 60 fy = 4000 kg/cm2
11 Deformed Bar dia.16mm SNI 07-2052-2002 BJTP 40 OR ASTM A615 0.32 ton 11,340,000.00 540,000.00 1,620,000.00 13,500,000.00 3,677,623.03 175,124.91 525,374.72 4,378,122.66
GRADE 60 fy = 4000 kg/cm2
12 Deformed Bar dia.19mm SNI 07-2052-2002 BJTP 40 OR ASTM A615 3.16 ton 11,340,000.00 540,000.00 1,620,000.00 13,500,000.00 35,791,796.08 1,704,371.24 5,113,113.73 42,609,281.05
GRADE 60 fy = 4000 kg/cm2
13 Grouting Non Shrink Min Compressive Strength 35 Mpa at 7 Day 0.11 m3 7,234,668.00 344,508.00 1,033,524.00 8,612,700.00 781,344.14 37,206.86 111,620.59 930,171.60
- - - - -
Total II 145,678,236.78
III. STEEL WORK - - - - -
1 Steel plate 9 Thk. ASTM A-36 318.44 kg 26,000.00 2,000.00 9,000.00 37,000.00 8,279,407.94 636,877.53 2,865,948.90 11,782,234.37 Include Fabrication, Sand Blasting and Instalation
2 Steel plate 12 Thk. ASTM A-36 7,087.50 kg 26,000.00 2,000.00 9,000.00 37,000.00 184,275,012.97 14,175,001.00 63,787,504.49 262,237,518.46 Include Fabrication, Sand Blasting and Instalation
3 Steel plate 25 Thk. ASTM A-36 436.19 kg 26,000.00 2,000.00 9,000.00 37,000.00 11,341,020.60 872,386.20 3,925,737.90 16,139,144.70 Include Fabrication, Sand Blasting and Instalation
4 HB-200x200x8x12 ASTM A-36 26,812.20 kg 26,000.00 2,000.00 9,000.00 37,000.00 697,117,222.40 53,624,401.72 241,309,807.75 992,051,431.88 Include Fabrication, Sand Blasting and Instalation
5 UNP-150x75x6.5x10 ASTM A-36 9,434.53 kg 26,000.00 2,000.00 9,000.00 37,000.00 245,297,834.45 18,869,064.19 84,910,788.85 349,077,687.49 Include Fabrication, Sand Blasting and Instalation
6 L-75x75x6 ASTM A-36 137.32 kg 26,000.00 2,000.00 9,000.00 37,000.00 3,570,277.60 274,636.74 1,235,865.32 5,080,779.66 Include Fabrication, Sand Blasting and Instalation
7 Steel Painting Include sand blasting 1,103.88 m2 11,650.00 890.00 4,460.00 17,000.00 12,860,231.00 982,455.42 4,923,315.90 18,766,002.31 Blue colour, PLN vendor list Jotun or Hempel
8 M14 H.S. Bolt HTB A325, Grade B 64.00 pcs - - - - -
9 M20 H.S. Bolt HTB A325, Grade B 3,328.00 pcs 28,770.00 2,055.00 10,275.00 41,100.00 95,746,560.00 6,839,040.00 34,195,200.00 136,780,800.00
10 M25 Anchor Bolt ASTM A307, Grade B 51.00 pcs 143,570.00 10,255.00 51,275.00 205,100.00 7,322,070.00 523,005.00 2,615,025.00 10,460,100.00
- - - - -
Total III 1,802,375,698.87
TOTAL I + II + III 1,948,053,935.65
B PEKERJAAN PERSIAPAN
I. PEKERJAAN PERSIAPAN 1.00 Ls 5,736,668.23
GRAND TOTAL 1,953,790,603.88
Page 14 of 23
BILL OF QUANTITIES AND PRICES (FINAL)
PACKAGE OF WORK : POWER GENERATOR ENGINE FOUNDATION Status Date 23-Mar-21
LOCATION : ALOR Rev 1
PROJECT NO. :
SUBCONTRAKTOR :
UNIT PRICE TOTAL PRICE
NO DESCRIPTION SPECIFICATION QTY UNIT Equipment & Tool ( TOTAL PRICE REMARKS
Material ( a ) Labour ( c ) Total (a+b+c) Material Equipment & Tool Labour
b)
I. ARCHITECTURAL WORK
- - - - -
Total I -
II. CONCRETE WORK - - - - -
1 Cutting Pile 51.00 Nos - 21,000.00 154,000.00 175,000.00 - 1,071,000.00 7,854,000.00 8,925,000.00
2 Excavation 297.00 M3 - 22,200.00 14,800.00 37,000.00 - 6,593,400.00 4,395,600.00 10,989,000.00
3 Backfill With Compacted 40.11 M3 - 4,050.00 10,950.00 15,000.00 - 162,457.65 439,237.35 601,695.00
4 Disposal 256.89 M3 - 5,000.00 21,000.00 26,000.00 - 1,284,435.00 5,394,627.00 6,679,062.00
5 Compacted Sub Grade 180.00 M2 - 4,131.00 11,169.00 15,300.00 - 743,580.00 2,010,420.00 2,754,000.00
6 Compacted sand 16.01 M3 12,800.00 800.00 2,400.00 16,000.00 204,902.40 12,806.40 38,419.20 256,128.00
Ready Mix Concrete With Cement Type I fc' = 15
7 Lean Concrete Mpa 8.00 M3 770,800.00 18,800.00 150,400.00 940,000.00 6,169,483.20 150,475.20 1,203,801.60 7,523,760.00
8 Concrete fc'30 Sub Structure Ready Mix Concrete With Cement Type I 294.98 M3 984,000.00 24,000.00 192,000.00 1,200,000.00 290,255,400.00 7,079,400.00 56,635,200.00 353,970,000.00
9 Formwork Use Plywood t = 9 mm, incld frame 182.40 M2 138,600.00 6,600.00 19,800.00 165,000.00 25,280,640.00 1,203,840.00 3,611,520.00 30,096,000.00
10 Deformed Bar dia.13mm SNI 07-2052-2002 BJTP 40 OR ASTM A615 GRADE 2.34 Ton 11,256,000.00 536,000.00 1,608,000.00 13,400,000.00 26,337,354.30 1,254,159.73 3,762,479.19 31,353,993.22
60 fy = 4000 kg/cm2
SNI 07-2052-2002 BJTP 40 OR ASTM A615 GRADE
11 Deformed Bar dia.25mm 40.83 Ton 11,256,000.00 536,000.00 1,608,000.00 13,400,000.00 459,553,236.91 21,883,487.47 65,650,462.42 547,087,186.80
60 fy = 4000 kg/cm2
12 Grouting Non Shrink Min Compressive Strength 35 Mpa at 7 Day 0.66 M3 7,308,000.00 348,000.00 1,044,000.00 8,700,000.00 4,788,201.60 228,009.60 684,028.80 5,700,240.00
- - - - -
Total II 1,005,936,065.02
III. STEEL WORK - - - - -
- - - - -
Total III -
TOTAL I + II + III 1,005,936,065.02
B PEKERJAAN PERSIAPAN
I. PEKERJAAN PERSIAPAN 1.00 Ls 9,758,187.00
GRAND TOTAL 1,015,694,252.02
Page 15 of 23
BILL OF QUANTITIES AND PRICES (FINAL)
PACKAGE OF WORK : COOLING RADIATOR FOUNDATION Status Date 23-Mar-21
LOCATION : ALOR Rev 1
PROJECT NO. :
SUBCONTRAKTOR :
UNIT PRICE TOTAL PRICE
NO DESCRIPTION SPECIFICATION QTY UNIT Equioment & Tool ( TOTAL PRICE REMARKS
Material ( a ) Labour ( c ) Total (a+b+c) Material Equioment & Tool Labour
b)
I. ARCHITECTURAL WORK
- - - - -
Total I -
II. CONCRETE WORK - - - - -
1 Cutting Pile 9.00 nos 21,000.00 154,000.00 175,000.00 - 189,000.00 1,386,000.00 1,575,000.00
2 Excavation 83.44 m3 - 2,820.00 32,430.00 35,250.00 - 235,297.98 2,705,926.77 2,941,224.75
3 Backfill With Compacted 5.90 m3 - 1,800.00 13,200.00 15,000.00 - 10,616.40 77,853.60 88,470.00
4 Disposal 77.54 m3 5,000.00 21,000.00 26,000.00 - 387,705.00 1,628,361.00 2,016,066.00
5 Compacted Sub Grade 185.42 m2 - 4,050.00 10,950.00 15,000.00 - 750,951.00 2,030,349.00 2,781,300.00
Ready Mix Concrete With Cement Type I
6 Lean Concrete fc' = 15 Mpa 8.73 m3 733,320.00 34,920.00 104,760.00 873,000.00 6,404,083.56 304,956.36 914,869.08 7,623,909.00
7 Concrete fc'30 Sub Structure Ready Mix Concrete With Cement Type I 87.59 m3 984,000.00 24,000.00 192,000.00 1,200,000.00 86,192,496.00 2,102,256.00 16,818,048.00 105,112,800.00
8 Formwork Use Plywood t = 9 mm, incld frame 42.14 m2 136,500.00 6,500.00 19,500.00 162,500.00 5,752,110.00 273,910.00 821,730.00 6,847,750.00
9 Deformed Bar dia.10mm SNI 07-2052-2002 BJTP 40 OR ASTM A615 0.15 ton 10,920,000.00 520,000.00 1,560,000.00 13,000,000.00 1,659,925.61 79,044.08 237,132.23 1,976,101.92
GRADE 60 fy = 4000 kg/cm2
SNI 07-2052-2002 BJTP 40 OR ASTM A615
10 Deformed Bar dia.16mm 6.69 ton 10,920,000.00 520,000.00 1,560,000.00 13,000,000.00 73,035,598.55 3,477,885.65 10,433,656.94 86,947,141.13
GRADE 60 fy = 4000 kg/cm2
11 Grouting Non Shrink Min Compressive Strength 35 Mpa at 7 0.13 m3 6,959,400.00 331,400.00 994,200.00 8,285,000.00 918,640.80 43,744.80 131,234.40 1,093,620.00
Day
- - - - -
Total II 219,003,382.80
III. STEEL WORK - - - - -
- - - - -
Total III -
TOTAL I + II + III 219,003,382.80
B PEKERJAAN PERSIAPAN
I. PEKERJAAN PERSIAPAN 1.00 Ls 708,697.80
GRAND TOTAL 219,712,080.60
BILL OF QUANTITIES AND PRICES (FINAL)
PACKAGE OF WORK : BUND WALL D.O TANK AREA Status Date 23-Mar-21
LOCATION : ALOR Rev 1
PROJECT NO. :
SUBCONTRAKTOR :
UNIT PRICE TOTAL PRICE
NO DESCRIPTION SPECIFICATION QTY UNIT Equioment & Tool ( TOTAL PRICE REMARKS
Material ( a ) Labour ( c ) Total (a+b+c) Material Equioment & Tool Labour
b)
I. ARCHITECTURAL WORK - - - - -
- - - - -
Total I -
II. CONCRETE WORK - - - - -
1 Excavation 256.19 m3 - 2,848.00 32,752.00 35,600.00 - 729,636.52 8,390,820.04 9,120,456.56
2 Backfill With Compacted 184.21 m3 - 1,800.00 13,200.00 15,000.00 - 331,581.60 2,431,598.40 2,763,180.00
3 Disposal 71.98 m3 - 5,000.00 21,000.00 26,000.00 - 359,903.00 1,511,592.60 1,871,495.60
4 Compacted Sub Grade 1,381.76 m2 - 4,050.00 10,950.00 15,000.00 - 5,596,128.00 15,130,272.00 20,726,400.00
5 Plastic Sheet 1,196.00 m2 10,286.00 139.00 3,475.00 13,900.00 12,302,056.00 166,244.00 4,156,100.00 16,624,400.00
6 Lean Concrete Ready Mix Concrete With Cement Type I fc' = 14.31 m3 649,128.00 8,772.00 219,300.00 877,200.00 9,288,762.03 125,523.81 3,138,095.28 12,552,381.12
15 Mpa
7 Concrete fc'25 Upper Structure Ready Mix Concrete With Cement Type I 264.72 m3 828,726.00 11,199.00 279,975.00 1,119,900.00 219,382,004.17 2,964,621.68 74,115,541.95 296,462,167.80
8 Formwork Use Plywood t = 9 mm, incld frame 973.77 m2 130,640.00 8,165.00 24,495.00 163,300.00 127,213,312.80 7,950,832.05 23,852,496.15 159,016,641.00
9 Deformed Bar dia.10mm SNI 07-2052-2002 BJTP 40 OR ASTM A615 0.06 ton 10,713,874.00 261,314.00 2,090,512.00 13,065,700.00 602,329.88 14,690.97 117,527.78 734,548.64
GRADE 60 fy = 4000 kg/cm2
10 Deformed Bar dia.13mm SNI 07-2052-2002 BJTP 40 OR ASTM A615 21.85 ton 10,713,874.00 261,314.00 2,090,512.00 13,065,700.00 234,129,680.59 5,710,480.01 45,683,840.12 285,524,000.72
GRADE 60 fy = 4000 kg/cm2
11 Wiremesh M6-150 SR 24, Grade U-50 1,296.97 m2 21,812.00 532.00 4,256.00 26,600.00 28,289,553.26 689,989.10 5,519,912.83 34,499,455.20
12 Grouting Non Shrink Min Compressive Strength 35 Mpa at 7 Day 0.05 m3 5,830,580.00 832,940.00 1,665,880.00 8,329,400.00 293,861.23 41,980.18 83,960.35 419,801.76
13 Sealant compound Polymeric asphal base, ASTM D3405-97 220.14 m1 39,648.00 1,888.00 5,664.00 47,200.00 8,728,031.42 415,620.54 1,246,861.63 10,390,513.60
14 Steel Trowel Finish 1,196.00 m2 15,624.00 744.00 2,232.00 18,600.00 18,686,304.00 889,824.00 2,669,472.00 22,245,600.00
15 UNP-200x75x8.5x11.5 ASTM A-36 536.22 kg 26,000.00 2,000.00 9,000.00 37,000.00 13,941,749.49 1,072,442.27 4,825,990.21 19,840,181.97 Include Fabrication, Sand Blasting and
Instalation
16 Stairtreads Grating, 32mm Thk. Hot dip galvanized WA 405/1, Hot dip 7.52 m2 14,784.00 704.00 2,112.00 17,600.00 111,175.68 5,294.08 15,882.24 132,352.00 Webforge
galvanized WA 756/1
17 Steel plate 12 Thk. ASTM A-36 0.36 kg 26,000.00 2,000.00 9,000.00 37,000.00 9,360.00 720.00 3,240.00 13,320.00 Include Fabrication, Sand Blasting and
Instalation
18 Steel plate 3 Thk. ASTM A-36 1.60 kg 26,000.00 2,000.00 9,000.00 37,000.00 41,600.00 3,200.00 14,400.00 59,200.00 Include Fabrication, Sand Blasting and
Instalation
19 M16 Anchor Bolt, PJTN 60, Length=400 ASTM A307, Grade B 8.00 pcs 132,720.00 6,320.00 18,960.00 158,000.00 1,061,760.00 50,560.00 151,680.00 1,264,000.00
20 Pipe Drainage dia. 6" to Sump Pit By Mechanical - m - - - - - - - -
21 Valve 6" By Mechanical - pcs - - - - - - - -
- - - - -
Total II 894,260,095.96
III. STEEL WORK - - - - -
- - - - -
Total III -
TOTAL I + II + III TOTAL I + II + III 894,260,095.96
B PEKERJAAN PERSIAPAN
I. PEKERJAAN PERSIAPAN 1.00 Ls 919,994.99
GRAND TOTAL 895,180,090.95
Page 17 of 23
BILL OF QUANTITIES AND PRICES (FINAL)
PACKAGE OF WORK : WATER TANK TOWER & FOUNDATION (Water Reservoir) Status Date 23-Mar-21
LOCATION : ALOR Rev 1
PROJECT NO. :
SUBCONTRAKTOR :
UNIT PRICE TOTAL PRICE
NO DESCRIPTION SPECIFICATION QTY UNIT Equioment & Tool ( TOTAL PRICE REMARKS
Material ( a ) Labour ( c ) Total (a+b+c) Material Equioment & Tool Labour
b)
I. ARCHITECTURAL WORK - - - - -
- - - - -
Total I -
II. CONCRETE WORK - - - - -
1 Excavation 77.68 m3 - 2,840.00 32,660.00 35,500.00 - 220,618.30 2,537,110.45 2,757,728.75
2 Backfill With Compacted 62.33 m3 - 1,800.00 13,200.00 15,000.00 - 112,185.00 822,690.00 934,875.00
3 Disposal 15.36 m3 5,000.00 21,000.00 26,000.00 - 76,787.50 322,507.50 399,295.00
4 Compacted Sub Grade 95.65 m2 - 4,050.00 10,950.00 15,000.00 - 387,382.50 1,047,367.50 1,434,750.00
5 Lean Concrete Ready Mix Concrete With Cement Type I fc' = 2.62 m3 - 235,548.00 636,852.00 872,400.00 - 617,724.63 1,670,144.37 2,287,869.00
15 Mpa
6 Concrete fc'25 Sub Structure Ready Mix Concrete With Cement Type I 12.74 m3 957,600.00 45,600.00 136,800.00 1,140,000.00 12,195,036.00 580,716.00 1,742,148.00 14,517,900.00
7 Concrete fc'25 Upper Structure Ready Mix Concrete With Cement Type I 2.03 m3 957,600.00 45,600.00 136,800.00 1,140,000.00 1,939,140.00 92,340.00 277,020.00 2,308,500.00
8 Formwork Use Plywood t = 9 mm, incld frame 84.00 m2 136,416.00 6,496.00 19,488.00 162,400.00 11,458,944.00 545,664.00 1,636,992.00 13,641,600.00
SNI 07-2052-2002 BJTP 40 OR ASTM A615
9 Deformed Bar dia.10mm GRADE 60 fy = 4000 kg/cm2 0.53 ton 11,172,000.00 532,000.00 1,596,000.00 13,300,000.00 5,925,872.70 282,184.41 846,553.24 7,054,610.35
11 Deformed Bar dia.16mm SNI 07-2052-2002 BJTP 40 OR ASTM A615 1.15 ton 11,172,000.00 532,000.00 1,596,000.00 13,300,000.00 12,867,099.44 612,719.02 1,838,157.06 15,317,975.52
GRADE 60 fy = 4000 kg/cm2
12 Grouting Non Shrink Min Compressive Strength 35 Mpa at 7 Day 0.06 m3 6,957,216.00 331,296.00 993,888.00 8,282,400.00 391,343.40 18,635.40 55,906.20 465,885.00
- - - - -
Total II 75,962,670.85
III. STEEL WORK - - - - -
Include Fabrication, Sand
1 Steel plate 6 Thk. ASTM A-36 1,545.47 kg 26,000.00 2,000.00 9,000.00 37,000.00 40,182,187.50 3,090,937.50 13,909,218.75 57,182,343.75
Blasting and Instalation
Include Fabrication, Sand
2 Steel plate 12 Thk. ASTM A-36 79.13 kg 26,000.00 2,000.00 9,000.00 37,000.00 2,057,328.00 158,256.00 712,152.00 2,927,736.00
Blasting and Instalation
3 L-40x40x4 ASTM A-36 727.10 kg 26,000.00 2,000.00 9,000.00 37,000.00 18,904,485.60 1,454,191.20 6,543,860.40 26,902,537.20 Include Fabrication, Sand
Blasting and Instalation
Include Fabrication, Sand
4 L-60x60x5 ASTM A-36 1,681.68 kg 26,000.00 2,000.00 9,000.00 37,000.00 43,723,680.00 3,363,360.00 15,135,120.00 62,222,160.00 Blasting and Instalation
8 M16 Anchor Bolt ASTM A307, Grade B 84.00 pcs 88,410.00 6,315.00 31,575.00 126,300.00 7,426,440.00 530,460.00 2,652,300.00 10,609,200.00
- - - - -
Total III 183,521,649.97
TOTAL I + II + III 259,484,320.82
B PEKERJAAN PERSIAPAN
I. PEKERJAAN PERSIAPAN 1.00 Ls 1,614,532.26
GRAND TOTAL 261,098,853.08
Page 18 of 23
BILL OF QUANTITIES AND PRICES (FINAL)
PACKAGE OF WORK : ROAD AND PAVEMENT (INCLUDE DRAINAGE) Status Date 23-Mar-21
LOCATION : ALOR Rev 1
PROJECT NO. :
PROJECT :
SUBCONTRAKTOR :
UNIT PRICE TOTAL PRICE
NO DESCRIPTION SPECIFICATION QTY UNIT Equioment & Tool ( TOTAL PRICE REMARKS
Material ( a ) b) Labour ( c ) Total (a+b+c) Material Equioment & Tool Labour
I. ARCHITECTURAL WORK - - - - -
- - - - -
Total I -
II. CONCRETE WORK - - - - -
1 Excavation 4,111.06 m3 22,200.00 14,800.00 37,000.00 - 91,265,598.46 60,843,732.31 152,109,330.76
2 Backfill With Compacted 916.67 m3 4,320.00 11,680.00 16,000.00 - 3,959,995.27 10,706,653.86 14,666,649.13
3 Disposal 3,184.16 m3 5,000.00 21,000.00 26,000.00 - 15,920,817.12 66,867,431.88 82,788,249.00
4 Compacted Sub Grade CBR Min. 6% 8,362.89 m2 4,320.00 11,680.00 16,000.00 - 36,127,679.05 97,678,539.65 133,806,218.70
5 Compacted Subbase CBR Min. 30% 1,216.42 m3 - 230,796.00 624,004.00 854,800.00 - 280,744,909.56 759,051,051.76 1,039,795,961.32
6 Plastic Sheet 5,227.31 m2 11,100.00 150.00 3,750.00 15,000.00 58,023,167.64 784,096.86 19,602,421.50 78,409,686.00
7 Lean Concrete Ready Mix Concrete With Cement Type I fc' = 118.02 m3 770,800.00 18,800.00 150,400.00 940,000.00 90,971,483.24 2,218,816.66 17,750,533.32 110,940,833.22
15 Mpa
8 Concrete fc'25 Sub Structure Ready Mix Concrete With Cement Type I 1,805.17 m3 984,000.00 24,000.00 192,000.00 1,200,000.00 1,776,290,810.59 43,324,166.11 346,593,328.90 2,166,208,305.60
9 Formwork Use Plywood t = 9 mm, incld frame 8,909.96 m2 138,600.00 6,600.00 19,800.00 165,000.00 1,234,920,180.88 58,805,722.90 176,417,168.70 1,470,143,072.48
SNI 07-2052-2002 BJTP 40 OR ASTM A615
10 Deformed Bar dia.10mm GRADE 60 fy = 4000 kg/cm2 52.78 ton 11,340,000.00 540,000.00 1,620,000.00 13,500,000.00 598,507,919.91 28,500,377.14 85,501,131.42 712,509,428.46
11 Deformed Bar dia.13mm SNI 07-2052-2002 BJTP 40 OR ASTM A615 9.74 ton 11,340,000.00 540,000.00 1,620,000.00 13,500,000.00 110,491,758.64 5,261,512.32 15,784,536.95 131,537,807.90
GRADE 60 fy = 4000 kg/cm2
SNI 07-2052-2002 BJTP 40 OR ASTM A615
12 Deformed Bar dia.16mm GRADE 60 fy = 4000 kg/cm2 51.53 ton 11,340,000.00 540,000.00 1,620,000.00 13,500,000.00 584,392,768.36 27,828,227.06 83,484,681.19 695,705,676.62
I. ARCHITECTURAL WORK - - - - -
Concrete Block (Vol.3, Page:21,
1 Brickwall No.:4.4.1.5.1.8) 191.00 M2 38,400.00 16,640.00 72,960.00 128,000.00 7,334,400.00 3,178,240.00 13,935,360.00 24,448,000.00
2 Plaster & Aci (1 :3) 10mm Thk. & lath, Plaster 1PCC : 3 sand tide 319.42 M2 16,500.00 7,150.00 31,350.00 55,000.00 5,270,430.00 2,283,853.00 10,013,817.00 17,568,100.00
3 Interior wall Vinyl Acetate paint finish Acetate paint finish 689.95 M2 25,420.00 620.00 4,960.00 31,000.00 17,538,592.55 427,770.55 3,422,164.40 21,388,527.50 Delux pentalite
9 Seating Closet TOTO, CW421J/SW420JP 2.00 Unit 1,280,000.00 32,000.00 288,000.00 1,600,000.00 2,560,000.00 64,000.00 576,000.00 3,200,000.00
10 Floor drain TOTO, TX 1BV1 6.00 Unit 76,500.00 6,000.00 67,500.00 150,000.00 459,000.00 36,000.00 405,000.00 900,000.00
11 Foucet (kran) TOTO, T 23 BQ 13N 14.00 Unit 361,600.00 9,040.00 81,360.00 452,000.00 5,062,400.00 126,560.00 1,139,040.00 6,328,000.00
12 Stainless Steel Toilet Paper Holder TOTO, TX 703 AESV1 2.00 Unit 185,600.00 4,640.00 41,760.00 232,000.00 371,200.00 9,280.00 83,520.00 464,000.00
13 Clean Out SAN EI, HN 58 Co 4" 2.00 Unit 101,592.00 7,968.00 89,640.00 199,200.00 203,184.00 15,936.00 179,280.00 398,400.00
14 SkimCoat Sika Skim coat 126.88 M2 44,000.00 1,100.00 9,900.00 55,000.00 5,582,720.00 139,568.00 1,256,112.00 6,978,400.00
15 Ceramic Tile Floor (200x200) Un-Gluzed Roman 14.00 M2 66,300.00 5,200.00 58,500.00 130,000.00 928,200.00 72,800.00 819,000.00 1,820,000.00
16 Ceramic Tile Wall (200x250) Glazed Roman 43.20 M2 69,360.00 5,440.00 61,200.00 136,000.00 2,996,352.00 235,008.00 2,643,840.00 5,875,200.00
17 Ceramic Tile Floor (600x600) Glazed Roman 66.00 M2 65,433.00 5,132.00 57,735.00 128,300.00 4,318,578.00 338,712.00 3,810,510.00 8,467,800.00
18 Ceramic Tile Floor (600x600) Un-Glazed Roman 47.00 M2 111,520.00 2,720.00 21,760.00 136,000.00 5,241,440.00 127,840.00 1,022,720.00 6,392,000.00
19 Base plint Glazed Ceramic tile 100x600 Roman 78.00 M 40,800.00 3,200.00 36,000.00 80,000.00 3,182,400.00 249,600.00 2,808,000.00 6,240,000.00
20 Ceiling gybsum board 15mm Thk. Gybsum tile x 1200 (metal furing & C Channel) 170.22 M2 47,787.00 3,748.00 42,165.00 93,700.00 8,134,303.14 637,984.56 7,177,326.30 15,949,614.00
21 Ceiling GRC board 6mm Thk. w/paint 6mm Thk. (metal furing & C Channel) 94.31 M2 20,400.00 1,600.00 18,000.00 40,000.00 1,923,975.00 150,900.00 1,697,625.00 3,772,500.00
22 Roof Drain UPVC dia.4" W/ BracketStrainer 12.00 Nos 60,000.00 1,500.00 13,500.00 75,000.00 720,000.00 18,000.00 162,000.00 900,000.00
23 Downspot UPVC Pipe dia. 4" W/ BracketStrainer 85.20 M 80,000.00 2,000.00 18,000.00 100,000.00 6,816,000.00 170,400.00 1,533,600.00 8,520,000.00
24 Steel Trowel Finish 80.31 M2 16,000.00 400.00 3,600.00 20,000.00 1,285,000.00 32,125.00 289,125.00 1,606,250.00
25 Roof Corrugated Zincalume sheet 0.7mm BMT BlueScope 243.60 M2 261,300.00 23,450.00 50,250.00 335,000.00 63,653,648.95 5,712,506.96 12,241,086.34 81,607,242.24
26 Gutter Plate Galvalum 0.7mm Thk. BlueScope 56.70 M1 234,000.00 21,000.00 45,000.00 300,000.00 13,267,800.00 1,190,700.00 2,551,500.00 17,010,000.00
27 Waterproofing Membrane Waterproofing Membrane w/ 50mm Mortar 17.00 M2 45,900.00 3,600.00 40,500.00 90,000.00 780,300.00 61,200.00 688,500.00 1,530,000.00
Screed, Chicken mesh dia. 2mm
28 Waterproofing Coating Sika BIT @T membranes 17.00 M2 36,900.00 900.00 7,200.00 45,000.00 627,300.00 15,300.00 122,400.00 765,000.00
- - - - -
Total I 273,134,933.74
II. CONCRETE WORK - - - - -
1 Excavation 190.10 M3 - 22,200.00 14,800.00 37,000.00 - 4,220,164.50 2,813,443.00 7,033,607.50
2 Backfill With Compacted 160.11 M3 - 4,320.00 11,680.00 16,000.00 - 691,655.76 1,870,032.24 2,561,688.00
3 Disposal 29.99 M3 - 5,000.00 21,000.00 26,000.00 - 149,960.00 629,832.00 779,792.00
4 Compacted Sub Grade 337.48 M2 - 4,320.00 11,680.00 16,000.00 - 1,457,924.40 3,941,795.60 5,399,720.00
5 Plastic Sheet 163.16 M2 11,100.00 150.00 3,750.00 15,000.00 1,811,048.25 24,473.63 611,840.63 2,447,362.50
6 Compacted sand 12.07 M3 12,800.00 800.00 2,400.00 16,000.00 154,500.80 9,656.30 28,968.90 193,126.00
7 Lean Concrete Ready Mix Concrete With Cement Type I fc' = 4.65 M3 770,800.00 18,800.00 150,400.00 940,000.00 3,587,495.90 87,499.90 699,999.20 4,374,995.00
15 Mpa
8 Concrete fc'25 Sub Structure Ready Mix Concrete With Cement Type I 30.97 M3 984,000.00 24,000.00 192,000.00 1,200,000.00 30,475,956.00 743,316.00 5,946,528.00 37,165,800.00
9 Concrete fc'25 Upper Structure Ready Mix Concrete With Cement Type I 43.97 M3 984,000.00 24,000.00 192,000.00 1,200,000.00 43,262,396.40 1,055,180.40 8,441,443.20 52,759,020.00
Page 20 of 23
BILL OF QUANTITIES AND PRICES (FINAL)
PACKAGE OF WORK : MOSQUE AND FOUNDATION Status Date 23-Mar-21
LOCATION : ALOR Rev
PROJECT NO. :
SUBCONTRAKTOR : PT. MULTI BUANA TECHINDO
UNIT PRICE TOTAL PRICE
NO DESCRIPTION SPECIFICATION QTY UNIT Material Equipment & Tool Labour UNIT PRICE Material Equipment & Tool Labour TOTAL PRICE REMARKS
10 Formwork Use Plywood t = 9 mm, incld frame 470.23 M2 138,600.00 6,600.00 19,800.00 165,000.00 65,173,323.60 3,103,491.60 9,310,474.80 77,587,290.00
SNI 07-2052-2002 BJTP 40 OR ASTM A615
11 Deformed Bar dia.10mm GRADE 60 fy = 4000 kg/cm2 5.25 Ton 11,340,000.00 540,000.00 1,620,000.00 13,500,000.00 59,543,809.06 2,835,419.48 8,506,258.44 70,885,486.98
12 Deformed Bar dia.13mm SNI 07-2052-2002 BJTP 40 OR ASTM A615 2.40 Ton 11,340,000.00 540,000.00 1,620,000.00 13,500,000.00 27,223,576.52 1,296,360.79 3,889,082.36 32,409,019.67
GRADE 60 fy = 4000 kg/cm2
SNI 07-2052-2002 BJTP 40 OR ASTM A615
13 Deformed Bar dia.16mm GRADE 60 fy = 4000 kg/cm2 4.61 Ton 11,340,000.00 540,000.00 1,620,000.00 13,500,000.00 52,308,183.22 2,490,865.87 7,472,597.60 62,271,646.69
14 Sealant compound Polymeric asphal base, ASTM D3405-97 257.70 M1 42,000.00 2,000.00 6,000.00 50,000.00 10,823,400.00 515,400.00 1,546,200.00 12,885,000.00 Sika
- - - - -
Total II 368,753,554.34
III. STEEL WORK - - - - -
1 Steel plate 9 Thk. ASTM A-36 496.56 Kg 26,000.00 2,000.00 9,000.00 37,000.00 12,910,441.43 993,110.88 4,468,998.96 18,372,551.27 Include Fabrication, Sand Blasting and Instalation
2 Steel plate 16 Thk. ASTM A-36 197.82 Kg 26,000.00 2,000.00 9,000.00 37,000.00 5,143,320.00 395,640.00 1,780,380.00 7,319,340.00 Include Fabrication, Sand Blasting and Instalation
3 Steel plate 22 Thk. ASTM A-36 261.12 Kg 26,000.00 2,000.00 9,000.00 37,000.00 6,789,182.40 522,244.80 2,350,101.60 9,661,528.80 Include Fabrication, Sand Blasting and Instalation
4 WF-200x100x5.5x8 ASTM A-36 2,975.72 Kg 26,000.00 2,000.00 9,000.00 37,000.00 77,368,729.78 5,951,440.75 26,781,483.39 110,101,653.92 Include Fabrication, Sand Blasting and Instalation
5 UNP-150x75x6.5x10 ASTM A-36 1,054.62 Kg 26,000.00 2,000.00 9,000.00 37,000.00 27,420,120.00 2,109,240.00 9,491,580.00 39,020,940.00 Include Fabrication, Sand Blasting and Instalation
6 CNP-150x65x20x3.2 ASTM A-36 1,851.76 Kg 26,000.00 2,000.00 9,000.00 37,000.00 48,145,734.00 3,703,518.00 16,665,831.00 68,515,083.00 Include Fabrication, Sand Blasting and Instalation
7 L-40x40x4 ASTM A-36 313.16 Kg 26,000.00 2,000.00 9,000.00 37,000.00 8,142,091.31 626,314.72 2,818,416.22 11,586,822.25 Include Fabrication, Sand Blasting and Instalation
8 Steel Pipe dia. 219.1x8.1 ASTM A-36 454.71 Kg - - - - - Include Fabrication, Sand Blasting and Instalation
9 Steel Painting Include sand blasting 335.02 M2 11,650.00 890.00 4,460.00 17,000.00 3,902,940.19 298,164.53 1,494,172.81 5,695,277.53 Blue colour, PLN vendor list Jotun or Hempel
10 M8 O.S. Bolt HTB A325, Grade B 294.00 Pcs 11,900.00 850.00 4,250.00 17,000.00 3,498,600.00 249,900.00 1,249,500.00 4,998,000.00
11 M16 O.S. Bolt HTB A325, Grade B 287.00 Pcs 22,400.00 1,600.00 8,000.00 32,000.00 6,428,800.00 459,200.00 2,296,000.00 9,184,000.00
12 M16 H.S. Bolt HTB A325, Grade B 51.00 Pcs 22,400.00 1,600.00 8,000.00 32,000.00 1,142,400.00 81,600.00 408,000.00 1,632,000.00
13 M20 H.S. Bolt HTB A325, Grade B 400.00 Pcs 29,400.00 2,100.00 10,500.00 42,000.00 11,760,000.00 840,000.00 4,200,000.00 16,800,000.00
14 M20 Anchor Bolt ASTM A307, Grade B 68.00 Pcs 105,000.00 7,500.00 37,500.00 150,000.00 7,140,000.00 510,000.00 2,550,000.00 10,200,000.00
Grade SR 24/JIS G 3112, Nut&Washer : Grade
15 Sagrod, dia. 12 Round Bar 73.00 Set 126,000.00 9,000.00 45,000.00 180,000.00 9,198,000.00 657,000.00 3,285,000.00 13,140,000.00
B ASTM A307
- - - - -
Total III 326,227,196.77
TOTAL I + II + III 968,115,684.84
Page 21 of 23
RINCIAN PENAWARAN HARGA
Pekerjaan Jasa Pile Dynamic Load Test (PDA Test)
AMOUNT 625,000,000.00
BILL OF QUANTITIES AND PRICES (FINAL)
PACKAGE OF WORK : LAIN-LAIN Status Date 23-Mar-21
LOCATION : ALOR Rev 1
PROJECT NO. :
SUBCONTRAKTOR :
UNIT PRICE TOTAL PRICE
NO DESCRIPTION SPECIFICATION QTY UNIT Equioment & Tool ( TOTAL PRICE REMARKS
Material ( a ) Labour ( c ) Total (a+b+c) Material Equioment & Tool Labour
b)
I. PEMBERSIHAN LAHAN 1 Ls - - - - - - - 17,750,000.00
- - - - -
Total I 17,750,000.00
II. PENYELESAIAN LOKAL 1 LOT - - - - - - - 485,000,000.00
- - - - -
Total II 485,000,000.00
TOTAL I + II 502,750,000.00