PROJECT PROCEDURE

SYSTEM & SUB-SYSTEM


SUBDIVISION
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0003
KARBALA REFINERY PROJECT Rev. 2 Page 1/15
Ref. FEED DOC. No. :

SYSTEM & SUB-SYSTEM SUBDIVISION

PROJECT : KARBALA REFINERY PROJECT

LOCATION : KARBALA, IRAQ

EMPLOYER : STATE COMPANY FOR OIL PROJECTS (SCOP)

2 12 OCT 19 REVISED FOR IFC H.H.BYUN J.B.KIM Y.S.KIM Y.B.IM H.S.HWANG


ISSEUD FOR
1 27 JUN 19 H.H.BYUN J.B.KIM Y.S.KIM Y.B.IM H.S.HWANG
CONSTRUCTION
ISSEUD FOR
0 05 JAN 19 H.H.BYUN J.B.KIM Y.S.KIM Y.B.IM H.S.HWANG
CONSTRUCTION
A 04 NOV 18 ISSUED FOR REVIEW H.H.BYUN J.B.KIM Y.S.KIM Y.B.IM H.S.HWANG

REVD REVD APPRD CONFD


REV. DATE DESCRIPTION PRPD CHKD
(PQM) (PM) (PD) (SCOP)

Joint Venture of Hyundai Engineering & Construction Co., Ltd., GS Engineering & Construction Co., Ltd., SK Engineering

& Construction Co., Ltd., and Hyundai Engineering Co., Ltd.,

Note :

a) Revision bar(vertical line) shall be placed in the right hand margin to indicate where the changes has been made
b) PRPD = Prepared by, CHKD = Checked by, REVD = Reviewed by, APPRD = Approved by, CONFD = Confirmed by
PROJECT PROCEDURE

SYSTEM & SUB-SYSTEM


SUBDIVISION
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0003
KARBALA REFINERY PROJECT Rev. 2 Page 2/15
Ref. FEED DOC. No. :

REVISION HISTORY

Rev Date Description Page

A 04 NOV 18 Initial Issue -


Add the sentence “The purpose of this procedure is to define
0 05 JAN 19 the methodology for performing the split in system and 4
subsystem of the KARBALA REFINERY Project”
Add the sentence “Facilities will be divided in systems and
subsystems with further objective of providing the
0 05 JAN 19 construction team with a sequential mechanical completion 4
schedule and a sequence of pre-commissioning priority by
systems.”
0 05 JAN 19 Change the word 5

0 05 JAN 19 Change the word 7


Add the sentence “which has the highest priority and is to be
0 05 JAN 19 10
commissioned first.”
Add the sentence “In case of two isolation valves, one valve
0 05 JAN 19 10
will be allocated to each SYSTEM/SUBSYSTEM.”
Add the clause” PSV, pressure control valves, blow down
0 05 JAN 19 12
valves, etc.”
0 05 JAN 19 Add the 8.6 Section “Instrument System / Sub-system” 13

0 05 JAN 19 Add the 8.7 Section “Electrical System / Sub-system” 13


Add the Attachment #3 “Karbala Refinery -List of systems
0 05 JAN 19 -
and subsystems”
Revise the 1 Section “hand-over (by UNIT / System / Sub-
1 27 JUN 19 4
system)”
Add the sentence “Process and Non-process System and
1 27 JUN 19 9
Sub-system list can be updated.”
Revise the drawing of 8.6 Section “Instrument system sub-
1 27 JUN 19 13
system”

1 27 JUN 19 Revise the ATTACHMENT #2-1 Summary of Non-process 15


Sub-system for Discipline (Field)

2 12 OCT 19 Revise the Attachment #3 Karbala Refinery List of -


Systems and Sub-systems

2 12 OCT 19 Revise the Attachment ATTACHEMTN #2-1 Summary of -


Non-process Sub-system for Discipline (Field)
PROJECT PROCEDURE

SYSTEM & SUB-SYSTEM


SUBDIVISION
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0003
KARBALA REFINERY PROJECT Rev. 2 Page 3/15
Ref. FEED DOC. No. :

TABLE OF CONTENTS

1. PURPOSE ...................................................................................................................................................4

2. SCOPE ........................................................................................................................................................4

3. DEFINITIONS ..............................................................................................................................................5

4. COMPOSITION OF THE KARBALA REFINERY PLANT .........................................................................5

5. REFERENCE ..............................................................................................................................................6

6. SYSTEM AND SUB-SYSTEM PHILOSOPHY ...........................................................................................7

7. RULE AND GUIDELINES FOR SYSTEM IDENTIFICATION .....................................................................7


7.1 Process System................................................................................................................................... 7
7.2 Non-process System .......................................................................................................................... 8
7.2.1 The numbering sample will be as follows (Non-process of Field) ..............................................8
7.2.2 The numbering sample will be as follows: (Non-process of Building) ........................................9

8. LIMITS OF SUB-SYSTEM ........................................................................................................................10


8.1. General Rule ...............................................................................................................................10
8.2. Package Item ............................................................................................................................... 11
8.3. Heat Exchangers ........................................................................................................................ 11
8.4. Closed Drain system / sub-system ...........................................................................................12
8.5. Flare system / sub-system ........................................................................................................12
8.6. Instrument system / sub-system ..............................................................................................13
8.7. Electrical system / sub-system .................................................................................................13

Attachment #1 SUBPROJECT for UNICCS ..................................................................................................14

Attachment #2 Summary of Non-process Sub-system for Discipline ......................................................14

Attachment #3 Karbala Refinery List of Systems and Sub-systems ........................................................14


PROJECT PROCEDURE

SYSTEM & SUB-SYSTEM


SUBDIVISION
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0003
KARBALA REFINERY PROJECT Rev. 2 Page 4/15
Ref. FEED DOC. No. :

1. PURPOSE

The purpose of this procedure is to define the methodology for performing the split in system and sub-
system of the KARBALA REFINERY Project.
A plant subdivision approach for the project is used to optimize the overall schedule and prioritize the
works according to the pre-commissioning, commissioning and start-up sequence. This facilitates also
ensures a quick and efficient hand-over (by UNIT / System / Sub-system) of the facility after completion
of pre-commissioning, commissioning and start-up.
Facilities will be divided in system and sub-system with further objective of providing the construction
team with a sequential mechanical completion schedule and a sequence of pre-commissioning priority
by systems.

2. SCOPE

The scope of this document is to outline the guidelines for the identification of the system, sub-system
of process, non-process facility to be applied to Karbala Refinery Project.

The Plant Breakdown Structure are:

SYSTEM and SUB-SYSTEM will be managed by UNICCS (Unified Construction to Commissioning


System).
PROJECT PROCEDURE

SYSTEM & SUB-SYSTEM


SUBDIVISION
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0003
KARBALA REFINERY PROJECT Rev. 2 Page 5/15
Ref. FEED DOC. No. :

3. DEFINITIONS

PROJECT means the Karbala Refinery Project

SUBPROJECT means the UNIT No. or WBS+UNIT No.

SYSTEM means a functional grouping of piping, equipment, and instruments, which are logically
related to each other according to the process and which can be isolated from other systems for the
purposes of managing Mechanical Completion, Pre-commissioning, Commissioning, Start-up and
Handover. System of Non-process will be designated as AREA except Building. Building system will
be handed over by number of building.

SUB-SYSTEM means a part of the system that can be completed and commissioned as a separate
system.

ITEM GROUP means a group of the Mechanical equipment, piping, Electrical Circuits, Instrument
Loops and Test Packages that are contained within the project.

ITEM means an Individual tagged items such as Equipment, Pipe lines, Valves, Vessels & Instruments
and may be a part of the item group.

PROCESS is defined and illustrated on a set of marked-up PID’s.

Non-Process are defined as not showing on P&ID such as Electrical (EL), Instrument (IN), Civil (CI),
Steel Structure (SS), HVAC (HV), and Architecture (BLDG).

4. COMPOSITION OF THE KARBALA REFINERY PLANT

The refinery facilities consist of the following units;

Unit No. Description Abbreviation

01 Unit Crude and Vacuum Distillation Unit CDU / VDU


02 Unit Naphtha Hydrotreating Unit NHT
03 Unit Isomerization Unit ISOM
04 Unit Catalytic Reforming Unit CCR
05 Unit Kerosene Hydrodesulfurization Unit KHT
06 Unit Diesel Hydrodesulfurization Unit DHT
07 Unit VGO Hydrotreating Unit VGO HDT
08 Unit Fluid Catalytic Cracking Unit FCC
09 Unit PolyNaphtha Unit PNU
10 Unit Asphalt Blowing Unit ABU
11 Unit LPG Production Unit LPG
13 Unit Hydrogen Production Unit – Train 1 HPU
PROJECT PROCEDURE

SYSTEM & SUB-SYSTEM


SUBDIVISION
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0003
KARBALA REFINERY PROJECT Rev. 2 Page 6/15
Ref. FEED DOC. No. :

14 Unit Hydrogen Production Unit – Train 2 HPU


15 Unit Hydrogen Production unit - Common Parts HPU
16 Unit Gas Sweetening and Amine Regeneration Unit ARU
17 Unit Sour Water Stripper Unit SWS
18 Unit Sulphur Recovery Unit – Train 1 SRU
19 Unit Sulphur Recovery Unit – Train 2 SRU
20 Unit Sulphur Recovery Unit – Common Parts and TGT SRU
30 Unit Raw Water Treatment Unit RWT
31 Unit Fire Water Unit FWU
33 Unit Cooling Water Unit CWU
34 Unit Drinking Water Unit DWU
35 Unit Condensate Collection and Treatment Unit CCT
36 Unit BFW & Steam Generation Unit SGU
37 Unit Power Generation Unit PGU
41 Unit Instrument and Plant Air Unit IPA
42 Unit Nitrogen Generation Unit NGU
43 Unit Caustic Soda Unit CAU
44 Unit Refinery Fuels Unit RFU
45 Unit Natural Gas Receiving Facilities Unit NGU
50 Unit Flare Unit FLA
51 Unit Waste Water Collection and Treatment Plant WWT
52 Unit Tank Farm Unit (Crude, Intermediate, Final) TFU
53 Unit Asphalt Loading ASL
54 Unit Sulphur Solidification and Bagging SSB
58 Unit Refinery Interconnecting Unit RIU
60 Unit River Water Intake Unit RWI
61 Unit Heavy Fuel Oil Pipeline FOP
90 Unit Distribution Depot DPU

5. REFERENCE

a) IONE-AA00-PE-CM-0001 (Pre-commissioning & Commissioning Execution Plan)


b) IONE-AA00-PE-CM-0006 (Pre-commissioning & Commissioning Schedule level-1)
c) IONE-AA00-PE-CM-0007 (UNICCS CONTROL PROCEDURE)
PROJECT PROCEDURE

SYSTEM & SUB-SYSTEM


SUBDIVISION
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0003
KARBALA REFINERY PROJECT Rev. 2 Page 7/15
Ref. FEED DOC. No. :

6. SYSTEM AND SUB-SYSTEM PHILOSOPHY

The delimitation of unit in systems and sub-system of Karbala Refinery Project process units are realized
in the sequential order needed for the Pre-Commissioning, Commissioning and Start Up. In that way the
available resources are prioritized in accordance with this sequence.

General criteria for the system / sub-system division consist in the fact that each system must perform a
specific operational function, with the minimum interference with other systems.
As mentioned before, there is no advantage to divide the whole plant into too many systems when this
is not necessary. Having too many, too small systems, can lead to more adverse effects than advantages.
The split has to be undertaken when there is a real advantage for the physical implementation of the
Pre-Commissioning and Commissioning activities.

The sub-system shall be defined so as to be as independent as possible, not too small, but of
manageable size, and adapted to the requirement of the work sequence.

In general, the system / sub-system shall be considered as independent as possible for completion
purposes, for the case of Process and Utilities facilities, the subdivision of the Plant into sub-system shall
correspond to the general principles exposed in the following paragraph.

A system comprises mechanical equipment, piping and in-line instrumentation within the processing
facilities. Typically the system could include:

 A reactor with its associated facilities.

 A distillation column with its associated overhead condenser, reflux drum and pump, re-boiler,
bottoms pump and piping.

 A compressor and its auxiliary equipment and piping.

The main advantage of the System and Sub-system partition is related with the schedule optimization
and control of completion activities. The basic principles of these activities are:

 Define, organise, prepare, carry out and report all Pre-commissioning and Commissioning activities
by System and Sub-system.

 The Completion activities progress will be reported with a partial overlapping between systems and
Sub-system, according to the Start-up sequence.

This system and sub-system division will be developed on updated PIDs and the index color coding will
be used to differentiate sub-system among them. The number of system and sub-system are as below
and numbering rule is defined in the Section 7 hereunder.

7. RULE AND GUIDELINES FOR SYSTEM IDENTIFICATION

7.1 Process System


Process Systems covers process, utility and offsite systems, including static equipment, rotating
equipment and machineries, and their drivers, tanks, piping, in-line instruments and packaged
PROJECT PROCEDURE

SYSTEM & SUB-SYSTEM


SUBDIVISION
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0003
KARBALA REFINERY PROJECT Rev. 2 Page 8/15
Ref. FEED DOC. No. :

equipment. The process Systems shall be generally identified on the Piping & Instrument Diagram
(P&ID’s).
The numbering of process system will be as follows;

7.2 Non-process System


Non-process (Non P&ID) facilities within the Plant, such as substations, structures and buildings
shall be similarly identified as System(s) for the purpose of completion acceptance and making
them ready for use. Non-process System include as follows;
 Buildings
 Civil
 Instruments
 Etc.

7.2.1 The numbering sample will be as follows (Non-process of Field)

1. Electrical sub-system
1C01-EL-EF&A (Fire alarm of 1C01 Area)
2. Civil sub-system
1C01-CI-PITR (Pipe trench of 1C01 Area)
PROJECT PROCEDURE

SYSTEM & SUB-SYSTEM


SUBDIVISION
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0003
KARBALA REFINERY PROJECT Rev. 2 Page 9/15
Ref. FEED DOC. No. :

3. Steel Structure sub-system


1C01-SS-SSEQ (Equipment Structure of 1C01 Area)
4. Instrument sub-system
1C01-IN-ICAB (Cable Tray of 1C01 Area)
 Sub-system type is included in Attachment 2-1

7.2.2 The numbering sample will be as follows: (Non-process of Building)

1. Electrical sub-system
B1A-01-EUPS (UPS of B1A-01)
2. Arch. sub-system
B1A-01-BLDG (Building Work of B1A-01)
3. HVAC sub-system
B1A-01-HVCT (HVAC Control System of B1A-01)
4. Instrument sub-system
B1A-01-IPCS (PCS (Control system) of B1A-01)
 Sub-system type is included in Attachment 2-2

 Process and Non-process System and Sub-system list can be updated.


PROJECT PROCEDURE

SYSTEM & SUB-SYSTEM


SUBDIVISION
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0003
KARBALA REFINERY PROJECT Rev. 2 Page 10/15
Ref. FEED DOC. No. :

8. LIMITS OF SUB-SYSTEM

8.1. General Rule


As a general rule, the physical limit of a process or utility or offsite system or sub-system wherever
possible, an isolation valve allocated to the system or sub-system which has the highest priority
and is to be commissioned first. As shown in diagram below for different cases. In case of two
isolation valves, one valve will be allocated to each SYSTEM/SUB-SYSTEM.

Sub-system Sub-system

A process system comprises mechanical equipment, piping, and in-line instrumentation within the
processing facilities. In some cases, the physical limit could be Battery Limit block valves.
Where a blind is necessary, the sub-system limit will be at the most suitable flange. In certain cases
where a facility exists till the tie-in point, the limit will be at that point.
PROJECT PROCEDURE

SYSTEM & SUB-SYSTEM


SUBDIVISION
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0003
KARBALA REFINERY PROJECT Rev. 2 Page 11/15
Ref. FEED DOC. No. :

8.2. Package Item


When the case is a package, it may be assigned as separate sub-system wherever possible and
the physical limit point is as shown in the below diagram. If there is valve or flange on the boundary
limits, the boundary limit itself will become the physical limit point.

 In Some case, this line(*) can be combined in package sub-system

8.3. Heat Exchangers


When Heat Exchangers require a utility service, such as cooling water, hot oil, steam, etc., to control
the temperature of a Process stream, the Heat Exchanger will be part of the Process system / sub-
system.

CWS

Process sub-system

CW sub-system
CWR
PROJECT PROCEDURE

SYSTEM & SUB-SYSTEM


SUBDIVISION
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0003
KARBALA REFINERY PROJECT Rev. 2 Page 12/15
Ref. FEED DOC. No. :

8.4. Closed Drain system / sub-system


Closed drain sub-system does not include the isolation valves between associated process systems
and closed drain systems as follows.

8.5. Flare system / sub-system


In case of the PSV, pressure control valves, blow down valves, etc. the downstream of flare system
will be the battery limits. Refer the below diagram.
PROJECT PROCEDURE

SYSTEM & SUB-SYSTEM


SUBDIVISION
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0003
KARBALA REFINERY PROJECT Rev. 2 Page 13/15
Ref. FEED DOC. No. :

8.6. Instrument system / sub-system


Process system / sub-system of Instrumentation can be defined by Tagged items such as Loop and
Function test of transmitter, control valve on P&ID. Non-Process system / sub-system of
instrumentation can be defined by Common items such as PCS, JB (Junction Box), Cable Tray, Air
piping.

8.7. Electrical system / sub-system


Motor installation and solo run will be included in process sub-system. Non-process sub-system of
Building include SAT of Electrical equipment such as Switch Gear, Panel, UPS, Etc. and Power
System such as MV, LV Cable, Etc. Non-process of Field sub-system include SAT of Lighting,
Telecommunication system, Fire Alarm system, Heat Tracing, Etc.
PROJECT PROCEDURE

SYSTEM & SUB-SYSTEM


SUBDIVISION
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0003
KARBALA REFINERY PROJECT Rev. 2 Page 14/15
Ref. FEED DOC. No. :

ATTACHMENT LIST

Attachment #1 SUBPROJECT for UNICCS

Attachment #2 Summary of Non-process Sub-system for Discipline

Attachment #3 Karbala Refinery List of Systems and Sub-systems


SUB
PROJECT
SUBPROJECT Description

Attachment #1 SUBPROJECT for UNICCS 1A13


1A14
1A15
HPU-1
HPU-2
HPU Common
7B61 1B02 NHT
1B03 ISOM (PENEX)
7A60 1B04 CCR
1C01 CDU / VDU
Heavy Fuel Oil Pipeline(14" x 23km)
1D05 KHT
1D06 DHT
7B61(P) 1E11 LPG Production
1E09 Poly Naphtha (PNU)
1F08 FCC
Waste Water 1G07 VGO HDT
Point 1H16 Gas Sweetening & ARU
1H17 SWS
5B00 1H18 SRU-1
1H19 SRU-2
1H20 TGTU
Raw Water Pipeline (24" X 35km)
33KV Overhead Transmission Line

Waste Water Pipeline(18" x 35km)

1H44 Refinery Fuel Unit


7A60(E)

1I10 Asphalt Blowing (ABU)


3B37(B) 2A00 Admin. Building (North)
3A31 Fire Water Unit
3C33 1I10 5A53 3A31(B) Control Room Building
6C90 3A35 Condensate Collection and Treatment
5A61
1H18 3A36 BFW & Steam Generation
1H20 3A41 IA & PA Unit
1H19 3A42 N2 Generation Unit
1D06 3A43 Caustic Soda and Sulfuric Acid Unit
4C52(H) 3B37 Power Generation
3B37 5A54 3C33 Cooling Water Unit
1H17 1H44
1H16 5A51 3B37(B) 132KV SUBSTATION
1D05 4A45 Natural Gas Receiving Facilities
4A51 Oily Water and Clean Water Pond
4A52 Tank Farm Unit (Crude)
6A90 4B52 Tank Farm Unit (Intermediate)
5E58 5E58 5E58
7A60(P)

4C52(G) Tank Farm Unit (Component) /GS


3A31(B)
4C52(H) Tank Farm Unit (Component) /HD
4D52 Tank Farm Unit (Final)
1G07 Waste water collection and
5A51
3A35

3A36 1C01 treatment plant Unit


6D90 5A53 Asphalt Loading
5A54 Sulfur Solidification Unit
3A31 5A61 Heavy Fuel Oil Pipeline Unit
1B04 1F08 5B00 Fencing (5B)
2A00 4C52(G) 5C50 Flare unit
4D52 5D30 Raw Water Treatment Unit
3A41
3A42

5D34 Drinking Water Unit


1B02 5D51 Waste Water Treatment unit
1E09
5E58 Refinery Interconnecting Unit
3A43 6A90 Depot Building (South)
1B03 6B00 Fencing (6B)
1E11 6C90 Loading and Dispatching Facilities
1A15 6D90 Tankage and Interconnecting Area
7A60 River Water Intake Unit
Raw Water Pipeline (24" x 33km),
1A13 1A14 7A60(P)
Waste Water Pipeline (18" x 35km)
5C50 7A60(E) 33KV Overhead Transmission Line
6B00 7B61 AL-KHAIRAT POWER STATION
7B61(P) Heavy Fuel Oil Pipeline (14" x 23km)
Crude Oil Pipeline (32" x 1.25km),
7C62
Natural Gas Pipeline (14" x 1.25km)
4A51 4A45 Total 58
(2/2)
5D51

4A52 4B52

5D30
5D34

변형

Existing
Pipiline Crude Oil Pipeline(32" x 1.25km)
Tie-In 7C62
Natural Gas Pipeline(14" x 1.25km)
PROJECT PROCEDURE

SYSTEM & SUB-SYSTEM


SUBDIVISION
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0003
KARBALA REFINERY PROJECT Rev. 2 Page 15/15
Ref. FEED DOC. No. :

ATTACHEMTN #2-1 Summary of Non-process Sub-system for Discipline (Field)

FIELD
DICIPLINE DESCRIPTION SUB-SYSTEM TYPE DESCRIPTION
PACO Paving Concrete
CI CIVIL PAGR Paving Gravel
ROAD Road
EF&A Fire Alarm
ELSP Lighting & Small Power
EGLT Grounding & Lightning
EL ELECTRICAL EPST Power System
ECPR Cathodic Protection
EEHT Electric Heat Tracing
TELE Telecommunication
SSEQ Equipment Structure
SS STEEL STRUCTURE OTST Other Structure
1
PIRK Piperack 1
IN INSTRUMENT IF&G Fire and gas System

ATTACHEMTN #2-2 Summary of Non-process Sub-system for Discipline (BLDG)

BUILDING
DICIPLINE DESCRIPTION SUB-SYSTEM TYPE DESCRIPTION
ELEQ Electrical Equipment
EEDG Emergency Diesel Generator
EUPS UPS
EPST Power System
EL Electrical
EILS Indoor Lighting System
EGLT Grounding & Lightning
TELE Telecomm. System
EF&A Fire Alarm System
HVEQ Equipment & Duct
HVPL Plumbing
HVAC HVAC
HVCT Control System
HVFF FM-200
AR Architecture BLDG Building Work
IN INSTRUMENT IPCS PCS(Control System)
PROCESS SYSTEM & SUB-SYSTEM LIST
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area B U00-FWA BLDG FIREWATER U00-FWA-101 BLDG FIREWATER(UG)
Area B U00-FWA BLDG FIREWATER U00-FWA-102 BLDG FIREWATER(AG)
Area B U00-INA ADMIN BLDG INSTRUMENT AIR U00-INA-101 ADMIN BLDG INSTRUMENT AIR
Area B U00-LPC ADMIN BLDG LP CONDENSATE U00-LPC-101 ADMIN BLDG LP CONDENSATE
Area B U00-LPS ADMIN BLDG LP STEAM U00-LPS-101 ADMIN BLDG LP STEAM
Area B U00-NIT ADMIN BLDG NITROGEN U00-NIT-101 ADMIN BLDG NITROGEN
Area B U00-RWA ADMIN BLDG RAW WATER U00-RWA-101 ADMIN BLDG RAW WATER
Area B U00-SWA ADMIN BLDG SERVICE WATER U00-SWA-101 ADMIN BLDG SERVICE WATER
Area B U00-UTA ADMIN BLDG UTILITY AIR U00-UTA-101 ADMIN BLDG UTILITY AIR
Area B U01-BFW CDU/VDU BOILER FEED WATER U01-BFW-101 CDU/VDU BOILER FEED WATER
Area B U01-CLD CDU/VDU CLOSED DRAIN U01-CLD-101 CDU/VDU CLOSED DRAIN
Area B U01-CND CDU/VDU CLEAN CONDENSATE U01-CND-101 CDU/VDU CLEAN CONDENSATE
Area B U01-CW CDU/VDU COOLING WATER U01-CW-101 CDU/VDU COOLING WATER SUPPLY
Area B U01-CW CDU/VDU COOLING WATER U01-CW-102 CDU/VDU COOLING WATER RETURN
Area B U01-DWA CDU/VDU DEMI WATER U01-DWA-101 CDU/VDU DEMI WATER
Area B U01-FLD CDU/VDU LP FLARE U01-FLD-101 CDU/VDU LP FLARE
Area B U01-FLO CDU/VDU FLUSHING OIL U01-FLO-101 CDU/VDU FLUSHING OIL TO 52-E-001
Area B U01-FLO CDU/VDU FLUSHING OIL U01-FLO-102 CDU/VDU FLUSHING OIL FROM 52-FL-001A/B
Area B U01-FUG CDU/VDU FUEL GAS U01-FUG-101 CDU/VDU FUEL GAS
Area B U01-FUO CDU/VDU FUEL OIL U01-FUO-101 CDU/VDU FUEL OIL SUPPLY
Area B U01-FUO CDU/VDU FUEL OIL U01-FUO-102 CDU/VDU FUEL OIL RETURN
Area B U01-FWA CDU/VDU FIRE WATER NETWORK U01-FWA-101 CDU/VDU FIRE WATER NETWORK(UG)
Area B U01-FWA CDU/VDU FIRE WATER NETWORK U01-FWA-102 CDU/VDU FIRE WATER NETWORK(AG)
Area B U01-HPC CDU/VDU HP CONDENSATE U01-HPC-101 CDU/VDU HP CONDENSATE
Area B U01-HPS CDU/VDU HP STEAM U01-HPS-101 CDU/VDU HP STEAM
Area B U01-INA CDU/VDU INSTRUMENT AIR U01-INA-101 CDU/VDU INSTRUMENT AIR
Area B U01-LPC CDU/VDU LP CONDENSATE U01-LPC-101 CDU/VDU LP CONDENSATE
Area B U01-LPS CDU/VDU LP STEAM U01-LPS-101 CDU/VDU LP STEAM
Area B U01-MBFW CDU/VDU BOILER FEED WATER U01-MBFW-101 CDU/VDU BOILER FEED WATER
Area B U01-MPC CDU/VDU MP CONDENSATE U01-MPC-101 CDU/VDU MP CONDENSATE
Area B U01-MPS CDU/VDU MP STEAM U01-MPS-101 CDU/VDU MP STEAM
Area B U01-NIT CDU/VDU NITROGEN U01-NIT-101 CDU/VDU NITROGEN
Area B U01-OWS CDU/VDU OWS U01-OWS-101 CDU/VDU OWS
Area B U01-P01 CDU/VDU CRUDE PREHEAT SECTION U01-P01-101 CDU/VDU CRUDE DESALTERS AND PREHEATERS
Area B U01-P01 CDU/VDU CRUDE PREHEAT SECTION U01-P01-201 CDU/VDU DESALTER WATER SYSTEM
Area B U01-P02 CDU/VDU CRUDE DISTILATION SECTION U01-P02-101 CDU/VDU CRUDE HEATER
Area B U01-P02 CDU/VDU CRUDE DISTILATION SECTION U01-P02-102 CDU/VDU HEATER DECOKING
Area B U01-P02 CDU/VDU CRUDE DISTILATION SECTION U01-P02-201 CDU/VDU ATMOSHERIC TOWER
Area B U01-P02 CDU/VDU CRUDE DISTILATION SECTION U01-P02-202 CDU/VDU ATMOSHERIC TOWER OVERHEAD
Area B U01-P02 CDU/VDU CRUDE DISTILATION SECTION U01-P02-301 CDU/VDU KERO AND DIESEL STRIPPERS
Area B U01-P02 CDU/VDU CRUDE DISTILATION SECTION U01-P02-302 CDU/VDU KERO PRODUCT
Area B U01-P02 CDU/VDU CRUDE DISTILATION SECTION U01-P02-303 CDU/VDU DIESEL PRODUCT
Area B U01-P02 CDU/VDU CRUDE DISTILATION SECTION U01-P02-401 CDU/VDU HEAVY DIESEL STRIPPER
Area B U01-P03 CDU/VDU GAS COMPRESSION SECTION U01-P03-101 CDU/VDU CDU OVERHEAD VAPOR COMPRESSOR
Area B U01-P04 CDU/VDU VACUUM DISTILLATION SECTION U01-P04-101 CDU/VDU VACUUM HEATER
Area B U01-P04 CDU/VDU VACUUM DISTILLATION SECTION U01-P04-201 CDU/VDU VACUUM TOWER
Area B U01-P04 CDU/VDU VACUUM DISTILLATION SECTION U01-P04-301 CDU/VDU VACUUM SYSTEM
Area B U01-P04 CDU/VDU VACUUM DISTILLATION SECTION U01-P04-401 CDU/VDU HEAVY VACUUM GASOIL COOLING AND TEMPERED WATER SYSTEM
Area B U01-P70 CDU/VDU PKG U01-P70-101 CDU/VDU CORROSION INHIBITOR INJECTION SYSTEM(01-PK-001)
Area B U01-P70 CDU/VDU PKG U01-P70-102 CDU/VDU NEUTRALIZING AMINES INJECTION SYSTEM(01-PK-002)
Area B U01-P70 CDU/VDU PKG U01-P70-103 CDU/VDU FILMING AMINES INJECTION SYSTEM(01-PK-003)
Area B U01-P70 CDU/VDU PKG U01-P70-104 CDU/VDU DEMULSIFIER INJECTION SYSTEM(01-PK-004)
Area B U01-P70 CDU/VDU PKG U01-P70-105 CDU/VDU PHOSPHATE INJECTION SYSTEM(01-PK-005)
Area B U01-P70 CDU/VDU PKG U01-P70-106 CDU/VDU CAUSTIC INJECTION SYSTEM(01-PK-006)
Area B U01-P70 CDU/VDU PKG U01-P70-107 CDU/VDU CAUSTIC SODA REPLACER INJECTION SYSTEM(01-PK-007)
Area B U01-PWA CDU/VDU DRINKING WATER U01-PWA-101 CDU/VDU DRINKING WATER SUPPLY
Area B U01-SLP CDU/VDU LIGHT SLOP / HEAVY SLOP U01-SLP-101 CDU/VDU LIGHT SLOP
Area B U01-SLP CDU/VDU LIGHT SLOP / HEAVY SLOP U01-SLP-102 CDU/VDU HEAVY SLOP
Area B U01-SWA CDU/VDU SERVICE WATER U01-SWA-101 CDU/VDU SERVICE WATER
Area B U01-UTA CDU/VDU UTILITY AIR U01-UTA-101 CDU/VDU UTILITY AIR
Area B U01-VT CDU / VDU Vent Line U01-VT-101 CDU / VDU Vent Line
Area B U02-CLD NHT CLOSED DRAIN U02-CLD-101 NHT CLOSED DRAIN
Area B U02-CND NHT CLEAN CONDENSATE U02-CND-101 NHT CLEAN CONDENSATE
Area B U02-CW NHT COOLING WATER U02-CW-101 NHT COOLING WATER SUPPLY
Area B U02-CW NHT COOLING WATER U02-CW-102 NHT COOLING WATER RETURN
Area B U02-FLD NHT LP FLARE U02-FLD-101 NHT LP FLARE
Area B U02-FUG NHT FUEL GAS U02-FUG-101 NHT FUEL GAS
Area B U02-FWA NHT FIRE WATER NETWORK U02-FWA-101 NHT FIRE WATER NETWORK(UG)
Area B U02-FWA NHT FIRE WATER NETWORK U02-FWA-102 NHT FIRE WATER NETWORK(AG)
Area B U02-HBFW NHT HP BOILER FEED WATER U02-HBFW-101 NHT HP BOILER FEED WATER
Area B U02-HPC NHT HP CONDENSATE U02-HPC-101 NHT HP CONDENSATE
Area B U02-HPS NHT HP STEAM U02-HPS-101 NHT HP STEAM
Area B U02-INA NHT INSTRUMENT AIR U02-INA-101 NHT INSTRUMENT AIR
Area B U02-LPC NHT LP CONDENSATE U02-LPC-101 NHT LP CONDENSATE
Area B U02-LPS NHT LP STEAM U02-LPS-101 NHT LP STEAM
Area B U02-MBFW NHT MP BOILER FEED WATER U02-MBFW-101 NHT MP BOILER FEED WATER
Area B U02-MPC NHT MP CONDENSATE U02-MPC-101 NHT MP CONDENSATE
Area B U02-MPS NHT MP STEAM U02-MPS-101 NHT MP STEAM
Area B U02-NIT NHT NITROGEN U02-NIT-101 NHT NITROGEN
Area B U02-OWS NHT OWS U02-OWS-101 NHT OWS
Area B U02-P01 NHT REACTOR AND COMPRESSOR SECTION U02-P01-101 NHT FEED SURGE DRUM AND CHARGE PUMPS
Area B U02-P01 NHT REACTOR AND COMPRESSOR SECTION U02-P01-201 NHT CHARGE HEATER AND REACTOR
Area B U02-P01 NHT REACTOR AND COMPRESSOR SECTION U02-P01-301 NHT PRODUCT CONDENSER AND RECYCLE GAS COMPRESSORS
Area B U02-P01 NHT REACTOR AND COMPRESSOR SECTION U02-P01-401 NHT FRESH CAUSTIC
Area B U02-P01 NHT REACTOR AND COMPRESSOR SECTION U02-P01-501 NHT WASH WATER SYSTEM
Area B U02-P02 NHT DEBUTANIZER SECTION U02-P02-101 NHT DEBUTANIZER
Area B U02-P02 NHT DEBUTANIZER SECTION U02-P02-201 NHT SPONGE ABSORBER
Area B U02-P03 NHT NATHASPLITTER SECTION U02-P03-101 NHT NAPHTHA SPLITTER
Area B U02-P70 NHT PKG U02-P70-101 NHT CORROSION INHIBITOR INJECTION SYSTEM
Area B U02-PWA NHT DRINKING WATER U02-PWA-101 NHT DRINKING WATER SUPPLY
Area B U02-SLP NHT LIGHT SLOP U02-SLP-101 NHT LIGHT SLOP
Area B U02-SWA NHT SERVICE WATER U02-SWA-101 NHT SERVICE WATER
Area B U02-UTA NHT UTILITY AIR U02-UTA-101 NHT UTILITY AIR
Area B U02-VT NHT Vent Line U02-VT-101 NHT Vent Line
Area B U03-CLD ISOMER CLOSED DRAIN U03-CLD-101 ISOMER CLOSED DRAIN
Area B U03-CND ISOMER CLEAN CONDESATE U03-CND-101 ISOMER CLEAN CONDESATE
Area B U03-CW ISOMER COOLING WATER U03-CW-101 ISOMER COOLING WATER SUPPLY
Area B U03-CW ISOMER COOLING WATER U03-CW-102 ISOMER COOLING WAER RETURN
Area B U03-FLD ISOMER LP FLARE U03-FLD-101 ISOMER LP FLARE
Area B U03-FUG ISOMER FUEL GAS U03-FUG-101 ISOMER FUEL GAS
Area B U03-FWA ISOMER FIRE WATER NETWORK U03-FWA-101 ISOMER FIRE WATER NETWORK(UG)
Area B U03-FWA ISOMER FIRE WATER NETWORK U03-FWA-102 ISOMER FIRE WATER NETWORK(AG)
Area B U03-HBFW ISOMER HP BOILER FEED WATER U03-HBFW-101 ISOMER HP BOILER FEED WATER
Area B U03-HPC ISOMER HP CONDENSATE U03-HPC-101 ISOMER HP CONDENSATE
Area B U03-HPS ISOMER HP STEAM U03-HPS-101 ISOMER HP STEAM
Area B U03-INA ISOMER INSTRUMENT AIR U03-INA-101 ISOMER INSTRUMENT AIR
Area B U03-LPC ISOMER LP CONDENSATE U03-LPC-101 ISOMER LP CONDENSATE
Area B U03-LPS ISOMER LP STEAM U03-LPS-101 ISOMER LP STEAM
Area B U03-MBFW ISOMER MP BOILER FEED WATER U03-MBFW-101 ISOMER MP BOILER FEED WATER
Area B U03-MPC ISOMER MP CONDENSATE U03-MPC-101 ISOMER MP CONDENSATE
Area B U03-MPS ISOMER MP STEAM U03-MPS-101 ISOMER MP STEAM
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area B U03-NIT ISOMER NITROGEN U03-NIT-101 ISOMER NITROGEN
Area B U03-OWS ISOMER OWS U03-OWS-101 ISOMER OWS
Area B U03-P01 ISOMER MAKEUP GAS SECTION U03-P01-101 ISOMER METHANATOR REACTOR
Area B U03-P01 ISOMER MAKEUP GAS SECTION U03-P01-201 ISOMER MAKEUP COMPRESSOR
Area B U03-P01 ISOMER MAKEUP GAS SECTION U03-P01-301 ISOMER MAKEUP GAS DRIERS
Area B U03-P02 ISOMER FEED AND REGENERTION SECTION U03-P02-101 ISOMER FEED DRIERS
Area B U03-P02 ISOMER FEED AND REGENERTION SECTION U03-P02-201 ISOMER REGENERATION SECTION
Area B U03-P03 ISOMER REACTOR SECTION U03-P03-101 ISOMER REACTORS
Area B U03-P04 ISOMER STABILIZER AND SCRUBBER SECTION U03-P04-101 ISOMER STABILIZER
Area B U03-P04 ISOMER STABILIZER AND SCRUBBER SECTION U03-P04-201 ISOMER NET GAS SCRUBBER
Area B U03-P04 ISOMER STABILIZER AND SCRUBBER SECTION U03-P04-301 ISOMER NET GAS SCRUBBER WATER INJECTION SECTION
Area B U03-P04 ISOMER STABILIZER AND SCRUBBER SECTION U03-P04-401 ISOMER NET GAS SCRUBBER CAUSTIC SECTION
Area B U03-P05 ISOMER DEISOHEXANIZER SECTION U03-P05-101 ISOMER DEISOHEXANIZER
Area B U03-P70 ISOMER PKG U03-P70-101 ISOMER CHLORIDE INJECTION SYSTEM
Area B U03-P70 ISOMER PKG U03-P70-102 ISOMER ANHYDROUS HCL
Area B U03-PWA ISOMER DRINKING WATER U03-PWA-101 ISOMER DRINKING WATER
Area B U03-SWA ISOMER SERVICE WATER U03-SWA-101 ISOMER SERVICE WATER
Area B U03-UTA ISOMER UTILITY AIR U03-UTA-101 ISOMER UTILITY AIR
Area B U03-VT ISOMER Vent Line U03-VT-101 ISOMER Vent Line
Area B U04-CLD CCR CLOSED DRAIN U04-CLD-101 CCR CLOSED DRAIN
Area B U04-CND CCR CLEAN CONDENSATE U04-CND-101 CCR CLEAN CONDENSATE
Area B U04-CW CCR COOLING WATER U04-CW-101 CCR COOLING WATER SUPPLY
Area B U04-CW CCR COOLING WATER U04-CW-102 CCR COOLOING WATER RETURN
Area B U04-DWA CCR DEMI WATER U04-DWA-101 CCR DEMI WATER
Area B U04-FLD CCR LP FLARE U04-FLD-101 CCR LP FLARE
Area B U04-FUG CCR FUEL GAS U04-FUG-101 CCR FUEL GAS
Area B U04-FWA CCR FIRE WATER NETWORK U04-FWA-101 CCR FIRE WATER NETWORK(UG)
Area B U04-FWA CCR FIRE WATER NETWORK U04-FWA-102 CCR FIRE WATER NETWORK(AG)
Area B U04-HPC CCR HP CONDENSATE U04-HPC-101 CCR HP CONDENSATE
Area B U04-HPS CCR HP STEAM U04-HPS-101 CCR HP STEAM
Area B U04-INA CCR INSTRUMENT AIR U04-INA-101 CCR INSTRUMENT AIR
Area B U04-LPC CCR LP CONDENSATE U04-LPC-101 CCR LP CONDENSATE
Area B U04-LPS CCR LP STEAM U04-LPS-101 CCR LP STEAM
Area B U04-MBFW CCR BOILER FEED WATER U04-MBFW-101 CCR BOILER FEED WATER
Area B U04-MPC CCR MP CONDENSATE U04-MPC-101 CCR MP CONDENSATE
Area B U04-MPS CCR MP STEAM U04-MPS-101 CCR MP STEAM
Area B U04-NIT CCR NITROGEN1(FOR PROCESS) & (UTILITY) U04-NIT-101 CCR NITROGEN1(FOR PROCESS)
Area B U04-NIT CCR NITROGEN1(FOR PROCESS) & (UTILITY) U04-NIT-102 CCR NITROGEN2(UTILITY)
Area B U04-OWS CCR OWS U04-OWS-101 CCR OWS
Area B U04-P01 CCR REACTION SECTION U04-P01-101 CCR REACTOR SECTION
Area B U04-P01 CCR REACTION SECTION U04-P01-201 CCR RECYCLE COMPRESSOR
Area B U04-P02 CCR RECONTACT SECTION U04-P02-101 CCR NET GAS COMPRESSORS AND RECONTACT
Area B U04-P02 CCR RECONTACT SECTION U04-P02-201 CCR NET GAS CHLORIDE TREATERS
Area B U04-P03 CCR DEBUTANIZER SECTION U04-P03-101 CCR DEBUTANIZER
Area B U04-P03 CCR DEBUTANIZER SECTION U04-P03-201 CCR LPG CHLORIDE TREATERS
Area B U04-P04 CCR CHLORIDE, CONDENSATE INJECTION SECTION U04-P04-101 CCR CHLORIDE, CONDENSATE INJECTION SECTION
Area B U04-P05 CCR STEAM GENERATION SECTION U04-P05-101 CCR STEAM GENERATION SECTION
Area B U04-P11 CCR REGENERATION TOWER U04-P11-101 CCR REGENRATION TOWER
Area B U04-P11 CCR REGENERATION TOWER U04-P11-201 CCR REDUCTION GAS HEATER
Area B U04-P11 CCR REGENERATION TOWER U04-P11-301 CCR BOOSTER GAS COALESCER
Area B U04-P12 CCR REGENERATION TOWER ZONE U04-P12-101 CCR REGENERATION HEATER
Area B U04-P12 CCR REGENERATION TOWER ZONE U04-P12-201 CCR COOLER BLOWER
Area B U04-P12 CCR REGENERATION TOWER ZONE U04-P12-301 CCR COOLING ZONE COOLER/AIR DRIER PACKAGE
Area B U04-P13 CCR CATALYST TRANSFER U04-P13-101 CCR SPENT CATALYST LIFT GAS BLOWER
Area B U04-P13 CCR CATALYST TRANSFER U04-P13-201 CCR REGENRATED CATALYST LIFT GAS BLOWER
Area B U04-P70 CCR PKG U04-P70-101 CCR SULFIDE INJECTION SYSTEM PACKAGE(PK-101)
Area B U04-P70 CCR PKG U04-P70-102 CCR PHOSPHATE INJECTION SYSTEM PACKAGE(PK-102)
Area B U04-P70 CCR PKG U04-P70-103 CCR CHLORIDE INJECTION PACKAGE(PK201)
Area B U04-PWA CCR DRINKING WATER SUPPLY U04-PWA-101 CCR DRINKING WATER SUPPLY
Area B U04-SLP CCR LIGHT SLOP U04-SLP-101 CCR LIGHT SLOP
Area B U04-SWA CCR SERVICE WATER U04-SWA-101 CCR SERVICE WATER
Area B U04-UTA CCR UTILITY AIR U04-UTA-101 CCR UTILITY AIR
Area B U04-VT CCR Vent Line U04-VT-101 CCR Vent Line
Area C U05-CLD KHT CLOSED DRAIN U05-CLD-101 KHT HYDROCARBON CLOSED DRAIN (CLD)
Area C U05-CLD KHT CLOSED DRAIN U05-CLD-102 KHT HYDROCARBON CLOSED DRAIN (CLD) DRUM
Area C U05-CW KHT COOLING WATER U05-CW-101 KHT COOLING WATER
Area C U05-FLD KHT LP FLARE U05-FLD-101 KHT LP FLARE
Area C U05-FLH KHT HP FLARE U05-FLH-101 KHT HP FLARE
Area C U05-FUG KHT FUEL GAS U05-FUG-101 KHT FUEL GAS HEADER(TO FLARE HEADER PURGE & PRESS. CONTROL)
Area C U05-FUG KHT FUEL GAS U05-FUG-102 KHT FUEL GAS HEADER(TO HEATER MAIN & PILOT FUEL)
Area C U05-FUO KHT FUEL OIL U05-FUO-101 KHT FUEL OIL
Area C U05-FWA KHT FIREWATER NETWORK U05-FWA-101 KHT FIREWATER NETWORK(UG)
Area C U05-FWA KHT FIREWATER NETWORK U05-FWA-102 KHT FIREWATER NETWORK(AG)
Area C U05-INA KHT INSTRUMENT AIR U05-INA-101 KHT INSTRUMENT AIR
Area C U05-LPC KHT LP CONDENSATE U05-LPC-101 KHT LP CONDENSATE
Area C U05-LPS KHT LP STEAM U05-LPS-101 KHT LP STEAM DISTRIBUTION HEADER
Area C U05-MBFW KHT MP BFW U05-MBFW-101 KHT MP BFW DISTRIBUTION HEADER
Area C U05-MPC KHT MP CONDENSATE U05-MPC-101 KHT MP CONDENSATE
Area C U05-MPS KHT MP STEAM U05-MPS-101 KHT MP STEAM DISTRIBUTION HEADER
Area C U05-MPS KHT MP STEAM U05-MPS-102 KHT MPS&(LPS) TO & (FROM) STRIPPER REBOILER TURBINE
Area C U05-NIT KHT NITROGEN U05-NIT-101 KHT NITROGEN
Area C U05-OWS KHT OWS U05-OWS-101 KHT OWS
Area C U05-P01 KHT FEED AND MAKE-UP SECTION U05-P01-101 KHT FRESH FEED SECTION
Area C U05-P01 KHT FEED AND MAKE-UP SECTION U05-P01-201 KHT FEED/EFFLUENT EXCHANGER
Area C U05-P02 KHT REACTION SECTION U05-P02-101 KHT REACTOR
Area C U05-P02 KHT REACTION SECTION U05-P02-102 KHT REACTOR FEED HEATER FUELS SYSTEM
Area C U05-P02 KHT REACTION SECTION U05-P02-201 KHT COLD HP SEPARATION SECTION
Area C U05-P02 KHT REACTION SECTION U05-P02-401 KHT WASHING WATER SECTION
Area C U05-P03 KHT STRIPPER SECTION U05-P03-101 KHT RECYCLE COMPRESSOR
Area C U05-P04 KHT MAKE-UP COMPRESSOR U05-P04-101 KHT M/UP COMPRESSORS K.O DRUM & 1ST STAGE SUCTION LINE
Area C U05-P04 KHT MAKE-UP COMPRESSOR U05-P04-201 KHT MAKE-UP COMPRESSOR-B
Area C U05-P05 KHT STRIPPER U05-P05-101 KHT STRIPPER, BOTTOM & OVERHEAD SECTION
Area C U05-P05 KHT STRIPPER U05-P05-201 KHT STRIPPER REBOILER
Area C U05-P05 KHT STRIPPER U05-P05-301 KHT STRIPPER REFLUX SECTION
Area C U05-P05 KHT STRIPPER U05-P05-401 KHT STRIPPER FEED/BOTTOM EXCHANGER & KEROSENE PRODUCT
Area C U05-P70 KHT PKG U05-P70-101 KHT ANTIFOULING INJECTION PKG
Area C U05-P70 KHT PKG U05-P70-102 KHT CORROSION INHIBITOR INJECTION PKG
Area C U05-P70 KHT PKG U05-P70-103 KHT SULFIDING INJECTION PKG
Area C U05-PWA KHT DRINKING WATER U05-PWA-101 KHT DRINKING WATER DISTRIBUTION HEADER
Area C U05-SLP KHT LIGHT SLOP U05-SLP-101 KHT LIGHT SLOP
Area C U05-SRW KHT SOUR WATER U05-SRW-101 KHT SOUR WATER
Area C U05-SWA KHT SERVICE WATER U05-SWA-101 KHT SERVICE WATER
Area C U05-UTA KHT UTILITY AIR U05-UTA-101 KHT UTILITY AIR
Area C U06-AMW DHT AMINE DRAIN SYSTEM(AMW) U06-AMN-101 DHT AMINE DRAIN SYSTEM(AMW)
Area C U06-CLD DHT CLOSED DRAIN U06-CLD-101 DHT CLOSED DRAIN
Area C U06-CW DHT COOLING WATER U06-CW-101 DHT COOLING WATER
Area C U06-DWA DHT DEMI. WATER U06-DWA-101 DHT DEMI. WATER DISTRIBUTION
Area C U06-FLD DHT LP FLARE U06-FLD-101 DHT LP FLARE
Area C U06-FLH DHT HP FLARE U06-FLH-101 DHT HP FLARE
Area C U06-FUG DHT FUEL GAS & FUEL GAS HDR(TO HEATER MAIN & PILOT FUEL) U06-FUG-101 DHT FUEL GAS
Area C U06-FUG DHT FUEL GAS & FUEL GAS HDR(TO HEATER MAIN & PILOT FUEL) U06-FUG-102 DHT FUEL GAS HDR(TO HEATER MAIN & PILOT FUEL)
Area C U06-FUO DHT FUEL OIL DISTRIBUTION HEADER U06-FUO-101 DHT FUEL OIL DISTRIBUTION HEADER
Area C U06-FWA DHT FIREWATER NETWORK U06-FWA-101 DHT FIREWATER NETWORK(UG)
Area C U06-FWA DHT FIREWATER NETWORK U06-FWA-102 DHT FIREWATER NETWORK(AG)
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area C U06-HPS DHT HP STEAM U06-HPS-101 DHT HP STEAM
Area C U06-HPS DHT HP STEAM U06-HPS-102 DHT HPS&(LPS) TO&(FROM) RECYCLE COMP' TURBINE
Area C U06-INA DHT INSTRUMENT AIR U06-INA-101 DHT INSTRUMENT AIR
Area C U06-LPC DHT LP CONDENSATE U06-LPC-101 DHT LP CONDENSATE
Area C U06-LPS DHT LP STEAM U06-LPS-101 DHT LP STEAM
Area C U06-LPS DHT LP STEAM U06-LPS-102 DHT LP STEAM TO E-010(LEAN AMINE PREHEATER)
Area C U06-MBFW DHT MP BOILER FEED WATER U06-MBFW-101 DHT MP BOILER FEED WATER
Area C U06-MPC DHT MP CONDENSATE U06-MPC-101 DHT MP CONDENSATE
Area C U06-MPS DHT MP STEAM U06-MPS-101 DHT MP STEAM
Area C U06-MPS DHT MP STEAM U06-MPS-102 DHT SUPERHEATED MP STEAM
Area C U06-MPS DHT MP STEAM U06-MPS-103 DHT MPS&(LPS) TO &(FROM) STRIPPER REBOILER TURBINE
Area C U06-NIT DHT NITROGEN U06-NIT-101 DHT NITROGEN
Area C U06-OWS DHT OWS U06-OWS-101 DHT OWS
Area C U06-P01 DHT FRESH FEED SECTION U06-P01-101 DHT FRESH FEED SECTION
Area C U06-P01 DHT FRESH FEED SECTION U06-P01-201 DHT FEED/EFFLUENT EXCHANGER
Area C U06-P02 DHT REACTOR U06-P02-101 DHT REACTOR FEED HEATER
Area C U06-P02 DHT REACTOR U06-P02-201 DHT HOT HP SEPARATOR
Area C U06-P02 DHT REACTOR U06-P02-301 DHT HP AMINE ABSORBER
Area C U06-P02 DHT REACTOR U06-P02-401 DHT RECYCLE COMPRESSOR K.O DRUM
Area C U06-P02 DHT REACTOR U06-P02-501 DHT REACTOR FEED HEATER FUELS SYSTEM
Area C U06-P03 DHT MAKE-UP COMPRESSORS U06-P03-101 DHT MAKE-UP COMPRESSORS FIRST STAGE
Area C U06-P03 DHT MAKE-UP COMPRESSORS U06-P03-201 DHT MAKE-UP COMPRESSORS SECOND STAGE
Area C U06-P04 DHT AMINE SYSTEM U06-P04-101 DHT LEAN AMINE
Area C U06-P04 DHT AMINE SYSTEM U06-P04-201 DHT RICH AMINE
Area C U06-P05 DHT STRIPPER U06-P05-101 DHT STRIPPER
Area C U06-P05 DHT STRIPPER U06-P05-201 DHT STRIPPER REBOILER
Area C U06-P05 DHT STRIPPER U06-P05-301 DHT STRIPPER REFLUX SECTION
Area C U06-P05 DHT STRIPPER U06-P05-401 DHT STRIPPER FEED/BOTTOM EXCHANGER AND DIESEL PRODUCT
Area C U06-P06 DHT OFF GAS COMPRESSOR U06-P06-101 DHT OFF GAS COMPRESSORS FIRST STAGE
Area C U06-P06 DHT OFF GAS COMPRESSOR U06-P06-201 DHT OFF GAS COMPRESSORS SECOND STAGE
Area C U06-P70 DHT PKG U06-P70-101 DHT ANTIFOAMING INJECTION PKG
Area C U06-P70 DHT PKG U06-P70-102 DHT CORROSION INHIBITOR INJECTION PKG
Area C U06-P70 DHT PKG U06-P70-103 DHT ANTIFOULING INJECTION PKG
Area C U06-P70 DHT PKG U06-P70-104 DHT PHOSPHATE INJECTION PKG
Area C U06-PWA DHT DRINKING WATER U06-PWA-101 DHT DRINKING WATER DISTRIBUTION HEADER
Area C U06-SLP DHT LIGHT SLOP & LIGHT SLOP DISTRIBUTION U06-SLP-101 DHT LIGHT SLOP
Area C U06-SLP DHT LIGHT SLOP & LIGHT SLOP DISTRIBUTION U06-SLP-102 DHT LIGHT SLOP DISTRIBUTION
Area C U06-SRW DHT SOUR WATER U06-SRW-101 DHT SOUR WATER
Area C U06-SWA DHT SERVICE WATER U06-SWA-101 DHT SERVICE WATER DISTRIBUTION
Area C U06-UTA DHT UTILITY AIR U06-UTA-101 DHT UTILITY AIR
Area C U07-AMW VGOHT Amine Drain System(AMW) U07-AMW-101 VGOHT Amine Drain System(AMW)
Area C U07-BDD VGOHT Steam Generator Blowdown, IBD & CBD U07-BDD-101 VGOHT Steam Generator Blowdown, IBD & CBD
Area C U07-CHP VGOHT Neutralization System (Chemical Product) U07-CHP-101 VGOHT Neutralization System (Chemical Product)
Area C U07-CLD VGOHT Closed Drain U07-CLD-101 VGOHT Hydrocarbon Closed Drain(CLD)
Area C U07-CLD VGOHT Closed Drain U07-CLD-102 VGOHT Hydrocarbon Closed Drain Drum(CLD)
Area C U07-CND VGOHT Clean Condensate U07-CND-101 VGOHT Clean Condensate Collection Header
Area C U07-CW VGOHT Cooling Water U07-CW-101 VGOHT Cooling Water
Area C U07-DWA VGOHT Demi. Water U07-DWA-101 VGOHT Demi. Water Distribution
Area C U07-FLD VGOHT LP Flare U07-FLD-101 VGOHT LP Flare Header
Area C U07-FLH VGOHT HP Flare U07-FLH-101 VGOHT HP Flare Header
Area C U07-FLO VGOHT Flushing Oil U07-FLO-101 VGOHT Flushing Oil
Area C U07-FUG VGOHT Fuel Gas U07-FUG-101 VGOHT Fuel Gas Header(to Flare header Purge & Press. Control)
Area C U07-FUG VGOHT Fuel Gas U07-FUG-102 VGOHT Fuel Gas Header(to Heater Main & Pilot Fuel)
Area C U07-FUO VGOHT Fuel Oil U07-FUO-101 VGOHT Fuel Oil Distribution Header
Area C U07-FWA VGOHT FIREWATER NETWORK U07-FWA-101 VGOHT FIREWATER NETWORK(UG)
Area C U07-FWA VGOHT FIREWATER NETWORK U07-FWA-102 VGOHT FIREWATER NETWORK(AG)
Area C U07-HPS VGOHT HP Steam U07-HPS-101 VGOHT HP Steam Distribution Header
Area C U07-INA VGOHT Instrument Air U07-INA-101 VGOHT Instrument Air Distribution Header
Area C U07-LPC VGOHT LP Condensate U07-LPC-101 VGOHT LP Condensate Collection Header
Area C U07-LPS VGOHT LS Steam U07-LPS-101 VGOHT LS Steam Distribution Header
Area C U07-MBFW VGOHT MP BFW U07-MBFW-101 VGOHT MP BFW Distribution Header
Area C U07-MPC VGOHT MP Condensate U07-MPC-101 VGOHT MP Condensate Collection Header
Area C U07-MPS VGOHT MP Steam U07-MPS-101 VGOHT MP Steam Distribution Header
Area C U07-MPS VGOHT MP Steam U07-MPS-102 VGOHT MPS&(LPS) to & (from) Preflash Drum Pump Steam Turbine
Area C U07-MPS VGOHT MP Steam U07-MPS-103 VGOHT MPS&(LPS) to & (from) Product Fractionator BTM Pumps Steam Turbine
Area C U07-MPS VGOHT MP Steam U07-MPS-104 VGOHT MPS From/to Stripper/Fractionator Bottoms MPS Generator
Area C U07-NIT VGOHT Nitrogen U07-NIT-101 VGOHT Nitrogen Distribution Header
Area C U07-OWS VGOHT OWS U07-OWS-101 VGOHT OWS
Area C U07-P01 VGOHT Fresh Feed Section U07-P01-101 VGOHT Fresh Feed Section
Area C U07-P01 VGOHT Fresh Feed Section U07-P01-102 VGOHT Feed Surge Drum and Feed Pumps
Area C U07-P01 VGOHT Fresh Feed Section U07-P01-103 VGOHT VGO Feed Effluent Exchanger
Area C U07-P02 VGOHT Reactor Feed Heater U07-P02-101 VGOHT Reactor Feed Heater
Area C U07-P02 VGOHT Reactor Feed Heater U07-P02-102 VGOHT Reactor Feed Heater Fuel System
Area C U07-P03 VGOHT Reactor U07-P03-101 VGOHT Reactor
Area C U07-P03 VGOHT Reactor U07-P03-201 VGOHT Hot Separation Section
Area C U07-P03 VGOHT Reactor U07-P03-301 VGOHT Cold Separation Section
Area C U07-P04 VGOHT Amine System U07-P04-101 VGOHT Rich Amine Flash Drum
Area C U07-P04 VGOHT Amine System U07-P04-102 VGOHT Lean Amine Surge Drum
Area C U07-P05 VGOHT Recycle Compressor U07-P05-101 VGOHT Recycle Gas Scrubber & K.O. Drum
Area C U07-P05 VGOHT Recycle Compressor U07-P05-102 VGOHT Recycle Gas Compressor
Area C U07-P05 VGOHT Recycle Compressor U07-P05-104 VGOHT Recycle Gas Compressor Discharge Loop
Area C U07-P05 VGOHT Recycle Compressor U07-P05-201 VGOHT Recycle Gas Compressor Surface Condenser PKG
Area C U07-P06 VGOHT Make-Up Gas Compressors U07-P06-101 VGOHT Make-Up Compressors K.O. Drum & 1st Stage Suction Line
Area C U07-P06 VGOHT Make-Up Gas Compressors U07-P06-201 VGOHT Make-Up Compressor A
Area C U07-P06 VGOHT Make-Up Gas Compressors U07-P06-202 VGOHT Make-Up Compressors - Discharge Cooler/ 2nd K.O. Drum
Area C U07-P07 VGOHT Stripper U07-P06-301 VGOHT Make-Up Compressor B
Area C U07-P06 VGOHT Make-Up Gas Compressors U07-P06-401 VGOHT Make-Up Compressors 2nd stage Discharge Loop
Area C U07-P06 VGOHT Make-Up Gas Compressors U07-P06-501 VGOHT Ejector System
Area C U07-P07 VGOHT Stripper U07-P07-101 VGOHT Stripper Bottom & Overhead Section
Area C U07-P07 VGOHT Stripper U07-P07-102 VGOHT Stripper Reflux Section
Area C U07-P08 VGOHT Fractionator U07-P08-101 VGOHT Preflash Drum & Feed Heater Section
Area C U07-P08 VGOHT Fractionator U07-P08-102 VGOHT Product Fractionator Feed Heater Soot Blower System
Area C U07-P08 VGOHT Fractionator U07-P08-103 VGOHT Product Fractionator, Bottom & Overhead & Side Cut Section
Area C U07-P08 VGOHT Fractionator U07-P08-104 VGOHT Product Fractionator Reflux & Off Spec Naphtha Cooling Section
Area C U07-P08 VGOHT Fractionator U07-P08-201 VGOHT FCC Feed oil Cooling Section
Area C U07-P08 VGOHT Fractionator U07-P08-301 VGOHT Product Fractionator Feed Heater Fuel Gas System
Area C U07-P08 VGOHT Fractionator U07-P08-302 VGOHT Product Fractionator Feed Heater Fuel Oil & Steam Atomizing System
Area C U07-P08 VGOHT Fractionator U07-P08-303 VGOHT Product Fractionator Feed Heater Air Preheater System
Area C U07-P09 VGOHT Diesel Stripper U07-P09-101 VGOHT Diesel Stripper Bottom & Overhead Section
Area C U07-P09 VGOHT Diesel Stripper U07-P09-102 VGOHT Diesel Product Cooling Section
Area C U07-P70 VGOHT PKG U07-P70-101 VGOHT Sulfiding Injection Package
Area C U07-P70 VGOHT PKG U07-P70-102 VGOHT Phosphate Injection Package
Area C U07-P70 VGOHT PKG U07-P70-103 VGOHT Corrosion Inhibitor Injection Package
Area C U07-PWA VGOHT Drinking Water U07-PWA-101 VGOHT Drinking Water Distribution Header
Area C U07-SGS VGOHT Off Gas U07-SGS-101 VGOHT Off Gas
Area C U07-SLP VGOHT Light Slop U07-SLP-101 VGOHT Light Slop Distribution
Area C U07-SRW VGOHT Sour Water U07-SRW-101 VGOHT Sour Water
Area C U07-SWA VGOHT Service Water U07-SWA-101 VGOHT Service Water Distribution
Area C U07-UTA VGOHT Utility Air U07-UTA-101 VGOHT Utility Air Distribution Header
Area C U07-WAT VGOHT Back Wash Water U07-WAT-101 VGOHT Back Wash Water
Area C U08-AMW FCC AMINE DRAIN U08-AMW-101 FCC AMINE DRAIN
Area C U08-BDD FCC BLOW DOWN U08-BDD-101 FCC BLOW DOWN
Area C U08-CLD FCC CLOSED DRAIN U08-CLD-101 FCC CLOSED DRAIN
Area C U08-CND FCC CLEAN CONDENSATE U08-CND-101 FCC CLEAN CONDENSATE
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area C U08-CW FCC CW SYSTEM U08-CW-101 FCC CW SYSTEM
Area C U08-DWA FCC DEMI WATER U08-DWA-101 FCC DEMI WATER
Area C U08-FLD FCC LP FLARE U08-FLD-101 FCC LP FLARE
Area C U08-FLH FCC HP FLARE U08-FLH-101 FCC HP FLARE
Area C U08-FLO FCC FLUSHING OIL U08-FLO-101 FCC FLUSHING OIL
Area C U08-FUG FCC FUEL GAS U08-FUG-101 FCC FUEL GAS
Area C U08-FWA FCC FIREWATER NETWORK U08-FWA-101 FCC FIREWATER NETWORK(UG)
Area C U08-FWA FCC FIREWATER NETWORK U08-FWA-102 FCC FIREWATER NETWORK(AG)
Area C U08-HBFW FCC HP BFW U08-HBFW-101 FCC HP BFW
Area C U08-HPS FCC HP STEAM U08-HPS-101 FCC HP STEAM
Area C U08-INA FCC INSTRUMENT AIR U08-INA-101 FCC INSTRUMENT AIR
Area C U08-LPC FCC LP CONDENSATE U08-LPC-101 FCC LP CONDENSATE
Area C U08-LPS FCC LP STEAM U08-LPS-101 FCC LP STEAM
Area C U08-MBFW FCC MP BFW U08-MBFW-101 FCC MP BFW
Area C U08-MPC FCC MP CONDENSATE U08-MPC-101 FCC MP CONDENSATE
Area C U08-MPS FCC MP STEAM U08-MPS-101 FCC MP STEAM
Area C U08-NIT FCC NITROGEN U08-NIT-101 FCC NITROGEN
Area C U08-OWS FCC OWS U08-OWS-101 FCC OWS
Area C U08-P01 FCC REACTOR & REGENERATOR U08-P01-101 FCC FLUE GAS STEAM GENERATOR
Area C U08-P01 FCC REACTOR & REGENERATOR U08-P01-201 FCC REACTOR
Area C U08-P01 FCC REACTOR & REGENERATOR U08-P01-301 FCC REGENERATOR
Area C U08-P01 FCC REACTOR & REGENERATOR U08-P01-302 FCC DIRECT FIRE AIR HEATER
Area C U08-P01 FCC REACTOR & REGENERATOR U08-P01-401 FCC CATALYST HOPPER
Area C U08-P02 FCC MAIN COLUMN U08-P02-101 FCC FEED OIL
Area C U08-P02 FCC MAIN COLUMN U08-P02-201 FCC MAIN COLUMN & OVERHEAD
Area C U08-P02 FCC MAIN COLUMN U08-P02-301 FCC LIGHT CYCLE OIL STRIPPER
Area C U08-P02 FCC MAIN COLUMN U08-P02-401 FCC HEAVY CYCLE OIL
Area C U08-P02 FCC MAIN COLUMN U08-P02-501 FCC SLURRY
Area C U08-P02 FCC MAIN COLUMN U08-P02-601 FCC HEAVY NAPHTHA
Area C U08-P02 FCC MAIN COLUMN U08-P02-701 FCC MAIN COLUMN RECEIVER & HC LIQUID
Area C U08-P03 FCC GAS CONCENTRATION U08-P03-101 FCC WET GAS COMPRESSING
Area C U08-P03 FCC GAS CONCENTRATION U08-P03-301 FCC PRIMARY ABSORBER
Area C U08-P03 FCC GAS CONCENTRATION U08-P03-401 FCC SPONGE ABSORBER
Area C U08-P03 FCC GAS CONCENTRATION U08-P03-501 FCC AMINE ABSORBER & FCC OFF GAS
Area C U08-P03 FCC GAS CONCENTRATION U08-P03-601 FCC STRIPPER & UNSTABILIZED GASOLINE
Area C U08-P03 FCC GAS CONCENTRATION U08-P03-701 FCC DEBUTANIZER & GASOLINE
Area C U08-P03 FCC GAS CONCENTRATION U08-P03-801 FCC DEBUTANIZER & LPG
Area C U08-P03 FCC GAS CONCENTRATION U08-P03-901 FCC WET GAS COMPRESSOR SURFACE CONDENSOR PACKAGE
Area C U08-P04 FCC AMINE U08-P04-101 FCC AMINE
Area C U08-P05 FCC CAUSTIC U08-P05-101 FCC CAUSTIC & COS SOLVENT
Area C U08-P05 FCC CAUSTIC U08-P05-201 FCC SPENT CAUSTIC & CAUSTIC DRAINAGE
Area C U08-P70 FCC PKG U08-P70-101 FCC PHOSPHATE INJECTION PACKAGE
Area C U08-PWA FCC DW U08-PWA-101 FCC DW
Area C U08-SLP FCC LIGHT SLOP U08-SLP-101 FCC LIGHT SLOP
Area C U08-SRW FCC SOUR WATER U08-SRW-101 FCC SOUR WATER
Area C U08-SWA FCC SERVICE WATER U08-SWA-101 FCC SERVICE WATER
Area C U08-UTA FCC UTILITY AIR U08-UTA-101 FCC UTILITY AIR
Area C U09-CAU PNU CAUSTIC U09-CAU-101 PNU CAUSTIC
Area C U09-CLD PNU CLOSED DRAIN U09-CLD-101 PNU CLOSED DRAIN
Area C U09-CW PNU COOLING WATER SUPPLY & RETURN U09-CW-101 PNU COOLING WATER SUPPLY
Area C U09-CW PNU COOLING WATER SUPPLY & RETURN U09-CW-102 PNU COOLING WATER RETURN
Area C U09-FLD PNU LP FLARE U09-FLD-101 PNU LP FLARE
Area C U09-FLH PNU HP FLARE U09-FLH-101 PNU HP FLARE
Area C U09-FUG PNU FUEL GAS U09-FUG-101 PNU FUEL GAS
Area C U09-FWA PNU FIREWATER NETWORK U09-FWA-101 PNU FIREWATER NETWORK(UG)
Area C U09-FWA PNU FIREWATER NETWORK U09-FWA-102 PNU FIREWATER NETWORK(AG)
Area C U09-HBFW PNU HP BOILER FEED WATER U09-HBFW-101 PNU HP BOILER FEED WATER
Area C U09-HPC PNU HP CONDENSATE U09-HPC-101 PNU HP CONDENSATE
Area C U09-HPS PNU HP STEAM U09-HPS-101 PNU HP STEAM
Area C U09-HYD PNU HYDROGEN U09-HYD-101 PNU HYDROGEN from VGO HDT
Area C U09-HYD PNU HYDROGEN U09-HYD-102 PNU HYDROGEN from PSA
Area C U09-INA PNU INSTRUMENT AIR U09-INA-101 PNU INSTRUMENT AIR
Area C U09-LPC PNU LP CONDENSATE U09-LPC-101 PNU LP CONDENSATE
Area C U09-LPS PNU LP STEAM U09-LPS-101 PNU LP STEAM
Area C U09-MBFW PNU MP BOILER FEED WATER U09-MBFW-101 PNU MP BOILER FEED WATER
Area C U09-MPC PNU MP CONDENSATE U09-MPC-101 PNU MP CONDENSATE
Area C U09-MPS PNU MP STEAM U09-MPS-101 PNU MP STEAM
Area C U09-NIT PNU NITROGEN U09-NIT-101 PNU NITROGEN
Area C U09-OWS PNU OWS U09-OWS-101 PNU OWS
Area C U09-P01 PNU ALKYFINING SECTION U09-P01-101 PNU LPG CAUSTIC WASH
Area C U09-P01 PNU ALKYFINING SECTION U09-P01-102 PNU LPG WATER WASHING
Area C U09-P01 PNU ALKYFINING SECTION U09-P01-201 PNU ALKYFINING REACTOR
Area C U09-P01 PNU ALKYFINING SECTION U09-P01-202 PNU LPG WATERAND SULFUR GUARD BED
Area C U09-P01 PNU ALKYFINING SECTION U09-P01-301 PNU FRESH REGENERANT
Area C U09-P01 PNU ALKYFINING SECTION U09-P01-302 PNU SPENT REGENERANT
Area C U09-P01 PNU ALKYFINING SECTION U09-P01-401 PNU CATALYST TREATMENT
Area C U09-P02 PNU OLIGOMERIZATION SECTION U09-P02-101 PNU OLIGOMERIZATION REACTION
Area C U09-P02 PNU OLIGOMERIZATION SECTION U09-P02-201 PNU POLYNAPHTA DEBUTANIZER
Area C U09-P02 PNU OLIGOMERIZATION SECTION U09-P02-301 PNU SPLITTER
Area C U09-P03 PNU POLYGASOLINE HYDROGENATION SECTION U09-P03-101 PNU HYDROGENERATION REACTOR
Area C U09-P03 PNU POLYGASOLINE HYDROGENATION SECTION U09-P03-201 PNU STABILIZER
Area C U09-P03 PNU POLYGASOLINE HYDROGENATION SECTION U09-P03-301 PNU ANTI-POLIMERIZATION INJECTION PACKAGE
Area C U09-P04 PNU START-UP U09-P04-101 PNU START-UP LPG
Area C U09-P04 PNU START-UP U09-P04-102 PNU START-UP NAPHTHA
Area C U09-PWA PNU DRINKING WATER U09-PWA-101 PNU DRINKING WATER
Area C U09-SLP PNU LIGHT SLOP U09-SLP-101 PNU LIGHT SLOP
Area C U09-SWA PNU SERVICE WATER U09-SWA-101 PNU SERVICE WATER
Area C U09-UTA PNU UTILITY AIR U09-UTA-101 PNU UTILITY AIR
Area C U09-WWT PNU WASTE WATER U09-WWT-101 PNU SPENT WATER
Area C U10-CLD ABU CLOSED DRAIN U10-CLD-101 ABU CLOSED DRAIN
Area C U10-CW ABU COOLING WATER U10-CW-101 ABU COOLING WATER SUPPLY
Area C U10-CW ABU COOLING WATER U10-CW-102 ABU COOLING WATER RETURN
Area C U10-FLO ABU FLUSHING OIL U10-FLO-101 ABU FLUSHING OIL(TK-206A/B) (PRO)
Area C U10-FLO ABU FLUSHING OIL U10-FLO-102 ABU FLUSHING OIL(TK-003) (FLO)
Area C U10-FUG ABU FUEL GAS U10-FUG-101 ABU FUEL GAS
Area C U10-FWA ABU FIREWATER NETWORK U10-FWA-101 ABU FIREWATER NETWORK(UG)
Area C U10-FWA ABU FIREWATER NETWORK U10-FWA-102 ABU FIREWATER NETWORK(AG)
Area C U10-HBFW ABU HP BOILER FEED WATER U10-HBFW-101 ABU HP BOILER FEED WATER
Area C U10-HPC ABU HP CONDENSATE U10-HPC-101 ABU HP CONDENSATE
Area C U10-HPS ABU HP STEAM U10-HPS-101 ABU HP STEAM
Area C U10-INA ABU INSTRUMENT AIR U10-INA-101 ABU INSTRUMENT AIR
Area C U10-LPC ABU LP CONDENSATE U10-LPC-101 ABU LP CONDENSATE
Area C U10-LPS ABU LP STEAM U10-LPS-101 ABU LP STEAM
Area C U10-MBFW ABU MP BOILER FEED WATER U10-MBFW-101 ABU MP BOILER FEED WATER
Area C U10-MPC ABU MP CONDENSATE U10-MPC-101 ABU MP CONDENSATE
Area C U10-MPS ABU MP STEAM U10-MPS-101 ABU MP STEAM
Area C U10-NIT ABU NITROGEN U10-NIT-101 ABU NITROGEN
Area C U10-OWS ABU OWS U10-OWS-101 ABU OWS
Area C U10-P01 ABU BITUROX SECTION U10-P01-101 ABU BITUROX REACTOR
Area C U10-P01 ABU BITUROX SECTION U10-P01-102 ABU BITUROX REACTOR OFF GAS
Area C U10-P01 ABU BITUROX SECTION U10-P01-201 ABU PROCESS WATER PUMP
Area C U10-P01 ABU BITUROX SECTION U10-P01-301 ABU PROCESS AIR COMPRESSORS
Area C U10-P02 ABU OFF GAS TREATMENT U10-P02-101 ABU INCINERATOR PACKAGE
Area C U10-P70 ABU PKG U10-P70-101 ABU CHEMICAL DOSING PACKAGE
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area C U10-PWA ABU DRINKING WATER SUPPLY U10-PWA-101 ABU DRINKING WATER SUPPLY
Area C U10-SLP ABU SLOP OIL U10-SLP-101 ABU SLOP OIL
Area C U10-SWA ABU SERVICE WATER U10-SWA-101 ABU SERVICE WATER
Area C U10-UTA ABU UTILITY AIR U10-UTA-101 ABU UTILITY AIR
Area C U11-AMN LPG AMINE U11-AMN-101 LPG AMINE
Area C U11-BFW LPG BFW U11-BFW-101 LPG BFW
Area C U11-CLD LPG LPG DRAIN U11-CLD-101 LPG LPG DRAIN
Area C U11-CND LPG PUMPED CONDENSATE U11-CND-101 LPG PUMPED CONDENSATE
Area C U11-CW LPG COOLING WATER U11-CW-101 LPG COOLING WATER
Area C U11-FLD LPG LP FLARE U11-FLD-101 LPG LP FLARE
Area C U11-FLH LPG HP FLARE U11-FLH-101 LPG HP FLARE
Area C U11-FUG LPG FUEL GAS U11-FUG-101 LPG FUEL GAS
Area C U11-FWA LPG PRODUCTION UNIT FIREWATER NETWORK U11-FWA-101 LPG PRODUCTION UNIT FIREWATER NETWORK(UG)
Area C U11-FWA LPG PRODUCTION UNIT FIREWATER NETWORK U11-FWA-102 LPG PRODUCTION UNIT FIREWATER NETWORK(AG)
Area C U11-INA LPG INSTRUMENT AIR U11-INA-101 LPG INSTRUMENT AIR
Area C U11-LPC LPG LP CONDENSATE U11-LPC-101 LPG LP CONDENSATE
Area C U11-LPS LPG LP STEAM U11-LPS-101 LPG LP STEAM
Area C U11-NIT LPG NITROGEN U11-NIT-101 LPG NITROGEN
Area C U11-OWS LPG OWS U11-OWS-101 LPG OWS
Area C U11-P01 LPG PRODUCTION UNIT AMINE WASHING U11-P01-101 LPG NHT LPG AMINE ABSORBER
Area C U11-P01 LPG PRODUCTION UNIT AMINE WASHING U11-P01-201 LPG WATER MAKE UP PUMP
Area C U11-P02 LPG PRODUCTION UNIT DEETHANIZER U11-P02-101 LPG DEETHANIZER
Area C U11-P03 LPG PRODUCTION UNIT DEPROPANIZER U11-P03-101 LPG DEPROPANIZER
Area C U11-PWA LPG DRINKING WATER U11-PWA-101 LPG DRINKING WATER
Area C U11-SWA LPG SERVICE WATER U11-SWA-101 LPG SERVICE WATER
Area C U11-UTA LPG UTILITY AIR U11-UTA-101 LPG UTILITY AIR
Area B U13-BFW HPU BOILER FEED WATER U13-BFW-101 HPU BOILER FEED WATER
Area B U13-CLD HPU CLOSED DRAIN U13-CLD-101 HPU CLOSED DRAIN
Area B U13-CW HPU COOLING WATER U13-CW-101 HPU COOLING WATER SUPPLY
Area B U13-CW HPU COOLING WATER U13-CW-102 HPU COOLOING WATER RETURN
Area B U13-DWA HPU DEMINERALIZED WATER U13-DWA-101 HPU DEMINERALIZED WATER
Area B U13-FLD HPU LP FLARE U13-FLD-101 HPU LP FLARE
Area B U13-FUG HPU FUEL GAS U13-FUG-101 HPU FUEL GAS
Area B U13-FWA HPU FIRE WATER NETWORK U13-FWA-101 HPU FIRE WATER NETWORK(UG)
Area B U13-FWA HPU FIRE WATER NETWORK U13-FWA-102 HPU FIRE WATER NETWORK(AG)
Area B U13-HPC HPU HP CONDENSATE U13-HPC-101 HPU HP CONDENSATE
Area B U13-INA HPU INSTRUMENT AIR U13-INA-101 HPU INSTRUMENT AIR
Area B U13-LPC HPU LP CONDENSATE U13-LPC-101 HPU LP CONDENSATE
Area B U13-LPS HPU LP STEAM U13-LPS-101 HPU LP STEAM
Area B U13-NIT HPU NITROGEN U13-NIT-101 HPU NITROGEN
Area B U13-OWS HPU OWS U13-OWS-101 HPU OWS
Area B U13-P01 HPU FEED PREPARATION U13-P01-101 HPU NATURAL GAS FEED
Area B U13-P01 HPU FEED PREPARATION U13-P01-201 HPU NAPHTHA FEED
Area B U13-P01 HPU FEED PREPARATION U13-P01-301 HPU LPG/C4 SURGE FEED
Area B U13-P02 HPU HEAVY NAPHTHA DESULPHURIZATION AND REFORMING U13-P02-101 HPU HYDRODESULFURIZER
Area B U13-P02 HPU HEAVY NAPHTHA DESULPHURIZATION AND REFORMING U13-P02-201 HPU REFORMER
Area B U13-P02 HPU HEAVY NAPHTHA DESULPHURIZATION AND REFORMING U13-P02-301 HPU PROCESS STEAM GENERATION
Area B U13-P03 HPU HEAVY NAPHTHA DESULPHURIZATION AND REFORMING U13-P03-101 HPU MT SHIFT CONVERSION
Area B U13-P03 HPU HEAVY NAPHTHA DESULPHURIZATION AND REFORMING U13-P03-201 HPU PSA UNIT PACKAGE
Area B U13-P70 HPU PKG U13-P70-101 HPU PHOSPHATE DISING UNIT(Chemical Product)
Area B U13-P70 HPU PKG U13-P70-102 HPU MOROHOLINE INJECTION PACKAGE
Area B U13-P70 HPU PKG U13-P70-103 HPU DMDS INJECTION PACKAGE
Area B U13-PWA HPU DRINKING WATER U13-PWA-101 HPU DRINKING WATER
Area B U13-SWA HPU SERVICE WATER U13-SWA-101 HPU SERVICE WATER
Area B U13-UTA HPU UTILITY AIR U13-UTA-101 HPU UTILITY AIR
Area B U13-VT HPU Vent Line U13-VT-101 HPU Vent Line
Area B U14-BFW HPU BOILER FEED WATER U14-BFW-101 HPU BOILER FEED WATER
Area B U14-CW HPU COOLING WATER SUPPLY &RETURN U14-CW-101 HPU COOLING WATER SUPPLY
Area B U14-CW HPU COOLING WATER SUPPLY &RETURN U14-CW-102 HPU COOLOING WATER RETURN
Area B U14-DWA HPU DEMINERALIZED WATER U14-DWA-101 HPU DEMINERALIZED WATER
Area B U14-FUG HPU FUEL GAS U14-FUG-101 HPU FUEL GAS
Area B U14-HPC HPU HP CONDENSATE U14-HPC-101 HPU HP CONDENSATE
Area B U14-INA HPU INSTRUMENT AIR U14-INA-101 HPU INSTRUMENT AIR
Area B U14-LPC HPU LP CONDENSATE U14-LPC-101 HPU LP CONDENSATE
Area B U14-LPS HPU LP STEAM U14-LPS-101 HPU LP STEAM
Area B U14-OWS HPU OWS U14-OWS-101 HPU OWS
Area B U14-P01 HPU FEED PREPARATION U14-P01-101 HPU NATURAL GAS FEED
Area B U14-P01 HPU FEED PREPARATION U14-P01-201 HPU NAPHTHA FEED
Area B U14-P01 HPU FEED PREPARATION U14-P01-301 HPU LPG/C4 SURGE FEED
Area B U14-P02 HPU DESULPHURIZATION AND REFORMING U14-P02-101 HPU HYDRODESULFURIZER
Area B U14-P02 HPU DESULPHURIZATION AND REFORMING U14-P02-201 HPU REFORMER
Area B U14-P02 HPU DESULPHURIZATION AND REFORMING U14-P02-301 HPU PROCESS STEAM GENERATION
Area B U14-P03 HPU CO CONVERSION & PSA U14-P03-101 HPU MT SHIFT CONVERSION
Area B U14-P03 HPU CO CONVERSION & PSA U14-P03-201 HPU PSA UNIT PACKAGE
Area B U14-P70 HPU PKG U14-P70-101 HPU PHOSPHATE DISING UNIT
Area B U14-P70 HPU PKG U14-P70-102 HPU MOROHOLINE INJECTION PACKAGE
Area B U14-P70 HPU PKG U14-P70-103 HPU DMDS INJECTION PACKAGE
Area B U14-SWA HPU SERVICE WATER U14-SWA-101 HPU SERVICE WATER
Area B U14-UTA HPU UTILITY AIR U14-UTA-101 HPU UTILITY AIR
Area B U14-VT HPU Vent Line U14-VT-101 HPU Vent Line
Area B U15-CW HPU COOLING WATER SUPPLY & RETURN U15-CW-101 HPU COOLING WATER SUPPLY
Area B U15-CW HPU COOLING WATER SUPPLY & RETURN U15-CW-102 HPU COOLING WATER RETURN
Area B U15-HPC HPU HP CONDENSATE U15-HPC-101 HPU HP CONDENSATE
Area B U15-INA HPU INSTRUMENT AIR U15-INA-101 HPU INSTRUMENT AIR
Area B U15-LPC HPU LP CONDENSATE U15-LPC-101 HPU LP CONDENSATE
Area B U15-LPS HPU LP STEAM U15-LPS-101 HPU LP STEAM
Area B U15-OWS HPU OWS U15-OWS-101 HPU OWS
Area B U15-P01 HPU CCR PSA UNIT U15-P01-101 HPU PSA UNIT
Area B U15-P01 HPU CCR PSA UNIT U15-P01-201 HPU PSA OFF GAS COMPRESSORS
Area B U15-P02 HPU COMPRESSOR U15-P02-101 HPU H2 recycle compressor
Area B U15-P02 HPU COMPRESSOR U15-P02-201 HPU Start up N2 compressor
Area B U15-P70 HPU PKG U15-P70-101 HPU METHANOL INJECTION PACKAGE
Area B U15-SWA HPU SERVICE WATER U15-SWA-101 HPU SERVICE WATER
Area B U15-UTA HPU UTILITY AIR U15-UTA-101 HPU UTILITY AIR
Area B U15-VT HPU Vent Line U15-VT-101 HPU Vent Line
Area C U16-AMW GSARU AMINE DRAIN U16-AMW-101 GSARU AMINE DRAIN
Area C U16-CND GSARU CLEAN CONDENSATE U16-CND-101 GSARU CLEAN CONDENSATE
Area C U16-CW GSARU CW SUPPLY U16-CW-101 GSARU CW
Area C U16-DWA GSARU DEMIWATER U16-DWA-101 GSARU DEMIWATER
Area C U16-FLA GSARU ACID FLARE U16-FLA-101 GSARU ACID FLARE
Area C U16-FUG GSARU FUEL GAS U16-FUG-101 GSARU FUEL GAS
Area C U16-FWA GSARU FIREWATER NETWORK U16-FWA-101 GSARU FIREWATER NETWORK(UG)
Area C U16-FWA GSARU FIREWATER NETWORK U16-FWA-102 GSARU FIREWATER NETWORK(AG)
Area C U16-INA GSARU INSTRUMENT AIR U16-INA-101 GSARU INSTRUMENT AIR
Area C U16-LPC GSARU LP CONDENSATE U16-LPC-101 GSARU LP CONDENSATE
Area C U16-LPS GSARU LP STEAM U16-LPS-101 GSARU LP STEAM
Area C U16-MBFW GSARU MP BFW U16-MBFW-101 GSARU MP BFW
Area C U16-NIT GSARU N2 U16-NIT-101 GSARU N2
Area C U16-OWS GSARU OWS U16-OWS-101 GSARU OWS
Area C U16-P01 GSARU AMINE U16-P01-101 GSARU AMINE ABSORBER
Area C U16-P01 GSARU AMINE U16-P01-201 GSARU AMINE STORAGE
Area C U16-P01 GSARU AMINE U16-P01-301 GSARU AMINE REGENERATOR 1
Area C U16-P01 GSARU AMINE U16-P01-401 GSARU AMINE REGENERATOR 2
Area C U16-P70 GSARU PKG U16-P70-101 GSARU 16-PK-001 ANTI-FOAM
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area C U16-P70 GSARU PKG U16-P70-102 GSARU 16-PK-101 ANTI-FOAM
Area C U16-P70 GSARU PKG U16-P70-103 GSARU 16-PK-102 C/I
Area C U16-P70 GSARU PKG U16-P70-104 GSARU 16-PK-201 ANTI-FOAM
Area C U16-P70 GSARU PKG U16-P70-105 GSARU 16-PK-202 C/I
Area C U16-PWA GSARU DW U16-PWA-101 GSARU DW
Area C U16-SLP GSARU SLOP OIL U16-SLP-101 GSARU SLOP OIL
Area C U16-SWA GSARU SERVICE WATER U16-SWA-101 GSARU SERVICE WATER
Area C U16-UTA GSARU UTILITY AIR U16-UTA-101 GSARU UTILITY AIR
Area C U17-CAU SWS CAUSTIC U17-CAU-101 SWS CAUSTIC
Area C U17-CW SWS CW SUPPLY U17-CW-101 SWS CW
Area C U17-FLA SWS ACID FLARE U17-FLA-101 SWS ACID FLARE
Area C U17-FUG SWS FUEL GAS U17-FUG-101 SWS FUEL GAS
Area C U17-FWA SWS FIREWATER NETWORK U17-FWA-101 SWS FIREWATER NETWORK(UG)
Area C U17-FWA SWS FIREWATER NETWORK U17-FWA-102 SWS FIREWATER NETWORK(AG)
Area C U17-INA SWS INSTRUMENT AIR U17-INA-101 SWS INSTRUMENT AIR
Area C U17-LPC SWS LP CONDENSATE U17-LPC-101 SWS LP CONDENSATE
Area C U17-LPS SWS LP STEAM U17-LPS-101 SWS LP STEAM
Area C U17-MBFW SWS MP BFW U17-MBFW-101 SWS MP BFW
Area C U17-NIT SWS N2 U17-NIT-101 SWS N2
Area C U17-OWS SWS OWS U17-OWS-101 SWS OWS
Area C U17-P01 SWS SOUR WATER 1 U17-P01-101 SWS1 FEED DRUM & TANK
Area C U17-P01 SWS SOUR WATER 1 U17-P01-201 SWS1 STRIPPER
Area C U17-P01 SWS SOUR WATER 1 U17-P01-301 SWS1 STRIPPER BOTTOM
Area C U17-P02 SWS SOUR WATER 2 U17-P02-101 SWS2 FEED DRUM & TANK
Area C U17-P02 SWS SOUR WATER 2 U17-P02-201 SWS2 STRIPPER
Area C U17-P02 SWS SOUR WATER 2 U17-P02-301 SWS2 STRIPPER BOTTOM
Area C U17-SLP SWS SLOP OIL U17-SLP-101 SWS SLOP OIL
Area C U17-SRW SWS SOUR WATER DRAIN U17-SRW-101 SWS SOUR WATER DRAIN
Area C U17-SWA SWS SERVICE WATER U17-SWA-101 SWS SERVICE WATER
Area C U17-UTA SWS UTILITY AIR U17-UTA-101 SWS UTILITY AIR
Area C U18-AMW SRU1 AMINE DRAIN U18-AMW-101 SRU1 AMINE DRAIN
Area C U18-HBFW SRU1 HP BFW U18-HBFW-101 SRU1 HP BFW
Area C U18-HPC SRU1 HP CONDENSATE U18-HPC-101 SRU1 HP CONDENSATE 18-V-004
Area C U18-HPS SRU1 HP STEAM U18-HPS-101 SRU1 HP STEAM GENERATION & HEADER
Area C U18-INA SRU1 INSTRUMENT AIR U18-INA-101 SRU1 INSTRUMENT AIR
Area C U18-LPC SRU1 LP CONDENSATE U18-LPC-101 SRU1 LP CONDENSATE
Area C U18-LPS SRU1 LP STEAM U18-LPS-101 SRU1 LP STEAM
Area C U18-LPS SRU1 LP STEAM U18-LPS-102 SRU1 SATURATED LP STEAM
Area C U18-LPS SRU1 LP STEAM U18-LPS-103 SRU1 SUPERHEATED LP STEAM
Area C U18-MBFW SRU1 MP BFW U18-MBFW-101 SRU1 MP BFW
Area C U18-NIT SRU1 N2 U18-NIT-101 SRU1 N2
Area C U18-NTG SRU1 NATURAL GAS U18-NTG-101 SRU1 NATURAL GAS
Area C U18-P01 SRU1 U18-P01-101 SRU1 THERMAL REACTOR
Area C U18-P01 SRU1 U18-P01-201 SRU1 1ST CLAUS REACTOR
Area C U18-P01 SRU1 U18-P01-202 SRU1 2ND CLAUS REACTOR
Area C U18-P01 SRU1 U18-P01-301 SRU1 SULFUR PIT
Area C U18-P01 SRU1 U18-P01-401 SRU1 DEGASSING
Area C U18-P01 SRU1 U18-P01-501 SRU1 SULFUR TANK
Area C U18-PRA SRU1 COMBUSTION AIR (Process Air) U18-PRA-101 SRU1 COMBUSTION AIR (Process Air)
Area C U18-UTA SRU1 UTILITY AIR U18-UTA-101 SRU1 UTILITY AIR
Area C U19-AMW SRU2 AMINE DRAIN U19-AMW-101 SRU2 AMINE DRAIN
Area C U19-HBFW SRU2 HP BFW U19-HBFW-101 SRU2 HP BFW
Area C U19-HPC SRU2 HP CONDENSATE U19-HPC-101 SRU2 HP CONDENSATE 19-V-004
Area C U19-HPS SRU2 HP STEAM U19-HPS-101 SRU2 HP STEAM GENERATION & HEADER
Area C U19-INA SRU2 INSTRUMENT AIR U19-INA-101 SRU2 INSTRUMENT AIR
Area C U19-LPC SRU2 LP CONDENSATE U19-LPC-101 SRU2 LP CONDENSATE
Area C U19-LPS SRU2 LP STEAM U19-LPS-101 SRU2 LP STEAM
Area C U19-LPS SRU2 LP STEAM U19-LPS-102 SRU2 SATURATED LP STEAM
Area C U19-LPS SRU2 LP STEAM U19-LPS-103 SRU2 SUPERHEATED LP STEAM
Area C U19-MBFW SRU2 MP BFW U19-MBFW-101 SRU2 MP BFW
Area C U19-NIT SRU2 N2 U19-NIT-101 SRU2 N2
Area C U19-NTG SRU2 NATURAL GAS U19-NTG-101 SRU2 NATURAL GAS
Area C U19-P01 SRU2 U19-P01-101 SRU2 THERMAL REACTOR
Area C U19-P01 SRU2 U19-P01-201 SRU2 1ST CLAUS REACTOR
Area C U19-P01 SRU2 U19-P01-202 SRU2 2ND CLAUS REACTOR
Area C U19-P01 SRU2 U19-P01-301 SRU2 SULFUR PIT
Area C U19-P01 SRU2 U19-P01-401 SRU2 DEGASSING
Area C U19-P01 SRU2 U19-P01-501 SRU2 SULFUR TANK
Area C U19-PRA SRU2 COMBUSTION AIR U19-PRA-101 SRU2 COMBUSTION AIR
Area C U19-UTA SRU2 UTILITY AIR U19-UTA-101 SRU2 UTILITY AIR
Area C U20-AMW TGTU AMINE DRAIN U20-AMW-101 TGTU AMINE DRAIN
Area C U20-BDD TGTU BLOWDOWN U20-BDD-101 TGTU BLOWDOWN
Area C U20-CW TGTU CW SYSTEM U20-CW-101 TGTU CW
Area C U20-DWA TGTU DEMI WATER U20-DWA-101 TGTU DEMI WATER
Area C U20-FLA TGTU ACID FLARE U20-FLA-101 TGTU ACID FLARE
Area C U20-FUG TGTU FUEL GAS U20-FUG-101 TGTU FUEL GAS
Area C U20-FWA TGTU FIREWATER NETWORK U20-FWA-101 TGTU FIREWATER NETWORK(UG)
Area C U20-FWA TGTU FIREWATER NETWORK U20-FWA-102 TGTU FIREWATER NETWORK(AG)
Area C U20-HBFW TGTU HP BFW U20-HBFW-101 TGTU HP BFW
Area C U20-HPC TGTU HP CONDENSATE U20-HPC-101 TGTU HP CONDENSATE
Area C U20-HPS TGTU HP STEAM U20-HPS-101 TGTU HP STEAM
Area C U20-HYD TGTU H2 U20-HYD-101 TGTU H2
Area C U20-INA TGTU INSTRUMENT AIR U20-INA-101 TGTU INSTRUMENT AIR
Area C U20-LPC TGTU LP CONDENSATE U20-LPC-101 TGTU LP CONDENSATE
Area C U20-LPS TGTU LP STEAM U20-LPS-101 TGTU LP STEAM
Area C U20-LPS TGTU LP STEAM U20-LPS-102 TGTU SATURATED LP STEAM
Area C U20-LPS TGTU LP STEAM U20-LPS-103 TGTU SUPERHEAT LP STEAM
Area C U20-MBFW TGTU MP BFW U20-MBFW-101 TGTU MP BFW
Area C U20-MPS TGTU MP STEAM U20-MPS-101 TGTU MP STEAM
Area C U20-MPS TGTU MP STEAM U20-MPS-102 TGTU MP STEAM GENERATION 20-V-005
Area C U20-NIT TGTU NITROGEN U20-NIT-101 TGTU NITROGEN
Area C U20-NTG TGTU NATURAL GAS U20-NTG-101 TGTU NATURAL GAS for 20/18/19
Area C U20-OWS TGTU OWS U20-OWS-101 TGTU OWS
Area C U20-P01 TGTU SEPARATION U20-P01-101 TGTU AMINE ACID GAS SEPARATOR
Area C U20-P01 TGTU SEPARATION U20-P01-201 TGTU SWS ACID GAS SEPARATOR
Area C U20-P01 TGTU SEPARATION U20-P01-301 TGTU AIR BLOWER
Area C U20-P02 TGTU TREATING U20-P02-101 TGTU HYDROGENATION
Area C U20-P02 TGTU TREATING U20-P02-201 TGTU QUENCH
Area C U20-P02 TGTU TREATING U20-P02-301 TGTU INCINERATOR
Area C U20-P02 TGTU TREATING U20-P02-401 TGTU RECYCLE GAS
Area C U20-P03 TGTU AMINE U20-P03-101 TGTU AMINE ABSORBER
Area C U20-P03 TGTU AMINE U20-P03-201 TGTU AMINE REGENERATOR
Area C U20-P03 TGTU AMINE U20-P03-301 TGTU AMINE REGENERATION ACID GAS
Area C U20-P03 TGTU AMINE U20-P03-401 TGTU AMINE STORAGE
Area C U20-P70 TGTU PKG U20-P70-101 TGTU PHOSPHATE INJECTION PACKAGE
Area C U20-P70 TGTU PKG U20-P70-102 TGTU ANTI-FOAM INJECTION PACKAGE
Area C U20-PWA TGTU DW U20-PWA-101 TGTU DW
Area C U20-SWA TGTU SERVICE WATER U20-SWA-101 TGTU SERVICE WATER
Area C U20-UTA TGTU UTILITY AIR U20-UTA-101 TGTU UTILITY AIR
Area A U30-CAU RWT CAUSTIC U30-CAU-101 RWT CAUSTIC SOLUTION
Area A U30-FWA RWT FIRE WATER U30-FWA-101 RWT(30) FIRE WATER NETWORK(UG)
Area A U30-FWA RWT FIRE WATER U30-FWA-102 RWT(30) FIRE WATER NETWORK(AG)
Area A U30-INA RWT INSTRUMENT AIR U30-INA-101 RWT INSTRUMENT AIR
Area A U30-LPC RWT LP CONDENSATE U30-LPC-101 RWT LP CONDENSATE
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area A U30-LPS RWT LP STEAM U30-LPS-101 RWT LP STEAM
Area A U30-NIT RWT N2 SERVICE U30-NIT-101 RWT N2 SERVICE
Area A U30-OWS RWT OWS U30-OWS-101 RWT OWS
Area A U30-P01 RWT WATER U30-P01-101 RWT WATER RECEIVING STORAGE & PUMP
Area A U30-P01 RWT WATER U30-P01-101A RWT WATER RECEIVING STORAGE & PUMP (Train A)
Area A U30-P01 RWT WATER U30-P01-101B RWT WATER RECEIVING STORAGE & PUMP (Train B)
Area A U30-P01 RWT WATER U30-P01-102 RWT IRRIGATION & STORM WATER STORAGE & PUMP
Area A U30-P01 RWT WATER U30-P01-103 RWT CLARIFIED WATER & STORAGE
Area A U30-P01 RWT WATER U30-P01-103A RWT CLARIFIED WATER & STORAGE (Train A)
Area A U30-P01 RWT WATER U30-P01-103B RWT CLARIFIED WATER & STORAGE (Train B)
Area A U30-P01 RWT WATER U30-P01-104 RWT SLUDGE TREATMENT
Area A U30-P01 RWT WATER U30-P01-104A RWT SLUDGE TREATMENT (Train A)
Area A U30-P01 RWT WATER U30-P01-104B RWT SLUDGE TREATMENT (Train B)
Area A U30-P01 RWT WATER U30-P01-105 RWT FILTERED WATER STORAGE & DISTRIBUTION
Area A U30-P01 RWT WATER U30-P01-105A RWT FILTERED WATER STORAGE & DISTRIBUTION (Train A)
Area A U30-P01 RWT WATER U30-P01-105B RWT FILTERED WATER STORAGE & DISTRIBUTION (Train B)
Area A U30-P01 RWT WATER U30-P01-201 RWT UF WATER & STORAGE
Area A U30-P01 RWT WATER U30-P01-201A RWT UF WATER & STORAGE (Train A)
Area A U30-P01 RWT WATER U30-P01-201B RWT UF WATER & STORAGE (Train B)
Area A U30-P01 RWT WATER U30-P01-202 RWT 1ST RO WATER & STORAGE
Area A U30-P01 RWT WATER U30-P01-202A RWT 1ST RO WATER & STORAGE (Train A)
Area A U30-P01 RWT WATER U30-P01-202B RWT 1ST RO WATER & STORAGE (Train B)
Area A U30-P01 RWT WATER U30-P01-203 RWT 2ND RO WATER & STORAGE
Area A U30-P01 RWT WATER U30-P01-203A RWT 2ND RO WATER & STORAGE (Train A)
Area A U30-P01 RWT WATER U30-P01-203B RWT 2ND RO WATER & STORAGE (Train B)
Area A U30-P01 RWT WATER U30-P01-204 RWT DEMI WATER STORAGE & DISTRIBUTION
Area A U30-P01 RWT WATER U30-P01-204A RWT DEMI WATER STORAGE & DISTRIBUTION (Train A)
Area A U30-P01 RWT WATER U30-P01-204B RWT DEMI WATER STORAGE & DISTRIBUTION (Train B)
Area A U30-P70 RWT PKG U30-P70-101 RWT SULPHURIC ACID
Area A U30-PWA RWT DRINKING WATER U30-PWA-101 RWT DRINKING WATER
Area A U30-UTA RWT PLANT AIR U30-UTA-101 RWT PLANT AIR
Area A U31-FWA FW FIRE WATER U31-FWA-101 FW(31) FIRE WATER STORAGE & PUMP(UG)
Area A U31-FWA FW FIRE WATER U31-FWA-102 FW(31) FIRE WATER STORAGE & PUMP(AG)
Area A U33-CW CW COOLING WATER U33-CW-101 CWS COOLING TOWER BASIN & PUMP
Area A U33-CW CW COOLING WATER U33-CW-102 CWS COOLING TOWER & PUMP FOR BLACK START UP
Area A U33-FWA CW FIRE WATER U33-FWA-101 CW(33) FIRE WATER NETWORK(UG)
Area A U33-FWA CW FIRE WATER U33-FWA-102 CW(33) FIRE WATER NETWORK(AG)
Area A U33-HPC CW HP CONDENSATE U33-HPC-101 CW HP CONDENSATE
Area A U33-HPS CW HP STEAM U33-HPS-101 CW HP STEAM
Area A U33-INA CW INSTRUMENT AIR U33-INA-101 CW INSTRUMENT AIR
Area A U33-LPC CW LP CONDENSATE U33-LPC-101 CW LP CONDENSATE
Area A U33-LPS CW LP STEAM U33-LPS-101 CW LP STEAM
Area A U33-MBFW CW MP BFW U33-MBFW-101 CW MP BFW
Area A U33-MPC CW MP CONDENSATE U33-MPC-101 CW MP CONDENSATE
Area A U33-MPS CW MP STEAM U33-MPS-101 CW MP STEAM
Area A U33-OWS CW OWS U33-OWS-101 CW OWS
Area A U33-P70 CW PKG U33-P70-101 CW ANTI SCALE & DISPERSANT
Area A U33-P70 CW PKG U33-P70-102 CW CORROSION INHIBITOR
Area A U33-P70 CW PKG U33-P70-103 CW SODIUM HYPOCHLORITE SOLUTION
Area A U33-P70 CW PKG U33-P70-104 CW Side Stream Filter PKG
Area A U33-P70 CW PKG U33-P70-105 CW Sulphuric Acid
Area A U33-PWA CW DRINKING WATER U33-PWA-101 CW DRINKING WATER
Area A U33-SWA CW SERVICE WATER U33-SWA-101 CW SERVICE WATER
Area A U33-UTA CW PLANT AIR U33-UTA-101 CW PLANT AIR
Area A U34-FWA DWU FIRE WATER U34-FWA-102 DWU(34) FIRE WATER NETWORK(AG)
Area A U34-OWS DWU OWS U34-OWS-101 DWU OWS
Area A U34-P70 DWU DW CHLORINATION PKG U34-P70-101 DWU DW CHLORINATION PKG
Area A U34-PWA DWU DRINKING WATER U34-PWA-101 DWU 31/34/35/36 DRINKING WATER
Area A U35-CND CND CLEAN CONDENSATE U35-CND-101 CND 35-V-007 CONDENSATE
Area A U35-CND CND CLEAN CONDENSATE U35-CND-102 CND 35-V-008 CONDENSATE
Area A U35-CND CND CLEAN CONDENSATE U35-CND-103 CND FILTERED CONDENSATE & STORAGE
Area A U35-FWA CND FIRE WATER U35-FWA-102 CND(35) FIRE WATER NETWORK(AG)
Area A U35-HPC CND HP CONDENSATE U35-HPC-101 CND 35-V-005 HP CONDENSATE
Area A U35-LPC CND LP CONDENSATE U35-LPC-101 CND 35-V-001 LP CONDENSATE
Area A U35-LPC CND LP CONDENSATE U35-LPC-102 CND 35-V-002 LP CONDENSATE
Area A U35-LPC CND LP CONDENSATE U35-LPC-103 CND 35-V-003 LP CONDENSATE
Area A U35-LPC CND LP CONDENSATE U35-LPC-104 CND 35-V-004 LP CONDENSATE
Area A U35-MPC CND MP CONDENSATE U35-MPC-101 CND 35-V-006 MP CONDENSATE
Area A U35-OWS CND OWS U35-OWS-101 CND OWS
Area A U36-BDD SGU BLOW DOWN U36-BDD-101 SGU BLOW DOWN
Area A U36-CND SGU CLEAN CONDENSATE U36-CND-101 SGU CLEAN CONDENSATE
Area A U36-CW SGU Cooling Water Supply & Return U36-CW-101 SGU Cooling Water Supply & Return
Area A U36-DWA SGU DEMIWATER U36-DWA-101 SGU DEMIWATER
Area A U36-FLD SGU LP FALRE U36-FLD-101 SGU LP FALRE
Area A U36-FLU SGU FUEL GAS U36-FUG-101 SGU FUEL GAS FOR BOILER
Area A U36-FUO SGU FUEL OIL U36-FUO-101 SGU FUEL OIL SUPPLY & RETURN TO BOILER
Area A U36-FWA SGU FIRE WATER U36-FWA-101 SGU(36) FIRE WATER NETWORK(UG)
Area A U36-FWA SGU FIRE WATER U36-FWA-102 SGU(36) FIRE WATER NETWORK(AG)
Area A U36-HBFW SGU HP BFW U36-HBFW-101 SGU HP BFW
Area A U36-HPC SGU HP CONDENSATE U36-HPC-101 SGU HP CONDENSATE
Area A U36-HPS SGU HP STEAM U36-HPS-101 SGU HP STEAM
Area A U36-INA SGU INSTRUMENT AIR U36-INA-101 SGU INSTRUMENT AIR
Area A U36-LBFW SGU LP BFW U36-LBFW-101 SGU LP BFW
Area A U36-LLPS SGU LLP STEAM U36-LLPS-101 SGU LLP STEAM
Area A U36-LPC SGU LP CONDENSATE U36-LPC-101 SGU LP CONDENSATE
Area A U36-LPS SGU LP STEAM U36-LPS-101 SGU LP STEAM
Area A U36-MBFW SGU MP BFW U36-MBFW-101 SGU MP BFW
Area A U36-MPC SGU MP CONDENSATE U36-MPC-101 SGU MP CONDENSATE
Area A U36-MPS SGU MP STEAM U36-MPS-101 SGU MP STEAM
Area A U36-NIT SGU NITROGEN U36-NIT-101 SGU NITROGEN
Area A U36-OWS SGU OILY SEWER U36-OWS-101 SGU OILY SEWER
Area A U36-OWS SGU OILY SEWER U36-OWS-102 SGU OILY SEWER(AG)
Area A U36-P01 SGU BOILER U36-P01-101 SGU BOILER A
Area A U36-P01 SGU BOILER U36-P01-102 SGU BOILER B
Area A U36-P01 SGU BOILER U36-P01-103 SGU BOILER C
Area A U36-P02 SGU DEAERATOR U36-P02-101 SGU 36-V-001 DEAERATOR
Area A U36-P70 SGU PKG U36-P70-101 SGU PHOSPHATE INJECTION PACKAGE
Area A U36-P70 SGU PKG U36-P70-102 SGU FILMING AMINE INJECTION PACKAGE
Area A U36-P70 SGU PKG U36-P70-103 SGU OXYGEN SCAVENGER INJECTION PACKAGE
Area A U36-PWA SGU DRINKING WATER U36-PWA-101 SGU DRINKING WATER
Area A U36-SWA SGU SERVICE WATER U36-SWA-101 SGU SERVICE WATER
Area A U36-UTA SGU PLANT AIR U36-UTA-101 SGU PLANT AIR
Area A U37-BDD PGU HRSG BLOW DOWN U37-BDD-101 PGU HRSG BLOW-DOWN
Area A U37-CLD PGU CLOSED DRAIN U37-CLD-101 PGU CLOSED DRAIN
Area A U37-CND PGU CLEAN CONDENSATE U37-CND-101 PGU CLEAN CONDENSATE
Area A U37-CW PGU COOLING WATER U37-CW-101 PGU COOLING WATER SUPPLY & RETURN
Area A U37-CW PGU COOLING WATER U37-CW-102 PGU COOLING WATER SUPPLY & RETURN BLACK START UP
Area A U37-DWA PGU DEMI WATER U37-DWA-101 PGU DEMI WATER
Area A U37-FLD PGU LP FLARE U37-FLD-101 PGU LP FLARE
Area A U37-FLH PGU HP FLARE U37-FLH-101 PGU HP FLARE
Area A U37-FLU PGU FUEL GAS U37-FUG-101 PGU FUEL GAS
Area A U37-FUO PGU FUEL OIL U37-FUO-101 PGU FUEL OIL(include DIESEL/CYCLE OIL)
Area A U37-FWA PGU FIRE WATER U37-FWA-101 PGU(37) FIRE WATER NETWORK(UG)
Area A U37-FWA PGU FIRE WATER U37-FWA-102 PGU(37) FIRE WATER NETWORK(AG)
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area A U37-HBFW PGU HP BFW U37-HBFW-101 PGU HP BFW
Area A U37-HPC PGU HP CONDENSATE U37-HPC-101 PGU HP CONDENSATE
Area A U37-HPS PGU HP STEAM U37-HPS-101 PGU HP STEAM
Area A U37-INA PGU INSTRUMENT AIR U37-INA-101 PGU INSTRUMENT AIR
Area A U37-LPC PGU LP CONDENSATE U37-LPC-101 PGU LP CONDENSATE
Area A U37-LPS PGU LP STEAM U37-LPS-101 PGU LP STEAM
Area A U37-MPS PGU MP STEAM U37-MPS-101 PGU MP STEAM
Area A U37-NIT PGU NITROGEN U37-NIT-101 PGU NITROGEN
Area A U37-NTG PGU NATURAL GAS U37-NTG-101 PGU NATURAL GAS TO GTG
Area A U37-OWS PGU OWS U37-OWS-101 PGU OWS
Area A U37-P01 PGU GTG U37-P01-101 PGU GTG A
Area A U37-P01 PGU GTG U37-P01-102 PGU GTG B
Area A U37-P01 PGU GTG U37-P01-103 PGU GTG C
Area A U37-P01 PGU GTG U37-P01-104 PGU GTG D
Area A U37-P02 PGU HRSG U37-P02-101 PGU HRSG A
Area A U37-P02 PGU HRSG U37-P02-102 PGU HRSG B
Area A U37-P02 PGU HRSG U37-P02-103 PGU HRSG C
Area A U37-P02 PGU HRSG U37-P02-104 PGU HRSG D
Area A U37-P03 PGU STG U37-P03-101 PGU STG A
Area A U37-P03 PGU STG U37-P03-102 PGU STG B
Area A U37-P03 PGU STG U37-P03-103 PGU STG C
Area A U37-P03 PGU STG U37-P03-104 PGU STG D
Area A U37-P04 PGU GTG LUBE OIL U37-P04-101 PGU GTG LUBE OIL MAKE UP
Area A U37-P70 PGU PKG U37-P70-101 PGU PHOSPHATE PACKAGE
Area A U37-PWA PGU DRINKING WATER U37-PWA-101 PGU DRINKING WATER
Area A U37-SWA PGU SERVICE WATER U37-SWA-101 PGU SERVICE WATER
Area A U37-UTA PGU PLANT AIR U37-UTA-101 PGU PLANT AIR
Area A U41-CW APU COOLING WATER U41-CW-101 APU CW SUPPLY & RETURN
Area A U41-FWA APU FIRE WATER U41-FWA-101 APU(41) FIRE WATER NETWORK(UG)
Area A U41-FWA APU FIRE WATER U41-FWA-102 APU(41) FIRE WATER NETWORK(AG)
Area A U41-HBFW APU HP BFW U41-HBFW-101 APU HP BFW
Area A U41-HPC APU HP CONDENSATE U41-HPC-101 APU HP CONDENSATE
Area A U41-HPS APU HP STEAM U41-HPS-101 APU HP STEAM
Area A U41-INA APU INSTRUMENT AIR U41-INA-101 APU INSTRUMENT AIR
Area A U41-INA APU INSTRUMENT AIR U41-INA-102 APU INSTRUMENT AIR DRYERS PACKAGE
Area A U41-LPS APU LP STEAM U41-LPS-101 APU LP STEAM
Area A U41-OWS APU OWS U41-OWS-101 APU OWS
Area A U41-P01 APU COMPRESSOR U41-P01-101 APU COMPRESSOR A
Area A U41-P01 APU COMPRESSOR U41-P01-102 APU COMPRESSOR B
Area A U41-P01 APU COMPRESSOR U41-P01-103 APU COMPRESSOR C
Area A U41-PWA APU DRINKING WATER U41-PWA-101 APU DRINGKING WATER SUPPLY
Area A U41-SWA APU SERVICE WATER U41-SWA-101 APU SERVICE WATER
Area A U41-UTA APU PLANT AIR U41-UTA-101 APU PLANT AIR
Area A U42-FWA NGU FIRE WATER U42-FWA-102 NGU(42) FIRE WATER NETWORK(AG)
Area A U42-NIT NGU NITROGEN U42-NIT-101 NGU N2
Area A U42-P70 NGU N2 GENERATON PKG U42-P70-101 NGU N2 GENERATION PKG A
Area A U42-P70 NGU N2 GENERATON PKG U42-P70-102 NGU N2 GENERATION PKG FOR BLACK START-UP
Area A U43-CAU CSU STRONG CAUSTIC /DILUTED CAUSTIC U43-CAU-101 CSU STRONG CAUSTIC
Area A U43-CAU CSU STRONG CAUSTIC /DILUTED CAUSTIC U43-CAU-102 CSU DILUTED CAUSTIC
Area A U43-CW CSU COOLING WATER U43-CW-101 CSU CW SUPPLY & RETURN
Area A U43-DWA CSU DEMI WATER U43-DWA-101 CSU DEMI WATER
Area A U43-FWA CSU FIRE WATER U43-FWA-101 CSU(43) FIRE WATER NETWORK(UG)
Area A U43-FWA CSU FIRE WATER U43-FWA-102 CSU(43) FIRE WATER NETWORK(AG)
Area A U43-INA CSU INSTRUMENT AIR U43-INA-101 CSU INSTRUMENT AIR
Area A U43-LPC CSU LP CONDENSATE U43-LPC-101 CSU LP CONDENSATE
Area A U43-LPS CSU LP STEAM U43-LPS-101 CSU LP STEAM
Area A U43-OWS CSU AUXILIARY U43-OWS-101 CSU OWS
Area A U43-PWA CSU DRINGKING WATER U43-PWA-101 CSU DRINGKING WATER
Area A U43-SWA CSU SERVICE WATER U43-SWA-101 CSU SERVICE WATER
Area A U43-UTA CSU PLANT AIR U43-UTA-101 CSU PLANT AIR
Area C U44-CLG RFU LPG DRAIN U44-CLG-101 RFU LPG DRAIN
Area C U44-CW RFU CW SYSTEM U44-CW-101 RFU CW
Area C U44-FLD RFU LP FLARE U44-FLD-101 RFU LP FLARE
Area C U44-FLH RFU HP FLARE U44-FLH-101 RFU HP FLARE
Area C U44-FLO RFU FLUSHING OIL U44-FLO-101 RFU FLUSHING OIL
Area C U44-FUG RFU FUEL GAS U44-FUG-101 RFU FUEL GAS
Area C U44-FUO RFU REFINERY FUEL OIL /CLARIFIED SLURRY OIL /FUEL OIL BLENDING & DISTRIBUTION U44-FUO-101 RFU REFINERY FUEL OIL
Area C U44-FUO RFU REFINERY FUEL OIL /CLARIFIED SLURRY OIL /FUEL OIL BLENDING & DISTRIBUTION U44-FUO-102 RFU CLARIFIED SLURRY OIL
Area C U44-FUO RFU REFINERY FUEL OIL /CLARIFIED SLURRY OIL /FUEL OIL BLENDING & DISTRIBUTION U44-FUO-103 RFU FUEL OIL BLENDING & DISTRIBUTION
Area C U44-FWA RFU FIREWATER NETWORK U44-FWA-101 RFU FIREWATER NETWORK(UG)
Area C U44-FWA RFU FIREWATER NETWORK U44-FWA-102 RFU FIREWATER NETWORK(AG)
Area C U44-INA RFU INSTRUMENT AIR U44-INA-101 RFU INSTRUMENT AIR
Area C U44-LPC RFU LP CONDENSATE U44-LPC-101 RFU LP CONDENSATE
Area C U44-LPS RFU LP STEAM U44-LPS-101 RFU LP STEAM
Area C U44-MPC RFU MP CONDENSATE U44-MPC-101 RFU MP CONDENSATE
Area C U44-MPS RFU MP STEAM U44-MPS-101 RFU MP STEAM
Area C U44-NIT RFU NITROGEN U44-NIT-101 RFU NITROGEN
Area C U44-OWS RFU OWS U44-OWS-101 RFU OWS
Area C U44-SWA RFU SERVICE WATER U44-SWA-101 RFU SERVICE WATER
Area C U44-UTA RFU UTILITY AIR U44-UTA-101 RFU UTILITY AIR
Area B U45-CLD NGR AUXILIARY U45-CLD-101 NGR CLOSED DRAIN
Area B U45-NTG NGR NATURAL GAS U45-NTG-101 NGR RECEIVING & METERING
Area B U45-NTG NGR NATURAL GAS U45-NTG-102 NGR RECEIVING & METERING(OSBL)
Area B U45-VT NGR Vent Line U45-VT-101 NGR Vent Line
Area B U50-CW FLU COOLING WATER U50-CW-101 FLU CWS
Area B U50-CW FLU COOLING WATER U50-CW-102 FLU CWR
Area B U50-FLA FLU ACID FLARE U50-FLA-101 FLU ACID FLARE HEADER and STACK
Area B U50-FLD FLU LP FLARE U50-FLD-101 FLU LP FLARE HEADER and STACK
Area B U50-FLH FLU HP FLARE U50-FLH-101 FLU HP FLARE HEADER and STACK
Area B U50-FUG FLU FUEL GAS U50-FUG-101 FLU FUEL GAS
Area B U50-FWA FLU FIRE WATER NETWORK U50-FWA-101 FLU FIRE WATER NETWORK(UG)
Area B U50-FWA FLU FIRE WATER NETWORK U50-FWA-102 FLU FIRE WATER NETWORK(AG)
Area B U50-INA FLU INSTRUMENT AIR U50-INA-101 FLU INSTRUMENT AIR
Area B U50-LPC FLU LP CONDENSATE U50-LPC-101 FLU LP CONDENSATE
Area B U50-LPS FLU LP STEAM U50-LPS-101 FLU LP STEAM
Area B U50-MPC FLU MP CONDENSATE U50-MPC-101 FLU MP CONDENSATE
Area B U50-MPS FLU MP STEAM U50-MPS-101 FLU MP STEAM
Area B U50-NIT FLU N2 U50-NIT-101 FLU N2
Area B U50-OWS FLU OWS U50-OWS-101 FLU OWS
Area B U50-SRW FLU SOUR WATER U50-SRW-101 FLU SOUR WATER to SWS
Area B U50-SWA FLU SERVICE WATER U50-SWA-101 FLU SERVICE WATER
Area B U50-UTA FLU PLANT AIR U50-UTA-101 FLU PLANT AIR
Area B U50-VT Flare Vent Line U50-VT-101 Flare Vent Line
Area A U51-CW WWT COOLING WATER U51-CW-101 WWT CW SUPPLY & Return
Area A U51-FLD WWT LP FLARE U51-FLD-101 WWT LP FLARE
Area A U51-FLU WWT FUEL GAS U51-FUG-101 WWT FUEL GAS
Area A U51-FWA WWT FIRE WATER U51-FWA-101 WWT(51) FIRE WATER NETWORK(UG)
Area A U51-FWA WWT FIRE WATER U51-FWA-102 WWT(51) FIRE WATER NETWORK(AG)
Area A U51-INA10 WWT INSTRUMENT AIR(5D51) U51-INA10-101 WWT INSTRUMENT AIR(5D51)
Area A U51-INA20 WWT INSTRUMENT AIR(5A51) U51-INA20-101 WWT INSTRUMENT AIR(5A51)
Area A U51-INA30 WWT INSTRUMENT AIR(4A51) U51-INA30-101 WWT INSTRUMENT AIR(4A51)
Area A U51-LPC WWT LP CONDENSATE U51-LPC-101 WWT LP CONDENSATE
Area A U51-LPS10 WWT LP STEAM(5D51) U51-LPS10-101 WWT LP STEAM(5D51)
Area A U51-LPS20 WWT LP STEAM(5A51) U51-LPS20-101 WWT LP STEAM(5A51)
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area A U51-LPS30 WWT LP STEAM(4A51) U51-LPS30-101 WWT LP STEAM(4A51)
Area A U51-MPS WWT MP STEAM U51-MPS-101 WWT MP STEAM
Area A U51-NIT10 WWT N2 U51-NIT10-101 WWT N2
Area A U51-NIT20 WWT N2(4A51) U51-NIT20-101 WWT N2(4A51)
Area A U51-NIT30 WWT N2(4A51) U51-NIT30-101 WWT N2(4A51)
Area A U51-OWS WWT OWS U51-OWS-101 WWT OWS
Area A U51-P01 WWT PRIMARY U51-P01-101 WWT API SEPARATOR
Area A U51-P01 WWT PRIMARY U51-P01-101A WWT API SEPARATOR (Train A)
Area A U51-P01 WWT PRIMARY U51-P01-101B WWT API SEPARATOR (Train B)
Area A U51-P01 WWT PRIMARY U51-P01-102 WWT SPENT CAUSTIC
Area A U51-P01 WWT PRIMARY U51-P01-103 WWT SULFURIC ACID
Area A U51-P01 WWT PRIMARY U51-P01-104 WWT EQULIZATION
Area A U51-P01 WWT PRIMARY U51-P01-104A WWT EQULIZATION (Train A)
Area A U51-P01 WWT PRIMARY U51-P01-104B WWT EQULIZATION (Train B)
Area A U51-P01 WWT PRIMARY U51-P01-105 WWT DAF SYSTEM
Area A U51-P02 WWT SECONDARY U51-P02-101 WWT BIO & MBR TREATED WATER
Area A U51-P02 WWT SECONDARY U51-P02-101A WWT BIO & MBR TREATED WATER (Train A)
Area A U51-P02 WWT SECONDARY U51-P02-101B WWT BIO & MBR TREATED WATER (Train B)
Area A U51-P02 WWT SECONDARY U51-P02-102 WWT BIO & MBR TREATED WATER TANK
Area A U51-P03 WWT TERTIARY U51-P03-101 WWT REVERSE OSMOSIS SECTION
Area A U51-P03 WWT TERTIARY U51-P03-101A WWT REVERSE OSMOSIS SECTION (Train A)
Area A U51-P03 WWT TERTIARY U51-P03-101B WWT REVERSE OSMOSIS SECTION (Train B)
Area A U51-P03 WWT TERTIARY U51-P03-102A WWT REVERSE OSMOSIS SECTION (Train A)
Area A U51-P03 WWT TERTIARY U51-P03-102B WWT REVERSE OSMOSIS SECTION (Train B)
Area A U51-P03 WWT TERTIARY U51-P03-103 WWT REVERSE OSMOSIS SECTION
Area A U51-P03 WWT TERTIARY U51-P03-104 WWT REVERSE OSMOSIS SECTION
Area A U51-P04 WWT WATER COLLECTION U51-P04-101 WWT OILY WATER & CLEAN STORM WATER COLLECTION (5D51)
Area A U51-P05 WWT CLEAN COLLECTION(5D51) /SLUDGE U51-P05-101 WWT SLUDGE AND DEWATERING
Area A U51-P05 WWT CLEAN COLLECTION(5D51) /SLUDGE U51-P05-101A WWT SLUDGE AND DEWATERING (Train A)
Area A U51-P05 WWT CLEAN COLLECTION(5D51) /SLUDGE U51-P05-101B WWT SLUDGE AND DEWATERING (Train B)
Area A U51-P05 WWT CLEAN COLLECTION(5D51) /SLUDGE U51-P05-102 WWT INCINERATOR
Area A U51-P06 WWT CLEAN COLLECTION(4A51) U51-P06-101 WWT OILY WATER & CLEAN STORM WATER COLLECTION (5A51)
Area A U51-P07 WWT CLEAN COLLECTION(5A51) U51-P07-101 WWT OILY WATER & CLEAN STORM WATER COLLECTION (4A51)
Area A U51-P70 WWT PKG U51-P70-101 WWT NAOH STORAGE & DOSING(PK-005)
Area A U51-P70 WWT PKG U51-P70-102 WWT H2SO4 STORAGE & DOSING(PK-006)
Area A U51-P70 WWT PKG U51-P70-103 WWT COAGULANT ST & DOSING(PK-007)
Area A U51-P70 WWT PKG U51-P70-104 WWT POLY ST & DOSING(PK-008)
Area A U51-P70 WWT PKG U51-P70-105 WWT H3PO4 ST & DOSING(PK-009)
Area A U51-P70 WWT PKG U51-P70-106 WWT UREA ST & DOSING(PK-020)
Area A U51-P70 WWT PKG U51-P70-107 WWT SANITARY LIFT STATION PIT
Area A U51-PWA WWT DRINKING WATER U51-PWA-101 WWT DRINKING WATER
Area A U51-SWA WWT SERVICE WATER U51-SWA-101 WWT SERVICE WATER
Area A U51-UTA10 WWT PLANT AIR(5D51) U51-UTA10-101 WWT PLANT AIR(5D51)
Area A U51-UTA20 WWT PLANT AIR(5A51) U51-UTA20-101 WWT PLANT AIR(5A51)
Area A U51-UTA30 WWT PLANT AIR(4A51) U51-UTA30-101 WWT PLANT AIR(4A51)
Area B U52-CLD10 TFU CRUDE CLOSED DRAIN U52-CLD10-101 TFU CRUDE DRAIN 52-V-101
Area B U52-CLD20 TFU INTERM CLOSED DRAIN U52-CLD20-101 TFU INTERM AREA DRAIN & LIGHT SLOP 52-V-001
Area B U52-CLD20 TFU INTERM CLOSED DRAIN U52-CLD20-102 TFU INTERM AREA DRAIN & HEAVY SLOP 52-V-002
Area B U52-CLD30 TFU COMPO CLOSED DRAIN U52-CLD30-101 TFU COMPO AREA DRAIN & LIGHT SLOP 52-V-003
Area B U52-CLD30 TFU COMPO CLOSED DRAIN U52-CLD30-102 TFU COMPO AREA DRAIN & HEAVY SLOP 52-V-004
Area B U52-CLD40 TFU PROD CLOSED DRAIN U52-CLD40-101 TFU PROD AREA DRAIN & LIGHT SLOP 52-V-005
Area B U52-CLD40 TFU PROD CLOSED DRAIN U52-CLD40-102 TFU PROD AREA DRAIN & HEAVY SLOP 52-V-006
Area B U52-CLD40 TFU PROD CLOSED DRAIN U52-CLD40-103 TFU PROD AREA DRAIN (METERING PKG AREA)
Area B U52-CW10 TFU CRUDE COOLING WATER U52-CW10-101 TFU CRUDE AREA 4" COOLING WATER SUPPLY
Area B U52-CW10 TFU CRUDE COOLING WATER U52-CW10-102 TFU CRUDE AREA 4" COOLING WATER RETURN
Area B U52-CW20 TFU INTERM COOLING WATER U52-CW20-101 TFU INTERM AREA 3" COOLING WATER SUPPLY-1
Area B U52-CW20 TFU INTERM COOLING WATER U52-CW20-102 TFU INTERM AREA 3" COOLING WATER RETURN-1
Area B U52-CW20 TFU INTERM COOLING WATER U52-CW20-103 TFU INTERM AREA 2" COOLING WATER SUPPLY-1
Area B U52-CW20 TFU INTERM COOLING WATER U52-CW20-104 TFU INTERM AREA 2" COOLING WATER RETURN-1
Area B U52-CW20 TFU INTERM COOLING WATER U52-CW20-105 TFU INTERM AREA 3" COOLING WATER SUPPLY-2
Area B U52-CW20 TFU INTERM COOLING WATER U52-CW20-106 TFU INTERM AREA 3" COOLING WATER RETURN-2
Area B U52-CW30 TFU COMPO COOLING WATER U52-CW30-101 TFU COMPO AREA 4" COOLING WATER SUPPLY
Area B U52-CW30 TFU COMPO COOLING WATER U52-CW30-102 TFU COMPO AREA 4" COOLING WATER RETURN
Area B U52-CW30 TFU COMPO COOLING WATER U52-CW30-103 TFU COMPO AREA 3" COOLING WATER SUPPLY-1
Area B U52-CW30 TFU COMPO COOLING WATER U52-CW30-104 TFU COMPO AREA 3" COOLING WATER RETURN-1
Area B U52-CW30 TFU COMPO COOLING WATER U52-CW30-105 TFU COMPO AREA 3" COOLING WATER SUPPLY-2
Area B U52-CW30 TFU COMPO COOLING WATER U52-CW30-106 TFU COMPO AREA 3" COOLING WATER RETURN-2
Area B U52-CW40 TFU PROD COOLING WATER U52-CW40-101 TFU PROD AREA 3" COOLING WATER SUPPLY
Area B U52-CW40 TFU PROD COOLING WATER U52-CW40-102 TFU PROD AREA 3" COOLING WATER RETURN
Area B U52-CW40 TFU PROD COOLING WATER U52-CW40-103 TFU PROD AREA 4" COOLING WATER SUPPLY
Area B U52-CW40 TFU PROD COOLING WATER U52-CW40-104 TFU PROD AREA 4" COOLING WATER RETURN
Area B U52-CW50 TFU INTERM(H) COOLING WATER U52-CW50-101 TFU INTERM(H) AREA 2" COOLING WATER SUPPLY-1
Area B U52-CW50 TFU INTERM(H) COOLING WATER U52-CW50-102 TFU INTERM(H) AREA 2" COOLING WATER RETURN-1
Area B U52-FLD10 TFU CRUDE LP FLARE U52-FLD10-101 TFU CRUDE/NG AREA 24" LP FLARE
Area B U52-FLD10 TFU CRUDE LP FLARE U52-FLD10-102 TFU METERING PKG LP FLARE
Area B U52-FLD20 TFU INTERM LP FLARE U52-FLD20-101 TFU INTERM AREA 6" LP FLARE-1
Area B U52-FLD20 TFU INTERM LP FLARE U52-FLD20-102 TFU INTERM AREA 6" LP FLARE-2
Area B U52-FLD30 TFU COMPO LP FLARE U52-FLD30-101 TFU COMPO AREA 10" LP FLARE
Area B U52-FLD30 TFU COMPO LP FLARE U52-FLD30-102 TFU COMPO AREA 4" LP FLARE
Area B U52-FLD30 TFU COMPO LP FLARE U52-FLD30-103 TFU BULLET AREA 16" LP FLARE(52-V-401)
Area B U52-FLD40 TFU PROD LP FLARE U52-FLD40-101 TFU PROD AREA 12" LP FLARE
Area B U52-FLD40 TFU PROD LP FLARE U52-FLD40-102 TFU PROD AREA 3" LP FLARE
Area B U52-FLD40 TFU PROD LP FLARE U52-FLD40-103 TFU METERING PKG LP FLARE
Area B U52-FLO20 TFU INTERM FLUSHING OIL U52-FLO20-101 TFU INTERM AREA 4" FLUSHING OIL-1
Area B U52-FLO20 TFU INTERM FLUSHING OIL U52-FLO20-102 TFU INTERM AREA 4" FLUSHING OIL-2
Area B U52-FLO30 TFU COMPO FLUSHING OIL U52-FLO30-101 TFU COMPO AREA 4" FLUSHING OIL
Area B U52-FLO40 TFU PROD FLUSHING OIL U52-FLO40-101 TFU FLUSHING OIL TANK 52-TK-003A/B & PUMP
Area B U52-FLO50 TFU INTERM(H) FLUSHING OIL U52-FLO50-101 TFU INTERM AREA 4" FLUSHING OIL-3
Area B U52-FUG10 TFU CRUDE FUEL GAS U52-FUG10-101 TFU CRUDE/NG AREA 2" FUEL GAS
Area B U52-FUG20 TFU INTERM FUEL GAS U52-FUG20-101 TFU INTERM AREA 2" FUEL GAS-1
Area B U52-FUG20 TFU INTERM FUEL GAS U52-FUG20-102 TFU INTERM AREA 2" FUEL GAS-2
Area B U52-FUG30 TFU COMPO FUEL GAS U52-FUG30-101 TFU COMPO AREA 2" FUEL GAS-1
Area B U52-FUG30 TFU COMPO FUEL GAS U52-FUG30-102 TFU COMPO AREA 2" FUEL GAS-2
Area B U52-FUG30 TFU COMPO FUEL GAS U52-FUG30-103 TFU COMPO AREA 2" FUEL GAS-3
Area B U52-FUG40 TFU PROD FUEL GAS U52-FUG40-101 TFU PROD AREA 2" FUEL GAS-1
Area B U52-FUG40 TFU PROD FUEL GAS U52-FUG40-102 TFU PROD AREA 2" FUEL GAS-2
Area B U52-FUG40 TFU PROD FUEL GAS U52-FUG40-103 TFU PROD AREA 2" FUEL GAS-3
Area B U52-FWA10 TFU CRUDE FIRE WATER U52-FWA10-101 TFU CRUDE FIRE WATER NETWORK(UG)
Area B U52-FWA10 TFU CRUDE FIRE WATER U52-FWA10-102 TFU CRUDE FIRE WATER NETWORK(AG)
Area B U52-FWA20 TFU INTERM FIRE WATER U52-FWA20-101 TFU INTERM FIRE WATER NETWORK(UG)
Area B U52-FWA20 TFU INTERM FIRE WATER U52-FWA20-102 TFU INTERM FIRE WATER NETWORK(AG)
Area B U52-FWA30 TFU COMPO FIRE WATER U52-FWA30-101 TFU COMPO FIRE WATER NETWORK(UG)
Area B U52-FWA30 TFU COMPO FIRE WATER U52-FWA30-102 TFU COMPO FIRE WATER NETWORK(AG)
Area B U52-FWA40 TFU PROD FIRE WATER U52-FWA40-101 TFU PROD FIRE WATER NETWORK(UG)
Area B U52-FWA40 TFU PROD FIRE WATER U52-FWA40-102 TFU PROD FIRE WATER NETWORK(AG)
Area B U52-FWA50 TFU INTERM(H) FIRE WATER U52-FWA50-101 TFU INTERM(H) FIRE WATER NETWORK(UG)
Area B U52-FWA50 TFU INTERM(H) FIRE WATER U52-FWA50-102 TFU INTERM(H) FIRE WATER NETWORK(AG)
Area B U52-HPC10 TFU CRUDE HP CONDENSATE U52-HPC10-101 TFU CRUDE/NG AREA 2" HP CONDENSATE
Area B U52-HPS10 TFU CRUDE HP STEAM U52-HPS10-101 TFU CRUDE/NG AREA 16" HP STEAM
Area B U52-INA10 TFU CRUDE INSTRUMENT AIR U52-INA10-101 TFU CRUDE/NG AREA 2" IA
Area B U52-INA20 TFU INTERM INSTRUMENT AIR U52-INA20-101 TFU INTERM AREA 2" IA-1
Area B U52-INA20 TFU INTERM INSTRUMENT AIR U52-INA20-102 TFU INTERM AREA 2" IA-2
Area B U52-INA20 TFU INTERM INSTRUMENT AIR U52-INA20-103 TFU INTERM AREA 2" IA-3
Area B U52-INA30 TFU COMPO INSTRUMENT AIR U52-INA30-101 TFU COMPO AREA 2" IA-1
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area B U52-INA30 TFU COMPO INSTRUMENT AIR U52-INA30-102 TFU COMPO AREA 2" IA-2
Area B U52-INA30 TFU COMPO INSTRUMENT AIR U52-INA30-103 TFU COMPO AREA 2" IA-3
Area B U52-INA40 TFU PROD INSTRUMENT AIR U52-INA40-101 TFU PROD AREA 2" IA-1
Area B U52-INA40 TFU PROD INSTRUMENT AIR U52-INA40-102 TFU PROD AREA 2" IA-2
Area B U52-INA50 TFU INTERM(H) INSTRUMENT AIR U52-INA50-101 TFU INTERM AREA 2" IA-4
Area B U52-LPC10 TFU CRUDE LP CONDENSATE U52-LPC10-101 TFU CRUDE/NG AREA 2" LP CONDENSATE
Area B U52-LPC20 TFU INTERM LP CONDENSATE U52-LPC20-101 TFU INTERM 4" LP CONDENSATE
Area B U52-LPC20 TFU INTERM LP CONDENSATE U52-LPC20-102 TFU INTERM 6" LP CONDENSATE
Area B U52-LPC20 TFU INTERM LP CONDENSATE U52-LPC20-103 TFU INTERM 2" LP CONDENSATE
Area B U52-LPC30 TFU COMPO LP CONDENSATE U52-LPC30-101 TFU COMPO AREA 6" LP CONDENSATE
Area B U52-LPC30 TFU COMPO LP CONDENSATE U52-LPC30-102 TFU COMPO AREA 2" LP CONDENSATE-1
Area B U52-LPC30 TFU COMPO LP CONDENSATE U52-LPC30-103 TFU COMPO AREA 2" LP CONDENSATE-2
Area B U52-LPC40 TFU PROD LP CONDENSATE U52-LPC40-101 TFU PROD AREA 8" LP CONDENSATE
Area B U52-LPC40 TFU PROD LP CONDENSATE U52-LPC40-102 TFU PROD AREA 2" LP CONDENSATE
Area B U52-LPC50 TFU INTERM(H) LP CONDENSATE U52-LPC50-101 TFU INTERM(H) 2" LP CONDENSATE
Area B U52-LPS10 TFU CRUDE LP STEAM U52-LPS10-101 TFU CRUDE/NG AREA 2" LP STEAM
Area B U52-LPS20 TFU INTERM LP STEAM U52-LPS20-101 TFU INTERM AREA 6" LP STEAM
Area B U52-LPS20 TFU INTERM LP STEAM U52-LPS20-102 TFU INTERM AREA 8" LP STEAM
Area B U52-LPS20 TFU INTERM LP STEAM U52-LPS20-103 TFU INTERM AREA 3" LP STEAM
Area B U52-LPS30 TFU COMPO LP STEAM U52-LPS30-101 TFU COMPO AREA 8" LP STEAM-1
Area B U52-LPS30 TFU COMPO LP STEAM U52-LPS30-102 TFU COMPO AREA 3" LP STEAM
Area B U52-LPS30 TFU COMPO LP STEAM U52-LPS30-103 TFU COMPO AREA 8" LP STEAM-2
Area B U52-LPS40 TFU PROD LP STEAM U52-LPS40-101 TFU PROD AREA 14" LP STEAM
Area B U52-LPS40 TFU PROD LP STEAM U52-LPS40-102 TFU PROD AREA 3" LP STEAM
Area B U52-LPS50 TFU INTERM(H) LP STEAM U52-LPS50-101 TFU INTERM(H) AREA 2" LP STEAM
Area B U52-MBFW10 TFU CRUDE MP BOILER FEED WATER U52-MBFW10-101 TFU CRUDE/NG AREA 2" MP BFW
Area B U52-MPC50 TFU INTERM(H) MP CONDENSATE U52-MPC50-101 TFU INTERM(H) 2" MP CONDENSATE
Area B U52-MPS30 TFU COMPO MP STEAM U52-MPS30-101 TFU COMPO AREA 8" MP STEAM
Area B U52-MPS30 TFU COMPO MP STEAM U52-MPS30-102 TFU COMPO AREA 2" MP STEAM
Area B U52-MPS40 TFU PROD MP STEAM U52-MPS40-101 TFU PROD AREA 10" MP STEAM
Area B U52-MPS40 TFU PROD MP STEAM U52-MPS40-102 TFU PROD AREA 4" MP STEAM
Area B U52-NIT10 TFU CRUDE NITROGEN U52-NIT10-101 TFU CRUDE/NG AREA 3' N2
Area B U52-NIT20 TFU INTERM NITROGEN U52-NIT20-101 TFU INTERM AREA 4" N2-1
Area B U52-NIT20 TFU INTERM NITROGEN U52-NIT20-102 TFU INTERM AREA 4" N2-2
Area B U52-NIT20 TFU INTERM NITROGEN U52-NIT20-103 TFU INTERM AREA 4" N2-3
Area B U52-NIT30 TFU COMPO NITROGEN U52-NIT30-101 TFU COMPO AREA 4" N2
Area B U52-NIT30 TFU COMPO NITROGEN U52-NIT30-102 TFU COMPO AREA 6" N2
Area B U52-NIT30 TFU COMPO NITROGEN U52-NIT30-103 TFU COMPO AREA 2" N2
Area B U52-NIT40 TFU PROD NITROGEN U52-NIT40-101 TFU PROD AREA 8" N2
Area B U52-NIT40 TFU PROD NITROGEN U52-NIT40-102 TFU PROD AREA 6" N2
Area B U52-NIT50 TFU INTERM(H) NITROGEN U52-NIT50-101 TFU INTERM AREA 2" N2
Area B U52-OWS10 TFU CRUDE OWS U52-OWS10-101 TFU CRUDE OWS
Area B U52-OWS20 TFU INTERM OWS U52-OWS20-101 TFU INTERM OWS
Area B U52-OWS30 TFU COMPO OWS U52-OWS30-101 TFU COMPO OWS
Area B U52-OWS40 TFU PROD OWS U52-OWS40-101 TFU PROD OWS
Area B U52-OWS50 TFU INTERM(H) OWS U52-OWS50-101 TFU INTERM(H) OWS
Area B U52-P73 TFU COMPO PKG U52-P73-101 TFU DYE INJECTION PKG 52-PK-301
Area B U52-P73 TFU COMPO PKG U52-P73-102 TFU ANTI-OXIDANT PKG 52-PK-302
Area B U52-P73 TFU COMPO PKG U52-P73-103 TFU ASTATIC DISSIPATOR PKG 52-PK-303
Area B U52-P73 TFU COMPO PKG U52-P73-104 TFU ATK LUBRICITY PKG 52-PK-304
Area B U52-P73 TFU COMPO PKG U52-P73-105 TFU DIESEL LUBRICITY PKG 52-PK-305
Area B U52-P73 TFU COMPO PKG U52-P73-106 TFU ANTI-OXIDANT PKG 52-PK-306
Area B U52-P74 TFU PROD PKG U52-P74-101 TFU REGULAR GASOLINE METERING PKG 52-PK-401
Area B U52-P74 TFU PROD PKG U52-P74-102 TFU PREMIUM GASOLINE METERING PKG 52-PK-402
Area B U52-P74 TFU PROD PKG U52-P74-103 TFU KEROSENE METERING PKG 52-PK-403
Area B U52-P74 TFU PROD PKG U52-P74-104 TFU AVIATION TURBINE KEROSENE METERING PKG 52-PK-404
Area B U52-P74 TFU PROD PKG U52-P74-105 TFU DIESEL METERING PKG 52-PK-405
Area B U52-P74 TFU PROD PKG U52-P74-106 TFU HEAVY DIESEL METERING PKG 52-PK-406
Area B U52-P74 TFU PROD PKG U52-P74-107 TFU LPG METERING PKG 52-PK-407
Area B U52-P75 TFU FILLING STATION U52-P75-101 TFU FILLING STATION PKG 52-PK-307
Area B U52-PWA10 TFU CRUDE DRINKING WATER U52-PWA10-101 TFU CRUDE/NG AREA 2" DW
Area B U52-PWA20 TFU INTERM DRINKING WATER U52-PWA20-101 TFU INTERM AREA 2" DW
Area B U52-PWA30 TFU COMPO DRINKING WATER U52-PWA30-101 TFU COMPO AREA 3" DW
Area B U52-PWA30 TFU COMPO DRINKING WATER U52-PWA30-102 TFU COMPO AREA 2" DW-1
Area B U52-PWA30 TFU COMPO DRINKING WATER U52-PWA30-103 TFU COMPO AREA 2" DW-2
Area B U52-PWA40 TFU PROD DRINKING WATER U52-PWA40-101 TFU PROD AREA 2" DW
Area B U52-SLP20 TFU INTERM SLOP U52-SLP20-101 TFU LIGHT SLOP TANK 52-TK-001A/B
Area B U52-SLP30 TFU COMPO SLOP U52-SLP30-101 TFU COMPO AREA 8" LIGHT SLOP TO 52-TK-001A/B
Area B U52-SLP30 TFU COMPO SLOP U52-SLP30-102 TFU COMPO AREA 10" LIGHT SLOP TO 52-TK-001A/B
Area B U52-SLP30 TFU COMPO SLOP U52-SLP30-103 TFU COMPO AREA 12" LIGHT SLOP TO 52-TK-001A/B
Area B U52-SLP40 TFU PROD SLOP U52-SLP40-101 TFU PROD AREA 12" LIGHT SLOP to 52-TK-001A/B
Area B U52-SLP40 TFU PROD SLOP U52-SLP40-102 TFU PROD AREA 10" LIGHT SLOP to 52-TK-001A/B
Area B U52-SLP50 TFU INTERM(H) SLOP U52-SLP50-101 TFU INTERM(H) AREA 3" LIGHT SLOP to 52-V-006
Area B U52-SWA10 TFU CRUDE SERVICE WATER U52-SWA10-101 TFU CRUDE/NG AREA 2" SERVICE WATER
Area B U52-SWA20 TFU INTERM SERVICE WATER U52-SWA20-101 TFU INTERM AREA 2" SERVICE WATER-1
Area B U52-SWA20 TFU INTERM SERVICE WATER U52-SWA20-102 TFU INTERM AREA 2" SERVICE WATER-2
Area B U52-SWA20 TFU INTERM SERVICE WATER U52-SWA20-103 TFU INTERM AREA 2" SERVICE WATER-3
Area B U52-SWA30 TFU COMPO SERVICE WATER U52-SWA30-101 TFU COMPO AREA 2" SERVICE WATER-1
Area B U52-SWA30 TFU COMPO SERVICE WATER U52-SWA30-102 TFU COMPO AREA 2" SERVICE WATER-2
Area B U52-SWA30 TFU COMPO SERVICE WATER U52-SWA30-103 TFU COMPO AREA 2" SERVICE WATER-3
Area B U52-SWA40 TFU PROD SERVICE WATER U52-SWA40-101 TFU PROD AREA 2" SERVICE WATER-1
Area B U52-SWA40 TFU PROD SERVICE WATER U52-SWA40-102 TFU PROD AREA 2" SERVICE WATER-2
Area B U52-SWA50 TFU INTERM(H) SERVICE WATER U52-SWA50-101 TFU INTERM(H) AREA 2" SERVICE WATER-1
Area B U52-T10 TFU CRUDE U52-T10-101 TFU CRUDE METERING
Area B U52-T10 TFU CRUDE U52-T10-102 TFU CRUDE TANK 52-TK-101A/B/C
Area B U52-T10 TFU CRUDE U52-T10-103 TFU CRUDE TANK 52-TK-101D/E/F
Area B U52-T20 TFU INTERMEDIATE U52-T20-101 TFU NHT FEED TANK 52-TK-201A/B
Area B U52-T20 TFU INTERMEDIATE U52-T20-102 TFU LIGHT NAPH TANK 52-TK-202A/B
Area B U52-T20 TFU INTERMEDIATE U52-T20-103 TFU HEAVY NAPH TANK 52-TK-203A/B
Area B U52-T20 TFU INTERMEDIATE U52-T20-104 TFU KHT FEED TANK 52-TK-204A/B
Area B U52-T20 TFU INTERMEDIATE U52-T20-105 TFU DHT FEED TANK 52-TK-205A/B
Area B U52-T20 TFU INTERMEDIATE U52-T20-106 TFU SR HEAVY DIESEL TANK 52-TK-210A/B
Area B U52-T20 TFU INTERMEDIATE U52-T20-107 TFU VGOHT FEED TANK 52-TK-206A/B
Area B U52-T20 TFU INTERMEDIATE U52-T20-108 TFU FCC FEED TANK 52-TK-207A/B
Area B U52-T30 TFU COMPONENT U52-T30-101 TFU UNSAT LPG BULLET 52-TK-208A/B/C
Area B U52-T30 TFU COMPONENT U52-T30-102 TFU PNU S/UP LPG BULLET 52-TK-211
Area B U52-T30 TFU COMPONENT U52-T30-103 TFU ISOMERATE TANK 52-TK-301A/B
Area B U52-T30 TFU COMPONENT U52-T30-104 TFU REFORMATE TANK 52-TK-302A/B
Area B U52-T30 TFU COMPONENT U52-T30-105 TFU CRACKED GASOLINE TANK 52-TK-303A/B
Area B U52-T30 TFU COMPONENT U52-T30-106 TFU POLYNAPH TANK 52-TK-304A/B
Area B U52-T30 TFU COMPONENT U52-T30-107 TFU C.P. ISOMERATE BULLET 52-TK-313A/B
Area B U52-T30 TFU COMPONENT U52-T30-108 TFU REGULAR GASOLINE BLENDING
Area B U52-T30 TFU COMPONENT U52-T30-109 TFU PREMIUM GASOLINE BLENDING
Area B U52-T30 TFU COMPONENT U52-T30-110 TFU DESUL KEROSENE TANK 52-TK-305A/B
Area B U52-T30 TFU COMPONENT U52-T30-111 TFU DESUL DIESEL TANK 52-TK-306A/B
Area B U52-T30 TFU COMPONENT U52-T30-112 TFU DIESEL BLENDING
Area B U52-T30 TFU COMPONENT U52-T30-113 TFU CYCLE OIL TANK 52-TK-307A/B
Area B U52-T30 TFU COMPONENT U52-T30-114 TFU REDUCED CRUDE TANK 52-TK-308A/B
Area B U52-T30 TFU COMPONENT U52-T30-115 TFU SLURRY OIL TANK 52-TK-311A/B
Area B U52-T30 TFU COMPONENT U52-T30-116 TFU VGOHT DIESEL TANK 52-TK-312A/B
Area B U52-T30 TFU COMPONENT U52-T30-117 TFU HEAVY FUEL OIL BLENDING
Area B U52-T30 TFU COMPONENT U52-T30-118 TFU PROPANE BULLET 52-TK-309A/B
Area B U52-T30 TFU COMPONENT U52-T30-119 TFU BUTANE BULLET 52-TK-310A/B
Area B U52-T30 TFU COMPONENT U52-T30-120 TFU LPG PROD BULLET 52-TK-409A/B/C/D/E/F
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area B U52-T40 TFU PRODUCT U52-T40-101 TFU REGULAR GASOLINE TANK 52-TK-401A/B/C
Area B U52-T40 TFU PRODUCT U52-T40-102 TFU PREMIUM GASOLINE TANK 52-TK-402A/B/C
Area B U52-T40 TFU PRODUCT U52-T40-103 TFU KEROSENE TANK 52-TK-403A/B/C
Area B U52-T40 TFU PRODUCT U52-T40-104 TFU ATK TANK 52-TK-404A/B/C
Area B U52-T40 TFU PRODUCT U52-T40-105 TFU DIESEL TANK 52-TK-405A/B/C
Area B U52-T40 TFU PRODUCT U52-T40-106 TFU HEAVY DIESEL TANK 52-TK-406A/B/C
Area B U52-T40 TFU PRODUCT U52-T40-107 TFU HEAVY FUEL OIL TANK 52-TK-408A/B/C
Area B U52-T50 TFU INTERMEDIATE (H) U52-T50-101 TFU VAC RESIDUE TANK 52-TK-209A/B
Area B U52-UTA10 TFU CRUDE UTILITY WATER U52-UTA10-101 TFU CRUDE/NG AREA 2" PA
Area B U52-UTA20 TFU INTERM UTILITY WATER U52-UTA20-101 TFU INTERM AREA 2" PA-1
Area B U52-UTA20 TFU INTERM UTILITY WATER U52-UTA20-102 TFU INTERM AREA 2" PA-2
Area B U52-UTA20 TFU INTERM UTILITY WATER U52-UTA20-103 TFU INTERM AREA 2" PA-3
Area B U52-UTA30 TFU COMPO UTILITY WATER U52-UTA30-101 TFU COMPO AREA 2" PA-1
Area B U52-UTA30 TFU COMPO UTILITY WATER U52-UTA30-102 TFU COMPO AREA 2" PA-2
Area B U52-UTA30 TFU COMPO UTILITY WATER U52-UTA30-103 TFU COMPO AREA 2" PA-3
Area B U52-UTA40 TFU PROD UTILITY WATER U52-UTA40-101 TFU PROD AREA 2" PA-1
Area B U52-UTA40 TFU PROD UTILITY WATER U52-UTA40-102 TFU PROD AREA 2" PA-2
Area B U52-UTA50 TFU INTERM(H) UTILITY WATER U52-UTA50-101 TFU INTERM AREA 2" PA-4
Area B U52-VT10 TFU Crude Vent Line U52-VT10-101 TFU Crude Vent Line
Area B U52-VT20 TFU Intermediate Vent Line U52-VT20-101 TFU Intermediate Vent Line
Area B U52-VT30 TFU Component Vent Line U52-VT30-101 TFU Component Vent Line
Area B U52-VT40 TFU Product Vent Line U52-VT40-101 TFU Product Vent Line
Area B U52-VT50 TFU Component(H) Vent Line U52-VT50-101 TFU Component(H) Vent Line
Area C U53-CW ALU CW SYSTEM U53-CW-101 ALU CW SYSTEM
Area C U53-FLD ALU LP FLARE U53-FLD-101 ALU LP FLARE
Area C U53-FLO ALU FLUSHING OIL U53-FLO-101 ALU FLUSHING OIL
Area C U53-FUG ALU FUEL GAS U53-FUG-101 ALU FUEL GAS
Area C U53-FWA ALU HOT FIREWATER NETWORK U53-FWA-101 ALU HOT FIREWATER NETWORK(UG)
Area C U53-FWA ALU HOT FIREWATER NETWORK U53-FWA-102 ALU HOT FIREWATER NETWORK(AG)
Area C U53-HBFW ALU HP BFW U53-HBFW-101 ALU HP BFW
Area C U53-HOT ALU HOT OIL U53-HOT-101 ALU HOT OIL
Area C U53-HOT ALU HOT OIL U53-HOT-102 ALU HOT OIL RETURN & SUPPLY
Area C U53-HPC ALU HP CONDENSATE U53-HPC-101 ALU HP CONDENSATE
Area C U53-HPS ALU HP STEAM U53-HPS-101 ALU HP STEAM
Area C U53-INA ALU INSTRUMENT AIR U53-INA-101 ALU INSTRUMENT AIR
Area C U53-LPC ALU LP CONDENSATE U53-LPC-101 ALU LP CONDENSATE
Area C U53-LPS ALU LP STEAM U53-LPS-101 ALU LP STEAM
Area C U53-MPC ALU MP CONDENSATE U53-MPC-101 ALU MP CONDENSATE
Area C U53-MPS ALU MP STEAM U53-MPS-101 ALU MP STEAM
Area C U53-NIT ALU N2 U53-NIT-101 ALU N2
Area C U53-OWS ALU OWS U53-OWS-101 ALU OWS
Area C U53-P01 ALU PAVING ASPHALT U53-P01-101 ALU PAVING ASPHALT TANK
Area C U53-P01 ALU PAVING ASPHALT U53-P01-201 ALU PAVING ASPHALT LOADING SYSTEM
Area C U53-P01 ALU PAVING ASPHALT U53-P01-301 ALU PAVING ASPHALT VAPOR RECOVERY
Area C U53-P02 ALU BLOWN ASPHALT U53-P02-101 ALU BLOWN ASPHALT TANK
Area C U53-P02 ALU BLOWN ASPHALT U53-P02-201 ALU BLOWN ASPHALT FILLING
Area C U53-P03 ALU WEIGHING SCALE U53-P03-101 ALU WEIGHING SCALE
Area C U53-P70 ALU PKG U53-P70-101 ALU BLOWN ASPHALT BARREL FILLING PACKAGE
Area C U53-PWA ALU DRINKING WATER U53-PWA-101 ALU DRINKING WATER
Area C U53-SLP ALU SLOP U53-SLP-101 ALU SLOP
Area C U53-SWA ALU SERVICE WATER U53-SWA-101 ALU SERVICE WATER
Area C U53-UTA ALU UTILITY AIR U53-UTA-101 ALU UTILITY AIR
Area C U54-FWA SSU FIREWATER NETWORK U54-FWA-101 SSU FIREWATER NETWORK(UG)
Area C U54-FWA SSU FIREWATER NETWORK U54-FWA-102 SSU FIREWATER NETWORK(AG)
Area C U54-OWS SSU OWS U54-OWS-101 SSU OWS
Area C U54-P70 SSU PKG U54-P70-101 SSU SULPHUR SOLIDIFICATION PKG
Area C U54-P70 SSU PKG U54-P70-102 SSU HANDLING PKG
Area C U58-ACD INT ACID U58-ACD-101 INT SULPHURIC ACID from UNIT 51 to UNIT 30
Area C U58-AMN INT AMINE SOLUTION U58-AMN-101 INT LEAN AMINE HEADER to UNIT 06,08,11
Area C U58-AMN INT AMINE SOLUTION U58-AMN-102 INT LEAN AMINE HEADER to UNIT 07
Area C U58-AMN INT AMINE SOLUTION U58-AMN-103 INT RICH AMINE HEADER
Area C U58-BFW INT LP BOILER FEED WATER U58-BFW-101 INT LP BFW HEADER
Area C U58-CAU INT CAUSTIC U58-CAU-101 INT 50% CAUSTIC DISTRIBUTION
Area C U58-CAU INT CAUSTIC U58-CAU-102 INT 10% CAUSTIC DISTRIBUTION
Area C U58-CAU INT CAUSTIC U58-CAU-103 INT SPENT CAUSTIC/BRINE/WW HEADER to 51-BA-001
Area C U58-CAU INT CAUSTIC U58-CAU-104 INT SPENT CAUSTIC from 03/08/09 HEADER to 51-TK-009A/B
Area C U58-CHP INT CHEMICAL PRODUCT U58-CHP-101 INT ANTI SCALANT from UNIT 30 to UNIT 51
Area C U58-CHP INT CHEMICAL PRODUCT U58-CHP-102 INT SBS from UNIT 30 to UNIT 51
Area C U58-CHP INT CHEMICAL PRODUCT U58-CHP-103 INT COAGULANT from UNIT 30 to UNIT 51
Area C U58-CHP INT CHEMICAL PRODUCT U58-CHP-104 INT DMDS from UNIT 06 to UNIT 02
Area C U58-CHP INT CHEMICAL PRODUCT U58-CHP-105 INT DMDS from UNIT 07 to UNIT 02
Area C U58-CLD INT CLOSE DRAIN U58-CLD-101 INT CLOSED DRAIN from UNIT 10 to UNIT 53
Area C U58-CLD INT CLOSE DRAIN U58-CLD-102 INT CLOSED DRAIN from UNIT 52 to UNIT 53
Area C U58-CND INT CLEAN CONDENSATE U58-CND-101 INT PUMPED CONENSATE TO 35-V-007
Area C U58-CND INT CLEAN CONDENSATE U58-CND-102 INT PUMPED CONDENSATE FROM 20 TO 35-V-003
Area C U58-CND INT CLEAN CONDENSATE U58-CND-103 INT CLEAN CONDENSATE from UNIT 37 to 36-V-001
Area C U58-CW INT COOLING WATER U58-CW-101 INT UG COOLING WATER SUPPLY HEADER
Area C U58-CW INT COOLING WATER U58-CW-102 INT UG COOLING WATER RETURN HEADER
Area C U58-CW INT COOLING WATER U58-CW-103 INT COOLING WATER SUPPLY for BLACK START-UP
Area C U58-CW INT COOLING WATER U58-CW-104 INT COOLING WATER RETURN for BLACK START-UP
Area C U58-CW INT COOLING WATER U58-CW-105 INT COOLING WATER BLOW DOWN TO UNIT 30
Area C U58-DWA INT DEMINERALIZED WATER U58-DWA-101 INT DEMI WATER TO UNIT 35(DISTRIBUTION)
Area C U58-FLA INT ACID FLARE U58-FLA-101 INT ACID FLARE to 50-V-301
Area C U58-FLA INT ACID FLARE U58-FLA-102 INT ACID FLARE to 50-V-302
Area C U58-FLA INT ACID FLARE U58-FLA-103 INT ACID FLARE to 50-V-303
Area C U58-FLD INT LP FLARE U58-FLD-101 INT LP FLARE to 50-V-101
Area C U58-FLD INT LP FLARE U58-FLD-102 INT LP FLARE to 50-V-102
Area C U58-FLD INT LP FLARE U58-FLD-103 INT LP FLARE to 50-V-103
Area C U58-FLH INT HP FLARE U58-FLH-101 INT HP FLARE to 50-V-201
Area C U58-FLH INT HP FLARE U58-FLH-102 INT HP FLARE to 50-V-202
Area C U58-FLH INT HP FLARE U58-FLH-103 INT HP FLARE to 50-V-203
Area C U58-FLO INT FLUSHING OIL U58-FLO-101 INT FLUSHING OIL HEADER
Area C U58-FLO INT FLUSHING OIL U58-FLO-102 INT FLUSHING OIL to 52-TK-003A/B
Area C U58-FUG INT FUEL/OFF GAS U58-FUG-101 INT FUEL GAS HEADER
Area C U58-FUG INT FUEL/OFF GAS U58-FUG-102 INT FUEL GAS from 03/04/08/09/19 to UNIT 44
Area C U58-FUG INT FUEL/OFF GAS U58-FUG-103 INT FUEL GAS from UNIT 44 to UNIT 08
Area C U58-FUO INT FUEL/OFF GAS U58-FUO-101 INT FUEL OIL SUPPLY HEADER
Area C U58-FUO INT FUEL/OFF GAS U58-FUO-102 INT FUEL OIL RETURN HEADER
Area C U58-FUO INT FUEL/OFF GAS U58-FUO-103 INT REFINERY FUEL OIL to UNIT 37 from 44-P-004A/B
Area C U58-FUO INT FUEL/OFF GAS U58-FUO-104 INT VGOHT DIESEL FUEL to UNIT 37/44 from 52-P-322A/B
Area C U58-FUO INT FUEL/OFF GAS U58-FUO-105 INT SLURRY OIL FUEL from 52-P-321A/B to UNIT44
Area C U58-FWA INT UG FIRE WATER NETWORK U58-FWA-101 INT UG FIRE WATER NETWORK WBS 4A,4B(CRUDE TANK)
Area C U58-FWA INT UG FIRE WATER NETWORK U58-FWA-102 INT UG FIRE WATER NETWORK WBS 1A,1B,1C,1D,1E,1F,1G,1H,1I(PROCESS)
Area C U58-FWA INT UG FIRE WATER NETWORK U58-FWA-103 INT UG FIRE WATER NETWORK WBS 4C,4D(COMP, FINAL TANK)
Area C U58-FWA INT UG FIRE WATER NETWORK U58-FWA-104 INT UG FIRE WATER NETWORK WBS 4D, 5A(ASL, SSB)
Area C U58-FWA INT UG FIRE WATER NETWORK U58-FWA-105 INT UG FIRE WATER NETWORK FOR BSU
Area C U58-HBFW INT HP BOILER FEED WATER U58-HBFW-101 INT HP BFW HEADER
Area C U58-HPC INT HP CONDENSATE U58-HPC-101 INT HP CONDENSATE FROM UTILITY TO 35-V-007
Area C U58-HPC INT HP CONDENSATE U58-HPC-102 INT HP CONDENSATE FROM UNIT 10/53 TO 35-V-003
Area C U58-HPC INT HP CONDENSATE U58-HPC-103 INT HP CONDENSATE FROM UNIT 02/03/04/09 TO 35-V-005
Area C U58-HPS INT HP STEAM U58-HPS-101 INT HP STEAM HEADER
Area C U58-HYD INT NHYDROGEN U58-HYD-101 INT H2 LOW PURITY to UNIT 05/06 from UNIT 15
Area C U58-HYD INT NHYDROGEN U58-HYD-102 INT H2 RICH from UNIT 04 to UNIT 15
Area C U58-HYD INT NHYDROGEN U58-HYD-103 INT H2 from UNIT 07 to UNIT 09
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area C U58-HYD INT NHYDROGEN U58-HYD-104 INT H2 HIGH PURITY INTERCON from UNIT 15
Area C U58-HYD INT NHYDROGEN U58-HYD-105 INT H2 RICH from UNIT 04 to UNIT 02/03
Area C U58-HYP INT HYPOCHLORITE U58-HYP-101 INT SODIUM HYPOCHLORITE from UNIT 30 to UNIT 51
Area C U58-INA INT INSTRUMENT AIR U58-INA-101 INT INSTRUMENT AIR
Area C U58-LPC INT LP CONDENSATE U58-LPC-101 INT LP CONDENSATE FROM UTILITY TO 35-V-007
Area C U58-LPC INT LP CONDENSATE U58-LPC-102 INT CONDENSATE FROM 52/54/90 TO 35-V-001
Area C U58-LPC INT LP CONDENSATE U58-LPC-103 INT CONDENSATE FROM 07/08/09/11/52 TO 35-V-002
Area C U58-LPC INT LP CONDENSATE U58-LPC-104 INT CONDENSATE FROM 05/06/10/16/17/44 TO 35-V-003
Area C U58-LPC INT LP CONDENSATE U58-LPC-105 INT CONDENSATE FROM 01/02/03/04 TO 35-V-004
Area C U58-LPS INT LP STEAM U58-LPS-101 INT LP STEAM HEADER
Area C U58-LPS INT LP STEAM U58-LPS-102 INT LLP STEAM HEADER
Area C U58-MBFW INT MP BOILER FEED WATER U58-MBFW-101 INT MP BFW HEADER
Area C U58-MPC INT MP CONDENSATE U58-MPC-101 INT MP CONDENSATE FROM UTILITY TO 35-V-007
Area C U58-MPC INT MP CONDENSATE U58-MPC-102 INT MP CONDENSATE FROM 51 TO 35-V-001
Area C U58-MPC INT MP CONDENSATE U58-MPC-103 INT MP CONDENSATE FROM 07/08/09 TO 35-V-002
Area C U58-MPC INT MP CONDENSATE U58-MPC-104 INT MP CONDENSATE FROM 10 TO 35-V-003
Area C U58-MPC INT MP CONDENSATE U58-MPC-105 INT MP CONDENSATE FROM 02/03/04/09 TO 35-V-006
Area C U58-MPS INT MP STEAM U58-MPS-101 INT MP STEAM HEADER
Area C U58-NIT INT NITROGEN U58-NIT-101 INT NITROGEN HEADER
Area C U58-NIT INT NITROGEN U58-NIT-102 INT NITROGEN from UNIT 42 to CCR
Area C U58-NTG INT NATURAL GAS U58-NTG-101 INT NATURAL GAS HEADER
Area C U58-NTG INT NATURAL GAS U58-NTG-102 INT NATURAL GAS FOR BLACK START-UP
Area C U58-OWS INT OIL WATER SEWER U58-OWS-101 INT OILY WATER to 51-BA-001 from 51-BASIN
Area C U58-P01 INT CRUDE LINE U58-P01-101 INT CRUDE to CDU
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-101 INT S.R.NAPHTHA PRODUCT to 52-TK-201A/B
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-103 INT LIGHT NAPHTHA to 52-TK-202A/B
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-104 INT LIGHT NAPHTHA to UNIT 02/09/15, 52-TK-301A/B
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-105 INT HEAVY NAPHTHA to 52-TK-203A/B
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-106 INT SR and HEAVY NAPHTHA to UNIT 02/08/15
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-107 INT UNSAT NAPHTHA to UNIT 02/06 from UNIT 01
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-108 INT WILD NAPH to UNIT 01 from UNIT 06
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-109 INT NAPH OFF SPEC to UNIT 01 from UNIT 07
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-110 INT SUL SP ISOMERATE to UNIT 01 from UNIT 09
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-111 INT VGO HDT NAPHTHA to UNIT 02 from UNIT 07
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-112 INT HEAVY NAPHTHA FEED to UNIT 04 from UNIT 02
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-113 INT LIGHT NAPHTHA FEED to UNIT 03 from UNIT 02
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-114 INT START UP BY-PASS to UNIT 02 from UNIT 04
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-115 INT ISOMERATE to UNIT 09
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-116 INT WILD NAPH to UNIT 06 from UNIT 05
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-201 INT SR KEROSENE to 52-TK-204A/B
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-202 INT SR KEROSENE to UNIT 05 from 52-TK-204A/B
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-203 INT KEROSENE FEED to UNIT 05 from UNIT 01
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-301 INT SR DIESEL to 52-TK-205A/B
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-302 INT SR DIESEL to UNIT 06 from 52-TK-205A/B
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-303 INT SR HEAVY DIESEL to 52-TK-210A/B
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-304 INT SR HEAVY DIESEL to UNIT 07, FUEL BLEND, TK-406A/B
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-305 INT DIESEL FEED to UNIT 06 from UNIT 01
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-306 INT MID DISTILATE to UNIT 06 from UNIT 09
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-401 INT VGO to 52-TK-206A/B
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-402 INT VGO to UNIT 7/10/53
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-403 INT T-VGO to 52-TK-207A/B
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-404 INT T-VGO to UNIT 08
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-405 INT VR to 52-TK-209A/B, 52-TK-308
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-406 INT VR to UNIT 10 from 52-TK-209A/B
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-407 INT VR to FUEL OIL BLENDING
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-408 INT VR FEED to UNIT 10 from UNIT 01
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-409 INT VGO FEED to UNIT 07/10 from UNIT 01
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-410 INT FCC FEED OIL from UNIT 07
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-501 INT UNSAT LPG to 52-TK-208A/B/C
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-502 INT UNSAT LPG to UNIT 09
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-503 INT CCR LPG to 52-TK-211
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-504 INT S/UP LPG to UNIT 09
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-505 INT NHT SOUR LPG to UNIT 11 from UNIT 02
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-506 INT LPG FEED to UNIT 09 from UNIT 08
Area C U58-P02 INT INTERMEDIATE LINE U58-P02-507 INT LPG FEED to UNIT 11 from UNIT 09
Area C U58-P03 INT COMPONENT LINE U58-P03-101 INT ISOMERATE to 52-TK-301A/B
Area C U58-P03 INT COMPONENT LINE U58-P03-102 INT REFORMATE to 52-TK-302A/B
Area C U58-P03 INT COMPONENT LINE U58-P03-103 INT CRACKED GASOLINE to 52-TK-303A/B
Area C U58-P03 INT COMPONENT LINE U58-P03-104 INT POLYNAPH to 52-TK-304A/B
Area C U58-P03 INT COMPONENT LINE U58-P03-105 INT C.P. ISOMERATE to 52-TK-313A/B
Area C U58-P03 INT COMPONENT LINE U58-P03-106 INT C.P. ISOMERATE to BLENDING
Area C U58-P03 INT COMPONENT LINE U58-P03-107 INT CRACKED GASOLINE to UNIT 08
Area C U58-P03 INT COMPONENT LINE U58-P03-201 INT DESUL KEROSENE to 52-TK305A/B
Area C U58-P03 INT COMPONENT LINE U58-P03-202 INT S-UP KEROSENE to UNIT 09
Area C U58-P03 INT COMPONENT LINE U58-P03-301 INT DESUL DIESEL to 52-TK306A/B
Area C U58-P03 INT COMPONENT LINE U58-P03-302 INT DESUL DIESEL to 37-TK-001
Area C U58-P03 INT COMPONENT LINE U58-P03-401 INT CYCLE OIL to 52-TK-307-A/B
Area C U58-P03 INT COMPONENT LINE U58-P03-402 INT CYCLE OIL to 37-TK-001, 44-TK-001-A/B
Area C U58-P03 INT COMPONENT LINE U58-P03-403 INT CR. SLURRY OIL to 52-TK-311-A/B
Area C U58-P03 INT COMPONENT LINE U58-P03-404 INT VGO HDT DIESEL to 52-TK-312-A/B
Area C U58-P03 INT COMPONENT LINE U58-P03-501 INT PROPANE to 37-TK-309-A/B
Area C U58-P03 INT COMPONENT LINE U58-P03-502 INT BUTANE to 37-TK-310-A/B
Area C U58-P03 INT COMPONENT LINE U58-P03-503 INT BUTANE to BLENDING
Area C U58-P04 INT COMPONENT LINE U58-P04-101 INT R-GASOLINE PROD to 52-TK-401A/B/C
Area C U58-P04 INT COMPONENT LINE U58-P04-102 INT P-GASOLINE PROD to 52-TK-402A/B/C
Area C U58-P04 INT COMPONENT LINE U58-P04-103 INT R-GASOLINE to 52-PK-307
Area C U58-P04 INT COMPONENT LINE U58-P04-104 INT P-GASOLINE to 52-PK-307
Area C U58-P04 INT COMPONENT LINE U58-P04-105 INT R-GASOLINE to 90-TK-001A/B
Area C U58-P04 INT COMPONENT LINE U58-P04-106 INT P-GASOLINE to 90-TK-002A/B
Area C U58-P04 INT COMPONENT LINE U58-P04-107 INT R-GASOLINE PROD. to 52-TK-401A/B/C
Area C U58-P04 INT COMPONENT LINE U58-P04-108 INT P-GASOLINE PROD. to 52-TK-402A/B/C
Area C U58-P04 INT COMPONENT LINE U58-P04-201 INT KEROSENE to 52-PK-404
Area C U58-P04 INT COMPONENT LINE U58-P04-202 INT ATK to 52-PK-403
Area C U58-P04 INT COMPONENT LINE U58-P04-203 INT KEROSENE to 90-TK-003A/B/C
Area C U58-P04 INT COMPONENT LINE U58-P04-204 INT ATK to 90-TK-004A/B/C
Area C U58-P04 INT COMPONENT LINE U58-P04-205 INT KEROSENE/ATK to 52-TK-403A/B/C, 52-TK-404A/B/C
Area C U58-P04 INT COMPONENT LINE U58-P04-301 INT DIESEL PROD to 52-TK-405A/B/C
Area C U58-P04 INT COMPONENT LINE U58-P04-302 INT DIESEL to 52-PK-307/405 from UNIT 52
Area C U58-P04 INT COMPONENT LINE U58-P04-303 INT HEAVY DIESEL to 52-PK-406
Area C U58-P04 INT COMPONENT LINE U58-P04-304 INT DIESEL to 90-TK-005A/B/C
Area C U58-P04 INT COMPONENT LINE U58-P04-305 INT HEAVY DIESEL to 90-TK-006A/B/C
Area C U58-P04 INT COMPONENT LINE U58-P04-306 INT DIESEL 52-TK-405 from UNIT 52
Area C U58-P04 INT COMPONENT LINE U58-P04-401 INT HEAVY FUEL OIL to 52-TK-408A/B/C
Area C U58-P04 INT COMPONENT LINE U58-P04-402 INT HEAVY FUEL OIL to 61-TK-001
Area C U58-P04 INT COMPONENT LINE U58-P04-501 INT LPG PROD to 50-PK-407
Area C U58-P04 INT COMPONENT LINE U58-P04-502 INT LPG PROD to 90-TK-008A/B/C/D
Area C U58-P04 INT COMPONENT LINE U58-P04-503 INT LPG PROD to UNIT 13
Area C U58-P04 INT COMPONENT LINE U58-P04-504 INT LPG PROD to UNIT 44
Area C U58-P04 INT COMPONENT LINE U58-P04-601 INT BITUMEN to UNIT 53
Area C U58-P04 INT COMPONENT LINE U58-P04-602 INT LIQUID SULFUR to UNIT 54
Area C U58-P04 INT COMPONENT LINE U58-P04-603 INT LIQUID SULFUR to UNIT 19
Area C U58-P04 INT COMPONENT LINE U58-P04-604 INT LIQUID SULFUR from UNIT 18/19 to UNIT 54
Area C U58-P04 INT COMPONENT LINE U58-P04-605 INT LIQUID SULFUR from UNIT 54 to UNIT 18/19
Area C U58-P05 INT FUEL/OFF GAS U58-P05-101 INT OFF GAS to UNIT 02 from UNIT 09
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area C U58-P05 INT FUEL/OFF GAS U58-P05-102 INT OFF GAS to UNIT 04 from UNIT 15
Area C U58-P05 INT FUEL/OFF GAS U58-P05-103 INT OFF GAS to UNIT 04 from UNIT 03
Area C U58-P05 INT FUEL/OFF GAS U58-P05-104 INT OFF GAS to UNIT 20 from UNIT 17
Area C U58-PWA INT UG DRINKING WATER HEADER U58-PWA-101 INT UG DRINKING WATER HEADER
Area C U58-PWA INT UG DRINKING WATER HEADER U58-PWA-102 INT DRINKING WATER DISTRIBUTION for BUILDING
Area C U58-RNW INT RAIN WATER U58-RNW-101 INT OFF SPEC WASTE WATER TO UNIT 51
Area C U58-RWA INT RAW WATER U58-RWA-101 INT IRRIGATION WATER INTERCONNECTION
Area C U58-RWA INT RAW WATER U58-RWA-102 INT FILTERED WATER TO UNIT 31/33/90
Area C U58-RWA INT RAW WATER U58-RWA-103 INT UF WATER TO UNIT 51
Area C U58-SGS INT FUEL/OFF GAS U58-SGS-101 INT SOUR GAS to UNIT 16
Area C U58-SGS INT FUEL/OFF GAS U58-SGS-102 INT SOUR GAS to UNIT 06 from UNIT 05
Area C U58-SGS INT FUEL/OFF GAS U58-SGS-103 INT ACID GAS to UNIT 20 from UNIT 16
Area C U58-SGS INT FUEL/OFF GAS U58-SGS-104 INT SOUR GAS to UNIT 20 from UNIT 17
Area C U58-SLP INT SLOP OIL U58-SLP-101 INT LIGHT SLOP HEADER to 52-TK-001A/B
Area C U58-SLP INT SLOP OIL U58-SLP-102 INT LIGHT SLOP to 52-TK-101 from 52-TK-001A/B
Area C U58-SLP INT SLOP OIL U58-SLP-103 INT HEAVY SLOP HEADER to 52-TK-101A~F, 408A/B/C
Area C U58-SLP INT SLOP OIL U58-SLP-104 INT RECOVERY OIL from UNIT 51 to 52-TK-101A~F
Area C U58-SLP INT SLOP OIL U58-SLP-105 INT SLOP OIL from UNIT 10 to UNIT 44
Area C U58-SLP INT SLOP OIL U58-SLP-106 INT SLOP OIL from METERING to UNIT 52
Area C U58-SRW INT SOUR WATER U58-SRW-101 INT SOUR WATER HEADER(01/02/05/06/07) to 17-V-101
Area C U58-SRW INT SOUR WATER U58-SRW-102 INT SOUR WATER HEADER(04/08/20/50) to 17-V-201
Area C U58-SSW INT SANITARY SEWER U58-SSW-101 INT SANITARY WATER DISTRIBUTION
Area C U58-STW INT STRIPPED SOUR WATER U58-STW-101 INT STRIPPED WATER from UNIT 17 to 51-TK-002A/B
Area C U58-STW INT STRIPPED SOUR WATER U58-STW-102 INT STRIPPED WATER from UNIT 17 to UNIT 02/050/06/07
Area C U58-STW INT STRIPPED SOUR WATER U58-STW-103 INT STRIPPED WATER from UNIT 17 to UNIT 01
Area C U58-SWA INT SERVICE WATER U58-SWA-101 INT SERVICE WATER DISTRIBUTION
Area C U58-TWA INT TREATED WATER U58-TWA-101 INT PERMEATE WATER TO UNIT 34
Area C U58-UTA INT UTILITY AIR U58-UTA-101 INT PLANT AIR
Area C U58-WWT INT WASTE WATER U58-WWT-101 INT 1ST RO WATER TO UNIT 51
Area C U58-WWT INT WASTE WATER U58-WWT-102 INT NEUT WATER TO UNIT 51
Area B U60-FWA RWI FIRE WATER NETWORK U60-FWA-101 RWI FIRE WATER NETWORK(UG)
Area B U60-FWA RWI FIRE WATER NETWORK U60-FWA-102 RWI FIRE WATER NETWORK(AG)
Area B U60-INA RWI INSTRUMENT AIR U60-INA-101 RWI INSTRUMENT AIR & DISTRIBUTION
Area B U60-OWS RWI CHEMICAL U60-OWS-101 RWI OWS
Area B U60-P01 RWI EMERGENCY DIESEL GENERATION U60-P01-101 RWI EMERGENCY DIESEL GENERATION
Area B U60-P01 RWI EMERGENCY DIESEL GENERATION U60-P01-201 RWI POTABLE WATER TANK
Area B U60-P03 RWI WATER INTAKE U60-P03-101 RWI WATER INTAKE AND TANK
Area B U60-P03 RWI WATER INTAKE U60-P03-201 RWI WATER TRANSFER
Area B U60-P03 RWI WATER INTAKE U60-P03-301 RWI CLARIFIER AND SLUDGE TREATMENT
Area B U60-P70 RWI CHEMICAL U60-P70-101 RWI SODIUM HYPOCHLINE PACKAGE
Area B U60-UTA RWI PLANT AIR U60-UTA-101 RWI PLANT AIR & DISTRIBUTION
Area B U60-VT RWI Vent Line U60-VT-101 RWI Vent Line
Area B U61-FLO HFP AUXILIARY U61-FLO-101 HFP FLUSHING OIL
Area B U61-FUG HFP FUEL U61-FUG-101 HFP FUEL GAS
Area B U61-FWA HFP FIRE WATER U61-FWA-101 HFP FIRE WATER NETWORK(UG)
Area B U61-FWA HFP FIRE WATER U61-FWA-102 HFP FIRE WATER NETWORK(AG)
Area B U61-INA HFP AIR U61-INA-101 HFP INSTRUMENT AIR
Area B U61-LPC HFP CONDENSATE U61-LPC-101 HFP LP CONDENSATE
Area B U61-LPS HFP STEAM U61-LPS-101 HFP LP STEAM
Area B U61-NIT HFP NITROGEN U61-NIT-101 HFP NITROGEN
Area B U61-OWS HFP AUXILIARY U61-OWS-101 HFP OWS
Area B U61-P01 HFP HEAVY FUEL OIL U61-P01-101 HFP PUMP & METERING & LAUNCHER
Area B U61-P01 HFP HEAVY FUEL OIL U61-P01-201 HFP RECEIVER & METERING
Area B U61-SLP HFP AUXILIARY U61-SLP-101 HFP LAUNCHER SLOP
Area B U61-SLP HFP AUXILIARY U61-SLP-102 HFP RECEIVER SLOP
Area B U61-SWA HFP WATER U61-SWA-101 HFP SERVICE WATER
Area B U61-UTA HFP AIR U61-UTA-101 HFP UTILITY AIR
Area B U61-VT HFO Vent Line U61-VT-101 HFO Vent Line
Area B U62-P01 CRUDE PIPE LINE U62-P01-101 CRUDE PIPE LINE
Area C U90-FLD DPT LP FLARE U90-FLD-101 DPT FLARE COLLETION HEADER
Area C U90-FLD DPT LP FLARE U90-FLD-102 DPT FLARE K.O DRUM
Area C U90-FLD DPT LP FLARE U90-FLD-103 DPT FLARE PKG
Area C U90-FUG DPT FUEL GAS U90-FUG-101 DPT FUEL GAS
Area C U90-FWA DPT FW U90-FWA-101 DPT FW TANK
Area C U90-FWA DPT FW U90-FWA-102 DPT FW JOCKEY PUMP
Area C U90-FWA DPT FW U90-FWA-103 DPT FW DIESEL ENGINE PUMP
Area C U90-FWA DPT FW U90-FWA-104 DPT FW ELECTRIC PUMP
Area C U90-FWA DPT FW U90-FWA-105 DPT FW NETWORK A(UG)
Area C U90-FWA DPT FW U90-FWA-106 DPT FW NETWORK A(AG)
Area C U90-FWA DPT FW U90-FWA-107 DPT FW NETWORK B(UG)
Area C U90-FWA DPT FW U90-FWA-108 DPT FW NETWORK B(AG)
Area C U90-INA DPT INSTRUMENT AIR U90-INA-101 DPT INSTRUMENT AIR
Area C U90-INA DPT INSTRUMENT AIR U90-INA-201 DPT INSTRUMENT AIR(GS)
Area C U90-LPC DPT LP CONDENSATE U90-LPC-101 DPT LP CONDENSATE
Area C U90-LPC DPT LP CONDENSATE U90-LPC-201 DPT LP CONDENSATE(GS)
Area C U90-LPS DPT LP STEAM U90-LPS-101 DPT LP STEAM
Area C U90-LPS DPT LP STEAM U90-LPS-201 DPT LP STEAM(GS)
Area C U90-NIT DPT N2 U90-NIT-101 DPT N2
Area C U90-NIT DPT N2 U90-NIT-201 DPT N2(GS)
Area C U90-OWS DPT OWS U90-OWS-101 DPT OWS
Area C U90-P01 DPT REGULAR GASOLINE U90-P01-101 DPT R-GASOLINE METERING
Area C U90-P01 DPT REGULAR GASOLINE U90-P01-201 DPT R-GASOLINE STORAGE
Area C U90-P01 DPT REGULAR GASOLINE U90-P01-301 DPT R-GASOLINE PUMP
Area C U90-P01 DPT REGULAR GASOLINE U90-P01-401 DPT R-GASOLINE LOADING
Area C U90-P01 DPT REGULAR GASOLINE U90-P01-501 DPT GASOLINE VAPOR RECOVERY
Area C U90-P02 DPT PREMIUM GASOLINE U90-P02-101 DPT P-GASOLINE METERING
Area C U90-P02 DPT PREMIUM GASOLINE U90-P02-201 DPT P-GASOLINE STORAGE
Area C U90-P02 DPT PREMIUM GASOLINE U90-P02-301 DPT P-GASOLINE PUMP
Area C U90-P02 DPT PREMIUM GASOLINE U90-P02-401 DPT P-GASOLINE LOADING
Area C U90-P03 DPT KEROSENE U90-P03-101 DPT KEROSENE METERING
Area C U90-P03 DPT KEROSENE U90-P03-201 DPT KEROSENE STORAGE
Area C U90-P03 DPT KEROSENE U90-P03-301 DPT KEROSENE PUMP
Area C U90-P03 DPT KEROSENE U90-P03-401 DPT KEROSENE LOADING
Area C U90-P03 DPT KEROSENE U90-P03-501 DPT KERO/DIESEL VAPOR RECOVERY
Area C U90-P04 DPT ATK U90-P04-101 DPT ATK METERING
Area C U90-P04 DPT ATK U90-P04-201 DPT ATK STORAGE
Area C U90-P04 DPT ATK U90-P04-301 DPT ATK PUMP
Area C U90-P04 DPT ATK U90-P04-401 DPT ATK LOADING
Area C U90-P04 DPT ATK U90-P04-501 DPT ATK/H-DIESEL VAPOR RECOVERY
Area C U90-P05 DPT DIESEL U90-P05-101 DPT DIESEL METERING
Area C U90-P05 DPT DIESEL U90-P05-201 DPT DIESEL STORAGE
Area C U90-P05 DPT DIESEL U90-P05-301 DPT DIESEL PUMP
Area C U90-P05 DPT DIESEL U90-P05-401 DPT DIESEL LOADING
Area C U90-P06 DPT HEAVY DIESEL U90-P06-101 DPT HEAVY DIESEL METERING
Area C U90-P06 DPT HEAVY DIESEL U90-P06-201 DPT HEAVY DIESEL STORAGE
Area C U90-P06 DPT HEAVY DIESEL U90-P06-301 DPT HEAVY DIESEL PUMP
Area C U90-P06 DPT HEAVY DIESEL U90-P06-401 DPT HEAVY DIESEL LOADING
Area C U90-P07 DPT LPG U90-P07-101 DPT LPG METERING
Area C U90-P07 DPT LPG U90-P07-201 DPT LPG STORAGE
Area C U90-P07 DPT LPG U90-P07-301 DPT LPG PUMP
Area C U90-P07 DPT LPG U90-P07-401 DPT LPG LOADING
Area C U90-P07 DPT LPG U90-P07-501 DPT LPG ODORIZATION
Area C U90-P08 DPT EXPORT U90-P08-101 DPT GASOLINE EXPORT to KARKH
Area C U90-P08 DPT EXPORT U90-P08-201 DPT GASOLINE EXPORT to KARBALA
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area C U90-P08 DPT EXPORT U90-P08-301 DPT GASOLINE EXPORT to NAJAF
Area C U90-P08 DPT EXPORT U90-P08-501 DPT KERO/DIESEL EXPORT to KARKH
Area C U90-P08 DPT EXPORT U90-P08-601 DPT KERO/DIESEL EXPORT to KARBALA
Area C U90-P08 DPT EXPORT U90-P08-701 DPT KERO/DIESEL EXPORT to NAJAF
Area C U90-P08 DPT EXPORT U90-P08-901 DPT LPG EXPORT to NAJAF & KARBALA
Area C U90-P09 DEPOT BUILDING (GS) U90-P09-101 DEPOT BUILDING (GS) PREMIUM GASOLINE
Area C U90-P09 DEPOT BUILDING (GS) U90-P09-201 DEPOT BUILDING (GS) REGULAR GASOLINE
Area C U90-P09 DEPOT BUILDING (GS) U90-P09-301 DEPOT BUILDING (GS) DIESEL
Area C U90-P70 DPT PKG U90-P70-101 DPT CATALYTIC OXIDATION PKG
Area C U90-P70 DPT PKG U90-P70-102 DPT WEIGHING STATION
Area C U90-P70 DPT PKG U90-P70-103 DPT FILLING STATION PKG
Area C U90-PWA DPT DRINKING WATER U90-PWA-101 DPT DRINKING WATER
Area C U90-PWA DPT DRINKING WATER U90-PWA-201 DPT DRINKING WATER(GS)
Area C U90-SLP DPT SLOP U90-SLP-101 DPT SLOP 90-V-001
Area C U90-SLP DPT SLOP U90-SLP-102 DPT SLOP 90-V-002
Area C U90-SLP DPT SLOP U90-SLP-103 DPT SLOP 90-V-004
Area C U90-SLP DPT SLOP U90-SLP-104 DPT SLOP TANK 90-TK-010A/B
Area C U90-SWA DPT SERVICE WATER U90-SWA-101 DPT SERVICE WATER
Area C U90-SWA DPT SERVICE WATER U90-SWA-201 DPT SERVICE WATER(GS)
Area C U90-UTA DPT UTILITY AIR U90-UTA-101 DPT UTILITY AIR
Area C U90-UTA DPT UTILITY AIR U90-UTA-201 DPT UTILITY AIR(GS)
NON-PROCESS SYSTEM & SUB-SYSTEM LIST
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area B 1A13-CI [1A] U13 CIVIL (HPU-1) 1A13-CI-PACO [1A] U13 Paving Concrete
Area B 1A13-CI [1A] U13 CIVIL (HPU-1) 1A13-CI-PAGR [1A] U13 Paving Gravel
Area B 1A13-CI [1A] U13 CIVIL (HPU-1) 1A13-CI-ROAD [1A] U13 Road
Area B 1A13-EL [1A] U13 ELECTRICAL (HPU-1) 1A13-EL-EEHT Electric Heat Tracing
Area B 1A13-EL [1A] U13 ELECTRICAL (HPU-1) 1A13-EL-EF&A Fire Alarm
Area B 1A13-EL [1A] U13 ELECTRICAL (HPU-1) 1A13-EL-EGLT Grounding & Lightning
Area B 1A13-EL [1A] U13 ELECTRICAL (HPU-1) 1A13-EL-ELSP Lighting & Small Power
Area B 1A13-EL [1A] U13 ELECTRICAL (HPU-1) 1A13-EL-EPST Power System
Area B 1A13-EL [1A] U13 ELECTRICAL (HPU-1) 1A13-EL-TELE Telecommunication
Area B 1A13-IN [1A] U13 INSTRUMENT (HPU-1) 1A13-IN-IF&G FIRE&GAS SYSTEM
Area B 1A13-SS [1A] U13 STEEL STRUCTURE (HPU-1) 1A13-SS-OTST [1A] U13 Other Structure
Area B 1A13-SS [1A] U13 STEEL STRUCTURE (HPU-1) 1A13-SS-PIRK [1A] U13 Piperack
Area B 1A13-SS [1A] U13 STEEL STRUCTURE (HPU-1) 1A13-SS-SSEQ [1A] U13 Equipment Structure
Area B 1A14-CI [1A] U14 CIVIL (HPU-2) 1A14-CI-PACO [1A] U14 Paving Concrete
Area B 1A14-CI [1A] U14 CIVIL (HPU-2) 1A14-CI-PAGR [1A] U14 Paving Gravel
Area B 1A14-CI [1A] U14 CIVIL (HPU-2) 1A14-CI-ROAD [1A] U14 Road
Area B 1A14-EL [1A] U14 ELECTRICAL (HPU-2) 1A14-EL-EEHT Electric Heat Tracing
Area B 1A14-EL [1A] U14 ELECTRICAL (HPU-2) 1A14-EL-EF&A Fire Alarm
Area B 1A14-EL [1A] U14 ELECTRICAL (HPU-2) 1A14-EL-EGLT Grounding & Lightning
Area B 1A14-EL [1A] U14 ELECTRICAL (HPU-2) 1A14-EL-ELSP Lighting & Small Power
Area B 1A14-EL [1A] U14 ELECTRICAL (HPU-2) 1A14-EL-EPST Power System
Area B 1A14-EL [1A] U14 ELECTRICAL (HPU-2) 1A14-EL-TELE Telecommunication
Area B 1A14-IN [1A] U14 INSTRUMENT (HPU-2) 1A14-IN-IF&G FIRE&GAS SYSTEM
Area B 1A14-SS [1A] U14 STEEL STRUCTURE (HPU-2) 1A14-SS-OTST [1A] U14 Other Structure
Area B 1A14-SS [1A] U14 STEEL STRUCTURE (HPU-2) 1A14-SS-PIRK [1A] U14 Piperack
Area B 1A14-SS [1A] U14 STEEL STRUCTURE (HPU-2) 1A14-SS-SSEQ [1A] U14 Equipment Structure
Area B 1A15-CI [1A] U15 CIVIL (HPU Common) 1A15-CI-PACO [1A] U15 Paving Concrete
Area B 1A15-CI [1A] U15 CIVIL (HPU Common) 1A15-CI-PAGR [1A] U15 Paving Gravel
Area B 1A15-CI [1A] U15 CIVIL (HPU Common) 1A15-CI-ROAD [1A] U15 Road
Area B 1A15-EL [1A] U15 ELECTRICAL (HPU Common) 1A15-EL-EEHT Electric Heat Tracing
Area B 1A15-EL [1A] U15 ELECTRICAL (HPU Common) 1A15-EL-EF&A Fire Alarm
Area B 1A15-EL [1A] U15 ELECTRICAL (HPU Common) 1A15-EL-EGLT Grounding & Lightning
Area B 1A15-EL [1A] U15 ELECTRICAL (HPU Common) 1A15-EL-ELSP Lighting & Small Power
Area B 1A15-EL [1A] U15 ELECTRICAL (HPU Common) 1A15-EL-EPST Power System
Area B 1A15-EL [1A] U15 ELECTRICAL (HPU Common) 1A15-EL-TELE Telecommunication
Area B 1A15-IN [1A] U15 INSTRUMENT (HPU Common) 1A15-IN-IF&G FIRE&GAS SYSTEM
Area B 1A15-SS [1A] U15 STEEL STRUCTURE (HPU Common) 1A15-SS-OTST [1A] U15 Other Structure
Area B 1A15-SS [1A] U15 STEEL STRUCTURE (HPU Common) 1A15-SS-PIRK [1A] U15 Piperack
Area B 1A15-SS [1A] U15 STEEL STRUCTURE (HPU Common) 1A15-SS-SSEQ [1A] U15 Equipment Structure
Area B 1B02-CI [1B] U02 CIVIL (NHT) 1B02-CI-PACO [1B] U02 Paving Concrete
Area B 1B02-CI [1B] U02 CIVIL (NHT) 1B02-CI-PAGR [1B] U02 Paving Gravel
Area B 1B02-CI [1B] U02 CIVIL (NHT) 1B02-CI-ROAD [1B] U02 Road
Area B 1B02-EL [1B] U02 ELECTRICAL (NHT) 1B02-EL-EEHT Electric Heat Tracing
Area B 1B02-EL [1B] U02 ELECTRICAL (NHT) 1B02-EL-EF&A Fire Alarm
Area B 1B02-EL [1B] U02 ELECTRICAL (NHT) 1B02-EL-EGLT Grounding & Lightning
Area B 1B02-EL [1B] U02 ELECTRICAL (NHT) 1B02-EL-ELSP Lighting & Small Power
Area B 1B02-EL [1B] U02 ELECTRICAL (NHT) 1B02-EL-EPST Power System
Area B 1B02-EL [1B] U02 ELECTRICAL (NHT) 1B02-EL-TELE Telecommunication
Area B 1B02-IN [1B] U02 INSTRUMENT (NHT) 1B02-IN-IF&G FIRE&GAS SYSTEM
Area B 1B02-SS [1B] U02 STEEL STRUCTURE (NHT) 1B02-SS-OTST [1B] U02 Other Structure
Area B 1B02-SS [1B] U02 STEEL STRUCTURE (NHT) 1B02-SS-PIRK [1B] U02 Piperack
Area B 1B02-SS [1B] U02 STEEL STRUCTURE (NHT) 1B02-SS-SSEQ [1B] U02 Equipment Structure
Area B 1B03-CI [1B] U03 CIVIL (ISOM (PENEX)) 1B03-CI-PACO [1B] U03 Paving Concrete
Area B 1B03-CI [1B] U03 CIVIL (ISOM (PENEX)) 1B03-CI-PAGR [1B] U03 Paving Gravel
Area B 1B03-CI [1B] U03 CIVIL (ISOM (PENEX)) 1B03-CI-ROAD [1B] U03 Road
Area B 1B03-EL [1B] U03 ELECTRICAL (ISOM (PENEX)) 1B03-EL-EEHT Electric Heat Tracing
Area B 1B03-EL [1B] U03 ELECTRICAL (ISOM (PENEX)) 1B03-EL-EF&A Fire Alarm
Area B 1B03-EL [1B] U03 ELECTRICAL (ISOM (PENEX)) 1B03-EL-EGLT Grounding & Lightning
Area B 1B03-EL [1B] U03 ELECTRICAL (ISOM (PENEX)) 1B03-EL-ELSP Lighting & Small Power
Area B 1B03-EL [1B] U03 ELECTRICAL (ISOM (PENEX)) 1B03-EL-EPST Power System
Area B 1B03-EL [1B] U03 ELECTRICAL (ISOM (PENEX)) 1B03-EL-TELE Telecommunication
Area B 1B03-IN [1B] U03 INSTRUMENT (ISOM (PENEX)) 1B03-IN-IF&G FIRE&GAS SYSTEM
Area B 1B03-SS [1B] U03 STEEL STRUCTURE (ISOM (PENEX)) 1B03-SS-OTST [1B] U03 Other Structure
Area B 1B03-SS [1B] U03 STEEL STRUCTURE (ISOM (PENEX)) 1B03-SS-PIRK [1B] U03 Piperack
Area B 1B03-SS [1B] U03 STEEL STRUCTURE (ISOM (PENEX)) 1B03-SS-SSEQ [1B] U03 Equipment Structure
Area B 1B04-CI [1B] U04 CIVIL (CCR) 1B04-CI-PACO [1B] U04 Paving Concrete
Area B 1B04-CI [1B] U04 CIVIL (CCR) 1B04-CI-PAGR [1B] U04 Paving Gravel
Area B 1B04-CI [1B] U04 CIVIL (CCR) 1B04-CI-ROAD [1B] U04 Road
Area B 1B04-EL [1B] U04 ELECTRICAL (CCR) 1B04-EL-EEHT Electric Heat Tracing
Area B 1B04-EL [1B] U04 ELECTRICAL (CCR) 1B04-EL-EF&A Fire Alarm
Area B 1B04-EL [1B] U04 ELECTRICAL (CCR) 1B04-EL-EGLT Grounding & Lightning
Area B 1B04-EL [1B] U04 ELECTRICAL (CCR) 1B04-EL-ELSP Lighting & Small Power
Area B 1B04-EL [1B] U04 ELECTRICAL (CCR) 1B04-EL-EPST Power System
Area B 1B04-EL [1B] U04 ELECTRICAL (CCR) 1B04-EL-TELE Telecommunication
Area B 1B04-IN [1B] U04 INSTRUMENT (CCR) 1B04-IN-IF&G FIRE&GAS SYSTEM
Area B 1B04-SS [1B] U04 STEEL STRUCTURE (CCR) 1B04-SS-OTST [1B] U04 Other Structure
Area B 1B04-SS [1B] U04 STEEL STRUCTURE (CCR) 1B04-SS-PIRK [1B] U04 Piperack
Area B 1B04-SS [1B] U04 STEEL STRUCTURE (CCR) 1B04-SS-SSEQ [1B] U04 Equipment Structure
Area B 1C01-CI [1C] U01 CIVIL (CDU / VDU) 1C01-CI-PACO [1C] U01 Paving Concrete
Area B 1C01-CI [1C] U01 CIVIL (CDU / VDU) 1C01-CI-PAGR [1C] U01 Paving Gravel
Area B 1C01-CI [1C] U01 CIVIL (CDU / VDU) 1C01-CI-ROAD [1C] U01 Road
Area B 1C01-EL [1C] U01 ELECTRICAL (CDU / VDU) 1C01-EL-EEHT Electric Heat Tracing
Area B 1C01-EL [1C] U01 ELECTRICAL (CDU / VDU) 1C01-EL-EF&A Fire Alarm
Area B 1C01-EL [1C] U01 ELECTRICAL (CDU / VDU) 1C01-EL-EGLT Grounding & Lightning
Area B 1C01-EL [1C] U01 ELECTRICAL (CDU / VDU) 1C01-EL-ELSP Lighting & Small Power
Area B 1C01-EL [1C] U01 ELECTRICAL (CDU / VDU) 1C01-EL-EPST Power System
Area B 1C01-EL [1C] U01 ELECTRICAL (CDU / VDU) 1C01-EL-TELE Telecommunication
Area B 1C01-IN [1C] U01 INSTRUMENT (CDU / VDU) 1C01-IN-IF&G FIRE&GAS SYSTEM
Area B 1C01-SS [1C] U01 STEEL STRUCTURE (CDU / VDU) 1C01-SS-OTST [1C] U01 Other Structure
Area B 1C01-SS [1C] U01 STEEL STRUCTURE (CDU / VDU) 1C01-SS-PIRK [1C] U01 Piperack
Area B 1C01-SS [1C] U01 STEEL STRUCTURE (CDU / VDU) 1C01-SS-SSEQ [1C] U01 Equipment Structure
Area A 1D05-CI [1D] U05 CIVIL (KHT) 1D05-CI-PACO [1D] U05 Paving Concrete
Area A 1D05-CI [1D] U05 CIVIL (KHT) 1D05-CI-PAGR [1D] U05 Paving Gravel
Area A 1D05-CI [1D] U05 CIVIL (KHT) 1D05-CI-ROAD [1D] U05 Road
Area A 1D05-EL [1D] U05 ELECTRICAL (KHT) 1D05-EL-EEHT Electric Heat Tracing
Area A 1D05-EL [1D] U05 ELECTRICAL (KHT) 1D05-EL-EGLT Grounding & Lightning
Area A 1D05-EL [1D] U05 ELECTRICAL (KHT) 1D05-EL-ELSP Lighting & Small Power
Area A 1D05-EL [1D] U05 ELECTRICAL (KHT) 1D05-EL-EPST Power System
Area A 1D05-EL [1D] U05 ELECTRICAL (KHT) 1D05-EL-TELE Telecommunication
Area A 1D05-IN [1D] U05 INSTRUMENT (KHT) 1D05-IN-IF&G FIRE&GAS SYSTEM
Area A 1D05-SS [1D] U05 STEEL STRUCTURE (KHT) 1D05-SS-OTST [1D] U05 Other Structure
Area A 1D05-SS [1D] U05 STEEL STRUCTURE (KHT) 1D05-SS-PIRK [1D] U05 Piperack
Area A 1D05-SS [1D] U05 STEEL STRUCTURE (KHT) 1D05-SS-SSEQ [1D] U05 Equipment Structure
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area A 1D06-CI [1D] U06 CIVIL (DHT) 1D06-CI-PACO [1D] U06 Paving Concrete
Area A 1D06-CI [1D] U06 CIVIL (DHT) 1D06-CI-PAGR [1D] U06 Paving Gravel
Area A 1D06-CI [1D] U06 CIVIL (DHT) 1D06-CI-ROAD [1D] U06 Road
Area A 1D06-EL [1D] U06 ELECTRICAL (DHT) 1D06-EL-EEHT Electric Heat Tracing
Area A 1D06-EL [1D] U06 ELECTRICAL (DHT) 1D06-EL-EGLT Grounding & Lightning
Area A 1D06-EL [1D] U06 ELECTRICAL (DHT) 1D06-EL-ELSP Lighting & Small Power
Area A 1D06-EL [1D] U06 ELECTRICAL (DHT) 1D06-EL-EPST Power System
Area A 1D06-EL [1D] U06 ELECTRICAL (DHT) 1D06-EL-TELE Telecommunication
Area A 1D06-IN [1D] U06 INSTRUMENT (DHT) 1D06-IN-IF&G FIRE&GAS SYSTEM
Area A 1D06-SS [1D] U06 STEEL STRUCTURE (DHT) 1D06-SS-OTST [1D] U06 Other Structure
Area A 1D06-SS [1D] U06 STEEL STRUCTURE (DHT) 1D06-SS-PIRK [1D] U06 Piperack
Area A 1D06-SS [1D] U06 STEEL STRUCTURE (DHT) 1D06-SS-SSEQ [1D] U06 Equipment Structure
Area C 1E09-CI [1E] U09 CIVIL (Poly Naphtha (PNU)) 1E09-CI-PACO [1E] U09 Paving Concrete
Area C 1E09-CI [1E] U09 CIVIL (Poly Naphtha (PNU)) 1E09-CI-PAGR [1E] U09 Paving Gravel
Area C 1E09-CI [1E] U09 CIVIL (Poly Naphtha (PNU)) 1E09-CI-ROAD [1E] U09 Road
Area C 1E09-EL [1E] U09 ELECTRICAL (Poly Naphtha (PNU)) 1E09-EL-EEHT Electric Heat Tracing
Area C 1E09-EL [1E] U09 ELECTRICAL (Poly Naphtha (PNU)) 1E09-EL-EF&A Fire Alarm
Area C 1E09-EL [1E] U09 ELECTRICAL (Poly Naphtha (PNU)) 1E09-EL-EGLT Grounding & Lightning
Area C 1E09-EL [1E] U09 ELECTRICAL (Poly Naphtha (PNU)) 1E09-EL-ELSP Lighting & Small Power
Area C 1E09-EL [1E] U09 ELECTRICAL (Poly Naphtha (PNU)) 1E09-EL-EPST Power System
Area C 1E09-EL [1E] U09 ELECTRICAL (Poly Naphtha (PNU)) 1E09-EL-TELE Telecommunication
Area C 1E09-IN [1E] U09 INSTRUMENT (Poly Naphtha (PNU)) 1E09-IN-IF&G FIRE&GAS SYSTEM
Area C 1E09-SS [1E] U09 STEEL STRUCTURE (Poly Naphtha (PNU)) 1E09-SS-OTST [1E] U09 other Structure
Area C 1E09-SS [1E] U09 STEEL STRUCTURE (Poly Naphtha (PNU)) 1E09-SS-PIRK [1E] U09 Piperack
Area C 1E09-SS [1E] U09 STEEL STRUCTURE (Poly Naphtha (PNU)) 1E09-SS-SSEQ [1E] U09 Equipment Structure
Area C 1E11-CI [1E] U11 CIVIL (LPG Production) 1E11-CI-PACO [1E] U11 Paving Concrete
Area C 1E11-CI [1E] U11 CIVIL (LPG Production) 1E11-CI-PAGR [1E] U11 Paving Gravel
Area C 1E11-CI [1E] U11 CIVIL (LPG Production) 1E11-CI-ROAD [1E] U11 Road
Area C 1E11-EL [1E] U11 ELECTRICAL (LPG Production) 1E11-EL-EEHT Electric Heat Tracing
Area C 1E11-EL [1E] U11 ELECTRICAL (LPG Production) 1E11-EL-EF&A Fire Alarm
Area C 1E11-EL [1E] U11 ELECTRICAL (LPG Production) 1E11-EL-EGLT Grounding & Lightning
Area C 1E11-EL [1E] U11 ELECTRICAL (LPG Production) 1E11-EL-ELSP Lighting & Small Power
Area C 1E11-EL [1E] U11 ELECTRICAL (LPG Production) 1E11-EL-EPST Power System
Area C 1E11-EL [1E] U11 ELECTRICAL (LPG Production) 1E11-EL-TELE Telecommunication
Area C 1E11-IN [1E] U11 INSTRUMENT (LPG Production) 1E11-IN-IF&G FIRE&GAS SYSTEM
Area C 1E11-SS [1E] U11 STEEL STRUCTURE (LPG Production) 1E11-SS-OTST [1E] U11 other Structure
Area C 1E11-SS [1E] U11 STEEL STRUCTURE (LPG Production) 1E11-SS-PIRK [1E] U11 Piperack
Area C 1E11-SS [1E] U11 STEEL STRUCTURE (LPG Production) 1E11-SS-SSEQ [1E] U11 Equipment Structure
Area C 1F08-CI [1F] U08 CIVIL (FCC) 1F08-CI-PACO [1F] U08 Paving Concrete
Area C 1F08-CI [1F] U08 CIVIL (FCC) 1F08-CI-PAGR [1F] U08 Paving Gravel
Area C 1F08-CI [1F] U08 CIVIL (FCC) 1F08-CI-ROAD [1F] U08 Road
Area C 1F08-EL [1F] U08 ELECTRICAL (FCC) 1F08-EL-EEHT Electric Heat Tracing
Area C 1F08-EL [1F] U08 ELECTRICAL (FCC) 1F08-EL-EF&A Fire Alarm
Area C 1F08-EL [1F] U08 ELECTRICAL (FCC) 1F08-EL-EGLT Grounding & Lightning
Area C 1F08-EL [1F] U08 ELECTRICAL (FCC) 1F08-EL-ELSP Lighting & Small Power
Area C 1F08-EL [1F] U08 ELECTRICAL (FCC) 1F08-EL-EPST Power System
Area C 1F08-EL [1F] U08 ELECTRICAL (FCC) 1F08-EL-TELE Telecommunication
Area C 1F08-IN [1F] U08 INSTRUMENT (FCC) 1F08-IN-IF&G FIRE&GAS SYSTEM
Area C 1F08-SS [1F] U08 STEEL STRUCTURE (FCC) 1F08-SS-OTST [1F] U08other Structure
Area C 1F08-SS [1F] U08 STEEL STRUCTURE (FCC) 1F08-SS-PIRK [1F] U08 Piperack
Area C 1F08-SS [1F] U08 STEEL STRUCTURE (FCC) 1F08-SS-SSEQ [1F] U08 Equipment Structure
Area C 1G07-CI [1G] U07 CIVIL (VGO HDT) 1G07-CI-PACO [1G] U07 Paving Concrete
Area C 1G07-CI [1G] U07 CIVIL (VGO HDT) 1G07-CI-PAGR [1G] U07 Paving Gravel
Area C 1G07-CI [1G] U07 CIVIL (VGO HDT) 1G07-CI-ROAD [1G] U07 Road
Area C 1G07-EL [1G] U07 ELECTRICAL (VGO HDT) 1G07-EL-ECPR Cathodic Protection
Area C 1G07-EL [1G] U07 ELECTRICAL (VGO HDT) 1G07-EL-EEHT Electric Heat Tracing
Area C 1G07-EL [1G] U07 ELECTRICAL (VGO HDT) 1G07-EL-EF&A Fire Alarm
Area C 1G07-EL [1G] U07 ELECTRICAL (VGO HDT) 1G07-EL-EGLT Grounding & Lightning
Area C 1G07-EL [1G] U07 ELECTRICAL (VGO HDT) 1G07-EL-ELSP Lighting & Small Power
Area C 1G07-EL [1G] U07 ELECTRICAL (VGO HDT) 1G07-EL-EPST Power System
Area C 1G07-EL [1G] U07 ELECTRICAL (VGO HDT) 1G07-EL-TELE Telecommunication
Area C 1G07-IN [1G] U07 INSTRUMENT (VGO HDT) 1G07-IN-IF&G FIRE&GAS SYSTEM
Area C 1G07-SS [1G] U07 STEEL STRUCTURE (VGO HDT) 1G07-SS-OTST [1G] U07 other Structure
Area C 1G07-SS [1G] U07 STEEL STRUCTURE (VGO HDT) 1G07-SS-PIRK [1G] U07 Piperack
Area C 1G07-SS [1G] U07 STEEL STRUCTURE (VGO HDT) 1G07-SS-SSEQ [1G] U07 Equipment Structure
Area C 1H16-CI [1H] U16 CIVIL (Gas Sweetening & ARU) 1H16-CI-PACO [1H] U16 Paving Concrete
Area C 1H16-CI [1H] U16 CIVIL (Gas Sweetening & ARU) 1H16-CI-PAGR [1H] U16 Paving Gravel
Area C 1H16-CI [1H] U16 CIVIL (Gas Sweetening & ARU) 1H16-CI-ROAD [1H] U16 Road
Area C 1H16-EL [1H] U16 ELECTRICAL (Gas Sweetening & ARU) 1H16-EL-ECPR Cathodic Protection
Area C 1H16-EL [1H] U16 ELECTRICAL (Gas Sweetening & ARU) 1H16-EL-EEHT Electric Heat Tracing
Area C 1H16-EL [1H] U16 ELECTRICAL (Gas Sweetening & ARU) 1H16-EL-EF&A Fire Alarm
Area C 1H16-EL [1H] U16 ELECTRICAL (Gas Sweetening & ARU) 1H16-EL-EGLT Grounding & Lightning
Area C 1H16-EL [1H] U16 ELECTRICAL (Gas Sweetening & ARU) 1H16-EL-ELSP Lighting & Small Power
Area C 1H16-EL [1H] U16 ELECTRICAL (Gas Sweetening & ARU) 1H16-EL-EPST Power System
Area C 1H16-EL [1H] U16 ELECTRICAL (Gas Sweetening & ARU) 1H16-EL-TELE Telecommunication
Area C 1H16-IN [1H] U16 INSTRUMENT (Gas Sweetening & ARU) 1H16-IN-IF&G FIRE&GAS SYSTEM
Area C 1H16-SS [1H] U16 STEEL STRUCTURE (Gas Sweetening & ARU) 1H16-SS-OTST [1H] U16 other Structure
Area C 1H16-SS [1H] U16 STEEL STRUCTURE (Gas Sweetening & ARU) 1H16-SS-PIRK [1H] U16 Piperack
Area C 1H16-SS [1H] U16 STEEL STRUCTURE (Gas Sweetening & ARU) 1H16-SS-SSEQ [1H] U16 Equipment Structure
Area C 1H17-CI [1H] U17 CIVIL (SWS) 1H17-CI-PACO [1H] U17 Paving Concrete
Area C 1H17-CI [1H] U17 CIVIL (SWS) 1H17-CI-PAGR [1H] U17 Paving Gravel
Area C 1H17-CI [1H] U17 CIVIL (SWS) 1H17-CI-ROAD [1H] U17 Road
Area C 1H17-EL [1H] U17 ELECTRICAL (SWS) 1H17-EL-ECPR Cathodic Protection
Area C 1H17-EL [1H] U17 ELECTRICAL (SWS) 1H17-EL-EEHT Electric Heat Tracing
Area C 1H17-EL [1H] U17 ELECTRICAL (SWS) 1H17-EL-EF&A Fire Alarm
Area C 1H17-EL [1H] U17 ELECTRICAL (SWS) 1H17-EL-EGLT Grounding & Lightning
Area C 1H17-EL [1H] U17 ELECTRICAL (SWS) 1H17-EL-ELSP Lighting & Small Power
Area C 1H17-EL [1H] U17 ELECTRICAL (SWS) 1H17-EL-EPST Power System
Area C 1H17-EL [1H] U17 ELECTRICAL (SWS) 1H17-EL-TELE Telecommunication
Area C 1H17-IN [1H] U17 INSTRUMENT (SWS) 1H17-IN-IF&G FIRE&GAS SYSTEM
Area C 1H17-SS [1H] U17 STEEL STRUCTURE (SWS) 1H17-SS-OTST [1H] U17 other Structure
Area C 1H17-SS [1H] U17 STEEL STRUCTURE (SWS) 1H17-SS-PIRK [1H] U17 Piperack
Area C 1H17-SS [1H] U17 STEEL STRUCTURE (SWS) 1H17-SS-SSEQ [1H] U17 Equipment Structure
Area C 1H18-CI [1H] U18 CIVIL (SRU-1/2/TGTU) 1H18-CI-PACO [1H] U18/U19/U20 Paving Concrete
Area C 1H18-CI [1H] U18 CIVIL (SRU-1/2/TGTU) 1H18-CI-PAGR [1H] U18/U19/U20 Paving Gravel
Area C 1H18-CI [1H] U18 CIVIL (SRU-1/2/TGTU) 1H18-CI-ROAD [1H] U18/U19/U20 Road
Area C 1H18-EL [1H] U18 ELECTRICAL (SRU-1) 1H18-EL-EEHT Electric Heat Tracing
Area C 1H18-EL [1H] U18 ELECTRICAL (SRU-1) 1H18-EL-EF&A Fire Alarm
Area C 1H18-EL [1H] U18 ELECTRICAL (SRU-1) 1H18-EL-EGLT Grounding & Lightning
Area C 1H18-EL [1H] U18 ELECTRICAL (SRU-1) 1H18-EL-ELSP Lighting & Small Power
Area C 1H18-EL [1H] U18 ELECTRICAL (SRU-1) 1H18-EL-EPST Power System
Area C 1H18-EL [1H] U18 ELECTRICAL (SRU-1) 1H18-EL-TELE Telecommunication
Area C 1H18-IN [1H] U18 INSTRUMENT (SRU-1) 1H18-IN-IF&G FIRE&GAS SYSTEM
Area C 1H18-SS [1H] U18 STEEL STRUCTURE (SRU-1/2/TGTU) 1H18-SS-OTST [1H] U18/U19/U20 other Structure
Area C 1H18-SS [1H] U18 STEEL STRUCTURE (SRU-1/2/TGTU) 1H18-SS-PIRK [1H] U18/U19/U20 Piperack
Area C 1H18-SS [1H] U18 STEEL STRUCTURE (SRU-1/2/TGTU) 1H18-SS-SSEQ [1H] U18/U19/U20 Equipment Structure
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area C 1H19-EL [1H] U19 ELECTRICAL (SRU-2) 1H19-EL-EEHT Electric Heat Tracing
Area C 1H19-EL [1H] U19 ELECTRICAL (SRU-2) 1H19-EL-EF&A Fire Alarm
Area C 1H19-EL [1H] U19 ELECTRICAL (SRU-2) 1H19-EL-EGLT Grounding & Lightning
Area C 1H19-EL [1H] U19 ELECTRICAL (SRU-2) 1H19-EL-ELSP Lighting & Small Power
Area C 1H19-EL [1H] U19 ELECTRICAL (SRU-2) 1H19-EL-EPST Power System
Area C 1H19-EL [1H] U19 ELECTRICAL (SRU-2) 1H19-EL-TELE Telecommunication
Area C 1H19-IN [1H] U19 INSTRUMENT (SRU-2) 1H19-IN-IF&G FIRE&GAS SYSTEM
Area C 1H20-EL [1H] U20 ELECTRICAL (TGTU) 1H20-EL-EEHT Electric Heat Tracing
Area C 1H20-EL [1H] U20 ELECTRICAL (TGTU) 1H20-EL-EF&A Fire Alarm
Area C 1H20-EL [1H] U20 ELECTRICAL (TGTU) 1H20-EL-EGLT Grounding & Lightning
Area C 1H20-EL [1H] U20 ELECTRICAL (TGTU) 1H20-EL-ELSP Lighting & Small Power
Area C 1H20-EL [1H] U20 ELECTRICAL (TGTU) 1H20-EL-EPST Power System
Area C 1H20-EL [1H] U20 ELECTRICAL (TGTU) 1H20-EL-TELE Telecommunication
Area C 1H20-IN [1H] U20 INSTRUMENT (TGTU) 1H20-IN-IF&G FIRE&GAS SYSTEM
Area C 1H44-CI [1H] U44 CIVIL (Refinery Fuel Unit) 1H44-CI-PACO [1H] U44 Paving Concrete
Area C 1H44-CI [1H] U44 CIVIL (Refinery Fuel Unit) 1H44-CI-PAGR [1H] U44 Paving Gravel
Area C 1H44-CI [1H] U44 CIVIL (Refinery Fuel Unit) 1H44-CI-ROAD [1H] U44 Road
Area C 1H44-EL [1H] U44 ELECTRICAL (Refinery Fuel Unit) 1H44-EL-ECPR Cathodic Protection
Area C 1H44-EL [1H] U44 ELECTRICAL (Refinery Fuel Unit) 1H44-EL-EEHT Electric Heat Tracing
Area C 1H44-EL [1H] U44 ELECTRICAL (Refinery Fuel Unit) 1H44-EL-EF&A Fire Alarm
Area C 1H44-EL [1H] U44 ELECTRICAL (Refinery Fuel Unit) 1H44-EL-EGLT Grounding & Lightning
Area C 1H44-EL [1H] U44 ELECTRICAL (Refinery Fuel Unit) 1H44-EL-ELSP Lighting & Small Power
Area C 1H44-EL [1H] U44 ELECTRICAL (Refinery Fuel Unit) 1H44-EL-EPST Power System
Area C 1H44-EL [1H] U44 ELECTRICAL (Refinery Fuel Unit) 1H44-EL-TELE Telecommunication
Area C 1H44-IN [1H] U44 INSTRUMENT (Refinery Fuel Unit) 1H44-IN-IF&G FIRE&GAS SYSTEM
Area C 1H44-SS [1H] U44 STEEL STRUCTURE (Refinery Fuel Unit) 1H44-SS-OTST [1H] U44 other Structure
Area C 1H44-SS [1H] U44 STEEL STRUCTURE (Refinery Fuel Unit) 1H44-SS-PIRK [1H] U44 Piperack
Area C 1I10-CI [1I] U10 CIVIL (Asphalt Blowing (ABU)) 1I10-CI-PACO [1I] U10 Paving Concrete
Area C 1I10-CI [1I] U10 CIVIL (Asphalt Blowing (ABU)) 1I10-CI-PAGR [1I] U10 Paving Gravel
Area C 1I10-CI [1I] U10 CIVIL (Asphalt Blowing (ABU)) 1I10-CI-ROAD [1I] U10 Road
Area C 1I10-EL [1I] U10 ELECTRICAL (Asphalt Blowing (ABU)) 1I10-EL-EEHT Electric Heat Tracing
Area C 1I10-EL [1I] U10 ELECTRICAL (Asphalt Blowing (ABU)) 1I10-EL-EF&A Fire Alarm
Area C 1I10-EL [1I] U10 ELECTRICAL (Asphalt Blowing (ABU)) 1I10-EL-EGLT Grounding & Lightning
Area C 1I10-EL [1I] U10 ELECTRICAL (Asphalt Blowing (ABU)) 1I10-EL-ELSP Lighting & Small Power
Area C 1I10-EL [1I] U10 ELECTRICAL (Asphalt Blowing (ABU)) 1I10-EL-EPST Power System
Area C 1I10-EL [1I] U10 ELECTRICAL (Asphalt Blowing (ABU)) 1I10-EL-TELE Telecommunication
Area C 1I10-IN [1I] U10 INSTRUMENT (Asphalt Blowing (ABU)) 1I10-IN-IF&G FIRE&GAS SYSTEM
Area C 1I10-SS [1I] U10 STEEL STRUCTURE (Asphalt Blowing (ABU)) 1I10-SS-OTST [1I] U10 other Structure
Area C 1I10-SS [1I] U10 STEEL STRUCTURE (Asphalt Blowing (ABU)) 1I10-SS-PIRK [1I] U10 Piperack
Area C 1I10-SS [1I] U10 STEEL STRUCTURE (Asphalt Blowing (ABU)) 1I10-SS-SSEQ [1I] U10 Equipment Structure
Area B 2A00-CI [2A] U00 CIVIL (Admin. Building (North)) 2A00-CI-PACO [2A] U00 Paving Concrete
Area B 2A00-CI [2A] U00 CIVIL (Admin. Building (North)) 2A00-CI-PAGR [2A] U00 Paving Gravel
Area B 2A00-CI [2A] U00 CIVIL (Admin. Building (North)) 2A00-CI-ROAD [2A] U00 Road
Area B 2A00-EL [2A] U00 ELECTRICAL (Admin. Building (North)) 2A00-EL-EGLT Grounding & Lightning
Area B 2A00-EL [2A] U00 ELECTRICAL (Admin. Building (North)) 2A00-EL-ELSP Lighting & Small Power
Area B 2A00-EL [2A] U00 ELECTRICAL (Admin. Building (North)) 2A00-EL-EPST Power System
Area B 2A00-IN [2A] U00 INSTRUMENT (Admin. Building (North) 2A00-IN-IF&G FIRE&GAS SYSTEM
Area B 2A00-SS [2A] U00 STEEL STRUCTURE (Admin. Building (North)) 2A00-SS-OTST [2A] U00 Other Structure
Area A 3A31(B)-EL [3A] U31(B) ELECTRICAL (Control Room Building) 3A31(B)-EL-ECPR Cathodic Protection
Area A 3A31(B)-EL [3A] U31(B) ELECTRICAL (Control Room Building) 3A31(B)-EL-EEHT Electric Heat Tracing
Area A 3A31(B)-EL [3A] U31(B) ELECTRICAL (Control Room Building) 3A31(B)-EL-EGLT Grounding & Lightning
Area A 3A31(B)-EL [3A] U31(B) ELECTRICAL (Control Room Building) 3A31(B)-EL-ELSP Lighting & Small Power
Area A 3A31(B)-EL [3A] U31(B) ELECTRICAL (Control Room Building) 3A31(B)-EL-EPST Power System
Area A 3A31(B)-EL [3A] U31(B) ELECTRICAL (Control Room Building) 3A31(B)-EL-TELE Telecommunication
Area A 3A31(B)-IN [3A] U31(B) INSTRUMENT (Control Room Building) 3A31(B)-IN-IF&G FIRE&GAS SYSTEM
Area A 3A31-CI [3A] U31 CIVIL (Fire Water Unit) 3A31-CI-PACO [3A] U31/35/U36 Paving Concrete
Area A 3A31-CI [3A] U31 CIVIL (Fire Water Unit) 3A31-CI-PAGR [3A] U31/35/U36 Paving Gravel
Area A 3A31-CI [3A] U31 CIVIL (Fire Water Unit) 3A31-CI-ROAD [3A] U31/35/U36 Road
Area A 3A31-EL [3A] U31 ELECTRICAL (Fire Water Unit) 3A31-EL-ECPR Cathodic Protection
Area A 3A31-EL [3A] U31 ELECTRICAL (Fire Water Unit) 3A31-EL-EEHT Electric Heat Tracing
Area A 3A31-EL [3A] U31 ELECTRICAL (Fire Water Unit) 3A31-EL-EGLT Grounding & Lightning
Area A 3A31-EL [3A] U31 ELECTRICAL (Fire Water Unit) 3A31-EL-ELSP Lighting & Small Power
Area A 3A31-EL [3A] U31 ELECTRICAL (Fire Water Unit) 3A31-EL-EPST Power System
Area A 3A31-EL [3A] U31 ELECTRICAL (Fire Water Unit) 3A31-EL-TELE Telecommunication
Area A 3A31-IN [3A] U31 INSTRUMENT (Fire Water Unit) 3A31-IN-IF&G FIRE&GAS SYSTEM
Area A 3A31-SS [3A] U31 STEEL STRUCTURE (Fire Water Unit) 3A31-SS-OTST [3A] U31/35/U36 Other Structure
Area A 3A31-SS [3A] U31 STEEL STRUCTURE (Fire Water Unit) 3A31-SS-PIRK [3A] U31/35/U36 Piperack
Area A 3A35-EL [3A] U35 ELECTRICAL (Condensate Collection and Treatment) 3A35-EL-ECPR Cathodic Protection
Area A 3A35-EL [3A] U35 ELECTRICAL (Condensate Collection and Treatment) 3A35-EL-EEHT Electric Heat Tracing
Area A 3A35-EL [3A] U35 ELECTRICAL (Condensate Collection and Treatment) 3A35-EL-EGLT Grounding & Lightning
Area A 3A35-EL [3A] U35 ELECTRICAL (Condensate Collection and Treatment) 3A35-EL-ELSP Lighting & Small Power
Area A 3A35-EL [3A] U35 ELECTRICAL (Condensate Collection and Treatment) 3A35-EL-EPST Power System
Area A 3A35-EL [3A] U35 ELECTRICAL (Condensate Collection and Treatment) 3A35-EL-TELE Telecommunication
Area A 3A35-IN [3A] U35 INSTRUMENT (Condensate Collection and Treatment) 3A35-IN-IF&G FIRE&GAS SYSTEM
Area A 3A36-EL [3A] U36 ELECTRICAL (BFW & Steam Generation) 3A36-EL-EEHT Electric Heat Tracing
Area A 3A36-EL [3A] U36 ELECTRICAL (BFW & Steam Generation) 3A36-EL-EGLT Grounding & Lightning
Area A 3A36-EL [3A] U36 ELECTRICAL (BFW & Steam Generation) 3A36-EL-ELSP Lighting & Small Power
Area A 3A36-EL [3A] U36 ELECTRICAL (BFW & Steam Generation) 3A36-EL-EPST Power System
Area A 3A36-EL [3A] U36 ELECTRICAL (BFW & Steam Generation) 3A36-EL-TELE Telecommunication
Area A 3A36-IN [3A] U36 INSTRUMENT (BFW & Steam Generation) 3A36-IN-IF&G FIRE&GAS SYSTEM
Area A 3A41-CI [3A] U41 CIVIL (IA & PA Unit) 3A41-CI-PACO [3A] U41/U42 Paving Concrete
Area A 3A41-CI [3A] U41 CIVIL (IA & PA Unit) 3A41-CI-PAGR [3A] U41/U42 Paving Gravel
Area A 3A41-CI [3A] U41 CIVIL (IA & PA Unit) 3A41-CI-ROAD [3A] U41/U42 Road
Area A 3A41-EL [3A] U41 ELECTRICAL (IA & PA Unit) 3A41-EL-EEHT Electric Heat Tracing
Area A 3A41-EL [3A] U41 ELECTRICAL (IA & PA Unit) 3A41-EL-EGLT Grounding & Lightning
Area A 3A41-EL [3A] U41 ELECTRICAL (IA & PA Unit) 3A41-EL-ELSP Lighting & Small Power
Area A 3A41-EL [3A] U41 ELECTRICAL (IA & PA Unit) 3A41-EL-EPST Power System
Area A 3A41-EL [3A] U41 ELECTRICAL (IA & PA Unit) 3A41-EL-TELE Telecommunication
Area A 3A41-IN [3A] U41 INSTRUMENT (IA & PA Unit) 3A41-IN-IF&G FIRE&GAS SYSTEM
Area A 3A41-SS [3A] U41 STEEL STRUCTURE (IA & PA Unit) 3A41-SS-OTST [3A] U41/U42 Other Structure
Area A 3A41-SS [3A] U41 STEEL STRUCTURE (IA & PA Unit) 3A41-SS-PIRK [3A] U41/U42 Piperack
Area A 3A42-EL [3A] U42 ELECTRICAL (N2 Generation Unit) 3A42-EL-EEHT Electric Heat Tracing
Area A 3A42-EL [3A] U42 ELECTRICAL (N2 Generation Unit) 3A42-EL-EGLT Grounding & Lightning
Area A 3A42-EL [3A] U42 ELECTRICAL (N2 Generation Unit) 3A42-EL-ELSP Lighting & Small Power
Area A 3A42-EL [3A] U42 ELECTRICAL (N2 Generation Unit) 3A42-EL-EPST Power System
Area A 3A42-EL [3A] U42 ELECTRICAL (N2 Generation Unit) 3A42-EL-TELE Telecommunication
Area A 3A42-IN [3A] U42 INSTRUMENT (N2 Generation Unit) 3A42-IN-IF&G FIRE&GAS SYSTEM
Area A 3A43-CI [3A] U43 CIVIL (Caustic Soda and Sulfuric Acid Unit) 3A43-CI-PACO [3A] U43 Paving Concrete
Area A 3A43-CI [3A] U43 CIVIL (Caustic Soda and Sulfuric Acid Unit) 3A43-CI-PAGR [3A] U43 Paving Gravel
Area A 3A43-CI [3A] U43 CIVIL (Caustic Soda and Sulfuric Acid Unit) 3A43-CI-ROAD [3A] U43 Road
Area A 3A43-EL [3A] U43 ELECTRICAL (Caustic Soda and Sulfuric Acid Unit) 3A43-EL-EEHT Electric Heat Tracing
Area A 3A43-EL [3A] U43 ELECTRICAL (Caustic Soda and Sulfuric Acid Unit) 3A43-EL-EGLT Grounding & Lightning
Area A 3A43-EL [3A] U43 ELECTRICAL (Caustic Soda and Sulfuric Acid Unit) 3A43-EL-ELSP Lighting & Small Power
Area A 3A43-EL [3A] U43 ELECTRICAL (Caustic Soda and Sulfuric Acid Unit) 3A43-EL-EPST Power System
Area A 3A43-EL [3A] U43 ELECTRICAL (Caustic Soda and Sulfuric Acid Unit) 3A43-EL-TELE Telecommunication
Area A 3A43-IN [3A] U43 INSTRUMENT (Caustic Soda and Sulfuric Acid Unit) 3A43-IN-IF&G FIRE&GAS SYSTEM
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area A 3A43-SS [3A] U43 STEEL STRUCTURE (Caustic Soda and Sulfuric Acid Unit) 3A43-SS-OTST [3A] U43 Other Structure
Area A 3A43-SS [3A] U43 STEEL STRUCTURE (Caustic Soda and Sulfuric Acid Unit) 3A43-SS-PIRK [3A] U43 Piperack
Area A 3B37-CI [3B] U37 CIVIL (Power Generation) 3B37-CI-PACO [4A] U51(B) Paving Concrete
Area A 3B37-CI [3B] U37 CIVIL (Power Generation) 3B37-CI-PAGR [4A] U51(B) Paving Gravel
Area A 3B37-CI [3B] U37 CIVIL (Power Generation) 3B37-CI-ROAD [4A] U51(B) Road
Area A 3B37-EL [3B] U37 ELECTRICAL (Power Generation) 3B37-EL-ECPR Cathodic Protection
Area A 3B37-EL [3B] U37 ELECTRICAL (Power Generation) 3B37-EL-EEHT Electric Heat Tracing
Area A 3B37-EL [3B] U37 ELECTRICAL (Power Generation) 3B37-EL-EGLT Grounding & Lightning
Area A 3B37-EL [3B] U37 ELECTRICAL (Power Generation) 3B37-EL-ELSP Lighting & Small Power
Area A 3B37-EL [3B] U37 ELECTRICAL (Power Generation) 3B37-EL-EPST Power System
Area A 3B37-EL [3B] U37 ELECTRICAL (Power Generation) 3B37-EL-TELE Telecommunication
Area A 3B37-IN [3B] U37 INSTRUMENT (Power Generation) 3B37-IN-IF&G FIRE&GAS SYSTEM
Area A 3B37-SS [3B] U37 STEEL STRUCTURE (Power Generation) 3B37-SS-OTST [3B] U37 Other Structure
Area A 3B37-SS [3B] U37 STEEL STRUCTURE (Power Generation) 3B37-SS-PIRK [3B] U37 Piperack
Area A 3C33-CI [3C] U33 CIVIL (Cooling Water Unit) 3C33-CI-PACO [3C] U33 Paving Concrete
Area A 3C33-CI [3C] U33 CIVIL (Cooling Water Unit) 3C33-CI-PAGR [3C] U33 Paving Gravel
Area A 3C33-CI [3C] U33 CIVIL (Cooling Water Unit) 3C33-CI-ROAD [3C] U33 Road
Area A 3C33-EL [3C] U33 ELECTRICAL (Cooling Water Unit) 3C33-EL-EEHT Electric Heat Tracing
Area A 3C33-EL [3C] U33 ELECTRICAL (Cooling Water Unit) 3C33-EL-EGLT Grounding & Lightning
Area A 3C33-EL [3C] U33 ELECTRICAL (Cooling Water Unit) 3C33-EL-ELSP Lighting & Small Power
Area A 3C33-EL [3C] U33 ELECTRICAL (Cooling Water Unit) 3C33-EL-EPST Power System
Area A 3C33-EL [3C] U33 ELECTRICAL (Cooling Water Unit) 3C33-EL-TELE Telecommunication
Area A 3C33-IN [3C] U33 INSTRUMENT (Cooling Water Unit) 3C33-IN-IF&G FIRE&GAS SYSTEM
Area A 3C33-SS [3C] U33 STEEL STRUCTURE (Cooling Water Unit) 3C33-SS-OTST [3C] U33 Other Structure
Area A 3C33-SS [3C] U33 STEEL STRUCTURE (Cooling Water Unit) 3C33-SS-PIRK [3C] U33 Piperack
Area A 3C33-SS [3C] U33 STEEL STRUCTURE (Cooling Water Unit) 3C33-SS-SSEQ [3C] U33 Equipment Structure
Area A 4A45-EL [4A] U45 ELECTRICAL (Natural Gas Receiving Facilities) 4A45-EL-EEHT Electric Heat Tracing
Area A 4A45-EL [4A] U45 ELECTRICAL (Natural Gas Receiving Facilities) 4A45-EL-EGLT Grounding & Lightning
Area A 4A45-EL [4A] U45 ELECTRICAL (Natural Gas Receiving Facilities) 4A45-EL-ELSP Lighting & Small Power
Area A 4A45-EL [4A] U45 ELECTRICAL (Natural Gas Receiving Facilities) 4A45-EL-EPST Power System
Area A 4A45-EL [4A] U45 ELECTRICAL (Natural Gas Receiving Facilities) 4A45-EL-TELE Telecommunication
Area A 4A45-IN [4A] U45 INSTRUMENT (Natural Gas Receiving Facilities) 4A45-IN-IF&G FIRE&GAS SYSTEM
Area A 4A51-CI [4A] U51 CIVIL (Oily Water and Clean Water Pond) 4A51-CI-PACO [4A] U51 Paving Concrete
Area A 4A51-CI [4A] U51 CIVIL (Oily Water and Clean Water Pond) 4A51-CI-PAGR [4A] U51 Paving Gravel
Area A 4A51-CI [4A] U51 CIVIL (Oily Water and Clean Water Pond) 4A51-CI-ROAD [4A] U51 Road
Area A 4A51-IN [4A] U51 INSTRUMENT (Oily Water and Clean Water Pond) 4A51-IN-IF&G FIRE&GAS SYSTEM
Area A 4A51-SS [4A] U51 STEEL STRUCTURE (Oily Water and Clean Water Pond) 4A51-SS-OTST [4A] U51 Other Structure
Area A 4A52-CI [4A] U52/U45 CIVIL (Tank Farm Unit (Crude) & Natural Gas Facilities) 4A52-CI-PACO [4A] U52/U45 Paving Concrete (G-06)
Area A 4A52-CI [4A] U52/U45 CIVIL (Tank Farm Unit (Crude) & Natural Gas Facilities) 4A52-CI-PAGR [4A] U52/U45 Paving Gravel (G-06)
Area A 4A52-CI [4A] U52/U45 CIVIL (Tank Farm Unit (Crude) & Natural Gas Facilities) 4A52-CI-ROAD [4A] U52/U45 Road (G-06)
Area A 4A52-EL [4A] U52 ELECTRICAL (Tank Farm Unit (Crude)) 4A52-EL-ECPR Cathodic Protection
Area A 4A52-EL [4A] U52 ELECTRICAL (Tank Farm Unit (Crude)) 4A52-EL-EEHT Electric Heat Tracing
Area A 4A52-EL [4A] U52 ELECTRICAL (Tank Farm Unit (Crude)) 4A52-EL-EGLT Grounding & Lightning
Area A 4A52-EL [4A] U52 ELECTRICAL (Tank Farm Unit (Crude)) 4A52-EL-ELSP Lighting & Small Power
Area A 4A52-EL [4A] U52 ELECTRICAL (Tank Farm Unit (Crude)) 4A52-EL-EPST Power System
Area A 4A52-EL [4A] U52 ELECTRICAL (Tank Farm Unit (Crude)) 4A52-EL-TELE Telecommunication
Area A 4A52-IN [4A] U52 INSTRUMENT (Tank Farm Unit (Crude)) 4A52-IN-IF&G FIRE&GAS SYSTEM
Area A 4A52-SS [4A] U52/U45 STEEL STRUCTURE (Tank Farm Unit (Crude) & Natural Gas Facilities) 4A52-SS-OTST [4A] U52/U45 Other Structure (G-06)
Area A 4A52-SS [4A] U52/U45 STEEL STRUCTURE (Tank Farm Unit (Crude) & Natural Gas Facilities) 4A52-SS-SSEQ [4A] U52/U45 Equipment Structure (G-06)
Area B 4B52-CI [4B] U52 CIVIL (Tank Farm Unit (Intermediate)) 4B52-CI-PACO [4B] U52 Paving Concrete (G-10)
Area B 4B52-CI [4B] U52 CIVIL (Tank Farm Unit (Intermediate)) 4B52-CI-PAGR [4B] U52 Paving Gravel (G-10)
Area B 4B52-CI [4B] U52 CIVIL (Tank Farm Unit (Intermediate)) 4B52-CI-ROAD [4B] U52 Road (G-10)
Area B 4B52-EL [4B] U52 ELECTRICAL (Tank Farm Unit (Intermediate)) 4B52-EL-ECPR Cathodic Protection
Area B 4B52-EL [4B] U52 ELECTRICAL (Tank Farm Unit (Intermediate)) 4B52-EL-EEHT Electric Heat Tracing
Area B 4B52-EL [4B] U52 ELECTRICAL (Tank Farm Unit (Intermediate)) 4B52-EL-EGLT Grounding & Lightning
Area B 4B52-EL [4B] U52 ELECTRICAL (Tank Farm Unit (Intermediate)) 4B52-EL-ELSP Lighting & Small Power
Area B 4B52-EL [4B] U52 ELECTRICAL (Tank Farm Unit (Intermediate)) 4B52-EL-EPST Power System
Area B 4B52-EL [4B] U52 ELECTRICAL (Tank Farm Unit (Intermediate)) 4B52-EL-TELE Telecommunication
Area B 4B52-IN [4B] U52 INSTRUMENT (Tank Farm Unit (Intermediate)) 4B52-IN-IF&G FIRE&GAS SYSTEM
Area B 4B52-SS [4B] U52 STEEL STRUCTURE (Tank Farm Unit (Intermediate)) 4B52-SS-OTST [4B] U52 Other Structure (G-10)
Area B 4C52(G)-CI [4C] U52(G) CIVIL (Tank Farm Unit (Component)) 4C52(G)-CI-PACO [4C] U52(G) Paving Concrete (G-13)
Area B 4C52(G)-CI [4C] U52(G) CIVIL (Tank Farm Unit (Component)) 4C52(G)-CI-PAGR [4C] U52(G) Paving Gravel (G-13)
Area B 4C52(G)-CI [4C] U52(G) CIVIL (Tank Farm Unit (Component)) 4C52(G)-CI-ROAD [4C] U52(G) Road (G-13)
Area B 4C52(G)-EL [4C] U52(G) ELECTRICAL (Tank Farm Unit (Component)) 4C52(G)-EL-ECPR Cathodic Protection
Area B 4C52(G)-EL [4C] U52(G) ELECTRICAL (Tank Farm Unit (Component)) 4C52(G)-EL-EF&A Fire Alarm
Area B 4C52(G)-EL [4C] U52(G) ELECTRICAL (Tank Farm Unit (Component)) 4C52(G)-EL-EGLT Grounding & Lightning
Area B 4C52(G)-EL [4C] U52(G) ELECTRICAL (Tank Farm Unit (Component)) 4C52(G)-EL-ELSP Lighting & Small Power
Area B 4C52(G)-EL [4C] U52(G) ELECTRICAL (Tank Farm Unit (Component)) 4C52(G)-EL-EPST Power System
Area B 4C52(G)-EL [4C] U52(G) ELECTRICAL (Tank Farm Unit (Component)) 4C52(G)-EL-TELE Telecommunication
Area B 4C52(G)-IN [4C] U52(G) INSTRUMENT (Tank Farm Unit (Component)) 4C52(G)-IN-IF&G FIRE&GAS SYSTEM
Area B 4C52(G)-SS [4C] U52(G) STEEL STRUCTURE (Tank Farm Unit (Component)) 4C52(G)-SS-OTST [4C] U52(G) Other Structure (G-13)
Area B 4C52(G)-SS [4C] U52(G) STEEL STRUCTURE (Tank Farm Unit (Component)) 4C52(G)-SS-PIRK [4C] U52(G) Piperack (G-13)
Area C 4C52(H)-CI [4C] U52(H) CIVIL (Tank Farm Unit (Component)) 4C52(H)-CI-PACO [4C] U52(H) Paving Concrete
Area C 4C52(H)-CI [4C] U52(H) CIVIL (Tank Farm Unit (Component)) 4C52(H)-CI-PAGR [4C] U52(H) Paving Gravel
Area C 4C52(H)-CI [4C] U52(H) CIVIL (Tank Farm Unit (Component)) 4C52(H)-CI-ROAD [4C] U52(H) Road
Area C 4C52(H)-EL [4C] U52(H) ELECTRICAL (Tank Farm Unit (Component)) 4C52(H)-EL-EEHT Electric Heat Tracing
Area C 4C52(H)-EL [4C] U52(H) ELECTRICAL (Tank Farm Unit (Component)) 4C52(H)-EL-EF&A Fire Alarm
Area C 4C52(H)-EL [4C] U52(H) ELECTRICAL (Tank Farm Unit (Component)) 4C52(H)-EL-EGLT Grounding & Lightning
Area C 4C52(H)-EL [4C] U52(H) ELECTRICAL (Tank Farm Unit (Component)) 4C52(H)-EL-ELSP Lighting & Small Power
Area C 4C52(H)-EL [4C] U52(H) ELECTRICAL (Tank Farm Unit (Component)) 4C52(H)-EL-EPST Power System
Area C 4C52(H)-EL [4C] U52(H) ELECTRICAL (Tank Farm Unit (Component)) 4C52(H)-EL-TELE Telecommunication
Area C 4C52(H)-IN [4C] U52(H) INSTRUMENT (Tank Farm Unit (Component)) 4C52(H)-IN-IF&G FIRE&GAS SYSTEM
Area C 4C52(H)-SS [4C] U52(H) STEEL STRUCTURE (Tank Farm Unit (Component)) 4C52(H)-SS-OTST [4C] U52(H) other Structure
Area C 4C52(H)-SS [4C] U52(H) STEEL STRUCTURE (Tank Farm Unit (Component)) 4C52(H)-SS-PIRK [4C] U52(H) Piperack
Area B 4D52-CI [4D] U52 CIVIL (Tank Farm Unit (Component & Final)) 4D52-CI-PACO [4D] U52 Paving Concrete (G-18)
Area B 4D52-CI [4D] U52 CIVIL (Tank Farm Unit (Component & Final)) 4D52-CI-PAGR [4D] U52 Paving Gravel (G-18)
Area B 4D52-CI [4D] U52 CIVIL (Tank Farm Unit (Component & Final)) 4D52-CI-ROAD [4D] U52 Road (G-18)
Area B 4D52-EL [4D] U52 ELECTRICAL (Tank Farm Unit (Component & Final)) 4D52-EL-ECPR Cathodic Protection
Area B 4D52-EL [4D] U52 ELECTRICAL (Tank Farm Unit (Component & Final)) 4D52-EL-EF&A Fire Alarm
Area B 4D52-EL [4D] U52 ELECTRICAL (Tank Farm Unit (Component & Final)) 4D52-EL-EGLT Grounding & Lightning
Area B 4D52-EL [4D] U52 ELECTRICAL (Tank Farm Unit (Component & Final)) 4D52-EL-ELSP Lighting & Small Power
Area B 4D52-EL [4D] U52 ELECTRICAL (Tank Farm Unit (Component & Final)) 4D52-EL-EPST Power System
Area B 4D52-EL [4D] U52 ELECTRICAL (Tank Farm Unit (Component & Final)) 4D52-EL-TELE Telecommunication
Area B 4D52-IN [4D] U52 INSTRUMENT (Tank Farm Unit (Component & Final)) 4D52-IN-IF&G FIRE&GAS SYSTEM
Area B 4D52-SS [4D] U52 STEEL STRUCTURE (Tank Farm Unit (Component & Final)) 4D52-SS-OTST [4D] U52 Other Structure (G-18)
Area B 4D52-SS [4D] U52 STEEL STRUCTURE (Tank Farm Unit (Component & Final)) 4D52-SS-PIRK [4D] U52 Piperack (G-18)
Area B 4D52-SS [4D] U52 STEEL STRUCTURE (Tank Farm Unit (Component & Final)) 4D52-SS-SSEQ [4D] U52 Equipment Structure (G-18)
Area C 5A51-CI [5A] U51 CIVIL (Waste water collection and treatment plant Unit) 5A51-CI-PACO [5A] U51 Paving Concrete
Area C 5A51-CI [5A] U51 CIVIL (Waste water collection and treatment plant Unit) 5A51-CI-PAGR [5A] U51 Paving Gravel
Area C 5A51-CI [5A] U51 CIVIL (Waste water collection and treatment plant Unit) 5A51-CI-ROAD [5A] U51 Road
Area C 5A51-EL [5A] U51 ELECTRICAL (Waste water collection and treatment plant Unit) 5A51-EL-EEHT Electric Heat Tracing
Area C 5A51-EL [5A] U51 ELECTRICAL (Waste water collection and treatment plant Unit) 5A51-EL-EF&A Fire Alarm
Area C 5A51-EL [5A] U51 ELECTRICAL (Waste water collection and treatment plant Unit) 5A51-EL-EGLT Grounding & Lightning
Area C 5A51-EL [5A] U51 ELECTRICAL (Waste water collection and treatment plant Unit) 5A51-EL-ELSP Lighting & Small Power
Area C 5A51-EL [5A] U51 ELECTRICAL (Waste water collection and treatment plant Unit) 5A51-EL-EPST Power System
Area C 5A51-EL [5A] U51 ELECTRICAL (Waste water collection and treatment plant Unit) 5A51-EL-TELE Telecommunication
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area C 5A51-IN [5A] U51 INSTRUMENT (Waste water collection and treatment plant Unit) 5A51-IN-IF&G FIRE&GAS SYSTEM
Area C 5A51-SS [5A] U51 STEEL STRUCTURE (Waste water collection and treatment plant Unit) 5A51-SS-OTST [5A] U51 other Structure
Area C 5A51-SS [5A] U51 STEEL STRUCTURE (Waste water collection and treatment plant Unit) 5A51-SS-PIRK [5A] U51 Piperack
Area C 5A51-SS [5A] U51 STEEL STRUCTURE (Waste water collection and treatment plant Unit) 5A51-SS-SSEQ [5A] U51 Equipment Structure
Area C 5A53-CI [5A] U53 CIVIL (Asphalt Loading) 5A53-CI-PACO [5A] U53 Paving Concrete (H-12)
Area C 5A53-CI [5A] U53 CIVIL (Asphalt Loading) 5A53-CI-PAGR [5A] U53 Paving Gravel (H-12)
Area C 5A53-CI [5A] U53 CIVIL (Asphalt Loading) 5A53-CI-ROAD [5A] U53 Road (H-12)
Area C 5A53-EL [5A] U53 ELECTRICAL (Asphalt Loading) 5A53-EL-EEHT Electric Heat Tracing
Area C 5A53-EL [5A] U53 ELECTRICAL (Asphalt Loading) 5A53-EL-EF&A Fire Alarm
Area C 5A53-EL [5A] U53 ELECTRICAL (Asphalt Loading) 5A53-EL-EGLT Grounding & Lightning
Area C 5A53-EL [5A] U53 ELECTRICAL (Asphalt Loading) 5A53-EL-ELSP Lighting & Small Power
Area C 5A53-EL [5A] U53 ELECTRICAL (Asphalt Loading) 5A53-EL-EPST Power System
Area C 5A53-EL [5A] U53 ELECTRICAL (Asphalt Loading) 5A53-EL-TELE Telecommunication
Area C 5A53-IN [5A] U53 INSTRUMENT (Asphalt Loading) 5A53-IN-IF&G FIRE&GAS SYSTEM
Area C 5A53-SS [5A] U53 STEEL STRUCTURE (Asphalt Loading) 5A53-SS-OTST [5A] U53 other Structure (H-12)
Area C 5A53-SS [5A] U53 STEEL STRUCTURE (Asphalt Loading) 5A53-SS-PIRK [5A] U53 Piperack (H-12)
Area C 5A53-SS [5A] U53 STEEL STRUCTURE (Asphalt Loading) 5A53-SS-SSEQ [5A] U53 Equipment Structure (H-12)
Area C 5A54-CI [5A] U54 CIVIL (Sulfur Solidification Unit) 5A54-CI-PAGR [5A] U54 Paving Gravel
Area C 5A54-CI [5A] U54 CIVIL (Sulfur Solidification Unit) 5A54-CI-ROAD [5A] U54 Road
Area C 5A54-EL [5A] U54 ELECTRICAL (Sulfur Solidification Unit) 5A54-EL-EEHT Electric Heat Tracing
Area C 5A54-EL [5A] U54 ELECTRICAL (Sulfur Solidification Unit) 5A54-EL-EF&A Fire Alarm
Area C 5A54-EL [5A] U54 ELECTRICAL (Sulfur Solidification Unit) 5A54-EL-EGLT Grounding & Lightning
Area C 5A54-EL [5A] U54 ELECTRICAL (Sulfur Solidification Unit) 5A54-EL-ELSP Lighting & Small Power
Area C 5A54-EL [5A] U54 ELECTRICAL (Sulfur Solidification Unit) 5A54-EL-EPST Power System
Area C 5A54-EL [5A] U54 ELECTRICAL (Sulfur Solidification Unit) 5A54-EL-TELE Telecommunication
Area C 5A54-IN [5A] U54 INSTRUMENT (Sulfur Solidification Unit) 5A54-IN-IF&G FIRE&GAS SYSTEM
Area C 5A61-CI [5A] U61 CIVIL (Heavy Fuel Oil Pipeline Unit) 5A61-CI-PACO [5A] U61 Paving Concrete
Area C 5A61-CI [5A] U61 CIVIL (Heavy Fuel Oil Pipeline Unit) 5A61-CI-PAGR [5A] U61 Paving Gravel
Area C 5A61-CI [5A] U61 CIVIL (Heavy Fuel Oil Pipeline Unit) 5A61-CI-ROAD [5A] U61 Road
Area C 5A61-EL [5A] U61 ELECTRICAL (Heavy Fuel Oil Pipeline Unit) 5A61-EL-EEHT Electric Heat Tracing
Area C 5A61-EL [5A] U61 ELECTRICAL (Heavy Fuel Oil Pipeline Unit) 5A61-EL-EF&A Fire Alarm
Area C 5A61-EL [5A] U61 ELECTRICAL (Heavy Fuel Oil Pipeline Unit) 5A61-EL-EGLT Grounding & Lightning
Area C 5A61-EL [5A] U61 ELECTRICAL (Heavy Fuel Oil Pipeline Unit) 5A61-EL-ELSP Lighting & Small Power
Area C 5A61-EL [5A] U61 ELECTRICAL (Heavy Fuel Oil Pipeline Unit) 5A61-EL-EPST Power System
Area C 5A61-EL [5A] U61 ELECTRICAL (Heavy Fuel Oil Pipeline Unit) 5A61-EL-TELE Telecommunication
Area C 5A61-IN [5A] U61 INSTRUMENT (Heavy Fuel Oil Pipeline Unit) 5A61-IN-IF&G FIRE&GAS SYSTEM
Area C 5A61-SS [5A] U61 STEEL STRUCTURE (Heavy Fuel Oil Pipeline Unit) 5A61-SS-OTST [5A] U61 other Structure
Area C 5A61-SS [5A] U61 STEEL STRUCTURE (Heavy Fuel Oil Pipeline Unit) 5A61-SS-PIRK [5A] U61 Piperack
Area C 5A61-SS [5A] U61 STEEL STRUCTURE (Heavy Fuel Oil Pipeline Unit) 5A61-SS-SSEQ [5A] U61 Equipment Structure
Area C 5B00-EL [5B] U00 ELECTRICAL (Fencing (5B)) 5B00-EL-EF&A Fire Alarm
Area C 5B00-EL [5B] U00 ELECTRICAL (Fencing (5B)) 5B00-EL-EGLT Grounding & Lightning
Area C 5B00-EL [5B] U00 ELECTRICAL (Fencing (5B)) 5B00-EL-ELSP Lighting & Small Power
Area C 5B00-EL [5B] U00 ELECTRICAL (Fencing (5B)) 5B00-EL-EPST Power System
Area B 5C50-CI [5C] U50 CIVIL (Flare unit) 5C50-CI-PACO [5C] U50 Paving Concrete (G-20)
Area B 5C50-CI [5C] U50 CIVIL (Flare unit) 5C50-CI-PAGR [5C] U50 Paving Gravel (G-20)
Area B 5C50-CI [5C] U50 CIVIL (Flare unit) 5C50-CI-ROAD [5C] U50 Road (G-20)
Area B 5C50-EL [5C] U50 ELECTRICAL (Flare unit) 5C50-EL-ECPR Cathodic Protection
Area B 5C50-EL [5C] U50 ELECTRICAL (Flare unit) 5C50-EL-EF&A Fire Alarm
Area B 5C50-EL [5C] U50 ELECTRICAL (Flare unit) 5C50-EL-EGLT Grounding & Lightning
Area B 5C50-EL [5C] U50 ELECTRICAL (Flare unit) 5C50-EL-ELSP Lighting & Small Power
Area B 5C50-EL [5C] U50 ELECTRICAL (Flare unit) 5C50-EL-EPST Power System
Area B 5C50-EL [5C] U50 ELECTRICAL (Flare unit) 5C50-EL-TELE Telecommunication
Area B 5C50-IN [5C] U50 INSTRUMENT (Flare unit) 5C50-IN-IF&G FIRE&GAS SYSTEM
Area B 5C50-SS [5C] U50 STEEL STRUCTURE (Flare unit) 5C50-SS-OTST [5C] U50 Other Structure (G-20)
Area B 5C50-SS [5C] U50 STEEL STRUCTURE (Flare unit) 5C50-SS-PIRK [5C] U50 Piperack (G-20)
Area A 5D30-CI [5D] U30/U34 CIVIL (Raw Water Treatment, Drinking Water Unit) 5D30-CI-PACO [5D] U30/U34 Paving Concrete
Area A 5D30-CI [5D] U30/U34 CIVIL (Raw Water Treatment, Drinking Water Unit) 5D30-CI-PAGR [5D] U30/U34 Paving Gravel
Area A 5D30-CI [5D] U30/U34 CIVIL (Raw Water Treatment, Drinking Water Unit) 5D30-CI-ROAD [5D] U30/U34 Road
Area A 5D30-EL [5D] U30 ELECTRICAL (Raw Water Treatment Unit) 5D30-EL-ECPR Cathodic Protection
Area A 5D30-EL [5D] U30 ELECTRICAL (Raw Water Treatment Unit) 5D30-EL-EEHT Electric Heat Tracing
Area A 5D30-EL [5D] U30 ELECTRICAL (Raw Water Treatment Unit) 5D30-EL-EGLT Grounding & Lightning
Area A 5D30-EL [5D] U30 ELECTRICAL (Raw Water Treatment Unit) 5D30-EL-ELSP Lighting & Small Power
Area A 5D30-EL [5D] U30 ELECTRICAL (Raw Water Treatment Unit) 5D30-EL-EPST Power System
Area A 5D30-EL [5D] U30 ELECTRICAL (Raw Water Treatment Unit) 5D30-EL-TELE Telecommunication
Area A 5D30-IN [5D] U30 INSTRUMENT (Raw Water Treatment Unit) 5D30-IN-IF&G FIRE&GAS SYSTEM
Area A 5D30-SS [5D] U30/U34 STEEL STRUCTURE (Raw Water Treatment, Drinking Water Unit) 5D30-SS-OTST [5D] U30/U34 Other Structure
Area A 5D30-SS [5D] U30/U34 STEEL STRUCTURE (Raw Water Treatment, Drinking Water Unit) 5D30-SS-PIRK [5D] U30/U34 Piperack
Area A 5D34-EL [5D] U34 ELECTRICAL (Drinking Water Unit) 5D34-EL-ECPR Cathodic Protection
Area A 5D34-EL [5D] U34 ELECTRICAL (Drinking Water Unit) 5D34-EL-EEHT Electric Heat Tracing
Area A 5D34-EL [5D] U34 ELECTRICAL (Drinking Water Unit) 5D34-EL-EGLT Grounding & Lightning
Area A 5D34-EL [5D] U34 ELECTRICAL (Drinking Water Unit) 5D34-EL-ELSP Lighting & Small Power
Area A 5D34-EL [5D] U34 ELECTRICAL (Drinking Water Unit) 5D34-EL-EPST Power System
Area A 5D34-EL [5D] U34 ELECTRICAL (Drinking Water Unit) 5D34-EL-TELE Telecommunication
Area A 5D34-IN [5D] U34 INSTRUMENT (Drinking Water Unit) 5D34-IN-IF&G FIRE&GAS SYSTEM
Area A 5D51-CI [5D] U51 CIVIL (Waste Water Treatment unit) 5D51-CI-PACO [5D] U51 Paving Concrete (S-10)
Area A 5D51-CI [5D] U51 CIVIL (Waste Water Treatment unit) 5D51-CI-PAGR [5D] U51 Paving Gravel (S-10)
Area A 5D51-CI [5D] U51 CIVIL (Waste Water Treatment unit) 5D51-CI-ROAD [5D] U51 Road (S-10)
Area A 5D51-EL [5D] U51 ELECTRICAL (Waste Water Treatment unit) 5D51-EL-ECPR Cathodic Protection
Area A 5D51-EL [5D] U51 ELECTRICAL (Waste Water Treatment unit) 5D51-EL-EEHT Electric Heat Tracing
Area A 5D51-EL [5D] U51 ELECTRICAL (Waste Water Treatment unit) 5D51-EL-EGLT Grounding & Lightning
Area A 5D51-EL [5D] U51 ELECTRICAL (Waste Water Treatment unit) 5D51-EL-ELSP Lighting & Small Power
Area A 5D51-EL [5D] U51 ELECTRICAL (Waste Water Treatment unit) 5D51-EL-EPST Power System
Area A 5D51-EL [5D] U51 ELECTRICAL (Waste Water Treatment unit) 5D51-EL-TELE Telecommunication
Area A 5D51-IN [5D] U51 INSTRUMENT (Waste Water Treatment unit) 5D51-IN-IF&G FIRE&GAS SYSTEM
Area A 5D51-SS [5D] U51 STEEL STRUCTURE (Waste Water Treatment unit) 5D51-SS-OTST [5D] U51 Other Structure (S-10)
Area A 5D51-SS [5D] U51 STEEL STRUCTURE (Waste Water Treatment unit) 5D51-SS-PIRK [5D] U51 Piperack (S-10)
Area A 5D51-SS [5D] U51 STEEL STRUCTURE (Waste Water Treatment unit) 5D51-SS-SSEQ [5D] U51 Equipment Structure (S-10)
Area C 5E58-CI [5E] U58 CIVIL (Refinery Interconnecting Unit) 5E58-CI-PACO [5E] U58 Paving Concrete (H-27)
Area C 5E58-CI [5E] U58 CIVIL (Refinery Interconnecting Unit) 5E58-CI-PAGR [5E] U58 Paving Gravel (H-27)
Area C 5E58-CI [5E] U58 CIVIL (Refinery Interconnecting Unit) 5E58-CI-ROAD [5E] U58 Road (H-27)
Area C 5E58-EL [5E] U58 ELECTRICAL (Refinery Interconnecting Unit) 5E58-EL-EEHT Electric Heat Tracing
Area C 5E58-EL [5E] U58 ELECTRICAL (Refinery Interconnecting Unit) 5E58-EL-EF&A Fire Alarm
Area C 5E58-EL [5E] U58 ELECTRICAL (Refinery Interconnecting Unit) 5E58-EL-EGLT Grounding & Lightning
Area C 5E58-EL [5E] U58 ELECTRICAL (Refinery Interconnecting Unit) 5E58-EL-ELSP Lighting & Small Power
Area C 5E58-EL [5E] U58 ELECTRICAL (Refinery Interconnecting Unit) 5E58-EL-EPST Power System
Area C 5E58-EL [5E] U58 ELECTRICAL (Refinery Interconnecting Unit) 5E58-EL-TELE Telecommunication
Area C 5E58-IN [5E] U58 INSTRUMENT (Refinery Interconnecting Unit) 5E58-IN-IF&G FIRE&GAS SYSTEM
Area C 5E58-SS [5E] U58 STEEL STRUCTURE (Refinery Interconnecting Unit) 5E58-SS-OTST [5E] U58 other Structure (H-27)
Area C 5E58-SS [5E] U58 STEEL STRUCTURE (Refinery Interconnecting Unit) 5E58-SS-PIRK [5E] U58 Piperack (H-27)
Area C 5E58-SS [5E] U58 STEEL STRUCTURE (Refinery Interconnecting Unit) 5E58-SS-SSEQ [5E] U58 Equipment Structure (H-27)
Area B 6A90-CI [6A] U90 CIVIL (Depot Building (South)) 6A90-CI-PACO [6A] U90 Paving Concrete
Area B 6A90-CI [6A] U90 CIVIL (Depot Building (South)) 6A90-CI-PAGR [6A] U90 Paving Gravel
Area B 6A90-CI [6A] U90 CIVIL (Depot Building (South)) 6A90-CI-ROAD [6A] U90 Road
Area B 6A90-EL [6A] U90 ELECTRICAL (Depot Building (South)) 6A90-EL-EGLT Grounding & Lightning
Area B 6A90-EL [6A] U90 ELECTRICAL (Depot Building (South)) 6A90-EL-ELSP Lighting & Small Power
Area B 6A90-EL [6A] U90 ELECTRICAL (Depot Building (South)) 6A90-EL-EPST Power System
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area B 6A90-IN [6A] U90 INSTRUMENT (Depot Building (South)) 6A90-IN-IF&G FIRE&GAS SYSTEM
Area C 6B00-EL [6B] U00 ELECTRICAL (Fencing (6B)) 6B00-EL-EF&A Fire Alarm
Area C 6B00-EL [6B] U00 ELECTRICAL (Fencing (6B)) 6B00-EL-EGLT Grounding & Lightning
Area C 6B00-EL [6B] U00 ELECTRICAL (Fencing (6B)) 6B00-EL-ELSP Lighting & Small Power
Area C 6B00-EL [6B] U00 ELECTRICAL (Fencing (6B)) 6B00-EL-EPST Power System
Area C 6B00-IN [6B] U00 INSTRUMENT (Fencing (6B)) 6B00-IN-IF&G FIRE&GAS SYSTEM
Area C 6C90-CI [6C] U90 CIVIL (Loading and Dispatching Facilities) 6C90-CI-PACO [6C] U90 Paving Concrete (H-18)
Area C 6C90-CI [6C] U90 CIVIL (Loading and Dispatching Facilities) 6C90-CI-PAGR [6C] U90 Paving Gravel (H-18)
Area C 6C90-CI [6C] U90 CIVIL (Loading and Dispatching Facilities) 6C90-CI-ROAD [6C] U90 Road (H-18)
Area C 6C90-EL [6C] U90 ELECTRICAL (Loading and Dispatching Facilities) 6C90-EL-EEHT Electric Heat Tracing
Area C 6C90-EL [6C] U90 ELECTRICAL (Loading and Dispatching Facilities) 6C90-EL-EF&A Fire Alarm
Area C 6C90-EL [6C] U90 ELECTRICAL (Loading and Dispatching Facilities) 6C90-EL-EGLT Grounding & Lightning
Area C 6C90-EL [6C] U90 ELECTRICAL (Loading and Dispatching Facilities) 6C90-EL-ELSP Lighting & Small Power
Area C 6C90-EL [6C] U90 ELECTRICAL (Loading and Dispatching Facilities) 6C90-EL-EPST Power System
Area C 6C90-EL [6C] U90 ELECTRICAL (Loading and Dispatching Facilities) 6C90-EL-TELE Telecommunication
Area C 6C90-IN [6C] U90 INSTRUMENT (Loading and Dispatching Facilities) 6C90-IN-IF&G FIRE&GAS SYSTEM
Area C 6C90-SS [6C] U90 STEEL STRUCTURE (Loading and Dispatching Facilities) 6C90-SS-OTST [6C] U90 other Structure (H-18)
Area C 6C90-SS [6C] U90 STEEL STRUCTURE (Loading and Dispatching Facilities) 6C90-SS-PIRK [6C] U90 Piperack (H-18)
Area C 6D90-CI [6D] U90 CIVIL (Tankage and Interconnecting Area) 6D90-CI-PACO [6D] U90 Paving Concrete (H-20)
Area C 6D90-CI [6D] U90 CIVIL (Tankage and Interconnecting Area) 6D90-CI-PAGR [6D] U90 Paving Gravel (H-20)
Area C 6D90-CI [6D] U90 CIVIL (Tankage and Interconnecting Area) 6D90-CI-ROAD [6D] U90 Road (H-20)
Area C 6D90-EL [6D] U90 ELECTRICAL (Tankage and Interconnecting Area) 6D90-EL-ECPR Cathodic Protection
Area C 6D90-EL [6D] U90 ELECTRICAL (Tankage and Interconnecting Area) 6D90-EL-EEHT Electric Heat Tracing
Area C 6D90-EL [6D] U90 ELECTRICAL (Tankage and Interconnecting Area) 6D90-EL-EF&A Fire Alarm
Area C 6D90-EL [6D] U90 ELECTRICAL (Tankage and Interconnecting Area) 6D90-EL-EGLT Grounding & Lightning
Area C 6D90-EL [6D] U90 ELECTRICAL (Tankage and Interconnecting Area) 6D90-EL-ELSP Lighting & Small Power
Area C 6D90-EL [6D] U90 ELECTRICAL (Tankage and Interconnecting Area) 6D90-EL-EPST Power System
Area C 6D90-EL [6D] U90 ELECTRICAL (Tankage and Interconnecting Area) 6D90-EL-TELE Telecommunication
Area C 6D90-IN [6D] U90 INSTRUMENT (Tankage and Interconnecting Area) 6D90-IN-IF&G FIRE&GAS SYSTEM
Area C 6D90-SS [6D] U90 STEEL STRUCTURE (Tankage and Interconnecting Area) 6D90-SS-OTST [6D] U90 other Structure (H-20)
Area C 6D90-SS [6D] U90 STEEL STRUCTURE (Tankage and Interconnecting Area) 6D90-SS-PIRK [6D] U90 Piperack (H-20)
Area B 7A60(E)-EL [7A] U60(E) ELECTRICAL 33 kv OHTL 7A60(E)-EL-EEHT Electric Heat Tracing
Area B 7A60(E)-EL [7A] U60(E) ELECTRICAL 33 kv OHTL 7A60(E)-EL-EGLT Grounding & Lightning
Area B 7A60(E)-EL [7A] U60(E) ELECTRICAL 33 kv OHTL 7A60(E)-EL-EPST Power System
Area B 7A60(E)-EL [7A] U60(E) ELECTRICAL 33 kv OHTL 7A60(E)-EL-TELE Telecommunication
Area B 7A60(E)-IN [7A] U60(E) INSTRUMENT 33 kv OHTL 7A60(E)-IN-IF&G FIRE&GAS SYSTEM
Area B 7A60-CI [7A] U60 CIVIL (River Water Intake Unit) 7A60-CI-PACO [7A] U60 Paving Concrete
Area B 7A60-CI [7A] U60 CIVIL (River Water Intake Unit) 7A60-CI-PAGR [7A] U60 Paving Gravel
Area B 7A60-CI [7A] U60 CIVIL (River Water Intake Unit) 7A60-CI-ROAD [7A] U60 Road
Area B 7A60-EL [7A] U60 ELECTRICAL (River Water Intake Unit) 7A60-EL-ECPR Cathodic Protection
Area B 7A60-EL [7A] U60 ELECTRICAL (River Water Intake Unit) 7A60-EL-EEHT Electric Heat Tracing
Area B 7A60-EL [7A] U60 ELECTRICAL (River Water Intake Unit) 7A60-EL-EF&A Fire Alarm
Area B 7A60-EL [7A] U60 ELECTRICAL (River Water Intake Unit) 7A60-EL-EGLT Grounding & Lightning
Area B 7A60-EL [7A] U60 ELECTRICAL (River Water Intake Unit) 7A60-EL-ELSP Lighting & Small Power
Area B 7A60-EL [7A] U60 ELECTRICAL (River Water Intake Unit) 7A60-EL-EPST Power System
Area B 7A60-EL [7A] U60 ELECTRICAL (River Water Intake Unit) 7A60-EL-TELE Telecommunication
Area B 7A60-IN [7A] U60 INSTRUMENT (River Water Intake Unit) 7A60-IN-IF&G FIRE&GAS SYSTEM
Area B 7A60-SS [7A] U60 STEEL STRUCTURE (River Water Intake Unit) 7A60-SS-OTST [7A] U60 Other Structure
Area B 7A60-SS [7A] U60 STEEL STRUCTURE (River Water Intake Unit) 7A60-SS-SSEQ [7A] U60 Equipment Structure
Area B 7B61(P)-IN [7B] U61 INSTRUMENT (Heavy Fuel Oil Pipeline (14" x 23km) 7B61(P)-IN-IF&G FIRE&GAS SYSTEM
Area B 7B61-CI [7B] U61 CIVIL (AL-KHAIRAT POWER STATION) 7B61-CI-PACO [7B] U61 Paving Concrete
Area B 7B61-CI [7B] U61 CIVIL (AL-KHAIRAT POWER STATION) 7B61-CI-PAGR [7B] U61 Paving Gravel
Area B 7B61-EL [7B] U61 ELECTRICAL (AL-KHAIRAT POWER STATION) 7B61-EL-ECPR Cathodic Protection
Area B 7B61-EL [7B] U61 ELECTRICAL (AL-KHAIRAT POWER STATION) 7B61-EL-EEHT Electric Heat Tracing
Area B 7B61-IN [7B] U61 INSTRUMENT (AL-KHAIRAT POWER STATION) 7B61-IN-IF&G FIRE&GAS SYSTEM
Area B 7C62-CI [7C] U62 CIVIL (Crude Oil Pipeline (32" x 1.25km), Natural Gas Pipeline (14" x 1.25km)) 7C62-CI-PACO [7C] U62 Paving Concrete
Area B 7C62-EL [7C] U62 ELECTRICAL (Crude Oil Pipeline (32" x 1.25km), Natural Gas Pipeline (14" x 1.25km)) 7C62-EL-ECPR Cathodic Protection
Area B 7C62-EL [7C] U62 ELECTRICAL (Crude Oil Pipeline (32" x 1.25km), Natural Gas Pipeline (14" x 1.25km)) 7C62-EL-EGLT Grounding & Lightning
Area B 7C62-EL [7C] U62 ELECTRICAL (Crude Oil Pipeline (32" x 1.25km), Natural Gas Pipeline (14" x 1.25km)) 7C62-EL-ELSP Lighting & Small Power
Area B B1A-01 PIBs/SS B1A-01-ARCH B1A-01 Architecture
Area B B1A-01 PIBs/SS B1A-01-EEDG Emergency Diesel Generator
Area B B1A-01 PIBs/SS B1A-01-EF&A Fire Alram system
Area B B1A-01 PIBs/SS B1A-01-EGLT Grounding & Lightning
Area B B1A-01 PIBs/SS B1A-01-EILS Indoor Lighting System
Area B B1A-01 PIBs/SS B1A-01-ELEQ Electrical Equipment
Area B B1A-01 PIBs/SS B1A-01-EPST Power System
Area B B1A-01 PIBs/SS B1A-01-EUPS UPS
Area B B1A-01 PIBs/SS B1A-01-HVCT B1A-01 for HVAC Control System
Area B B1A-01 PIBs/SS B1A-01-HVEQ B1A-01 for HVAC Equipment
Area B B1A-01 PIBs/SS B1A-01-HVFF B1A-01 for HVAC FM200
Area B B1A-01 PIBs/SS B1A-01-HVPL B1A-01 for HVAC Plumbing
Area B B1A-01 PIBs/SS B1A-01-IF&G FIRE&GAS SYSTEM
Area B B1A-01 PIBs/SS B1A-01-IPCS PROCESS CONTROL SYSTEM
Area B B1A-01 PIBs/SS B1A-01-TELE Telecomm. System
Area B B1A-02 COMPRESSOR SHELTER B1A-02-ARCH B1A-02 Architecture
Area B B1A-02 COMPRESSOR SHELTER B1A-02-IF&G FIRE&GAS SYSTEM
Area B B1A-03 COMPRESSOR SHELTER B1A-03-ARCH B1A-03 Architecture
Area B B1A-03 COMPRESSOR SHELTER B1A-03-IF&G FIRE&GAS SYSTEM
Area B B1A-04 COMPRESSOR SHELTER B1A-04-ARCH B1A-04 Architecture
Area B B1A-04 COMPRESSOR SHELTER B1A-04-IF&G FIRE&GAS SYSTEM
Area B B1A-05 COMPRESSOR SHELTER B1A-05-ARCH B1A-05 Architecture
Area B B1A-05 COMPRESSOR SHELTER B1A-05-IF&G FIRE&GAS SYSTEM
Area B B1A-06 PACKAGE SHELTER FOR 13-PK-102 B1A-06-ARCH B1A-06 Architecture
Area B B1A-06 PACKAGE SHELTER FOR 13-PK-102 B1A-06-IF&G FIRE&GAS SYSTEM
Area B B1A-07 PACKAGE SHELTER FOR 13-PK-103 B1A-07-ARCH B1A-07 Architecture
Area B B1A-07 PACKAGE SHELTER FOR 13-PK-103 B1A-07-IF&G FIRE&GAS SYSTEM
Area B B1A-08 PACKAGE SHELTER FOR 13-PK-105 B1A-08-ARCH B1A-08 Architecture
Area B B1A-08 PACKAGE SHELTER FOR 13-PK-105 B1A-08-IF&G FIRE&GAS SYSTEM
Area B B1A-09 PACKAGE SHELTER FOR 14-PK-102 B1A-09-ARCH B1A-09 Architecture
Area B B1A-09 PACKAGE SHELTER FOR 14-PK-102 B1A-09-IF&G FIRE&GAS SYSTEM
Area B B1A-10 PACKAGE SHELTER FOR 14-PK-103 B1A-10-ARCH B1A-10 Architecture
Area B B1A-10 PACKAGE SHELTER FOR 14-PK-103 B1A-10-IF&G FIRE&GAS SYSTEM
Area B B1A-11 PACKAGE SHELTER FOR 14-PK-105 B1A-11-ARCH B1A-11 Architecture
Area B B1A-11 PACKAGE SHELTER FOR 14-PK-105 B1A-11-IF&G FIRE&GAS SYSTEM
Area B B1B-01 PIBs/SS B1B-01-ARCH B1B-01 Architecture
Area B B1B-01 PIBs/SS B1B-01-EEDG Emergency Diesel Generator
Area B B1B-01 PIBs/SS B1B-01-EF&A Fire Alram system
Area B B1B-01 PIBs/SS B1B-01-EGLT Grounding & Lightning
Area B B1B-01 PIBs/SS B1B-01-EILS Indoor Lighting System
Area B B1B-01 PIBs/SS B1B-01-ELEQ Electrical Equipment
Area B B1B-01 PIBs/SS B1B-01-EPST Power System
Area B B1B-01 PIBs/SS B1B-01-EUPS UPS
Area B B1B-01 PIBs/SS B1B-01-HVCT B1B-01 for HVAC Control System
Area B B1B-01 PIBs/SS B1B-01-HVEQ B1B-01 for HVAC Equipment
Area B B1B-01 PIBs/SS B1B-01-HVFF B1B-01 for HVAC FM200
Area B B1B-01 PIBs/SS B1B-01-HVPL B1B-01 for HVAC Plumbing
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area B B1B-01 PIBs/SS B1B-01-IF&G FIRE&GAS SYSTEM
Area B B1B-01 PIBs/SS B1B-01-IPCS PROCESS CONTROL SYSTEM
Area B B1B-01 PIBs/SS B1B-01-TELE Telecomm. System
Area B B1B-02 COMPRESSOR SHELTER B1B-02-ARCH B1B-02 Architecture
Area B B1B-02 COMPRESSOR SHELTER B1B-02-IF&G FIRE&GAS SYSTEM
Area B B1B-03 COMPRESSOR SHELTER B1B-03-ARCH B1B-03 Architecture
Area B B1B-03 COMPRESSOR SHELTER B1B-03-IF&G FIRE&GAS SYSTEM
Area B B1B-04 COMPRESSOR SHELTER B1B-04-ARCH B1B-04 Architecture
Area B B1B-04 COMPRESSOR SHELTER B1B-04-IF&G FIRE&GAS SYSTEM
Area B B1B-12 PACKAGE SHELTER FOR 02-PK-001 B1B-12-ARCH B1B-12 Architecture
Area B B1B-12 PACKAGE SHELTER FOR 02-PK-001 B1B-12-IF&G FIRE&GAS SYSTEM
Area B B1B-13 PACKAGE SHELTER FOR 03-PK-001 B1B-13-ARCH B1B-13 Architecture
Area B B1B-13 PACKAGE SHELTER FOR 03-PK-001 B1B-13-IF&G FIRE&GAS SYSTEM
Area B B1B-14 PACKAGE SHELTER FOR 04-PK-201,04-PK-101,04-PK-102 B1B-14-ARCH B1B-14 Architecture
Area B B1B-14 PACKAGE SHELTER FOR 04-PK-201,04-PK-101,04-PK-102 B1B-14-IF&G FIRE&GAS SYSTEM
Area B B1B-17 PACKAGE SHELTER FOR 02-TK-001 B1B-17-ARCH B1B-17 Architecture
Area B B1B-17 PACKAGE SHELTER FOR 02-TK-001 B1B-17-IF&G FIRE&GAS SYSTEM
Area B B1C-01 PIBs/SS B1C-01-ARCH B1C-01 Architecture
Area B B1C-01 PIBs/SS B1C-01-EEDG Emergency Diesel Generator
Area B B1C-01 PIBs/SS B1C-01-EF&A Fire Alram system
Area B B1C-01 PIBs/SS B1C-01-EGLT Grounding & Lightning
Area B B1C-01 PIBs/SS B1C-01-EILS Indoor Lighting System
Area B B1C-01 PIBs/SS B1C-01-ELEQ Electrical Equipment
Area B B1C-01 PIBs/SS B1C-01-EPST Power System
Area B B1C-01 PIBs/SS B1C-01-EUPS UPS
Area B B1C-01 PIBs/SS B1C-01-HVCT B1C-01 for HVAC Control System
Area B B1C-01 PIBs/SS B1C-01-HVEQ B1C-01 for HVAC Equipment
Area B B1C-01 PIBs/SS B1C-01-HVFF B1C-01 for HVAC FM200
Area B B1C-01 PIBs/SS B1C-01-HVPL B1C-01 for HVAC Plumbing
Area B B1C-01 PIBs/SS B1C-01-IF&G FIRE&GAS SYSTEM
Area B B1C-01 PIBs/SS B1C-01-IPCS PROCESS CONTROL SYSTEM
Area B B1C-01 PIBs/SS B1C-01-TELE Telecomm. System
Area B B1C-02 COMPRESSOR SHELTER B1C-02-ARCH B1C-02 Architecture
Area B B1C-02 COMPRESSOR SHELTER B1C-02-IF&G FIRE&GAS SYSTEM
Area A B1D-01 PIBs/SS B1D-01-ARCH B1D-01 Architecture
Area A B1D-01 PIBs/SS B1D-01-EEDG Emergency Diesel Generator
Area A B1D-01 PIBs/SS B1D-01-EF&A Fire Alram system
Area A B1D-01 PIBs/SS B1D-01-EGLT Grounding & Lightning
Area A B1D-01 PIBs/SS B1D-01-EILS Indoor Lighting System
Area A B1D-01 PIBs/SS B1D-01-ELEQ Electrical Equipment
Area A B1D-01 PIBs/SS B1D-01-EPST Power System
Area A B1D-01 PIBs/SS B1D-01-EUPS UPS
Area A B1D-01 PIBs/SS B1D-01-HVCT B1D-01 for HVAC Control System
Area A B1D-01 PIBs/SS B1D-01-HVEQ B1D-01 for HVAC Equipment
Area A B1D-01 PIBs/SS B1D-01-HVFF B1D-01 for HVAC FM200
Area A B1D-01 PIBs/SS B1D-01-HVPL B1D-01 for HVAC Plumbing
Area A B1D-01 PIBs/SS B1D-01-IF&G FIRE&GAS SYSTEM
Area A B1D-01 PIBs/SS B1D-01-IPCS PROCESS CONTROL SYSTEM
Area A B1D-01 PIBs/SS B1D-01-TELE Telecomm. System
Area A B1D-02 Compressor Shelter B1D-02-ARCH B1D-02 Architecture
Area A B1D-02 Compressor Shelter B1D-02-IF&G FIRE&GAS SYSTEM
Area A B1D-03 Chemical Injection Package Shelter B1D-03-ARCH B1D-03 Architecture
Area A B1D-03 Chemical Injection Package Shelter B1D-03-IF&G FIRE&GAS SYSTEM
Area A B1D-04 Chemical Injection Package Shelter B1D-04-ARCH B1D-04 Architecture
Area A B1D-04 Chemical Injection Package Shelter B1D-04-IF&G FIRE&GAS SYSTEM
Area A B1D-05 Compressor Shelter B1D-05-ARCH B1D-05 Architecture
Area A B1D-05 Compressor Shelter B1D-05-IF&G FIRE&GAS SYSTEM
Area A B1D-06 Chemical Injection Package Shelter B1D-06-ARCH B1D-06 Architecture
Area A B1D-06 Chemical Injection Package Shelter B1D-06-IF&G FIRE&GAS SYSTEM
Area C B1E-01 PIBs/SS B1E-01-ARCH B1E-01 Architecture
Area C B1E-01 PIBs/SS B1E-01-EEDG Emergency Diesel Generator
Area C B1E-01 PIBs/SS B1E-01-EF&A Fire Alram system
Area C B1E-01 PIBs/SS B1E-01-EGLT Grounding & Lightning
Area C B1E-01 PIBs/SS B1E-01-EILS Indoor Lighting System
Area C B1E-01 PIBs/SS B1E-01-ELEQ Electrical Equipment
Area C B1E-01 PIBs/SS B1E-01-EPST Power System
Area C B1E-01 PIBs/SS B1E-01-EUPS UPS
Area C B1E-01 PIBs/SS B1E-01-HVCT B1E-01 for HVAC Control System
Area C B1E-01 PIBs/SS B1E-01-HVEQ B1E-01 for HVAC Equipment
Area C B1E-01 PIBs/SS B1E-01-HVFF B1E-01 for HVAC FM200
Area C B1E-01 PIBs/SS B1E-01-HVPL B1E-01 for HVAC Plumbing
Area C B1E-01 PIBs/SS B1E-01-IF&G FIRE&GAS SYSTEM
Area C B1E-01 PIBs/SS B1E-01-IPCS PROCESS CONTROL SYSTEM
Area C B1E-01 PIBs/SS B1E-01-TELE Telecomm. System
Area C B1E-02 Chemical Injection Package Shelter B1E-02-ARCH B1E-02 Architecture
Area C B1E-02 Chemical Injection Package Shelter B1E-02-EGLT Grounding & Lightning
Area C B1E-02 Chemical Injection Package Shelter B1E-02-EILS Indoor Lighting System
Area C B1E-02 Chemical Injection Package Shelter B1E-02-EPST Power System
Area C B1E-02 Chemical Injection Package Shelter B1E-02-IF&G FIRE&GAS SYSTEM
Area C B1E-03 Compressor Shelter B1E-03-ARCH B1E-03 Architecture
Area C B1E-03 Compressor Shelter B1E-03-EGLT Grounding & Lightning
Area C B1E-03 Compressor Shelter B1E-03-EILS Indoor Lighting System
Area C B1E-03 Compressor Shelter B1E-03-EPST Power System
Area C B1E-03 Compressor Shelter B1E-03-IF&G FIRE&GAS SYSTEM
Area C B1F-01 PIBs/SS B1F-01-ARCH B1F-01 Architecture
Area C B1F-01 PIBs/SS B1F-01-EEDG Emergency Diesel Generator
Area C B1F-01 PIBs/SS B1F-01-EF&A Fire Alram system
Area C B1F-01 PIBs/SS B1F-01-EGLT Grounding & Lightning
Area C B1F-01 PIBs/SS B1F-01-EILS Indoor Lighting System
Area C B1F-01 PIBs/SS B1F-01-ELEQ Electrical Equipment
Area C B1F-01 PIBs/SS B1F-01-EPST Power System
Area C B1F-01 PIBs/SS B1F-01-EUPS UPS
Area C B1F-01 PIBs/SS B1F-01-HVCT B1F-01 for HVAC Control System
Area C B1F-01 PIBs/SS B1F-01-HVEQ B1F-01 for HVAC Equipment
Area C B1F-01 PIBs/SS B1F-01-HVFF B1F-01 for HVAC FM200
Area C B1F-01 PIBs/SS B1F-01-HVPL B1F-01 for HVAC Plumbing
Area C B1F-01 PIBs/SS B1F-01-IF&G FIRE&GAS SYSTEM
Area C B1F-01 PIBs/SS B1F-01-IPCS PROCESS CONTROL SYSTEM
Area C B1F-01 PIBs/SS B1F-01-TELE Telecomm. System
Area C B1F-02 MEA Shelter B1F-02-ARCH B1F-02 Architecture
Area C B1F-02 MEA Shelter B1F-02-EGLT Grounding & Lightning
Area C B1F-02 MEA Shelter B1F-02-EILS Indoor Lighting System
Area C B1F-02 MEA Shelter B1F-02-EPST Power System
Area C B1F-02 MEA Shelter B1F-02-IF&G FIRE&GAS SYSTEM
Area C B1F-03 Compressor Shelter B1F-03-ARCH B1F-03 Architecture
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area C B1F-03 Compressor Shelter B1F-03-EGLT Grounding & Lightning
Area C B1F-03 Compressor Shelter B1F-03-EILS Indoor Lighting System
Area C B1F-03 Compressor Shelter B1F-03-EPST Power System
Area C B1F-03 Compressor Shelter B1F-03-IF&G FIRE&GAS SYSTEM
Area C B1F-04 COMPRESSOR SHELTER B1F-04-ARCH B1F-04 Architecture
Area C B1F-04 COMPRESSOR SHELTER B1F-04-EGLT Grounding & Lightning
Area C B1F-04 COMPRESSOR SHELTER B1F-04-EILS Indoor Lighting System
Area C B1F-04 COMPRESSOR SHELTER B1F-04-EPST Power System
Area C B1F-04 COMPRESSOR SHELTER B1F-04-IF&G FIRE&GAS SYSTEM
Area C B1F-05 Chemical Injection Package Shelter B1F-05-ARCH B1F-05 Architecture
Area C B1F-05 Chemical Injection Package Shelter B1F-05-EGLT Grounding & Lightning
Area C B1F-05 Chemical Injection Package Shelter B1F-05-EILS Indoor Lighting System
Area C B1F-05 Chemical Injection Package Shelter B1F-05-EPST Power System
Area C B1F-05 Chemical Injection Package Shelter B1F-05-IF&G FIRE&GAS SYSTEM
Area C B1G-01 PIBs/SS B1G-01-ARCH B1G-01 Architecture
Area C B1G-01 PIBs/SS B1G-01-EEDG Emergency Diesel Generator
Area C B1G-01 PIBs/SS B1G-01-EF&A Fire Alram system
Area C B1G-01 PIBs/SS B1G-01-EGLT Grounding & Lightning
Area C B1G-01 PIBs/SS B1G-01-EILS Indoor Lighting System
Area C B1G-01 PIBs/SS B1G-01-ELEQ Electrical Equipment
Area C B1G-01 PIBs/SS B1G-01-EPST Power System
Area C B1G-01 PIBs/SS B1G-01-EUPS UPS
Area C B1G-01 PIBs/SS B1G-01-HVCT B1G-01 for HVAC Control System
Area C B1G-01 PIBs/SS B1G-01-HVEQ B1G-01 for HVAC Equipment
Area C B1G-01 PIBs/SS B1G-01-HVFF B1G-01 for HVAC FM200
Area C B1G-01 PIBs/SS B1G-01-HVPL B1G-01 for HVAC Plumbing
Area C B1G-01 PIBs/SS B1G-01-IF&G FIRE&GAS SYSTEM
Area C B1G-01 PIBs/SS B1G-01-IPCS PROCESS CONTROL SYSTEM
Area C B1G-01 PIBs/SS B1G-01-TELE Telecomm. System
Area C B1G-02 Compressor Shelter B1G-02-ARCH B1G-02 Architecture
Area C B1G-02 Compressor Shelter B1G-02-EGLT Grounding & Lightning
Area C B1G-02 Compressor Shelter B1G-02-EILS Indoor Lighting System
Area C B1G-02 Compressor Shelter B1G-02-EPST Power System
Area C B1G-02 Compressor Shelter B1G-02-IF&G FIRE&GAS SYSTEM
Area C B1G-03 Chemical Injection Package Shelter B1G-03-ARCH B1G-03 Architecture
Area C B1G-03 Chemical Injection Package Shelter B1G-03-EGLT Grounding & Lightning
Area C B1G-03 Chemical Injection Package Shelter B1G-03-EILS Indoor Lighting System
Area C B1G-03 Chemical Injection Package Shelter B1G-03-EPST Power System
Area C B1G-03 Chemical Injection Package Shelter B1G-03-IF&G FIRE&GAS SYSTEM
Area C B1G-04 Chemical Injection Package Shelter B1G-04-ARCH B1G-04 Architecture
Area C B1G-04 Chemical Injection Package Shelter B1G-04-EGLT Grounding & Lightning
Area C B1G-04 Chemical Injection Package Shelter B1G-04-EILS Indoor Lighting System
Area C B1G-04 Chemical Injection Package Shelter B1G-04-EPST Power System
Area C B1G-04 Chemical Injection Package Shelter B1G-04-IF&G FIRE&GAS SYSTEM
Area C B1H-01 PIBs/SS B1H-01-ARCH B1H-01 Architecture
Area C B1H-01 PIBs/SS B1H-01-EEDG Emergency Diesel Generator
Area C B1H-01 PIBs/SS B1H-01-EF&A Fire Alram system
Area C B1H-01 PIBs/SS B1H-01-EGLT Grounding & Lightning
Area C B1H-01 PIBs/SS B1H-01-EILS Indoor Lighting System
Area C B1H-01 PIBs/SS B1H-01-ELEQ Electrical Equipment
Area C B1H-01 PIBs/SS B1H-01-EPST Power System
Area C B1H-01 PIBs/SS B1H-01-EUPS UPS
Area C B1H-01 PIBs/SS B1H-01-HVCT B1H-01 for HVAC Control System
Area C B1H-01 PIBs/SS B1H-01-HVEQ B1H-01 for HVAC Equipment
Area C B1H-01 PIBs/SS B1H-01-HVFF B1H-01 for HVAC FM200
Area C B1H-01 PIBs/SS B1H-01-HVPL B1H-01 for HVAC Plumbing
Area C B1H-01 PIBs/SS B1H-01-IF&G FIRE&GAS SYSTEM
Area C B1H-01 PIBs/SS B1H-01-IPCS PROCESS CONTROL SYSTEM
Area C B1H-01 PIBs/SS B1H-01-TELE Telecomm. System
Area C B1H-03 Chemical Injection Package Shelter B1H-03-ARCH B1H-03 Architecture
Area C B1H-03 Chemical Injection Package Shelter B1H-03-EGLT Grounding & Lightning
Area C B1H-03 Chemical Injection Package Shelter B1H-03-EILS Indoor Lighting System
Area C B1H-03 Chemical Injection Package Shelter B1H-03-EPST Power System
Area C B1H-03 Chemical Injection Package Shelter B1H-03-IF&G FIRE&GAS SYSTEM
Area C B1H-04 Chemical Injection Package Shelter B1H-04-ARCH B1H-04 Architecture
Area C B1H-04 Chemical Injection Package Shelter B1H-04-EGLT Grounding & Lightning
Area C B1H-04 Chemical Injection Package Shelter B1H-04-EILS Indoor Lighting System
Area C B1H-04 Chemical Injection Package Shelter B1H-04-EPST Power System
Area C B1H-04 Chemical Injection Package Shelter B1H-04-IF&G FIRE&GAS SYSTEM
Area C B1H-05 Chemical Injection Package Shelter B1H-05-ARCH B1H-05 Architecture
Area C B1H-05 Chemical Injection Package Shelter B1H-05-EGLT Grounding & Lightning
Area C B1H-05 Chemical Injection Package Shelter B1H-05-EILS Indoor Lighting System
Area C B1H-05 Chemical Injection Package Shelter B1H-05-EPST Power System
Area C B1H-05 Chemical Injection Package Shelter B1H-05-IF&G FIRE&GAS SYSTEM
Area C B1I-01 PIBs/SS B1I-01-ARCH B1I-01 Architecture
Area C B1I-01 PIBs/SS B1I-01-EEDG Emergency Diesel Generator
Area C B1I-01 PIBs/SS B1I-01-EF&A Fire Alram system
Area C B1I-01 PIBs/SS B1I-01-EGLT Grounding & Lightning
Area C B1I-01 PIBs/SS B1I-01-EILS Indoor Lighting System
Area C B1I-01 PIBs/SS B1I-01-ELEQ Electrical Equipment
Area C B1I-01 PIBs/SS B1I-01-EPST Power System
Area C B1I-01 PIBs/SS B1I-01-EUPS UPS
Area C B1I-01 PIBs/SS B1I-01-HVCT B1I-01 for HVAC Control System
Area C B1I-01 PIBs/SS B1I-01-HVEQ B1I-01 for HVAC Equipment
Area C B1I-01 PIBs/SS B1I-01-HVFF B1I-01 for HVAC FM200
Area C B1I-01 PIBs/SS B1I-01-HVPL B1I-01 for HVAC Plumbing
Area C B1I-01 PIBs/SS B1I-01-IF&G FIRE&GAS SYSTEM
Area C B1I-01 PIBs/SS B1I-01-IPCS PROCESS CONTROL SYSTEM
Area C B1I-01 PIBs/SS B1I-01-TELE Telecomm. System
Area C B1I-02 Compressor Shelter B1I-02-ARCH B1I-02 Architecture
Area C B1I-02 Compressor Shelter B1I-02-EGLT Grounding & Lightning
Area C B1I-02 Compressor Shelter B1I-02-EILS Indoor Lighting System
Area C B1I-02 Compressor Shelter B1I-02-EPST Power System
Area C B1I-02 Compressor Shelter B1I-02-IF&G FIRE&GAS SYSTEM
Area C B1I-03 Chemical Injection Package Shelter B1I-03-ARCH B1I-03 Architecture
Area C B1I-03 Chemical Injection Package Shelter B1I-03-EGLT Grounding & Lightning
Area C B1I-03 Chemical Injection Package Shelter B1I-03-EILS Indoor Lighting System
Area C B1I-03 Chemical Injection Package Shelter B1I-03-EPST Power System
Area C B1I-03 Chemical Injection Package Shelter B1I-03-IF&G FIRE&GAS SYSTEM
Area B B2A-01 ADMINISTRATION BUILDING B2A-01-ARCH B2A-01 Architecture
Area B B2A-01 ADMINISTRATION BUILDING B2A-01-EF&A Fire Alram system
Area B B2A-01 ADMINISTRATION BUILDING B2A-01-EGLT Grounding & Lightning
Area B B2A-01 ADMINISTRATION BUILDING B2A-01-EILS Indoor Lighting System
Area B B2A-01 ADMINISTRATION BUILDING B2A-01-ELEQ Electrical Equipment
Area B B2A-01 ADMINISTRATION BUILDING B2A-01-EPST Power System
Area B B2A-01 ADMINISTRATION BUILDING B2A-01-HVCT B2A-01 for HVAC Control System
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area B B2A-01 ADMINISTRATION BUILDING B2A-01-HVEQ B2A-01 for HVAC Equipment
Area B B2A-01 ADMINISTRATION BUILDING B2A-01-HVPL B2A-01 for HVAC Plumbing
Area B B2A-01 ADMINISTRATION BUILDING B2A-01-IF&G FIRE&GAS SYSTEM
Area B B2A-01 ADMINISTRATION BUILDING B2A-01-TELE Telecomm. System
Area B B2A-02 CANTEEN B2A-02-ARCH B2A-02 Architecture
Area B B2A-02 CANTEEN B2A-02-EF&A Fire Alram system
Area B B2A-02 CANTEEN B2A-02-EGLT Grounding & Lightning
Area B B2A-02 CANTEEN B2A-02-EILS Indoor Lighting System
Area B B2A-02 CANTEEN B2A-02-ELEQ Electrical Equipment
Area B B2A-02 CANTEEN B2A-02-EPST Power System
Area B B2A-02 CANTEEN B2A-02-HVEQ B2A-02 for HVAC Equipment
Area B B2A-02 CANTEEN B2A-02-HVPL B2A-02 for HVAC Plumbing
Area B B2A-02 CANTEEN B2A-02-IF&G FIRE&GAS SYSTEM
Area B B2A-02 CANTEEN B2A-02-TELE Telecomm. System
Area B B2A-03 SUBSTATION B2A-03-ARCH B2A-03 Architecture
Area B B2A-03 SUBSTATION B2A-03-EF&A Fire Alram system
Area B B2A-03 SUBSTATION B2A-03-EGLT Grounding & Lightning
Area B B2A-03 SUBSTATION B2A-03-EILS Indoor Lighting System
Area B B2A-03 SUBSTATION B2A-03-ELEQ Electrical Equipment
Area B B2A-03 SUBSTATION B2A-03-EPST Power System
Area B B2A-03 SUBSTATION B2A-03-EUPS UPS
Area B B2A-03 SUBSTATION B2A-03-HVCT B2A-03 for HVAC Control System
Area B B2A-03 SUBSTATION B2A-03-HVEQ B2A-03 for HVAC Equipment
Area B B2A-03 SUBSTATION B2A-03-HVFF B2A-03 for HVAC FM200
Area B B2A-03 SUBSTATION B2A-03-HVPL B2A-03 for HVAC Plumbing
Area B B2A-03 SUBSTATION B2A-03-IF&G FIRE&GAS SYSTEM
Area B B2A-03 SUBSTATION B2A-03-TELE Telecomm. System
Area B B2A-04 MEDICAL AND TRAINING BUILDING B2A-04-ARCH B2A-04 Architecture
Area B B2A-04 MEDICAL AND TRAINING BUILDING B2A-04-EF&A Fire Alram system
Area B B2A-04 MEDICAL AND TRAINING BUILDING B2A-04-EGLT Grounding & Lightning
Area B B2A-04 MEDICAL AND TRAINING BUILDING B2A-04-EILS Indoor Lighting System
Area B B2A-04 MEDICAL AND TRAINING BUILDING B2A-04-ELEQ Electrical Equipment
Area B B2A-04 MEDICAL AND TRAINING BUILDING B2A-04-EPST Power System
Area B B2A-04 MEDICAL AND TRAINING BUILDING B2A-04-HVCT B2A-04 for HVAC Control System
Area B B2A-04 MEDICAL AND TRAINING BUILDING B2A-04-HVEQ B2A-04 for HVAC Equipment
Area B B2A-04 MEDICAL AND TRAINING BUILDING B2A-04-HVPL B2A-04 for HVAC Plumbing
Area B B2A-04 MEDICAL AND TRAINING BUILDING B2A-04-IF&G FIRE&GAS SYSTEM
Area B B2A-04 MEDICAL AND TRAINING BUILDING B2A-04-TELE Telecomm. System
Area B B2A-05 FIRE-FIGHTING BUILDING B2A-05-ARCH B2A-05 Architecture
Area B B2A-05 FIRE-FIGHTING BUILDING B2A-05-EF&A Fire Alram system
Area B B2A-05 FIRE-FIGHTING BUILDING B2A-05-EGLT Grounding & Lightning
Area B B2A-05 FIRE-FIGHTING BUILDING B2A-05-EILS Indoor Lighting System
Area B B2A-05 FIRE-FIGHTING BUILDING B2A-05-ELEQ Electrical Equipment
Area B B2A-05 FIRE-FIGHTING BUILDING B2A-05-EPST Power System
Area B B2A-05 FIRE-FIGHTING BUILDING B2A-05-HVCT B2A-05 for HVAC Control System
Area B B2A-05 FIRE-FIGHTING BUILDING B2A-05-HVEQ B2A-05 for HVAC Equipment
Area B B2A-05 FIRE-FIGHTING BUILDING B2A-05-HVPL B2A-05 for HVAC Plumbing
Area B B2A-05 FIRE-FIGHTING BUILDING B2A-05-IF&G FIRE&GAS SYSTEM
Area B B2A-05 FIRE-FIGHTING BUILDING B2A-05-IPCS PROCESS CONTROL SYSTEM
Area B B2A-05 FIRE-FIGHTING BUILDING B2A-05-TELE Telecomm. System
Area B B2A-06 MAINTENANCE MECHANICAL WORKSHOP B2A-06-ARCH B2A-06 Architecture
Area B B2A-06 MAINTENANCE MECHANICAL WORKSHOP B2A-06-EF&A Fire Alram system
Area B B2A-06 MAINTENANCE MECHANICAL WORKSHOP B2A-06-EGLT Grounding & Lightning
Area B B2A-06 MAINTENANCE MECHANICAL WORKSHOP B2A-06-EILS Indoor Lighting System
Area B B2A-06 MAINTENANCE MECHANICAL WORKSHOP B2A-06-ELEQ Electrical Equipment
Area B B2A-06 MAINTENANCE MECHANICAL WORKSHOP B2A-06-EPST Power System
Area B B2A-06 MAINTENANCE MECHANICAL WORKSHOP B2A-06-HVCT B2A-06 for HVAC Control System
Area B B2A-06 MAINTENANCE MECHANICAL WORKSHOP B2A-06-HVEQ B2A-06 for HVAC Equipment
Area B B2A-06 MAINTENANCE MECHANICAL WORKSHOP B2A-06-HVPL B2A-06 for HVAC Plumbing
Area B B2A-06 MAINTENANCE MECHANICAL WORKSHOP B2A-06-IF&G FIRE&GAS SYSTEM
Area B B2A-06 MAINTENANCE MECHANICAL WORKSHOP B2A-06-TELE Telecomm. System
Area B B2A-07 MAINTENANCE ELECTR./INSTR. WORKSHOP B2A-07-ARCH B2A-07 Architecture
Area B B2A-07 MAINTENANCE ELECTR./INSTR. WORKSHOP B2A-07-EF&A Fire Alram system
Area B B2A-07 MAINTENANCE ELECTR./INSTR. WORKSHOP B2A-07-EGLT Grounding & Lightning
Area B B2A-07 MAINTENANCE ELECTR./INSTR. WORKSHOP B2A-07-EILS Indoor Lighting System
Area B B2A-07 MAINTENANCE ELECTR./INSTR. WORKSHOP B2A-07-ELEQ Electrical Equipment
Area B B2A-07 MAINTENANCE ELECTR./INSTR. WORKSHOP B2A-07-EPST Power System
Area B B2A-07 MAINTENANCE ELECTR./INSTR. WORKSHOP B2A-07-HVCT B2A-07 for HVAC Control System
Area B B2A-07 MAINTENANCE ELECTR./INSTR. WORKSHOP B2A-07-HVEQ B2A-07 for HVAC Equipment
Area B B2A-07 MAINTENANCE ELECTR./INSTR. WORKSHOP B2A-07-HVPL B2A-07 for HVAC Plumbing
Area B B2A-07 MAINTENANCE ELECTR./INSTR. WORKSHOP B2A-07-IF&G FIRE&GAS SYSTEM
Area B B2A-07 MAINTENANCE ELECTR./INSTR. WORKSHOP B2A-07-TELE Telecomm. System
Area B B2A-08 MATERIAL STORAGE BUILDING B2A-08-ARCH B2A-08 Architecture
Area B B2A-08 MATERIAL STORAGE BUILDING B2A-08-EF&A Fire Alram system
Area B B2A-08 MATERIAL STORAGE BUILDING B2A-08-EGLT Grounding & Lightning
Area B B2A-08 MATERIAL STORAGE BUILDING B2A-08-EILS Indoor Lighting System
Area B B2A-08 MATERIAL STORAGE BUILDING B2A-08-ELEQ Electrical Equipment
Area B B2A-08 MATERIAL STORAGE BUILDING B2A-08-EPST Power System
Area B B2A-08 MATERIAL STORAGE BUILDING B2A-08-HVCT B2A-08 for HVAC Control System
Area B B2A-08 MATERIAL STORAGE BUILDING B2A-08-HVEQ B2A-08 for HVAC Equipment
Area B B2A-08 MATERIAL STORAGE BUILDING B2A-08-HVPL B2A-08 for HVAC Plumbing
Area B B2A-08 MATERIAL STORAGE BUILDING B2A-08-IF&G FIRE&GAS SYSTEM
Area B B2A-08 MATERIAL STORAGE BUILDING B2A-08-TELE Telecomm. System
Area B B2A-09 CHEMICAL STORAGE BUILDING B2A-09-ARCH B2A-09 Architecture
Area B B2A-09 CHEMICAL STORAGE BUILDING B2A-09-EF&A Fire Alram system
Area B B2A-09 CHEMICAL STORAGE BUILDING B2A-09-EGLT Grounding & Lightning
Area B B2A-09 CHEMICAL STORAGE BUILDING B2A-09-EILS Indoor Lighting System
Area B B2A-09 CHEMICAL STORAGE BUILDING B2A-09-ELEQ Electrical Equipment
Area B B2A-09 CHEMICAL STORAGE BUILDING B2A-09-EPST Power System
Area B B2A-09 CHEMICAL STORAGE BUILDING B2A-09-HVCT B2A-09 for HVAC Control System
Area B B2A-09 CHEMICAL STORAGE BUILDING B2A-09-HVEQ B2A-09 for HVAC Equipment
Area B B2A-09 CHEMICAL STORAGE BUILDING B2A-09-HVPL B2A-09 for HVAC Plumbing
Area B B2A-09 CHEMICAL STORAGE BUILDING B2A-09-IF&G FIRE&GAS SYSTEM
Area B B2A-09 CHEMICAL STORAGE BUILDING B2A-09-TELE Telecomm. System
Area B B2A-10 MAIN GATE HOUSE B2A-10-ARCH B2A-10 Architecture
Area B B2A-10 MAIN GATE HOUSE B2A-10-EF&A Fire Alram system
Area B B2A-10 MAIN GATE HOUSE B2A-10-EGLT Grounding & Lightning
Area B B2A-10 MAIN GATE HOUSE B2A-10-EILS Indoor Lighting System
Area B B2A-10 MAIN GATE HOUSE B2A-10-ELEQ Electrical Equipment
Area B B2A-10 MAIN GATE HOUSE B2A-10-EPST Power System
Area B B2A-10 MAIN GATE HOUSE B2A-10-HVEQ B2A-10 for HVAC Equipment
Area B B2A-10 MAIN GATE HOUSE B2A-10-HVPL B2A-10 for HVAC Plumbing
Area B B2A-10 MAIN GATE HOUSE B2A-10-IF&G FIRE&GAS SYSTEM
Area B B2A-10 MAIN GATE HOUSE B2A-10-TELE Telecomm. System
Area B B2A-11 MOSQUE B2A-11-ARCH B2A-11 Architecture
Area B B2A-11 MOSQUE B2A-11-EF&A Fire Alram system
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area B B2A-11 MOSQUE B2A-11-EGLT Grounding & Lightning
Area B B2A-11 MOSQUE B2A-11-EILS Indoor Lighting System
Area B B2A-11 MOSQUE B2A-11-ELEQ Electrical Equipment
Area B B2A-11 MOSQUE B2A-11-EPST Power System
Area B B2A-11 MOSQUE B2A-11-HVCT B2A-11 for HVAC Control System
Area B B2A-11 MOSQUE B2A-11-HVEQ B2A-11 for HVAC Equipment
Area B B2A-11 MOSQUE B2A-11-HVPL B2A-11 for HVAC Plumbing
Area B B2A-11 MOSQUE B2A-11-IF&G FIRE&GAS SYSTEM
Area B B2A-11 MOSQUE B2A-11-TELE Telecomm. System
Area B B2A-12 LOCKER BUILDING B2A-12-ARCH B2A-12 Architecture
Area B B2A-12 LOCKER BUILDING B2A-12-EF&A Fire Alram system
Area B B2A-12 LOCKER BUILDING B2A-12-EGLT Grounding & Lightning
Area B B2A-12 LOCKER BUILDING B2A-12-EILS Indoor Lighting System
Area B B2A-12 LOCKER BUILDING B2A-12-ELEQ Electrical Equipment
Area B B2A-12 LOCKER BUILDING B2A-12-EPST Power System
Area B B2A-12 LOCKER BUILDING B2A-12-HVCT B2A-12 for HVAC Control System
Area B B2A-12 LOCKER BUILDING B2A-12-HVEQ B2A-12 for HVAC Equipment
Area B B2A-12 LOCKER BUILDING B2A-12-HVPL B2A-12 for HVAC Plumbing
Area B B2A-12 LOCKER BUILDING B2A-12-IF&G FIRE&GAS SYSTEM
Area B B2A-12 LOCKER BUILDING B2A-12-TELE Telecomm. System
Area B B2A-13 SECURITY BUILDING B2A-13-ARCH B2A-13 Architecture
Area B B2A-13 SECURITY BUILDING B2A-13-EF&A Fire Alram system
Area B B2A-13 SECURITY BUILDING B2A-13-EGLT Grounding & Lightning
Area B B2A-13 SECURITY BUILDING B2A-13-EILS Indoor Lighting System
Area B B2A-13 SECURITY BUILDING B2A-13-ELEQ Electrical Equipment
Area B B2A-13 SECURITY BUILDING B2A-13-EPST Power System
Area B B2A-13 SECURITY BUILDING B2A-13-HVCT B2A-13 for HVAC Control System
Area B B2A-13 SECURITY BUILDING B2A-13-HVEQ B2A-13 for HVAC Equipment
Area B B2A-13 SECURITY BUILDING B2A-13-HVPL B2A-13 for HVAC Plumbing
Area B B2A-13 SECURITY BUILDING B2A-13-IF&G FIRE&GAS SYSTEM
Area B B2A-13 SECURITY BUILDING B2A-13-TELE Telecomm. System
Area B B2A-14 PUBLIC RELATION BUILDING B2A-14-ARCH B2A-14 Architecture
Area B B2A-14 PUBLIC RELATION BUILDING B2A-14-EF&A Fire Alram system
Area B B2A-14 PUBLIC RELATION BUILDING B2A-14-EGLT Grounding & Lightning
Area B B2A-14 PUBLIC RELATION BUILDING B2A-14-EILS Indoor Lighting System
Area B B2A-14 PUBLIC RELATION BUILDING B2A-14-ELEQ Electrical Equipment
Area B B2A-14 PUBLIC RELATION BUILDING B2A-14-EPST Power System
Area B B2A-14 PUBLIC RELATION BUILDING B2A-14-HVEQ B2A-14 for HVAC Equipment
Area B B2A-14 PUBLIC RELATION BUILDING B2A-14-HVPL B2A-14 for HVAC Plumbing
Area B B2A-14 PUBLIC RELATION BUILDING B2A-14-IF&G FIRE&GAS SYSTEM
Area B B2A-14 PUBLIC RELATION BUILDING B2A-14-TELE Telecomm. System
Area B B2A-15 SAFETY AND INSPECTION BUILDING B2A-15-ARCH B2A-15 Architecture
Area B B2A-15 SAFETY AND INSPECTION BUILDING B2A-15-EF&A Fire Alram system
Area B B2A-15 SAFETY AND INSPECTION BUILDING B2A-15-EGLT Grounding & Lightning
Area B B2A-15 SAFETY AND INSPECTION BUILDING B2A-15-EILS Indoor Lighting System
Area B B2A-15 SAFETY AND INSPECTION BUILDING B2A-15-ELEQ Electrical Equipment
Area B B2A-15 SAFETY AND INSPECTION BUILDING B2A-15-EPST Power System
Area B B2A-15 SAFETY AND INSPECTION BUILDING B2A-15-HVCT B2A-15 for HVAC Control System
Area B B2A-15 SAFETY AND INSPECTION BUILDING B2A-15-HVEQ B2A-15 for HVAC Equipment
Area B B2A-15 SAFETY AND INSPECTION BUILDING B2A-15-HVPL B2A-15 for HVAC Plumbing
Area B B2A-15 SAFETY AND INSPECTION BUILDING B2A-15-IF&G FIRE&GAS SYSTEM
Area B B2A-15 SAFETY AND INSPECTION BUILDING B2A-15-TELE Telecomm. System
Area B B2A-16 MAINTENANCE ADMINISTRATION BUILDING B2A-16-ARCH B2A-16 Architecture
Area B B2A-16 MAINTENANCE ADMINISTRATION BUILDING B2A-16-EF&A Fire Alram system
Area B B2A-16 MAINTENANCE ADMINISTRATION BUILDING B2A-16-EGLT Grounding & Lightning
Area B B2A-16 MAINTENANCE ADMINISTRATION BUILDING B2A-16-EILS Indoor Lighting System
Area B B2A-16 MAINTENANCE ADMINISTRATION BUILDING B2A-16-ELEQ Electrical Equipment
Area B B2A-16 MAINTENANCE ADMINISTRATION BUILDING B2A-16-EPST Power System
Area B B2A-16 MAINTENANCE ADMINISTRATION BUILDING B2A-16-HVCT B2A-16 for HVAC Control System
Area B B2A-16 MAINTENANCE ADMINISTRATION BUILDING B2A-16-HVEQ B2A-16 for HVAC Equipment
Area B B2A-16 MAINTENANCE ADMINISTRATION BUILDING B2A-16-HVPL B2A-16 for HVAC Plumbing
Area B B2A-16 MAINTENANCE ADMINISTRATION BUILDING B2A-16-IF&G FIRE&GAS SYSTEM
Area B B2A-16 MAINTENANCE ADMINISTRATION BUILDING B2A-16-TELE Telecomm. System
Area B B2A-17 PROCESS ADMINISTRATION BUILDING B2A-17-ARCH B2A-17 Architecture
Area B B2A-17 PROCESS ADMINISTRATION BUILDING B2A-17-EF&A Fire Alram system
Area B B2A-17 PROCESS ADMINISTRATION BUILDING B2A-17-EGLT Grounding & Lightning
Area B B2A-17 PROCESS ADMINISTRATION BUILDING B2A-17-EILS Indoor Lighting System
Area B B2A-17 PROCESS ADMINISTRATION BUILDING B2A-17-ELEQ Electrical Equipment
Area B B2A-17 PROCESS ADMINISTRATION BUILDING B2A-17-EPST Power System
Area B B2A-17 PROCESS ADMINISTRATION BUILDING B2A-17-HVCT B2A-17 for HVAC Control System
Area B B2A-17 PROCESS ADMINISTRATION BUILDING B2A-17-HVEQ B2A-17 for HVAC Equipment
Area B B2A-17 PROCESS ADMINISTRATION BUILDING B2A-17-HVPL B2A-17 for HVAC Plumbing
Area B B2A-17 PROCESS ADMINISTRATION BUILDING B2A-17-IF&G FIRE&GAS SYSTEM
Area B B2A-17 PROCESS ADMINISTRATION BUILDING B2A-17-TELE Telecomm. System
Area B B2A-18 UTILITY ADMINISTRATION BUILDING B2A-18-ARCH B2A-18 Architecture
Area B B2A-18 UTILITY ADMINISTRATION BUILDING B2A-18-EF&A Fire Alram system
Area B B2A-18 UTILITY ADMINISTRATION BUILDING B2A-18-EGLT Grounding & Lightning
Area B B2A-18 UTILITY ADMINISTRATION BUILDING B2A-18-EILS Indoor Lighting System
Area B B2A-18 UTILITY ADMINISTRATION BUILDING B2A-18-ELEQ Electrical Equipment
Area B B2A-18 UTILITY ADMINISTRATION BUILDING B2A-18-EPST Power System
Area B B2A-18 UTILITY ADMINISTRATION BUILDING B2A-18-HVCT B2A-18 for HVAC Control System
Area B B2A-18 UTILITY ADMINISTRATION BUILDING B2A-18-HVEQ B2A-18 for HVAC Equipment
Area B B2A-18 UTILITY ADMINISTRATION BUILDING B2A-18-HVPL B2A-18 for HVAC Plumbing
Area B B2A-18 UTILITY ADMINISTRATION BUILDING B2A-18-IF&G FIRE&GAS SYSTEM
Area B B2A-18 UTILITY ADMINISTRATION BUILDING B2A-18-TELE Telecomm. System
Area B B2A-19 CONSTRUCTION BUILDING B2A-19-ARCH B2A-19 Architecture
Area B B2A-19 CONSTRUCTION BUILDING B2A-19-EF&A Fire Alram system
Area B B2A-19 CONSTRUCTION BUILDING B2A-19-EGLT Grounding & Lightning
Area B B2A-19 CONSTRUCTION BUILDING B2A-19-EILS Indoor Lighting System
Area B B2A-19 CONSTRUCTION BUILDING B2A-19-ELEQ Electrical Equipment
Area B B2A-19 CONSTRUCTION BUILDING B2A-19-EPST Power System
Area B B2A-19 CONSTRUCTION BUILDING B2A-19-HVCT B2A-19 for HVAC Control System
Area B B2A-19 CONSTRUCTION BUILDING B2A-19-HVEQ B2A-19 for HVAC Equipment
Area B B2A-19 CONSTRUCTION BUILDING B2A-19-HVPL B2A-19 for HVAC Plumbing
Area B B2A-19 CONSTRUCTION BUILDING B2A-19-IF&G FIRE&GAS SYSTEM
Area B B2A-19 CONSTRUCTION BUILDING B2A-19-TELE Telecomm. System
Area B B2A-20 MAINTENANCE WORKSHOP B2A-20-ARCH B2A-20 Architecture
Area B B2A-20 MAINTENANCE WORKSHOP B2A-20-EF&A Fire Alram system
Area B B2A-20 MAINTENANCE WORKSHOP B2A-20-EGLT Grounding & Lightning
Area B B2A-20 MAINTENANCE WORKSHOP B2A-20-EILS Indoor Lighting System
Area B B2A-20 MAINTENANCE WORKSHOP B2A-20-ELEQ Electrical Equipment
Area B B2A-20 MAINTENANCE WORKSHOP B2A-20-EPST Power System
Area B B2A-20 MAINTENANCE WORKSHOP B2A-20-HVCT B2A-20 for HVAC Control System
Area B B2A-20 MAINTENANCE WORKSHOP B2A-20-HVEQ B2A-20 for HVAC Equipment
Area B B2A-20 MAINTENANCE WORKSHOP B2A-20-HVPL B2A-20 for HVAC Plumbing
Area B B2A-20 MAINTENANCE WORKSHOP B2A-20-IF&G FIRE&GAS SYSTEM
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area B B2A-20 MAINTENANCE WORKSHOP B2A-20-TELE Telecomm. System
Area B B2A-21 MAINTENANCE TOOLS STORE B2A-21-ARCH B2A-21 Architecture
Area B B2A-21 MAINTENANCE TOOLS STORE B2A-21-EF&A Fire Alram system
Area B B2A-21 MAINTENANCE TOOLS STORE B2A-21-EGLT Grounding & Lightning
Area B B2A-21 MAINTENANCE TOOLS STORE B2A-21-EILS Indoor Lighting System
Area B B2A-21 MAINTENANCE TOOLS STORE B2A-21-ELEQ Electrical Equipment
Area B B2A-21 MAINTENANCE TOOLS STORE B2A-21-EPST Power System
Area B B2A-21 MAINTENANCE TOOLS STORE B2A-21-HVCT B2A-21 for HVAC Control System
Area B B2A-21 MAINTENANCE TOOLS STORE B2A-21-HVEQ B2A-21 for HVAC Equipment
Area B B2A-21 MAINTENANCE TOOLS STORE B2A-21-HVPL B2A-21 for HVAC Plumbing
Area B B2A-21 MAINTENANCE TOOLS STORE B2A-21-IF&G FIRE&GAS SYSTEM
Area B B2A-21 MAINTENANCE TOOLS STORE B2A-21-TELE Telecomm. System
Area B B2A-22 HEAVY EQUIPMENT BUILDING B2A-22-ARCH B2A-22 Architecture
Area B B2A-22 HEAVY EQUIPMENT BUILDING B2A-22-EF&A Fire Alram system
Area B B2A-22 HEAVY EQUIPMENT BUILDING B2A-22-EGLT Grounding & Lightning
Area B B2A-22 HEAVY EQUIPMENT BUILDING B2A-22-EILS Indoor Lighting System
Area B B2A-22 HEAVY EQUIPMENT BUILDING B2A-22-ELEQ Electrical Equipment
Area B B2A-22 HEAVY EQUIPMENT BUILDING B2A-22-EPST Power System
Area B B2A-22 HEAVY EQUIPMENT BUILDING B2A-22-HVEQ B2A-22 for HVAC Equipment
Area B B2A-22 HEAVY EQUIPMENT BUILDING B2A-22-HVPL B2A-22 for HVAC Plumbing
Area B B2A-22 HEAVY EQUIPMENT BUILDING B2A-22-IF&G FIRE&GAS SYSTEM
Area B B2A-22 HEAVY EQUIPMENT BUILDING B2A-22-TELE Telecomm. System
Area B B2A-23 BADGE READER CONTROL SYSTEM BUILDING B2A-23-ARCH B2A-23 Architecture
Area B B2A-23 BADGE READER CONTROL SYSTEM BUILDING B2A-23-EF&A Fire Alram system
Area B B2A-23 BADGE READER CONTROL SYSTEM BUILDING B2A-23-EGLT Grounding & Lightning
Area B B2A-23 BADGE READER CONTROL SYSTEM BUILDING B2A-23-EILS Indoor Lighting System
Area B B2A-23 BADGE READER CONTROL SYSTEM BUILDING B2A-23-ELEQ Electrical Equipment
Area B B2A-23 BADGE READER CONTROL SYSTEM BUILDING B2A-23-EPST Power System
Area B B2A-23 BADGE READER CONTROL SYSTEM BUILDING B2A-23-HVEQ B2A-23 for HVAC Equipment
Area B B2A-23 BADGE READER CONTROL SYSTEM BUILDING B2A-23-HVPL B2A-23 for HVAC Plumbing
Area B B2A-23 BADGE READER CONTROL SYSTEM BUILDING B2A-23-IF&G FIRE&GAS SYSTEM
Area B B2A-23 BADGE READER CONTROL SYSTEM BUILDING B2A-23-TELE Telecomm. System
Area B B2A-24 OPEN SHED B2A-24-ARCH B2A-24 Architecture
Area B B2A-24 OPEN SHED B2A-24-EGLT Grounding & Lightning
Area B B2A-24 OPEN SHED B2A-24-EILS Indoor Lighting System
Area B B2A-24 OPEN SHED B2A-24-EPST Power System
Area B B2A-24 OPEN SHED B2A-24-IF&G FIRE&GAS SYSTEM
Area B B2A-25 WELDING AREA B2A-25-ARCH B2A-25 Architecture
Area B B2A-25 WELDING AREA B2A-25-IF&G FIRE&GAS SYSTEM
Area B B2A-26 FILLING STATION B2A-26-ARCH B2A-26 Architecture
Area B B2A-26 FILLING STATION B2A-26-EGLT Grounding & Lightning
Area B B2A-26 FILLING STATION B2A-26-EILS Indoor Lighting System
Area B B2A-26 FILLING STATION B2A-26-EPST Power System
Area B B2A-26 FILLING STATION B2A-26-HVEQ B2A-26 for HVAC Equipment
Area B B2A-26 FILLING STATION B2A-26-HVPL B2A-26 for HVAC Plumbing
Area B B2A-26 FILLING STATION B2A-26-IF&G FIRE&GAS SYSTEM
Area A B3A-01 Control Room Building B3A-01-ARCH B3A-01 Architecture
Area A B3A-01 Control Room Building B3A-01-EEDG Emergency Diesel Generator
Area A B3A-01 Control Room Building B3A-01-EF&A Fire Alram system
Area A B3A-01 Control Room Building B3A-01-EGLT Grounding & Lightning
Area A B3A-01 Control Room Building B3A-01-EILS Indoor Lighting System
Area A B3A-01 Control Room Building B3A-01-ELEQ Electrical Equipment
Area A B3A-01 Control Room Building B3A-01-EPST Power System
Area A B3A-01 Control Room Building B3A-01-EUPS UPS
Area A B3A-01 Control Room Building B3A-01-HVEQ B3A-01 for HVAC Equipment
Area A B3A-01 Control Room Building B3A-01-HVFF B3A-01 for HVAC FM200
Area A B3A-01 Control Room Building B3A-01-HVPL B3A-01 for HVAC Plumbing
Area A B3A-01 Control Room Building B3A-01-IF&G FIRE&GAS SYSTEM
Area A B3A-01 Control Room Building B3A-01-IPCS PROCESS CONTROL SYSTEM
Area A B3A-01 Control Room Building B3A-01-TELE Telecomm. System
Area A B3A-02 Lab. Building B3A-02-ARCH B3A-02 Architecture
Area A B3A-02 Lab. Building B3A-02-EF&A Fire Alram system
Area A B3A-02 Lab. Building B3A-02-EGLT Grounding & Lightning
Area A B3A-02 Lab. Building B3A-02-EILS Indoor Lighting System
Area A B3A-02 Lab. Building B3A-02-ELEQ Electrical Equipment
Area A B3A-02 Lab. Building B3A-02-EPST Power System
Area A B3A-02 Lab. Building B3A-02-HVEQ B3A-02 for HVAC Equipment
Area A B3A-02 Lab. Building B3A-02-HVPL B3A-02 for HVAC Plumbing
Area A B3A-02 Lab. Building B3A-02-IF&G FIRE&GAS SYSTEM
Area A B3A-02 Lab. Building B3A-02-TELE Telecomm. System
Area A B3A-03 PIBs/SS B3A-03-ARCH B3A-03 Architecture
Area A B3A-03 PIBs/SS B3A-03-EEDG Emergency Diesel Generator
Area A B3A-03 PIBs/SS B3A-03-EF&A Fire Alram system
Area A B3A-03 PIBs/SS B3A-03-EGLT Grounding & Lightning
Area A B3A-03 PIBs/SS B3A-03-EILS Indoor Lighting System
Area A B3A-03 PIBs/SS B3A-03-ELEQ Electrical Equipment
Area A B3A-03 PIBs/SS B3A-03-EPST Power System
Area A B3A-03 PIBs/SS B3A-03-EUPS UPS
Area A B3A-03 PIBs/SS B3A-03-HVEQ B3A-03 for HVAC Equipment
Area A B3A-03 PIBs/SS B3A-03-HVFF B3A-03 for HVAC FM200
Area A B3A-03 PIBs/SS B3A-03-HVPL B3A-03 for HVAC Plumbing
Area A B3A-03 PIBs/SS B3A-03-IF&G FIRE&GAS SYSTEM
Area A B3A-03 PIBs/SS B3A-03-IPCS PROCESS CONTROL SYSTEM
Area A B3A-03 PIBs/SS B3A-03-TELE Telecomm. System
Area A B3A-06 Fire Water Pump Station (P/S 16) B3A-06-ARCH B3A-06 Architecture
Area A B3A-06 Fire Water Pump Station (P/S 16) B3A-06-HVCT B3A-06 for HVAC Control System
Area A B3A-06 Fire Water Pump Station (P/S 16) B3A-06-HVEQ B3A-06 for HVAC Equipment
Area A B3A-06 Fire Water Pump Station (P/S 16) B3A-06-IF&G FIRE&GAS SYSTEM
Area A B3A-07 Air Compressor Shelter B3A-07-ARCH B3A-07 Architecture
Area A B3A-07 Air Compressor Shelter B3A-07-IF&G FIRE&GAS SYSTEM
Area A B3A-08 N2 Air Compressor Shelter B3A-08-ARCH B3A-08 Architecture
Area A B3A-08 N2 Air Compressor Shelter B3A-08-IF&G FIRE&GAS SYSTEM
Area A B3A-10 Filling Station B3A-10-ARCH B3A-10 Architecture
Area A B3A-10 Filling Station B3A-10-IF&G FIRE&GAS SYSTEM
Area A B3A-11 Caustic Soda Sun Shelter B3A-11-ARCH B3A-11 Architecture
Area A B3A-11 Caustic Soda Sun Shelter B3A-11-IF&G FIRE&GAS SYSTEM
Area A B3A-12 Chemical Inj. PKG Shelter-36 B3A-12-ARCH B3A-12 Architecture
Area A B3A-12 Chemical Inj. PKG Shelter-36 B3A-12-IF&G FIRE&GAS SYSTEM
Area A B3B-01 Main Substation B3B-01-ARCH B3B-01 Architecture
Area A B3B-01 Main Substation B3B-01-EEDG Emergency Diesel Generator
Area A B3B-01 Main Substation B3B-01-EF&A Fire Alram system
Area A B3B-01 Main Substation B3B-01-EGLT Grounding & Lightning
Area A B3B-01 Main Substation B3B-01-EILS Indoor Lighting System
Area A B3B-01 Main Substation B3B-01-ELEQ Electrical Equipment
Area A B3B-01 Main Substation B3B-01-EPST Power System
Area A B3B-01 Main Substation B3B-01-EUPS UPS
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area A B3B-01 Main Substation B3B-01-HVEQ B3B-01 for HVAC Equipment
Area A B3B-01 Main Substation B3B-01-HVFF B3B-01 for HVAC FM200
Area A B3B-01 Main Substation B3B-01-HVPL B3B-01 for HVAC Plumbing
Area A B3B-01 Main Substation B3B-01-IF&G FIRE&GAS SYSTEM
Area A B3B-01 Main Substation B3B-01-IPCS PROCESS CONTROL SYSTEM
Area A B3B-01 Main Substation B3B-01-TELE Telecomm. System
Area A B3B-02 132KV SUBSTATION B3B-02-ARCH B3B-02 Architecture
Area A B3B-02 132KV SUBSTATION B3B-02-EF&A Fire Alram system
Area A B3B-02 132KV SUBSTATION B3B-02-EGLT Grounding & Lightning
Area A B3B-02 132KV SUBSTATION B3B-02-EILS Indoor Lighting System
Area A B3B-02 132KV SUBSTATION B3B-02-ELEQ Electrical Equipment
Area A B3B-02 132KV SUBSTATION B3B-02-EPST Power System
Area A B3B-02 132KV SUBSTATION B3B-02-EUPS UPS
Area A B3B-02 132KV SUBSTATION B3B-02-HVCT B3B-02 for HVAC Control System
Area A B3B-02 132KV SUBSTATION B3B-02-HVEQ B3B-02 for HVAC Equipment
Area A B3B-02 132KV SUBSTATION B3B-02-HVFF B3B-02 for HVAC FM200
Area A B3B-02 132KV SUBSTATION B3B-02-HVPL B3B-02 for HVAC Plumbing
Area A B3B-02 132KV SUBSTATION B3B-02-IF&G FIRE&GAS SYSTEM
Area A B3B-02 132KV SUBSTATION B3B-02-TELE Telecomm. System
Area A B3B-03 GATEHOUSE B3B-03-ARCH B3B-03 Architecture
Area A B3B-03 GATEHOUSE B3B-03-HVEQ B3B-03 for HVAC Equipment
Area A B3B-03 GATEHOUSE B3B-03-HVPL B3B-03 for HVAC Plumbing
Area A B3B-03 GATEHOUSE B3B-03-IF&G FIRE&GAS SYSTEM
Area A B3B-04 STG SHELTER-37A B3B-04-ARCH B3B-04 Architecture
Area A B3B-04 STG SHELTER-37A B3B-04-IF&G FIRE&GAS SYSTEM
Area A B3B-05 STG SHELTER-37B B3B-05-ARCH B3B-05 Architecture
Area A B3B-05 STG SHELTER-37B B3B-05-IF&G FIRE&GAS SYSTEM
Area A B3B-06 STG SHELTER-37C B3B-06-ARCH B3B-06 Architecture
Area A B3B-06 STG SHELTER-37C B3B-06-IF&G FIRE&GAS SYSTEM
Area A B3B-07 TR Shelter for STG PKG-37A B3B-07-ARCH B3B-07 Architecture
Area A B3B-07 TR Shelter for STG PKG-37A B3B-07-IF&G FIRE&GAS SYSTEM
Area A B3B-08 TR Shelter for STG PKG-37B B3B-08-ARCH B3B-08 Architecture
Area A B3B-08 TR Shelter for STG PKG-37B B3B-08-IF&G FIRE&GAS SYSTEM
Area A B3B-09 TR Shelter for STG PKG-37C B3B-09-ARCH B3B-09 Architecture
Area A B3B-09 TR Shelter for STG PKG-37C B3B-09-IF&G FIRE&GAS SYSTEM
Area A B3B-10 NG Compressor Shelter-37 B3B-10-ARCH B3B-10 Architecture
Area A B3B-10 NG Compressor Shelter-37 B3B-10-IF&G FIRE&GAS SYSTEM
Area A B3B-11 Phosphate Inj. PKG Shelter-37 B3B-11-ARCH B3B-11 Architecture
Area A B3B-11 Phosphate Inj. PKG Shelter-37 B3B-11-IF&G FIRE&GAS SYSTEM
Area A B3B-12 STG SHELTER-37D B3B-12-ARCH B3B-12 Architecture
Area A B3B-12 STG SHELTER-37D B3B-12-IF&G FIRE&GAS SYSTEM
Area A B3B-13 TR Shelter for STG PKG-37D B3B-13-ARCH B3B-13 Architecture
Area A B3B-13 TR Shelter for STG PKG-37D B3B-13-IF&G FIRE&GAS SYSTEM
Area A B3B-14 Generator Technical Shelter for GTG/STG A B3B-14-ARCH B3B-14 Architecture
Area A B3B-14 Generator Technical Shelter for GTG/STG A B3B-14-IF&G FIRE&GAS SYSTEM
Area A B3B-15 Generator Technical Shelter for GTG/STG B B3B-15-ARCH B3B-15 Architecture
Area A B3B-15 Generator Technical Shelter for GTG/STG B B3B-15-IF&G FIRE&GAS SYSTEM
Area A B3B-16 Generator Technical Shelter for GTG/STG C B3B-16-ARCH B3B-16 Architecture
Area A B3B-16 Generator Technical Shelter for GTG/STG C B3B-16-IF&G FIRE&GAS SYSTEM
Area A B3B-17 Generator Technical Shelter for GTG/STG D B3B-17-ARCH B3B-17 Architecture
Area A B3B-17 Generator Technical Shelter for GTG/STG D B3B-17-IF&G FIRE&GAS SYSTEM
Area A B3B-18 TR Shelter for GTG PKG-37A B3B-18-ARCH B3B-18 Architecture
Area A B3B-18 TR Shelter for GTG PKG-37A B3B-18-IF&G FIRE&GAS SYSTEM
Area A B3B-19 TR Shelter for GTG PKG-37B B3B-19-ARCH B3B-19 Architecture
Area A B3B-19 TR Shelter for GTG PKG-37B B3B-19-IF&G FIRE&GAS SYSTEM
Area A B3B-20 TR Shelter for GTG PKG-37C B3B-20-ARCH B3B-20 Architecture
Area A B3B-20 TR Shelter for GTG PKG-37C B3B-20-IF&G FIRE&GAS SYSTEM
Area A B3B-21 TR Shelter for GTG PKG-37D B3B-21-ARCH B3B-21 Architecture
Area A B3B-21 TR Shelter for GTG PKG-37D B3B-21-IF&G FIRE&GAS SYSTEM
Area A B3C-01 Chemical Inj. PKG Shelter-33 B3C-01-ARCH B3C-01 Architecture
Area A B3C-01 Chemical Inj. PKG Shelter-33 B3C-01-IF&G FIRE&GAS SYSTEM
Area A B4A-01 PIBs/SS B4A-01-ARCH B4A-01 Architecture
Area A B4A-01 PIBs/SS B4A-01-EEDG Emergency Diesel Generator
Area A B4A-01 PIBs/SS B4A-01-EF&A Fire Alram system
Area A B4A-01 PIBs/SS B4A-01-EGLT Grounding & Lightning
Area A B4A-01 PIBs/SS B4A-01-EILS Indoor Lighting System
Area A B4A-01 PIBs/SS B4A-01-ELEQ Electrical Equipment
Area A B4A-01 PIBs/SS B4A-01-EPST Power System
Area A B4A-01 PIBs/SS B4A-01-EUPS UPS
Area A B4A-01 PIBs/SS B4A-01-HVCT B4A-01 for HVAC Control System
Area A B4A-01 PIBs/SS B4A-01-HVEQ B4A-01 for HVAC Equipment
Area A B4A-01 PIBs/SS B4A-01-HVFF B4A-01 for HVAC FM200
Area A B4A-01 PIBs/SS B4A-01-HVPL B4A-01 for HVAC Plumbing
Area A B4A-01 PIBs/SS B4A-01-IF&G FIRE&GAS SYSTEM
Area A B4A-01 PIBs/SS B4A-01-IPCS PROCESS CONTROL SYSTEM
Area A B4A-01 PIBs/SS B4A-01-TELE Telecomm. System
Area A B4A-02 OPERATOR SHELTER B4A-02-ARCH B4A-02 Architecture
Area A B4A-02 OPERATOR SHELTER B4A-02-EF&A Fire Alram system
Area A B4A-02 OPERATOR SHELTER B4A-02-EGLT Grounding & Lightning
Area A B4A-02 OPERATOR SHELTER B4A-02-EILS Indoor Lighting System
Area A B4A-02 OPERATOR SHELTER B4A-02-ELEQ Electrical Equipment
Area A B4A-02 OPERATOR SHELTER B4A-02-HVEQ B4A-02 for HVAC Equipment
Area A B4A-02 OPERATOR SHELTER B4A-02-HVPL B4A-02 for HVAC Plumbing
Area A B4A-02 OPERATOR SHELTER B4A-02-IF&G FIRE&GAS SYSTEM
Area A B4A-02 OPERATOR SHELTER B4A-02-TELE Telecomm. System
Area A B4A-03 PUMP STATION (52-P-101A/B/C/D/E/F)(P/S-01) B4A-03-ARCH B4A-03 Architecture
Area A B4A-03 PUMP STATION (52-P-101A/B/C/D/E/F)(P/S-01) B4A-03-EEDG Emergency Diesel Generator
Area A B4A-03 PUMP STATION (52-P-101A/B/C/D/E/F)(P/S-01) B4A-03-EF&A Fire Alram system
Area A B4A-03 PUMP STATION (52-P-101A/B/C/D/E/F)(P/S-01) B4A-03-EGLT Grounding & Lightning
Area A B4A-03 PUMP STATION (52-P-101A/B/C/D/E/F)(P/S-01) B4A-03-EILS Indoor Lighting System
Area A B4A-03 PUMP STATION (52-P-101A/B/C/D/E/F)(P/S-01) B4A-03-ELEQ Electrical Equipment
Area A B4A-03 PUMP STATION (52-P-101A/B/C/D/E/F)(P/S-01) B4A-03-EPST Power System
Area A B4A-03 PUMP STATION (52-P-101A/B/C/D/E/F)(P/S-01) B4A-03-EUPS UPS
Area A B4A-03 PUMP STATION (52-P-101A/B/C/D/E/F)(P/S-01) B4A-03-IF&G FIRE&GAS SYSTEM
Area A B4A-03 PUMP STATION (52-P-101A/B/C/D/E/F)(P/S-01) B4A-03-TELE Telecomm. System
Area B B4B-01 PIBs/SS B4B-01-ARCH B4B-01 Architecture
Area B B4B-01 PIBs/SS B4B-01-EEDG Emergency Diesel Generator
Area B B4B-01 PIBs/SS B4B-01-EF&A Fire Alram system
Area B B4B-01 PIBs/SS B4B-01-EGLT Grounding & Lightning
Area B B4B-01 PIBs/SS B4B-01-EILS Indoor Lighting System
Area B B4B-01 PIBs/SS B4B-01-ELEQ Electrical Equipment
Area B B4B-01 PIBs/SS B4B-01-EPST Power System
Area B B4B-01 PIBs/SS B4B-01-EUPS UPS
Area B B4B-01 PIBs/SS B4B-01-HVCT B4B-01 for HVAC Control System
Area B B4B-01 PIBs/SS B4B-01-HVEQ B4B-01 for HVAC Equipment
Area B B4B-01 PIBs/SS B4B-01-HVFF B4B-01 for HVAC FM200
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area B B4B-01 PIBs/SS B4B-01-HVPL B4B-01 for HVAC Plumbing
Area B B4B-01 PIBs/SS B4B-01-IF&G FIRE&GAS SYSTEM
Area B B4B-01 PIBs/SS B4B-01-IPCS PROCESS CONTROL SYSTEM
Area B B4B-01 PIBs/SS B4B-01-TELE Telecomm. System
Area B B4B-02 OPERATOR SHELTER B4B-02-ARCH B4B-02 Architecture
Area B B4B-02 OPERATOR SHELTER B4B-02-EF&A Fire Alram system
Area B B4B-02 OPERATOR SHELTER B4B-02-EGLT Grounding & Lightning
Area B B4B-02 OPERATOR SHELTER B4B-02-EILS Indoor Lighting System
Area B B4B-02 OPERATOR SHELTER B4B-02-ELEQ Electrical Equipment
Area B B4B-02 OPERATOR SHELTER B4B-02-HVEQ B4B-02 for HVAC Equipment
Area B B4B-02 OPERATOR SHELTER B4B-02-HVPL B4B-02 for HVAC Plumbing
Area B B4B-02 OPERATOR SHELTER B4B-02-IF&G FIRE&GAS SYSTEM
Area B B4B-02 OPERATOR SHELTER B4B-02-TELE Telecomm. System
Area B B4B-03 OPERATOR SHELTER B4B-03-ARCH B4B-03 Architecture
Area B B4B-03 OPERATOR SHELTER B4B-03-EF&A Fire Alram system
Area B B4B-03 OPERATOR SHELTER B4B-03-EGLT Grounding & Lightning
Area B B4B-03 OPERATOR SHELTER B4B-03-EILS Indoor Lighting System
Area B B4B-03 OPERATOR SHELTER B4B-03-ELEQ Electrical Equipment
Area B B4B-03 OPERATOR SHELTER B4B-03-HVEQ B4B-03 for HVAC Equipment
Area B B4B-03 OPERATOR SHELTER B4B-03-HVPL B4B-03 for HVAC Plumbing
Area B B4B-03 OPERATOR SHELTER B4B-03-IF&G FIRE&GAS SYSTEM
Area B B4B-03 OPERATOR SHELTER B4B-03-TELE Telecomm. System
Area B B4B-04 PUMP STATION (52-P-201AB,202AB,205AB)(P/S-02) B4B-04-ARCH B4B-04 Architecture
Area B B4B-04 PUMP STATION (52-P-201AB,202AB,205AB)(P/S-02) B4B-04-EEDG Emergency Diesel Generator
Area B B4B-04 PUMP STATION (52-P-201AB,202AB,205AB)(P/S-02) B4B-04-EF&A Fire Alram system
Area B B4B-04 PUMP STATION (52-P-201AB,202AB,205AB)(P/S-02) B4B-04-EGLT Grounding & Lightning
Area B B4B-04 PUMP STATION (52-P-201AB,202AB,205AB)(P/S-02) B4B-04-EILS Indoor Lighting System
Area B B4B-04 PUMP STATION (52-P-201AB,202AB,205AB)(P/S-02) B4B-04-ELEQ Electrical Equipment
Area B B4B-04 PUMP STATION (52-P-201AB,202AB,205AB)(P/S-02) B4B-04-EPST Power System
Area B B4B-04 PUMP STATION (52-P-201AB,202AB,205AB)(P/S-02) B4B-04-EUPS UPS
Area B B4B-04 PUMP STATION (52-P-201AB,202AB,205AB)(P/S-02) B4B-04-IF&G FIRE&GAS SYSTEM
Area B B4B-04 PUMP STATION (52-P-201AB,202AB,205AB)(P/S-02) B4B-04-TELE Telecomm. System
Area B B4B-05 PUMP STATION (52-P-203AB,207AB)(P/S-03) B4B-05-ARCH B4B-05 Architecture
Area B B4B-05 PUMP STATION (52-P-203AB,207AB)(P/S-03) B4B-05-EEDG Emergency Diesel Generator
Area B B4B-05 PUMP STATION (52-P-203AB,207AB)(P/S-03) B4B-05-EF&A Fire Alram system
Area B B4B-05 PUMP STATION (52-P-203AB,207AB)(P/S-03) B4B-05-EGLT Grounding & Lightning
Area B B4B-05 PUMP STATION (52-P-203AB,207AB)(P/S-03) B4B-05-EILS Indoor Lighting System
Area B B4B-05 PUMP STATION (52-P-203AB,207AB)(P/S-03) B4B-05-ELEQ Electrical Equipment
Area B B4B-05 PUMP STATION (52-P-203AB,207AB)(P/S-03) B4B-05-EPST Power System
Area B B4B-05 PUMP STATION (52-P-203AB,207AB)(P/S-03) B4B-05-EUPS UPS
Area B B4B-05 PUMP STATION (52-P-203AB,207AB)(P/S-03) B4B-05-IF&G FIRE&GAS SYSTEM
Area B B4B-05 PUMP STATION (52-P-203AB,207AB)(P/S-03) B4B-05-TELE Telecomm. System
Area B B4B-06 PUMP STATION (52-P-003AB,204AB,206AB,210AB)(P/S-04) B4B-06-ARCH B4B-06 Architecture
Area B B4B-06 PUMP STATION (52-P-003AB,204AB,206AB,210AB)(P/S-04) B4B-06-EEDG Emergency Diesel Generator
Area B B4B-06 PUMP STATION (52-P-003AB,204AB,206AB,210AB)(P/S-04) B4B-06-EF&A Fire Alram system
Area B B4B-06 PUMP STATION (52-P-003AB,204AB,206AB,210AB)(P/S-04) B4B-06-EGLT Grounding & Lightning
Area B B4B-06 PUMP STATION (52-P-003AB,204AB,206AB,210AB)(P/S-04) B4B-06-EILS Indoor Lighting System
Area B B4B-06 PUMP STATION (52-P-003AB,204AB,206AB,210AB)(P/S-04) B4B-06-ELEQ Electrical Equipment
Area B B4B-06 PUMP STATION (52-P-003AB,204AB,206AB,210AB)(P/S-04) B4B-06-EPST Power System
Area B B4B-06 PUMP STATION (52-P-003AB,204AB,206AB,210AB)(P/S-04) B4B-06-EUPS UPS
Area B B4B-06 PUMP STATION (52-P-003AB,204AB,206AB,210AB)(P/S-04) B4B-06-IF&G FIRE&GAS SYSTEM
Area B B4B-06 PUMP STATION (52-P-003AB,204AB,206AB,210AB)(P/S-04) B4B-06-TELE Telecomm. System
Area B B4C-01 PIBs/SS B4C-01-ARCH B4C-01 Architecture
Area B B4C-01 PIBs/SS B4C-01-EEDG Emergency Diesel Generator
Area B B4C-01 PIBs/SS B4C-01-EF&A Fire Alram system
Area B B4C-01 PIBs/SS B4C-01-EGLT Grounding & Lightning
Area B B4C-01 PIBs/SS B4C-01-EILS Indoor Lighting System
Area B B4C-01 PIBs/SS B4C-01-ELEQ Electrical Equipment
Area B B4C-01 PIBs/SS B4C-01-EPST Power System
Area B B4C-01 PIBs/SS B4C-01-EUPS UPS
Area B B4C-01 PIBs/SS B4C-01-HVCT B4C-01 for HVAC Control System
Area B B4C-01 PIBs/SS B4C-01-HVEQ B4C-01 for HVAC Equipment
Area B B4C-01 PIBs/SS B4C-01-HVFF B4C-01 for HVAC FM200
Area B B4C-01 PIBs/SS B4C-01-HVPL B4C-01 for HVAC Plumbing
Area B B4C-01 PIBs/SS B4C-01-IF&G FIRE&GAS SYSTEM
Area B B4C-01 PIBs/SS B4C-01-IPCS PROCESS CONTROL SYSTEM
Area B B4C-01 PIBs/SS B4C-01-TELE Telecomm. System
Area B B4C-02 OPERATOR SHELTER B4C-02-ARCH B4C-02 Architecture
Area B B4C-02 OPERATOR SHELTER B4C-02-EF&A Fire Alram system
Area B B4C-02 OPERATOR SHELTER B4C-02-EGLT Grounding & Lightning
Area B B4C-02 OPERATOR SHELTER B4C-02-EILS Indoor Lighting System
Area B B4C-02 OPERATOR SHELTER B4C-02-ELEQ Electrical Equipment
Area B B4C-02 OPERATOR SHELTER B4C-02-EPST Power System
Area B B4C-02 OPERATOR SHELTER B4C-02-HVCT B4C-02 for HVAC Control System
Area B B4C-02 OPERATOR SHELTER B4C-02-HVEQ B4C-02 for HVAC Equipment
Area B B4C-02 OPERATOR SHELTER B4C-02-HVPL B4C-02 for HVAC Plumbing
Area B B4C-02 OPERATOR SHELTER B4C-02-IF&G FIRE&GAS SYSTEM
Area B B4C-02 OPERATOR SHELTER B4C-02-TELE Telecomm. System
Area B B4C-03 OPERATOR SHELTER B4C-03-ARCH B4C-03 Architecture
Area B B4C-03 OPERATOR SHELTER B4C-03-EF&A Fire Alram system
Area B B4C-03 OPERATOR SHELTER B4C-03-EGLT Grounding & Lightning
Area B B4C-03 OPERATOR SHELTER B4C-03-EILS Indoor Lighting System
Area B B4C-03 OPERATOR SHELTER B4C-03-ELEQ Electrical Equipment
Area B B4C-03 OPERATOR SHELTER B4C-03-EPST Power System
Area B B4C-03 OPERATOR SHELTER B4C-03-HVCT B4C-03 for HVAC Control System
Area B B4C-03 OPERATOR SHELTER B4C-03-HVEQ B4C-03 for HVAC Equipment
Area B B4C-03 OPERATOR SHELTER B4C-03-HVPL B4C-03 for HVAC Plumbing
Area B B4C-03 OPERATOR SHELTER B4C-03-IF&G FIRE&GAS SYSTEM
Area B B4C-03 OPERATOR SHELTER B4C-03-TELE Telecomm. System
Area B B4C-04 PACKAGE SHELTER FOR 52-PK-301/306 B4C-04-ARCH B4C-04 Architecture
Area B B4C-04 PACKAGE SHELTER FOR 52-PK-301/306 B4C-04-EPST Power System
Area B B4C-04 PACKAGE SHELTER FOR 52-PK-301/306 B4C-04-IF&G FIRE&GAS SYSTEM
Area B B4C-05 PACKAGE SHELTER FOR 52-PK-302/303/305 B4C-05-ARCH B4C-05 Architecture
Area B B4C-05 PACKAGE SHELTER FOR 52-PK-302/303/305 B4C-05-EPST Power System
Area B B4C-05 PACKAGE SHELTER FOR 52-PK-302/303/305 B4C-05-IF&G FIRE&GAS SYSTEM
Area B B4C-10 PUMP STATION (52-P-308AB,309AB,316ABC,319AB,322AB)(P/S-05) B4C-10-ARCH B4C-10 Architecture
Area B B4C-10 PUMP STATION (52-P-308AB,309AB,316ABC,319AB,322AB)(P/S-05) B4C-10-EPST Power System
Area B B4C-10 PUMP STATION (52-P-308AB,309AB,316ABC,319AB,322AB)(P/S-05) B4C-10-IF&G FIRE&GAS SYSTEM
Area B B4C-11 PUMP STATION (52-P-317AB,318AB,321AB)(P/S-06) B4C-11-ARCH B4C-11 Architecture
Area B B4C-11 PUMP STATION (52-P-317AB,318AB,321AB)(P/S-06) B4C-11-EPST Power System
Area B B4C-11 PUMP STATION (52-P-317AB,318AB,321AB)(P/S-06) B4C-11-IF&G FIRE&GAS SYSTEM
Area B B4C-12 PUMP STATION (52-P-304ABC,305ABC)(P/S-07) B4C-12-ARCH B4C-12 Architecture
Area B B4C-12 PUMP STATION (52-P-304ABC,305ABC)(P/S-07) B4C-12-EPST Power System
Area B B4C-12 PUMP STATION (52-P-304ABC,305ABC)(P/S-07) B4C-12-IF&G FIRE&GAS SYSTEM
Area B B4C-13 PUMP STATION (52-P-306ABC,307AB)(P/S-08) B4C-13-ARCH B4C-13 Architecture
Area B B4C-13 PUMP STATION (52-P-306ABC,307AB)(P/S-08) B4C-13-EPST Power System
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area B B4C-13 PUMP STATION (52-P-306ABC,307AB)(P/S-08) B4C-13-IF&G FIRE&GAS SYSTEM
Area B B4C-14 PUMP STATION (52-P-208AB,323AB,212,211AB,301AB,302AB,303AB,408AB,409AB,410AB)(P/S-13) B4C-14-ARCH B4C-14 Architecture
Area B B4C-14 PUMP STATION (52-P-208AB,323AB,212,211AB,301AB,302AB,303AB,408AB,409AB,410AB)(P/S-13) B4C-14-EPST Power System
Area B B4C-14 PUMP STATION (52-P-208AB,323AB,212,211AB,301AB,302AB,303AB,408AB,409AB,410AB)(P/S-13) B4C-14-IF&G FIRE&GAS SYSTEM
Area C B4C-15 Operator Shelter B4C-15-ARCH B4C-15 Architecture
Area C B4C-15 Operator Shelter B4C-15-EF&A Fire Alram system
Area C B4C-15 Operator Shelter B4C-15-EGLT Grounding & Lightning
Area C B4C-15 Operator Shelter B4C-15-EILS Indoor Lighting System
Area C B4C-15 Operator Shelter B4C-15-EPST Power System
Area C B4C-15 Operator Shelter B4C-15-HVEQ B4C-15 for HVAC Equipment
Area C B4C-15 Operator Shelter B4C-15-HVPL B4C-15 for HVAC Plumbing
Area C B4C-15 Operator Shelter B4C-15-IF&G FIRE&GAS SYSTEM
Area C B4C-16 Pumps(P/S 14 52-P-209A/B, 52-P-314 A/B/C) B4C-16-ARCH B4C-16 Architecture
Area C B4C-16 Pumps(P/S 14 52-P-209A/B, 52-P-314 A/B/C) B4C-16-EGLT Grounding & Lightning
Area C B4C-16 Pumps(P/S 14 52-P-209A/B, 52-P-314 A/B/C) B4C-16-EILS Indoor Lighting System
Area C B4C-16 Pumps(P/S 14 52-P-209A/B, 52-P-314 A/B/C) B4C-16-EPST Power System
Area C B4C-16 Pumps(P/S 14 52-P-209A/B, 52-P-314 A/B/C) B4C-16-IF&G FIRE&GAS SYSTEM
Area C B4C-17 Pumps(P/S 15 53-P-001 A/B/C, 53-P-002 A/B/C) B4C-17-ARCH B4C-17 Architecture
Area C B4C-17 Pumps(P/S 15 53-P-001 A/B/C, 53-P-002 A/B/C) B4C-17-EGLT Grounding & Lightning
Area C B4C-17 Pumps(P/S 15 53-P-001 A/B/C, 53-P-002 A/B/C) B4C-17-EILS Indoor Lighting System
Area C B4C-17 Pumps(P/S 15 53-P-001 A/B/C, 53-P-002 A/B/C) B4C-17-EPST Power System
Area C B4C-17 Pumps(P/S 15 53-P-001 A/B/C, 53-P-002 A/B/C) B4C-17-IF&G FIRE&GAS SYSTEM
Area B B4D-01 PIBs/SS B4D-01-ARCH B4D-01 Architecture
Area B B4D-01 PIBs/SS B4D-01-EEDG Emergency Diesel Generator
Area B B4D-01 PIBs/SS B4D-01-EF&A Fire Alram system
Area B B4D-01 PIBs/SS B4D-01-EGLT Grounding & Lightning
Area B B4D-01 PIBs/SS B4D-01-EILS Indoor Lighting System
Area B B4D-01 PIBs/SS B4D-01-ELEQ Electrical Equipment
Area B B4D-01 PIBs/SS B4D-01-EPST Power System
Area B B4D-01 PIBs/SS B4D-01-EUPS UPS
Area B B4D-01 PIBs/SS B4D-01-HVCT B4D-01 for HVAC Control System
Area B B4D-01 PIBs/SS B4D-01-HVEQ B4D-01 for HVAC Equipment
Area B B4D-01 PIBs/SS B4D-01-HVFF B4D-01 for HVAC FM200
Area B B4D-01 PIBs/SS B4D-01-HVPL B4D-01 for HVAC Plumbing
Area B B4D-01 PIBs/SS B4D-01-IF&G FIRE&GAS SYSTEM
Area B B4D-01 PIBs/SS B4D-01-IPCS PROCESS CONTROL SYSTEM
Area B B4D-01 PIBs/SS B4D-01-TELE Telecomm. System
Area B B4D-02 OPERATOR SHELTER B4D-02-ARCH B4D-02 Architecture
Area B B4D-02 OPERATOR SHELTER B4D-02-EF&A Fire Alram system
Area B B4D-02 OPERATOR SHELTER B4D-02-EGLT Grounding & Lightning
Area B B4D-02 OPERATOR SHELTER B4D-02-EILS Indoor Lighting System
Area B B4D-02 OPERATOR SHELTER B4D-02-ELEQ Electrical Equipment
Area B B4D-02 OPERATOR SHELTER B4D-02-EPST Power System
Area B B4D-02 OPERATOR SHELTER B4D-02-HVEQ B4D-02 for HVAC Equipment
Area B B4D-02 OPERATOR SHELTER B4D-02-HVPL B4D-02 for HVAC Plumbing
Area B B4D-02 OPERATOR SHELTER B4D-02-IF&G FIRE&GAS SYSTEM
Area B B4D-02 OPERATOR SHELTER B4D-02-TELE Telecomm. System
Area B B4D-03 PUMP STATION (61-P-001AB)(P/S-09) B4D-03-ARCH B4D-03 Architecture
Area B B4D-03 PUMP STATION (61-P-001AB)(P/S-09) B4D-03-IF&G FIRE&GAS SYSTEM
Area B B4D-04 PUMP STATION (52-P-005AB,405AB)(P/S-10) B4D-04-ARCH B4D-04 Architecture
Area B B4D-04 PUMP STATION (52-P-005AB,405AB)(P/S-10) B4D-04-IF&G FIRE&GAS SYSTEM
Area B B4D-05 PUMP STATION (52-P-406AB)(P/S-11) B4D-05-ARCH B4D-05 Architecture
Area B B4D-05 PUMP STATION (52-P-406AB)(P/S-11) B4D-05-IF&G FIRE&GAS SYSTEM
Area B B4D-06 PUMP STATION (52-P-401AB,402AB,403AB,404AB)(P/S-12) B4D-06-ARCH B4D-06 Architecture
Area B B4D-06 PUMP STATION (52-P-401AB,402AB,403AB,404AB)(P/S-12) B4D-06-IF&G FIRE&GAS SYSTEM
Area B B4D-07 PACKAGE SHELTER FOR 52-PK-304 B4D-07-ARCH B4D-07 Architecture
Area B B4D-07 PACKAGE SHELTER FOR 52-PK-304 B4D-07-IF&G FIRE&GAS SYSTEM
Area C B5A-01 Loading Control Building(PIBs/SS) B5A-01-ARCH B5A-01 Architecture
Area C B5A-01 Loading Control Building(PIBs/SS) B5A-01-EEDG Emergency Diesel Generator
Area C B5A-01 Loading Control Building(PIBs/SS) B5A-01-EF&A Fire Alram system
Area C B5A-01 Loading Control Building(PIBs/SS) B5A-01-EGLT Grounding & Lightning
Area C B5A-01 Loading Control Building(PIBs/SS) B5A-01-EILS Indoor Lighting System
Area C B5A-01 Loading Control Building(PIBs/SS) B5A-01-ELEQ Electrical Equipment
Area C B5A-01 Loading Control Building(PIBs/SS) B5A-01-EPST Power System
Area C B5A-01 Loading Control Building(PIBs/SS) B5A-01-EUPS UPS
Area C B5A-01 Loading Control Building(PIBs/SS) B5A-01-HVCT B5A-01 for HVAC Control System
Area C B5A-01 Loading Control Building(PIBs/SS) B5A-01-HVEQ B5A-01 for HVAC Equipment
Area C B5A-01 Loading Control Building(PIBs/SS) B5A-01-HVFF B5A-01 for HVAC FM200
Area C B5A-01 Loading Control Building(PIBs/SS) B5A-01-HVPL B5A-01 for HVAC Plumbing
Area C B5A-01 Loading Control Building(PIBs/SS) B5A-01-IF&G FIRE&GAS SYSTEM
Area C B5A-01 Loading Control Building(PIBs/SS) B5A-01-IPCS PROCESS CONTROL SYSTEM
Area C B5A-01 Loading Control Building(PIBs/SS) B5A-01-TELE Telecomm. System
Area C B5A-02 Refinery Second Gatehouse B5A-02-ARCH B5A-02 Architecture
Area C B5A-02 Refinery Second Gatehouse B5A-02-EF&A Fire Alram system
Area C B5A-02 Refinery Second Gatehouse B5A-02-EGLT Grounding & Lightning
Area C B5A-02 Refinery Second Gatehouse B5A-02-EILS Indoor Lighting System
Area C B5A-02 Refinery Second Gatehouse B5A-02-EPST Power System
Area C B5A-02 Refinery Second Gatehouse B5A-02-HVEQ B5A-02 for HVAC Equipment
Area C B5A-02 Refinery Second Gatehouse B5A-02-HVPL B5A-02 for HVAC Plumbing
Area C B5A-02 Refinery Second Gatehouse B5A-02-IF&G FIRE&GAS SYSTEM
Area C B5A-02 Refinery Second Gatehouse B5A-02-TELE Telecomm. System
Area C B5A-03 Guard House B5A-03-ARCH B5A-03 Architecture
Area C B5A-03 Guard House B5A-03-EF&A Fire Alram system
Area C B5A-03 Guard House B5A-03-EGLT Grounding & Lightning
Area C B5A-03 Guard House B5A-03-EILS Indoor Lighting System
Area C B5A-03 Guard House B5A-03-EPST Power System
Area C B5A-03 Guard House B5A-03-HVEQ B5A-03 for HVAC Equipment
Area C B5A-03 Guard House B5A-03-HVPL B5A-03 for HVAC Plumbing
Area C B5A-03 Guard House B5A-03-IF&G FIRE&GAS SYSTEM
Area C B5A-04 Asphalt Loading Weighting Station B5A-04-ARCH B5A-04 Architecture
Area C B5A-04 Asphalt Loading Weighting Station B5A-04-EF&A Fire Alram system
Area C B5A-04 Asphalt Loading Weighting Station B5A-04-EGLT Grounding & Lightning
Area C B5A-04 Asphalt Loading Weighting Station B5A-04-EILS Indoor Lighting System
Area C B5A-04 Asphalt Loading Weighting Station B5A-04-EPST Power System
Area C B5A-04 Asphalt Loading Weighting Station B5A-04-IF&G FIRE&GAS SYSTEM
Area C B5A-05 Asphalt Loading Shelter B5A-05-ARCH B5A-05 Architecture
Area C B5A-05 Asphalt Loading Shelter B5A-05-EGLT Grounding & Lightning
Area C B5A-05 Asphalt Loading Shelter B5A-05-EILS Indoor Lighting System
Area C B5A-05 Asphalt Loading Shelter B5A-05-EPST Power System
Area C B5A-05 Asphalt Loading Shelter B5A-05-IF&G FIRE&GAS SYSTEM
Area C B5A-06 Blown Asphalt Barrel Filling Package Shelter B5A-06-ARCH B5A-06 Architecture
Area C B5A-06 Blown Asphalt Barrel Filling Package Shelter B5A-06-EF&A Fire Alram system
Area C B5A-06 Blown Asphalt Barrel Filling Package Shelter B5A-06-EGLT Grounding & Lightning
Area C B5A-06 Blown Asphalt Barrel Filling Package Shelter B5A-06-EILS Indoor Lighting System
Area C B5A-06 Blown Asphalt Barrel Filling Package Shelter B5A-06-EPST Power System
Area C B5A-06 Blown Asphalt Barrel Filling Package Shelter B5A-06-IF&G FIRE&GAS SYSTEM
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area C B5A-07 Guard House B5A-07-ARCH B5A-07 Architecture
Area C B5A-07 Guard House B5A-07-EF&A Fire Alram system
Area C B5A-07 Guard House B5A-07-EGLT Grounding & Lightning
Area C B5A-07 Guard House B5A-07-EILS Indoor Lighting System
Area C B5A-07 Guard House B5A-07-EPST Power System
Area C B5A-07 Guard House B5A-07-HVEQ B5A-07 for HVAC Equipment
Area C B5A-07 Guard House B5A-07-HVPL B5A-07 for HVAC Plumbing
Area C B5A-07 Guard House B5A-07-IF&G FIRE&GAS SYSTEM
Area C B5A-07 Guard House B5A-07-TELE Telecomm. System
Area C B5A-08 Sulphur Bagging Weighting Station B5A-08-ARCH B5A-08 Architecture
Area C B5A-08 Sulphur Bagging Weighting Station B5A-08-EGLT Grounding & Lightning
Area C B5A-08 Sulphur Bagging Weighting Station B5A-08-EILS Indoor Lighting System
Area C B5A-08 Sulphur Bagging Weighting Station B5A-08-EPST Power System
Area C B5A-08 Sulphur Bagging Weighting Station B5A-08-IF&G FIRE&GAS SYSTEM
Area C B5A-09 Sulphur Solidification Shelter B5A-09-ARCH B5A-09 Architecture
Area C B5A-09 Sulphur Solidification Shelter B5A-09-EGLT Grounding & Lightning
Area C B5A-09 Sulphur Solidification Shelter B5A-09-EILS Indoor Lighting System
Area C B5A-09 Sulphur Solidification Shelter B5A-09-EPST Power System
Area C B5A-09 Sulphur Solidification Shelter B5A-09-IF&G FIRE&GAS SYSTEM
Area C B5A-10 SULPHUR STORAGE SHELTER B5A-10-ARCH B5A-10 Architecture
Area C B5A-10 SULPHUR STORAGE SHELTER B5A-10-EF&A Fire Alram system
Area C B5A-10 SULPHUR STORAGE SHELTER B5A-10-EGLT Grounding & Lightning
Area C B5A-10 SULPHUR STORAGE SHELTER B5A-10-EILS Indoor Lighting System
Area C B5A-10 SULPHUR STORAGE SHELTER B5A-10-EPST Power System
Area C B5A-10 SULPHUR STORAGE SHELTER B5A-10-HVCT B5A-10 for HVAC Control System
Area C B5A-10 SULPHUR STORAGE SHELTER B5A-10-HVEQ B5A-10 for HVAC Equipment
Area C B5A-10 SULPHUR STORAGE SHELTER B5A-10-HVPL B5A-10 for HVAC Plumbing
Area C B5A-10 SULPHUR STORAGE SHELTER B5A-10-IF&G FIRE&GAS SYSTEM
Area C B5A-13 AL-KHAIRAT POWER STATION SHELTER B5A-13-ARCH B5A-13 Architecture
Area C B5A-13 AL-KHAIRAT POWER STATION SHELTER B5A-13-EGLT Grounding & Lightning
Area C B5A-13 AL-KHAIRAT POWER STATION SHELTER B5A-13-EILS Indoor Lighting System
Area C B5A-13 AL-KHAIRAT POWER STATION SHELTER B5A-13-EPST Power System
Area C B5A-13 AL-KHAIRAT POWER STATION SHELTER B5A-13-IF&G FIRE&GAS SYSTEM
Area C B5B-01 Main Observation Post(North) B5B-01-ARCH B5B-01 Architecture
Area C B5B-01 Main Observation Post(North) B5B-01-EF&A Fire Alram system
Area C B5B-01 Main Observation Post(North) B5B-01-EGLT Grounding & Lightning
Area C B5B-01 Main Observation Post(North) B5B-01-EILS Indoor Lighting System
Area C B5B-01 Main Observation Post(North) B5B-01-EPST Power System
Area C B5B-01 Main Observation Post(North) B5B-01-HVEQ B5B-01 for HVAC Equipment
Area C B5B-01 Main Observation Post(North) B5B-01-HVPL B5B-01 for HVAC Plumbing
Area C B5B-01 Main Observation Post(North) B5B-01-IF&G FIRE&GAS SYSTEM
Area C B5B-01 Main Observation Post(North) B5B-01-TELE Telecomm. System
Area C B5B-02 Police Station(North) B5B-02-ARCH B5B-02 Architecture
Area C B5B-02 Police Station(North) B5B-02-EF&A Fire Alram system
Area C B5B-02 Police Station(North) B5B-02-EGLT Grounding & Lightning
Area C B5B-02 Police Station(North) B5B-02-EILS Indoor Lighting System
Area C B5B-02 Police Station(North) B5B-02-EPST Power System
Area C B5B-02 Police Station(North) B5B-02-HVCT B5B-02 for HVAC Control System
Area C B5B-02 Police Station(North) B5B-02-HVEQ B5B-02 for HVAC Equipment
Area C B5B-02 Police Station(North) B5B-02-HVPL B5B-02 for HVAC Plumbing
Area C B5B-02 Police Station(North) B5B-02-IF&G FIRE&GAS SYSTEM
Area C B5B-02 Police Station(North) B5B-02-TELE Telecomm. System
Area C B5B-03 Perimeter Observation Post B5B-03-ARCH B5B-03 Architecture
Area C B5B-03 Perimeter Observation Post B5B-03-EGLT Grounding & Lightning
Area C B5B-03 Perimeter Observation Post B5B-03-EILS Indoor Lighting System
Area C B5B-03 Perimeter Observation Post B5B-03-IF&G FIRE&GAS SYSTEM
Area C B5B-04 Perimeter Observation Post B5B-04-ARCH B5B-04 Architecture
Area C B5B-04 Perimeter Observation Post B5B-04-EGLT Grounding & Lightning
Area C B5B-04 Perimeter Observation Post B5B-04-EILS Indoor Lighting System
Area C B5B-04 Perimeter Observation Post B5B-04-IF&G FIRE&GAS SYSTEM
Area C B5B-05 Perimeter Observation Post B5B-05-ARCH B5B-05 Architecture
Area C B5B-05 Perimeter Observation Post B5B-05-EGLT Grounding & Lightning
Area C B5B-05 Perimeter Observation Post B5B-05-EILS Indoor Lighting System
Area C B5B-05 Perimeter Observation Post B5B-05-IF&G FIRE&GAS SYSTEM
Area C B5B-06 Perimeter Observation Post B5B-06-ARCH B5B-06 Architecture
Area C B5B-06 Perimeter Observation Post B5B-06-EGLT Grounding & Lightning
Area C B5B-06 Perimeter Observation Post B5B-06-EILS Indoor Lighting System
Area C B5B-06 Perimeter Observation Post B5B-06-IF&G FIRE&GAS SYSTEM
Area C B5B-07 Perimeter Observation Post B5B-07-ARCH B5B-07 Architecture
Area C B5B-07 Perimeter Observation Post B5B-07-EGLT Grounding & Lightning
Area C B5B-07 Perimeter Observation Post B5B-07-EILS Indoor Lighting System
Area C B5B-07 Perimeter Observation Post B5B-07-IF&G FIRE&GAS SYSTEM
Area C B5B-08 Perimeter Observation Post B5B-08-ARCH B5B-08 Architecture
Area C B5B-08 Perimeter Observation Post B5B-08-EGLT Grounding & Lightning
Area C B5B-08 Perimeter Observation Post B5B-08-EILS Indoor Lighting System
Area C B5B-08 Perimeter Observation Post B5B-08-IF&G FIRE&GAS SYSTEM
Area C B5B-09 Perimeter Observation Post B5B-09-ARCH B5B-09 Architecture
Area C B5B-09 Perimeter Observation Post B5B-09-EGLT Grounding & Lightning
Area C B5B-09 Perimeter Observation Post B5B-09-EILS Indoor Lighting System
Area C B5B-09 Perimeter Observation Post B5B-09-IF&G FIRE&GAS SYSTEM
Area C B5B-10 Perimeter Observation Post B5B-10-ARCH B5B-10 Architecture
Area C B5B-10 Perimeter Observation Post B5B-10-EGLT Grounding & Lightning
Area C B5B-10 Perimeter Observation Post B5B-10-EILS Indoor Lighting System
Area C B5B-10 Perimeter Observation Post B5B-10-IF&G FIRE&GAS SYSTEM
Area C B5B-11 Perimeter Observation Post B5B-11-ARCH B5B-11 Architecture
Area C B5B-11 Perimeter Observation Post B5B-11-EGLT Grounding & Lightning
Area C B5B-11 Perimeter Observation Post B5B-11-EILS Indoor Lighting System
Area C B5B-11 Perimeter Observation Post B5B-11-IF&G FIRE&GAS SYSTEM
Area C B5B-12 Perimeter Observation Post B5B-12-ARCH B5B-12 Architecture
Area C B5B-12 Perimeter Observation Post B5B-12-EGLT Grounding & Lightning
Area C B5B-12 Perimeter Observation Post B5B-12-EILS Indoor Lighting System
Area C B5B-12 Perimeter Observation Post B5B-12-IF&G FIRE&GAS SYSTEM
Area C B5B-13 Perimeter Observation Post B5B-13-ARCH B5B-13 Architecture
Area C B5B-13 Perimeter Observation Post B5B-13-EGLT Grounding & Lightning
Area C B5B-13 Perimeter Observation Post B5B-13-EILS Indoor Lighting System
Area C B5B-13 Perimeter Observation Post B5B-13-IF&G FIRE&GAS SYSTEM
Area C B5B-14 Perimeter Observation Post B5B-14-ARCH B5B-14 Architecture
Area C B5B-14 Perimeter Observation Post B5B-14-EGLT Grounding & Lightning
Area C B5B-14 Perimeter Observation Post B5B-14-EILS Indoor Lighting System
Area C B5B-14 Perimeter Observation Post B5B-14-IF&G FIRE&GAS SYSTEM
Area C B5B-15 Perimeter Observation Post B5B-15-ARCH B5B-15 Architecture
Area C B5B-15 Perimeter Observation Post B5B-15-EGLT Grounding & Lightning
Area C B5B-15 Perimeter Observation Post B5B-15-EILS Indoor Lighting System
Area C B5B-15 Perimeter Observation Post B5B-15-IF&G FIRE&GAS SYSTEM
Area C B5B-16 Perimeter Observation Post B5B-16-ARCH B5B-16 Architecture
Area C B5B-16 Perimeter Observation Post B5B-16-EGLT Grounding & Lightning
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area C B5B-16 Perimeter Observation Post B5B-16-EILS Indoor Lighting System
Area C B5B-16 Perimeter Observation Post B5B-16-IF&G FIRE&GAS SYSTEM
Area A B5D-01 PIBs/SS B5D-01-ARCH B5D-01 Architecture
Area A B5D-01 PIBs/SS B5D-01-EEDG Emergency Diesel Generator
Area A B5D-01 PIBs/SS B5D-01-EF&A Fire Alram system
Area A B5D-01 PIBs/SS B5D-01-EGLT Grounding & Lightning
Area A B5D-01 PIBs/SS B5D-01-EILS Indoor Lighting System
Area A B5D-01 PIBs/SS B5D-01-ELEQ Electrical Equipment
Area A B5D-01 PIBs/SS B5D-01-EPST Power System
Area A B5D-01 PIBs/SS B5D-01-EUPS UPS
Area A B5D-01 PIBs/SS B5D-01-HVEQ B5D-01 for HVAC Equipment
Area A B5D-01 PIBs/SS B5D-01-HVFF B5D-01 for HVAC FM200
Area A B5D-01 PIBs/SS B5D-01-HVPL B5D-01 for HVAC Plumbing
Area A B5D-01 PIBs/SS B5D-01-IF&G FIRE&GAS SYSTEM
Area A B5D-01 PIBs/SS B5D-01-IPCS PROCESS CONTROL SYSTEM
Area A B5D-01 PIBs/SS B5D-01-TELE Telecomm. System
Area A B5D-02 WWT RO House B5D-02-ARCH B5D-02 Architecture
Area A B5D-02 WWT RO House B5D-02-EF&A Fire Alram system
Area A B5D-02 WWT RO House B5D-02-EGLT Grounding & Lightning
Area A B5D-02 WWT RO House B5D-02-EILS Indoor Lighting System
Area A B5D-02 WWT RO House B5D-02-ELEQ Electrical Equipment
Area A B5D-02 WWT RO House B5D-02-EPST Power System
Area A B5D-02 WWT RO House B5D-02-HVCT B5D-02 for HVAC Control System
Area A B5D-02 WWT RO House B5D-02-HVEQ B5D-02 for HVAC Equipment
Area A B5D-02 WWT RO House B5D-02-HVPL B5D-02 for HVAC Plumbing
Area A B5D-02 WWT RO House B5D-02-IF&G FIRE&GAS SYSTEM
Area A B5D-03 WWT MBR House B5D-03-ARCH B5D-03 Architecture
Area A B5D-03 WWT MBR House B5D-03-IF&G FIRE&GAS SYSTEM
Area A B5D-04 CHEMICAL INJ. PKG SHELTER-51A B5D-04-ARCH B5D-04 Architecture
Area A B5D-04 CHEMICAL INJ. PKG SHELTER-51A B5D-04-IF&G FIRE&GAS SYSTEM
Area A B5D-05 Chemical Inj. PKG Shelter-51B B5D-05-ARCH B5D-05 Architecture
Area A B5D-05 Chemical Inj. PKG Shelter-51B B5D-05-IF&G FIRE&GAS SYSTEM
Area A B5D-06 Oily Sludge Dewatering Shelter B5D-06-ARCH B5D-06 Architecture
Area A B5D-06 Oily Sludge Dewatering Shelter B5D-06-IF&G FIRE&GAS SYSTEM
Area A B5D-07 BIOX Sludge Dewatering Shelter B5D-07-ARCH B5D-07 Architecture
Area A B5D-07 BIOX Sludge Dewatering Shelter B5D-07-IF&G FIRE&GAS SYSTEM
Area A B5D-10 RWT Chemical Storage Shelter B5D-10-ARCH B5D-10 Architecture
Area A B5D-10 RWT Chemical Storage Shelter B5D-10-IF&G FIRE&GAS SYSTEM
Area A B5D-11 RWT UF & RO House B5D-11-ARCH B5D-11 Architecture
Area A B5D-11 RWT UF & RO House B5D-11-EF&A Fire Alram system
Area A B5D-11 RWT UF & RO House B5D-11-EGLT Grounding & Lightning
Area A B5D-11 RWT UF & RO House B5D-11-EILS Indoor Lighting System
Area A B5D-11 RWT UF & RO House B5D-11-ELEQ Electrical Equipment
Area A B5D-11 RWT UF & RO House B5D-11-EPST Power System
Area A B5D-11 RWT UF & RO House B5D-11-HVCT B5D-11 for HVAC Control System
Area A B5D-11 RWT UF & RO House B5D-11-HVEQ B5D-11 for HVAC Equipment
Area A B5D-11 RWT UF & RO House B5D-11-HVPL B5D-11 for HVAC Plumbing
Area A B5D-11 RWT UF & RO House B5D-11-IF&G FIRE&GAS SYSTEM
Area A B5D-12 RWT Dehydrator Shelter B5D-12-ARCH B5D-12 Architecture
Area A B5D-12 RWT Dehydrator Shelter B5D-12-IF&G FIRE&GAS SYSTEM
Area A B5D-13 Drinking Water Chlorination PKG Shelter B5D-13-ARCH B5D-13 Architecture
Area A B5D-13 Drinking Water Chlorination PKG Shelter B5D-13-IF&G FIRE&GAS SYSTEM
Area B B6A-01 SUBSTATION B6A-01-ARCH B6A-01 Architecture
Area B B6A-01 SUBSTATION B6A-01-EF&A Fire Alram system
Area B B6A-01 SUBSTATION B6A-01-EGLT Grounding & Lightning
Area B B6A-01 SUBSTATION B6A-01-EILS Indoor Lighting System
Area B B6A-01 SUBSTATION B6A-01-ELEQ Electrical Equipment
Area B B6A-01 SUBSTATION B6A-01-EPST Power System
Area B B6A-01 SUBSTATION B6A-01-EUPS UPS
Area B B6A-01 SUBSTATION B6A-01-HVCT B6A-01 for HVAC Control System
Area B B6A-01 SUBSTATION B6A-01-HVEQ B6A-01 for HVAC Equipment
Area B B6A-01 SUBSTATION B6A-01-HVFF B6A-01 for HVAC FM200
Area B B6A-01 SUBSTATION B6A-01-HVPL B6A-01 for HVAC Plumbing
Area B B6A-01 SUBSTATION B6A-01-IF&G FIRE&GAS SYSTEM
Area B B6A-01 SUBSTATION B6A-01-IPCS PROCESS CONTROL SYSTEM
Area B B6A-01 SUBSTATION B6A-01-TELE Telecomm. System
Area B B6A-02 DEPOT GATEHOUSE B6A-02-ARCH B6A-02 Architecture
Area B B6A-02 DEPOT GATEHOUSE B6A-02-EF&A Fire Alram system
Area B B6A-02 DEPOT GATEHOUSE B6A-02-EGLT Grounding & Lightning
Area B B6A-02 DEPOT GATEHOUSE B6A-02-EILS Indoor Lighting System
Area B B6A-02 DEPOT GATEHOUSE B6A-02-ELEQ Electrical Equipment
Area B B6A-02 DEPOT GATEHOUSE B6A-02-EPST Power System
Area B B6A-02 DEPOT GATEHOUSE B6A-02-HVEQ B6A-02 for HVAC Equipment
Area B B6A-02 DEPOT GATEHOUSE B6A-02-HVPL B6A-02 for HVAC Plumbing
Area B B6A-02 DEPOT GATEHOUSE B6A-02-IF&G FIRE&GAS SYSTEM
Area B B6A-02 DEPOT GATEHOUSE B6A-02-TELE Telecomm. System
Area B B6A-03 SECURITY BUILDING B6A-03-ARCH B6A-03 Architecture
Area B B6A-03 SECURITY BUILDING B6A-03-EF&A Fire Alram system
Area B B6A-03 SECURITY BUILDING B6A-03-EGLT Grounding & Lightning
Area B B6A-03 SECURITY BUILDING B6A-03-EILS Indoor Lighting System
Area B B6A-03 SECURITY BUILDING B6A-03-ELEQ Electrical Equipment
Area B B6A-03 SECURITY BUILDING B6A-03-EPST Power System
Area B B6A-03 SECURITY BUILDING B6A-03-HVCT B6A-03 for HVAC Control System
Area B B6A-03 SECURITY BUILDING B6A-03-HVEQ B6A-03 for HVAC Equipment
Area B B6A-03 SECURITY BUILDING B6A-03-HVPL B6A-03 for HVAC Plumbing
Area B B6A-03 SECURITY BUILDING B6A-03-IF&G FIRE&GAS SYSTEM
Area B B6A-03 SECURITY BUILDING B6A-03-TELE Telecomm. System
Area B B6A-04 ADMINISTRATION BUILDING B6A-04-ARCH B6A-04 Architecture
Area B B6A-04 ADMINISTRATION BUILDING B6A-04-EF&A Fire Alram system
Area B B6A-04 ADMINISTRATION BUILDING B6A-04-EGLT Grounding & Lightning
Area B B6A-04 ADMINISTRATION BUILDING B6A-04-EILS Indoor Lighting System
Area B B6A-04 ADMINISTRATION BUILDING B6A-04-ELEQ Electrical Equipment
Area B B6A-04 ADMINISTRATION BUILDING B6A-04-EPST Power System
Area B B6A-04 ADMINISTRATION BUILDING B6A-04-HVCT B6A-04 for HVAC Control System
Area B B6A-04 ADMINISTRATION BUILDING B6A-04-HVEQ B6A-04 for HVAC Equipment
Area B B6A-04 ADMINISTRATION BUILDING B6A-04-HVPL B6A-04 for HVAC Plumbing
Area B B6A-04 ADMINISTRATION BUILDING B6A-04-IF&G FIRE&GAS SYSTEM
Area B B6A-04 ADMINISTRATION BUILDING B6A-04-TELE Telecomm. System
Area B B6A-05 CANTEEN B6A-05-ARCH B6A-05 Architecture
Area B B6A-05 CANTEEN B6A-05-EF&A Fire Alram system
Area B B6A-05 CANTEEN B6A-05-EGLT Grounding & Lightning
Area B B6A-05 CANTEEN B6A-05-EILS Indoor Lighting System
Area B B6A-05 CANTEEN B6A-05-ELEQ Electrical Equipment
Area B B6A-05 CANTEEN B6A-05-EPST Power System
Area B B6A-05 CANTEEN B6A-05-HVCT B6A-05 for HVAC Control System
Area B B6A-05 CANTEEN B6A-05-HVEQ B6A-05 for HVAC Equipment
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area B B6A-05 CANTEEN B6A-05-HVPL B6A-05 for HVAC Plumbing
Area B B6A-05 CANTEEN B6A-05-IF&G FIRE&GAS SYSTEM
Area B B6A-05 CANTEEN B6A-05-TELE Telecomm. System
Area B B6A-06 LABORATORY BUILDING B6A-06-ARCH B6A-06 Architecture
Area B B6A-06 LABORATORY BUILDING B6A-06-EF&A Fire Alram system
Area B B6A-06 LABORATORY BUILDING B6A-06-EGLT Grounding & Lightning
Area B B6A-06 LABORATORY BUILDING B6A-06-EILS Indoor Lighting System
Area B B6A-06 LABORATORY BUILDING B6A-06-ELEQ Electrical Equipment
Area B B6A-06 LABORATORY BUILDING B6A-06-EPST Power System
Area B B6A-06 LABORATORY BUILDING B6A-06-HVCT B6A-06 for HVAC Control System
Area B B6A-06 LABORATORY BUILDING B6A-06-HVEQ B6A-06 for HVAC Equipment
Area B B6A-06 LABORATORY BUILDING B6A-06-HVPL B6A-06 for HVAC Plumbing
Area B B6A-06 LABORATORY BUILDING B6A-06-IF&G FIRE&GAS SYSTEM
Area B B6A-06 LABORATORY BUILDING B6A-06-TELE Telecomm. System
Area B B6A-07 FIRE-FIGHTING BUILDING B6A-07-ARCH B6A-07 Architecture
Area B B6A-07 FIRE-FIGHTING BUILDING B6A-07-EF&A Fire Alram system
Area B B6A-07 FIRE-FIGHTING BUILDING B6A-07-EGLT Grounding & Lightning
Area B B6A-07 FIRE-FIGHTING BUILDING B6A-07-EILS Indoor Lighting System
Area B B6A-07 FIRE-FIGHTING BUILDING B6A-07-ELEQ Electrical Equipment
Area B B6A-07 FIRE-FIGHTING BUILDING B6A-07-EPST Power System
Area B B6A-07 FIRE-FIGHTING BUILDING B6A-07-HVCT B6A-07 for HVAC Control System
Area B B6A-07 FIRE-FIGHTING BUILDING B6A-07-HVEQ B6A-07 for HVAC Equipment
Area B B6A-07 FIRE-FIGHTING BUILDING B6A-07-HVPL B6A-07 for HVAC Plumbing
Area B B6A-07 FIRE-FIGHTING BUILDING B6A-07-IF&G FIRE&GAS SYSTEM
Area B B6A-07 FIRE-FIGHTING BUILDING B6A-07-IPCS PROCESS CONTROL SYSTEM
Area B B6A-07 FIRE-FIGHTING BUILDING B6A-07-TELE Telecomm. System
Area B B6A-08 LABOURERS BUILDING B6A-08-ARCH B6A-08 Architecture
Area B B6A-08 LABOURERS BUILDING B6A-08-EF&A Fire Alram system
Area B B6A-08 LABOURERS BUILDING B6A-08-EGLT Grounding & Lightning
Area B B6A-08 LABOURERS BUILDING B6A-08-EILS Indoor Lighting System
Area B B6A-08 LABOURERS BUILDING B6A-08-ELEQ Electrical Equipment
Area B B6A-08 LABOURERS BUILDING B6A-08-EPST Power System
Area B B6A-08 LABOURERS BUILDING B6A-08-HVCT B6A-08 for HVAC Control System
Area B B6A-08 LABOURERS BUILDING B6A-08-HVEQ B6A-08 for HVAC Equipment
Area B B6A-08 LABOURERS BUILDING B6A-08-HVPL B6A-08 for HVAC Plumbing
Area B B6A-08 LABOURERS BUILDING B6A-08-IF&G FIRE&GAS SYSTEM
Area B B6A-08 LABOURERS BUILDING B6A-08-TELE Telecomm. System
Area B B6A-09 REGISTRATION BUILDING B6A-09-ARCH B6A-09 Architecture
Area B B6A-09 REGISTRATION BUILDING B6A-09-EF&A Fire Alram system
Area B B6A-09 REGISTRATION BUILDING B6A-09-EGLT Grounding & Lightning
Area B B6A-09 REGISTRATION BUILDING B6A-09-EILS Indoor Lighting System
Area B B6A-09 REGISTRATION BUILDING B6A-09-ELEQ Electrical Equipment
Area B B6A-09 REGISTRATION BUILDING B6A-09-EPST Power System
Area B B6A-09 REGISTRATION BUILDING B6A-09-HVEQ B6A-09 for HVAC Equipment
Area B B6A-09 REGISTRATION BUILDING B6A-09-HVPL B6A-09 for HVAC Plumbing
Area B B6A-09 REGISTRATION BUILDING B6A-09-IF&G FIRE&GAS SYSTEM
Area B B6A-09 REGISTRATION BUILDING B6A-09-TELE Telecomm. System
Area B B6A-10 MECHANICAL AND ELECTRICAL WORKSHOP B6A-10-ARCH B6A-10 Architecture
Area B B6A-10 MECHANICAL AND ELECTRICAL WORKSHOP B6A-10-EF&A Fire Alram system
Area B B6A-10 MECHANICAL AND ELECTRICAL WORKSHOP B6A-10-EGLT Grounding & Lightning
Area B B6A-10 MECHANICAL AND ELECTRICAL WORKSHOP B6A-10-EILS Indoor Lighting System
Area B B6A-10 MECHANICAL AND ELECTRICAL WORKSHOP B6A-10-ELEQ Electrical Equipment
Area B B6A-10 MECHANICAL AND ELECTRICAL WORKSHOP B6A-10-EPST Power System
Area B B6A-10 MECHANICAL AND ELECTRICAL WORKSHOP B6A-10-HVCT B6A-10 for HVAC Control System
Area B B6A-10 MECHANICAL AND ELECTRICAL WORKSHOP B6A-10-HVEQ B6A-10 for HVAC Equipment
Area B B6A-10 MECHANICAL AND ELECTRICAL WORKSHOP B6A-10-HVPL B6A-10 for HVAC Plumbing
Area B B6A-10 MECHANICAL AND ELECTRICAL WORKSHOP B6A-10-IF&G FIRE&GAS SYSTEM
Area B B6A-10 MECHANICAL AND ELECTRICAL WORKSHOP B6A-10-TELE Telecomm. System
Area B B6A-11 OIL LUBRICANT STORAGE B6A-11-ARCH B6A-11 Architecture
Area B B6A-11 OIL LUBRICANT STORAGE B6A-11-EF&A Fire Alram system
Area B B6A-11 OIL LUBRICANT STORAGE B6A-11-EGLT Grounding & Lightning
Area B B6A-11 OIL LUBRICANT STORAGE B6A-11-EILS Indoor Lighting System
Area B B6A-11 OIL LUBRICANT STORAGE B6A-11-ELEQ Electrical Equipment
Area B B6A-11 OIL LUBRICANT STORAGE B6A-11-EPST Power System
Area B B6A-11 OIL LUBRICANT STORAGE B6A-11-HVEQ B6A-11 for HVAC Equipment
Area B B6A-11 OIL LUBRICANT STORAGE B6A-11-HVPL B6A-11 for HVAC Plumbing
Area B B6A-11 OIL LUBRICANT STORAGE B6A-11-IF&G FIRE&GAS SYSTEM
Area B B6A-11 OIL LUBRICANT STORAGE B6A-11-TELE Telecomm. System
Area B B6A-12 STORAGE BUILDING B6A-12-ARCH B6A-12 Architecture
Area B B6A-12 STORAGE BUILDING B6A-12-EF&A Fire Alram system
Area B B6A-12 STORAGE BUILDING B6A-12-EGLT Grounding & Lightning
Area B B6A-12 STORAGE BUILDING B6A-12-EILS Indoor Lighting System
Area B B6A-12 STORAGE BUILDING B6A-12-ELEQ Electrical Equipment
Area B B6A-12 STORAGE BUILDING B6A-12-EPST Power System
Area B B6A-12 STORAGE BUILDING B6A-12-HVCT B6A-12 for HVAC Control System
Area B B6A-12 STORAGE BUILDING B6A-12-HVEQ B6A-12 for HVAC Equipment
Area B B6A-12 STORAGE BUILDING B6A-12-HVPL B6A-12 for HVAC Plumbing
Area B B6A-12 STORAGE BUILDING B6A-12-IF&G FIRE&GAS SYSTEM
Area B B6A-12 STORAGE BUILDING B6A-12-TELE Telecomm. System
Area B B6A-13 BADGE READER CONTROL SYSTEM BUILDING B6A-13-ARCH B6A-13 Architecture
Area B B6A-13 BADGE READER CONTROL SYSTEM BUILDING B6A-13-EF&A Fire Alram system
Area B B6A-13 BADGE READER CONTROL SYSTEM BUILDING B6A-13-EGLT Grounding & Lightning
Area B B6A-13 BADGE READER CONTROL SYSTEM BUILDING B6A-13-EILS Indoor Lighting System
Area B B6A-13 BADGE READER CONTROL SYSTEM BUILDING B6A-13-ELEQ Electrical Equipment
Area B B6A-13 BADGE READER CONTROL SYSTEM BUILDING B6A-13-EPST Power System
Area B B6A-13 BADGE READER CONTROL SYSTEM BUILDING B6A-13-HVEQ B6A-13 for HVAC Equipment
Area B B6A-13 BADGE READER CONTROL SYSTEM BUILDING B6A-13-HVPL B6A-13 for HVAC Plumbing
Area B B6A-13 BADGE READER CONTROL SYSTEM BUILDING B6A-13-IF&G FIRE&GAS SYSTEM
Area B B6A-13 BADGE READER CONTROL SYSTEM BUILDING B6A-13-TELE Telecomm. System
Area B B6A-14 OPERATOR SHELTER B6A-14-ARCH B6A-14 Architecture
Area B B6A-14 OPERATOR SHELTER B6A-14-EF&A Fire Alram system
Area B B6A-14 OPERATOR SHELTER B6A-14-EGLT Grounding & Lightning
Area B B6A-14 OPERATOR SHELTER B6A-14-EILS Indoor Lighting System
Area B B6A-14 OPERATOR SHELTER B6A-14-ELEQ Electrical Equipment
Area B B6A-14 OPERATOR SHELTER B6A-14-EPST Power System
Area B B6A-14 OPERATOR SHELTER B6A-14-HVEQ B6A-14 for HVAC Equipment
Area B B6A-14 OPERATOR SHELTER B6A-14-HVPL B6A-14 for HVAC Plumbing
Area B B6A-14 OPERATOR SHELTER B6A-14-IF&G FIRE&GAS SYSTEM
Area B B6A-14 OPERATOR SHELTER B6A-14-TELE Telecomm. System
Area B B6A-15 FILLING STATION B6A-15-ARCH B6A-15 Architecture
Area B B6A-15 FILLING STATION B6A-15-EF&A Fire Alram system
Area B B6A-15 FILLING STATION B6A-15-EGLT Grounding & Lightning
Area B B6A-15 FILLING STATION B6A-15-EILS Indoor Lighting System
Area B B6A-15 FILLING STATION B6A-15-ELEQ Electrical Equipment
Area B B6A-15 FILLING STATION B6A-15-EPST Power System
Area B B6A-15 FILLING STATION B6A-15-HVEQ B6A-15 for HVAC Equipment
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area B B6A-15 FILLING STATION B6A-15-HVPL B6A-15 for HVAC Plumbing
Area B B6A-15 FILLING STATION B6A-15-IF&G FIRE&GAS SYSTEM
Area B B6A-15 FILLING STATION B6A-15-TELE Telecomm. System
Area C B6B-01 Main Observation Post(South) B6B-01-ARCH B6B-01 Architecture
Area C B6B-01 Main Observation Post(South) B6B-01-EF&A Fire Alram system
Area C B6B-01 Main Observation Post(South) B6B-01-EGLT Grounding & Lightning
Area C B6B-01 Main Observation Post(South) B6B-01-EILS Indoor Lighting System
Area C B6B-01 Main Observation Post(South) B6B-01-EPST Power System
Area C B6B-01 Main Observation Post(South) B6B-01-HVEQ B6B-01 for HVAC Equipment
Area C B6B-01 Main Observation Post(South) B6B-01-HVPL B6B-01 for HVAC Plumbing
Area C B6B-01 Main Observation Post(South) B6B-01-IF&G FIRE&GAS SYSTEM
Area C B6B-01 Main Observation Post(South) B6B-01-TELE Telecomm. System
Area C B6B-02 Police Station(South) B6B-02-ARCH B6B-02 Architecture
Area C B6B-02 Police Station(South) B6B-02-EF&A Fire Alram system
Area C B6B-02 Police Station(South) B6B-02-EGLT Grounding & Lightning
Area C B6B-02 Police Station(South) B6B-02-EILS Indoor Lighting System
Area C B6B-02 Police Station(South) B6B-02-EPST Power System
Area C B6B-02 Police Station(South) B6B-02-HVCT B6B-02 for HVAC Control System
Area C B6B-02 Police Station(South) B6B-02-HVEQ B6B-02 for HVAC Equipment
Area C B6B-02 Police Station(South) B6B-02-HVPL B6B-02 for HVAC Plumbing
Area C B6B-02 Police Station(South) B6B-02-IF&G FIRE&GAS SYSTEM
Area C B6B-02 Police Station(South) B6B-02-TELE Telecomm. System
Area C B6B-03 Perimeter Observation Post B6B-03-ARCH B6B-03 Architecture
Area C B6B-03 Perimeter Observation Post B6B-03-EGLT Grounding & Lightning
Area C B6B-03 Perimeter Observation Post B6B-03-EILS Indoor Lighting System
Area C B6B-03 Perimeter Observation Post B6B-03-IF&G FIRE&GAS SYSTEM
Area C B6B-04 Perimeter Observation Post B6B-04-ARCH B6B-04 Architecture
Area C B6B-04 Perimeter Observation Post B6B-04-EGLT Grounding & Lightning
Area C B6B-04 Perimeter Observation Post B6B-04-EILS Indoor Lighting System
Area C B6B-04 Perimeter Observation Post B6B-04-IF&G FIRE&GAS SYSTEM
Area C B6B-05 Perimeter Observation Post B6B-05-ARCH B6B-05 Architecture
Area C B6B-05 Perimeter Observation Post B6B-05-EGLT Grounding & Lightning
Area C B6B-05 Perimeter Observation Post B6B-05-EILS Indoor Lighting System
Area C B6B-05 Perimeter Observation Post B6B-05-IF&G FIRE&GAS SYSTEM
Area C B6B-06 Perimeter Observation Post B6B-06-ARCH B6B-06 Architecture
Area C B6B-06 Perimeter Observation Post B6B-06-EGLT Grounding & Lightning
Area C B6B-06 Perimeter Observation Post B6B-06-EILS Indoor Lighting System
Area C B6B-06 Perimeter Observation Post B6B-06-IF&G FIRE&GAS SYSTEM
Area C B6C-01 Depot Control and Communication Building B6C-01-ARCH B6C-01 Architecture
Area C B6C-01 Depot Control and Communication Building B6C-01-EEDG Emergency Diesel Generator
Area C B6C-01 Depot Control and Communication Building B6C-01-EF&A Fire Alram system
Area C B6C-01 Depot Control and Communication Building B6C-01-EGLT Grounding & Lightning
Area C B6C-01 Depot Control and Communication Building B6C-01-EILS Indoor Lighting System
Area C B6C-01 Depot Control and Communication Building B6C-01-ELEQ Electrical Equipment
Area C B6C-01 Depot Control and Communication Building B6C-01-EPST Power System
Area C B6C-01 Depot Control and Communication Building B6C-01-EUPS UPS
Area C B6C-01 Depot Control and Communication Building B6C-01-HVCT B6C-01 for HVAC Control System
Area C B6C-01 Depot Control and Communication Building B6C-01-HVEQ B6C-01 for HVAC Equipment
Area C B6C-01 Depot Control and Communication Building B6C-01-HVFF B6C-01 for HVAC FM200
Area C B6C-01 Depot Control and Communication Building B6C-01-HVPL B6C-01 for HVAC Plumbing
Area C B6C-01 Depot Control and Communication Building B6C-01-IF&G FIRE&GAS SYSTEM
Area C B6C-01 Depot Control and Communication Building B6C-01-IPCS PROCESS CONTROL SYSTEM
Area C B6C-01 Depot Control and Communication Building B6C-01-TELE Telecomm. System
Area C B6C-02 Guard House B6C-02-ARCH B6C-02 Architecture
Area C B6C-02 Guard House B6C-02-EF&A Fire Alram system
Area C B6C-02 Guard House B6C-02-EGLT Grounding & Lightning
Area C B6C-02 Guard House B6C-02-EILS Indoor Lighting System
Area C B6C-02 Guard House B6C-02-EPST Power System
Area C B6C-02 Guard House B6C-02-HVEQ B6C-02 for HVAC Equipment
Area C B6C-02 Guard House B6C-02-HVPL B6C-02 for HVAC Plumbing
Area C B6C-02 Guard House B6C-02-IF&G FIRE&GAS SYSTEM
Area C B6C-02 Guard House B6C-02-TELE Telecomm. System
Area C B6C-03 ATK Loading Shelter B6C-03-ARCH B6C-03 Architecture
Area C B6C-03 ATK Loading Shelter B6C-03-EGLT Grounding & Lightning
Area C B6C-03 ATK Loading Shelter B6C-03-EILS Indoor Lighting System
Area C B6C-03 ATK Loading Shelter B6C-03-EPST Power System
Area C B6C-03 ATK Loading Shelter B6C-03-IF&G FIRE&GAS SYSTEM
Area C B6C-04 Heavy Diesel Loading Shelter B6C-04-ARCH B6C-04 Architecture
Area C B6C-04 Heavy Diesel Loading Shelter B6C-04-EGLT Grounding & Lightning
Area C B6C-04 Heavy Diesel Loading Shelter B6C-04-EILS Indoor Lighting System
Area C B6C-04 Heavy Diesel Loading Shelter B6C-04-EPST Power System
Area C B6C-04 Heavy Diesel Loading Shelter B6C-04-IF&G FIRE&GAS SYSTEM
Area C B6C-05 Diesel Loading Shelter B6C-05-ARCH B6C-05 Architecture
Area C B6C-05 Diesel Loading Shelter B6C-05-EGLT Grounding & Lightning
Area C B6C-05 Diesel Loading Shelter B6C-05-EILS Indoor Lighting System
Area C B6C-05 Diesel Loading Shelter B6C-05-EPST Power System
Area C B6C-05 Diesel Loading Shelter B6C-05-IF&G FIRE&GAS SYSTEM
Area C B6C-06 LPG Loading Shelter B6C-06-ARCH B6C-06 Architecture
Area C B6C-06 LPG Loading Shelter B6C-06-EGLT Grounding & Lightning
Area C B6C-06 LPG Loading Shelter B6C-06-EILS Indoor Lighting System
Area C B6C-06 LPG Loading Shelter B6C-06-EPST Power System
Area C B6C-06 LPG Loading Shelter B6C-06-IF&G FIRE&GAS SYSTEM
Area C B6C-07 Kerosene Loading Shelter B6C-07-ARCH B6C-07 Architecture
Area C B6C-07 Kerosene Loading Shelter B6C-07-EGLT Grounding & Lightning
Area C B6C-07 Kerosene Loading Shelter B6C-07-EILS Indoor Lighting System
Area C B6C-07 Kerosene Loading Shelter B6C-07-EPST Power System
Area C B6C-07 Kerosene Loading Shelter B6C-07-IF&G FIRE&GAS SYSTEM
Area C B6C-08 Gasoline Loading Shelter B6C-08-ARCH B6C-08 Architecture
Area C B6C-08 Gasoline Loading Shelter B6C-08-EGLT Grounding & Lightning
Area C B6C-08 Gasoline Loading Shelter B6C-08-EILS Indoor Lighting System
Area C B6C-08 Gasoline Loading Shelter B6C-08-EPST Power System
Area C B6C-08 Gasoline Loading Shelter B6C-08-IF&G FIRE&GAS SYSTEM
Area C B6C-09 Weighting Station B6C-09-ARCH B6C-09 Architecture
Area C B6C-09 Weighting Station B6C-09-EGLT Grounding & Lightning
Area C B6C-09 Weighting Station B6C-09-EILS Indoor Lighting System
Area C B6C-09 Weighting Station B6C-09-EPST Power System
Area C B6C-09 Weighting Station B6C-09-IF&G FIRE&GAS SYSTEM
Area C B6C-10 Depot Secondary Gatehouse B6C-10-ARCH B6C-10 Architecture
Area C B6C-10 Depot Secondary Gatehouse B6C-10-EF&A Fire Alram system
Area C B6C-10 Depot Secondary Gatehouse B6C-10-EGLT Grounding & Lightning
Area C B6C-10 Depot Secondary Gatehouse B6C-10-EILS Indoor Lighting System
Area C B6C-10 Depot Secondary Gatehouse B6C-10-EPST Power System
Area C B6C-10 Depot Secondary Gatehouse B6C-10-HVEQ B6C-10 for HVAC Equipment
Area C B6C-10 Depot Secondary Gatehouse B6C-10-HVPL B6C-10 for HVAC Plumbing
Area C B6C-10 Depot Secondary Gatehouse B6C-10-IF&G FIRE&GAS SYSTEM
Area C B6D-01 PIB Utilities & Tank Farm East Side B6D-01-ARCH B6D-01 Architecture
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area C B6D-01 PIB Utilities & Tank Farm East Side B6D-01-EEDG Emergency Diesel Generator
Area C B6D-01 PIB Utilities & Tank Farm East Side B6D-01-EF&A Fire Alram system
Area C B6D-01 PIB Utilities & Tank Farm East Side B6D-01-EGLT Grounding & Lightning
Area C B6D-01 PIB Utilities & Tank Farm East Side B6D-01-EILS Indoor Lighting System
Area C B6D-01 PIB Utilities & Tank Farm East Side B6D-01-ELEQ Electrical Equipment
Area C B6D-01 PIB Utilities & Tank Farm East Side B6D-01-EPST Power System
Area C B6D-01 PIB Utilities & Tank Farm East Side B6D-01-EUPS UPS
Area C B6D-01 PIB Utilities & Tank Farm East Side B6D-01-HVCT B6D-01 for HVAC Control System
Area C B6D-01 PIB Utilities & Tank Farm East Side B6D-01-HVEQ B6D-01 for HVAC Equipment
Area C B6D-01 PIB Utilities & Tank Farm East Side B6D-01-HVFF B6D-01 for HVAC FM200
Area C B6D-01 PIB Utilities & Tank Farm East Side B6D-01-HVPL B6D-01 for HVAC Plumbing
Area C B6D-01 PIB Utilities & Tank Farm East Side B6D-01-IF&G FIRE&GAS SYSTEM
Area C B6D-01 PIB Utilities & Tank Farm East Side B6D-01-IPCS PROCESS CONTROL SYSTEM
Area C B6D-01 PIB Utilities & Tank Farm East Side B6D-01-TELE Telecomm. System
Area C B6D-02 PIB Tank Farm West Side B6D-02-ARCH B6D-02 Architecture
Area C B6D-02 PIB Tank Farm West Side B6D-02-EF&A Fire Alram system
Area C B6D-02 PIB Tank Farm West Side B6D-02-EGLT Grounding & Lightning
Area C B6D-02 PIB Tank Farm West Side B6D-02-EILS Indoor Lighting System
Area C B6D-02 PIB Tank Farm West Side B6D-02-ELEQ Electrical Equipment
Area C B6D-02 PIB Tank Farm West Side B6D-02-EPST Power System
Area C B6D-02 PIB Tank Farm West Side B6D-02-EUPS UPS
Area C B6D-02 PIB Tank Farm West Side B6D-02-HVCT B6D-02 for HVAC Control System
Area C B6D-02 PIB Tank Farm West Side B6D-02-HVEQ B6D-02 for HVAC Equipment
Area C B6D-02 PIB Tank Farm West Side B6D-02-HVFF B6D-02 for HVAC FM200
Area C B6D-02 PIB Tank Farm West Side B6D-02-HVPL B6D-02 for HVAC Plumbing
Area C B6D-02 PIB Tank Farm West Side B6D-02-IF&G FIRE&GAS SYSTEM
Area C B6D-02 PIB Tank Farm West Side B6D-02-IPCS PROCESS CONTROL SYSTEM
Area C B6D-02 PIB Tank Farm West Side B6D-02-TELE Telecomm. System
Area C B6D-03 Chemical Storage Shelter B6D-03-ARCH B6D-03 Architecture
Area C B6D-03 Chemical Storage Shelter B6D-03-EGLT Grounding & Lightning
Area C B6D-03 Chemical Storage Shelter B6D-03-EILS Indoor Lighting System
Area C B6D-03 Chemical Storage Shelter B6D-03-EPST Power System
Area C B6D-03 Chemical Storage Shelter B6D-03-IF&G FIRE&GAS SYSTEM
Area C B6D-04 FIRE WATER PUMPS STATION (P/S 10D) B6D-04-ARCH B6D-04 Architecture
Area C B6D-04 FIRE WATER PUMPS STATION (P/S 10D) B6D-04-EF&A Fire Alram system
Area C B6D-04 FIRE WATER PUMPS STATION (P/S 10D) B6D-04-EGLT Grounding & Lightning
Area C B6D-04 FIRE WATER PUMPS STATION (P/S 10D) B6D-04-EILS Indoor Lighting System
Area C B6D-04 FIRE WATER PUMPS STATION (P/S 10D) B6D-04-EPST Power System
Area C B6D-04 FIRE WATER PUMPS STATION (P/S 10D) B6D-04-HVCT B6D-04 for HVAC Control System
Area C B6D-04 FIRE WATER PUMPS STATION (P/S 10D) B6D-04-HVEQ B6D-04 for HVAC Equipment
Area C B6D-04 FIRE WATER PUMPS STATION (P/S 10D) B6D-04-IF&G FIRE&GAS SYSTEM
Area C B6D-05 Pumps(P/S 01D 90-P-001A/B, 90-P-018A/B) B6D-05-ARCH B6D-05 Architecture
Area C B6D-05 Pumps(P/S 01D 90-P-001A/B, 90-P-018A/B) B6D-05-EGLT Grounding & Lightning
Area C B6D-05 Pumps(P/S 01D 90-P-001A/B, 90-P-018A/B) B6D-05-EILS Indoor Lighting System
Area C B6D-05 Pumps(P/S 01D 90-P-001A/B, 90-P-018A/B) B6D-05-EPST Power System
Area C B6D-05 Pumps(P/S 01D 90-P-001A/B, 90-P-018A/B) B6D-05-IF&G FIRE&GAS SYSTEM
Area C B6D-06 Pumps(P/S 02D 90-P-010A/B, 90-P-015A/B/C 90-P-016A/B) B6D-06-ARCH B6D-06 Architecture
Area C B6D-06 Pumps(P/S 02D 90-P-010A/B, 90-P-015A/B/C 90-P-016A/B) B6D-06-EGLT Grounding & Lightning
Area C B6D-06 Pumps(P/S 02D 90-P-010A/B, 90-P-015A/B/C 90-P-016A/B) B6D-06-EILS Indoor Lighting System
Area C B6D-06 Pumps(P/S 02D 90-P-010A/B, 90-P-015A/B/C 90-P-016A/B) B6D-06-EPST Power System
Area C B6D-06 Pumps(P/S 02D 90-P-010A/B, 90-P-015A/B/C 90-P-016A/B) B6D-06-IF&G FIRE&GAS SYSTEM
Area C B6D-08 Pumps(P/S 04D 90-P-021A/B, 90-P-022A/B) B6D-08-ARCH B6D-08 Architecture
Area C B6D-08 Pumps(P/S 04D 90-P-021A/B, 90-P-022A/B) B6D-08-EGLT Grounding & Lightning
Area C B6D-08 Pumps(P/S 04D 90-P-021A/B, 90-P-022A/B) B6D-08-EILS Indoor Lighting System
Area C B6D-08 Pumps(P/S 04D 90-P-021A/B, 90-P-022A/B) B6D-08-EPST Power System
Area C B6D-08 Pumps(P/S 04D 90-P-021A/B, 90-P-022A/B) B6D-08-IF&G FIRE&GAS SYSTEM
Area C B6D-09 Pumps(P/S 05D 90-P-002A/B, 90-P-003A/B) B6D-09-ARCH B6D-09 Architecture
Area C B6D-09 Pumps(P/S 05D 90-P-002A/B, 90-P-003A/B) B6D-09-EGLT Grounding & Lightning
Area C B6D-09 Pumps(P/S 05D 90-P-002A/B, 90-P-003A/B) B6D-09-EILS Indoor Lighting System
Area C B6D-09 Pumps(P/S 05D 90-P-002A/B, 90-P-003A/B) B6D-09-EPST Power System
Area C B6D-09 Pumps(P/S 05D 90-P-002A/B, 90-P-003A/B) B6D-09-IF&G FIRE&GAS SYSTEM
Area C B6D-10 Pumps(P/S 06D 90-P-004A/B, 90-P-005A/B) B6D-10-ARCH B6D-10 Architecture
Area C B6D-10 Pumps(P/S 06D 90-P-004A/B, 90-P-005A/B) B6D-10-EGLT Grounding & Lightning
Area C B6D-10 Pumps(P/S 06D 90-P-004A/B, 90-P-005A/B) B6D-10-EILS Indoor Lighting System
Area C B6D-10 Pumps(P/S 06D 90-P-004A/B, 90-P-005A/B) B6D-10-EPST Power System
Area C B6D-10 Pumps(P/S 06D 90-P-004A/B, 90-P-005A/B) B6D-10-IF&G FIRE&GAS SYSTEM
Area C B6D-11 Pumps(P/S 07D 90-P-006A/B, 90-P-007A/B) B6D-11-ARCH B6D-11 Architecture
Area C B6D-11 Pumps(P/S 07D 90-P-006A/B, 90-P-007A/B) B6D-11-EGLT Grounding & Lightning
Area C B6D-11 Pumps(P/S 07D 90-P-006A/B, 90-P-007A/B) B6D-11-EILS Indoor Lighting System
Area C B6D-11 Pumps(P/S 07D 90-P-006A/B, 90-P-007A/B) B6D-11-EPST Power System
Area C B6D-11 Pumps(P/S 07D 90-P-006A/B, 90-P-007A/B) B6D-11-IF&G FIRE&GAS SYSTEM
Area C B6D-13 Pumps(P/S 09D 90-P-019A/B, 90-P-020A/B) B6D-13-ARCH B6D-13 Architecture
Area C B6D-13 Pumps(P/S 09D 90-P-019A/B, 90-P-020A/B) B6D-13-EGLT Grounding & Lightning
Area C B6D-13 Pumps(P/S 09D 90-P-019A/B, 90-P-020A/B) B6D-13-EILS Indoor Lighting System
Area C B6D-13 Pumps(P/S 09D 90-P-019A/B, 90-P-020A/B) B6D-13-EPST Power System
Area C B6D-13 Pumps(P/S 09D 90-P-019A/B, 90-P-020A/B) B6D-13-IF&G FIRE&GAS SYSTEM
Area C B6D-14 Operator Shelter B6D-14-ARCH B6D-14 Architecture
Area C B6D-14 Operator Shelter B6D-14-EF&A Fire Alram system
Area C B6D-14 Operator Shelter B6D-14-EGLT Grounding & Lightning
Area C B6D-14 Operator Shelter B6D-14-EILS Indoor Lighting System
Area C B6D-14 Operator Shelter B6D-14-EPST Power System
Area C B6D-14 Operator Shelter B6D-14-HVEQ B6D-14 for HVAC Equipment
Area C B6D-14 Operator Shelter B6D-14-HVPL B6D-14 for HVAC Plumbing
Area C B6D-14 Operator Shelter B6D-14-IF&G FIRE&GAS SYSTEM
Area C B6D-14 Operator Shelter B6D-14-TELE Telecomm. System
Area C B6D-15 Operator Shelter B6D-15-ARCH B6D-15 Architecture
Area C B6D-15 Operator Shelter B6D-15-EF&A Fire Alram system
Area C B6D-15 Operator Shelter B6D-15-EGLT Grounding & Lightning
Area C B6D-15 Operator Shelter B6D-15-EILS Indoor Lighting System
Area C B6D-15 Operator Shelter B6D-15-EPST Power System
Area C B6D-15 Operator Shelter B6D-15-HVEQ B6D-15 for HVAC Equipment
Area C B6D-15 Operator Shelter B6D-15-HVPL B6D-15 for HVAC Plumbing
Area C B6D-15 Operator Shelter B6D-15-IF&G FIRE&GAS SYSTEM
Area C B6D-15 Operator Shelter B6D-15-TELE Telecomm. System
Area B B7A-01 PIBs/SS B7A-01-ARCH B7A-01 Architecture
Area B B7A-01 PIBs/SS B7A-01-EEDG Emergency Diesel Generator
Area B B7A-01 PIBs/SS B7A-01-EF&A Fire Alram system
Area B B7A-01 PIBs/SS B7A-01-EGLT Grounding & Lightning
Area B B7A-01 PIBs/SS B7A-01-EILS Indoor Lighting System
Area B B7A-01 PIBs/SS B7A-01-ELEQ Electrical Equipment
Area B B7A-01 PIBs/SS B7A-01-EPST Power System
Area B B7A-01 PIBs/SS B7A-01-EUPS UPS
Area B B7A-01 PIBs/SS B7A-01-HVCT B7A-01 for HVAC Control System
Area B B7A-01 PIBs/SS B7A-01-HVEQ B7A-01 for HVAC Equipment
Area B B7A-01 PIBs/SS B7A-01-HVFF B7A-01 for HVAC FM200
Area B B7A-01 PIBs/SS B7A-01-HVPL B7A-01 for HVAC Plumbing
Area SYSTEM DESCRIPTION SUB-SYSTEM DESCRIPTION
Area B B7A-01 PIBs/SS B7A-01-IF&G FIRE&GAS SYSTEM
Area B B7A-01 PIBs/SS B7A-01-IPCS PROCESS CONTROL SYSTEM
Area B B7A-01 PIBs/SS B7A-01-TELE Telecomm. System
Area B B7A-02 WORKSHOP & WAREHOUSE B7A-02-ARCH B7A-02 Architecture
Area B B7A-02 WORKSHOP & WAREHOUSE B7A-02-EF&A Fire Alram system
Area B B7A-02 WORKSHOP & WAREHOUSE B7A-02-EGLT Grounding & Lightning
Area B B7A-02 WORKSHOP & WAREHOUSE B7A-02-EILS Indoor Lighting System
Area B B7A-02 WORKSHOP & WAREHOUSE B7A-02-ELEQ Electrical Equipment
Area B B7A-02 WORKSHOP & WAREHOUSE B7A-02-EPST Power System
Area B B7A-02 WORKSHOP & WAREHOUSE B7A-02-HVEQ B7A-02 for HVAC Equipment
Area B B7A-02 WORKSHOP & WAREHOUSE B7A-02-IF&G FIRE&GAS SYSTEM
Area B B7A-02 WORKSHOP & WAREHOUSE B7A-02-TELE Telecomm. System
Area B B7A-03 DIESEL TRUCK UNLOADING PUMP SHELTER B7A-03-ARCH B7A-03 Architecture
Area B B7A-03 DIESEL TRUCK UNLOADING PUMP SHELTER B7A-03-IF&G FIRE&GAS SYSTEM
Area B B7A-04 AIR COMPRESSOR SHELTER B7A-04-ARCH B7A-04 Architecture
Area B B7A-04 AIR COMPRESSOR SHELTER B7A-04-IF&G FIRE&GAS SYSTEM
Area B B7A-05 SLUDGE FILTERPRESS PACKAGE SHELTER B7A-05-ARCH B7A-05 Architecture
Area B B7A-05 SLUDGE FILTERPRESS PACKAGE SHELTER B7A-05-IF&G FIRE&GAS SYSTEM
Area B B7A-06 SLUDGE STORAGE SYSTEM PACKAGE SHELTER B7A-06-ARCH B7A-06 Architecture
Area B B7A-06 SLUDGE STORAGE SYSTEM PACKAGE SHELTER B7A-06-IF&G FIRE&GAS SYSTEM
Area B B7A-07 INJECTION PACKAGE SHELTER B7A-07-ARCH B7A-07 Architecture
Area B B7A-07 INJECTION PACKAGE SHELTER B7A-07-IF&G FIRE&GAS SYSTEM
Area B B7A-09 GATEHOUSE B7A-09-ARCH B7A-09 Architecture
Area B B7A-09 GATEHOUSE B7A-09-EF&A Fire Alram system
Area B B7A-09 GATEHOUSE B7A-09-EGLT Grounding & Lightning
Area B B7A-09 GATEHOUSE B7A-09-EILS Indoor Lighting System
Area B B7A-09 GATEHOUSE B7A-09-ELEQ Electrical Equipment
Area B B7A-09 GATEHOUSE B7A-09-EPST Power System
Area B B7A-09 GATEHOUSE B7A-09-HVEQ B7A-09 for HVAC Equipment
Area B B7A-09 GATEHOUSE B7A-09-HVPL B7A-09 for HVAC Plumbing
Area B B7A-09 GATEHOUSE B7A-09-IF&G FIRE&GAS SYSTEM
Area B B7A-09 GATEHOUSE B7A-09-TELE Telecomm. System
Area B B7A-12 Perimeter Observation Post B7A-12-ARCH B7A-12 Architecture
Area B B7A-12 Perimeter Observation Post B7A-12-IF&G FIRE&GAS SYSTEM
Area B B7A-19 Hydroburst Room B7A-19-ARCH B7A-19 Architecture
Area B B7A-19 Hydroburst Room B7A-19-EF&A Fire Alram system
Area B B7A-19 Hydroburst Room B7A-19-EGLT Grounding & Lightning
Area B B7A-19 Hydroburst Room B7A-19-EILS Indoor Lighting System
Area B B7A-19 Hydroburst Room B7A-19-ELEQ Electrical Equipment
Area B B7A-19 Hydroburst Room B7A-19-EPST Power System
Area B B7A-19 Hydroburst Room B7A-19-HVEQ B7A-19 for HVAC Equipment
Area B B7A-19 Hydroburst Room B7A-19-IF&G FIRE&GAS SYSTEM
Area B B7A-19 Hydroburst Room B7A-19-TELE Telecomm. System
Area B B7B-01 AL-KHAIRAT POWER STATION SHELTER B7B-01-ARCH B7B-01 Architecture
Area B B7B-01 AL-KHAIRAT POWER STATION SHELTER B7B-01-EF&A Fire Alram system
Area B B7B-01 AL-KHAIRAT POWER STATION SHELTER B7B-01-ELEQ Electrical Equipment
Area B B7B-01 AL-KHAIRAT POWER STATION SHELTER B7B-01-IF&G FIRE&GAS SYSTEM