Professional Documents
Culture Documents
Design For Open Pit Mines
Design For Open Pit Mines
Haul analysis
Lead, lift increase cost – decides mode of transport Dump limits available are
Dump area 100m from mine boundary
Dump area 50 m from internal access road.
Dump area 80-100 m. from mine infrastructure
OB volumes - Final slopes
Mineable Reserves – various losses, batter, barrier etc. - dilution etc (0-1 m agains Roof,floor)
Maximum depth increases haul cost (30-40% of total cost at 1 1/2 Km lead
Estimation of Coal, OB & Stripping ratio
Rough assessment is given below
• Assuming Pit slopes of 450, the Quarry floor and Quarry surface are delineated
• Volume of Coal & OB = Average area x Average depth - (A)
• Average area = (Quarry surface area + Quarry floor area) / 2
• Average depth = (Minimum depth + maximum depth) / 2
• Volume of Coal=(Quarry floor area x Cumulative thickness of all coal seams) - (B)
• Coal in tonnes = Volume of coal x Specific gravity – (C)
• OB Volume = Coal + OB Volume (A) – Coal Volume (B) - (D)
• Stripping ratio = OB Volume (D) / Coal in tones (C)
For accurate S.R,the volumes of OB and coal are to be made seam wise
The boundaries are firmed up based on the economic stripping ratio.
Economic stripping ratio varies with:
• Average sales realization i.e. higher the quality of coal, higher the realization.
• Capital investment requirements
• Operating cost.
• Also surface constraints
Projects are likely to be economically viable upto a maximum SR indicated against the grade of coal
C. Development Sequence
-Opening the deposit – Access trench
-Box cut – To accommodate all equipment
-Mine phases – Depends on the shape of the property
-Progress of Benches
-Coal production schedules
-OB excavation schedules
Note:- Maximize inventory of coal in the initial years
-Differ OB stripping requirements as much as possible – Average
SR versus natural SR
-Income generated in the first 5 to 10 years but not remote economics will either make or break the project.
-Profits for in the future have practically no impact on the project NPV.
Each successive phase will be less profitable and the ultimate limit will be loss even after ploughing in earlier
profits.
D. Design of Access Ramp & Haul roads
Location of Access ramp is guided by the following:
1) Generally located at the minimum depth of incrop of bottom most seam – So as to reduce initial waste stripping
(unproductive work)
2) Should facilitate maximizing of internal dumping and sectional working.
3) Should be near the External dump / Coal yard / Mine service facilities etc.
4) Main haul road upto the pit limit should be planned in the beginning only.
5) Since haul costs constitute about more than 40% and tyre costs about 10% of the total mining costs,priority for
design,construction and maintenance should be given.
6) Gradient,width,drainage,curves,super elevation,base,sub base,type and thickness of top dressing should be like
that of national high ways for heavy traffic.
Design of Access Ramp & Haul roads
S.No Particulars
1 Width Should facilities two way
traffic, dozer movement,
formation of drains, lighting
arrangement (Normal width –
30m,but depends on capacity
of dumpers).
2 Gradient 1 in 16 Short ramps 1 in 10
3 Lesser number of curves
4 In flat seams of larger strike haul roads can be formed over
length the floor of the strike length
seam 5 In steep seams
5 In steep seams Haul road for Coal & OB
benches can be planned along
highwall slopes say every
30m. This will also facilitate
internal dumping
E. Pit design.
General design parameters and planning data
• Density of seams, total coal column thickness
•Thickness of partings
• Gradient
• Geological disturbances
• Strike lengths, shape of property
• Geological Reserves
• Surface constraints/adjacent habitat
• Dump yards availability with lead and lift
• Mining system, optimum mining concept
• Depth of operation, mineable reserves after various losses, OB volumes, SR
• Spoil characteristics
• Work practices in the Area
• Diggability characteristics
Pit design
As per Regulation 98 of CMR 1957
In alluvial soil etc. - Sides shall be sloped at 450 or Benched – height not more than 1.5m
Width – not less than height
In hard ground - Sides adequately benched/sloped so as to prevent danger from fall of sides
Coal - Sides shall be sloped at 450 or Benched – height not more than 3m
However, exemption can be sought from Inspectorate.
. Pit design
Overall slope of a pit depends on several factors of the pit slope:
a) Geological disturbances like faults etc.
b) Hydrological condition of strata
c) Orientation of slip planes
d) Nature of strata – i.e. hardness, material consolidation etc.
e) Depth of workings f) Design of haul roads & ramps in the highwall
g) Stratigraphy – thickness, spacing of the clay bands or other weak layers
In general for OC mines upto a depth of 200m, overall slope angle of 450 is permitted.
Working benches:
1) General
Width - 40 – 45m
Height - Generally equal to height of the boom or in some cases upto 3m above the boom height. In case of
Backhoe – digging height of machine
Bench slope - 560 to 700
2) Dragline:
Width of the cut - 60m
Height of bench - maximum digging depth
3) In order to even out the yearly OB removal quantities and the economics sometimes alternative workings and
non-working benches (around 25 m wide) are proposed.