Professional Documents
Culture Documents
Load Testing of Prestressed Concrete Transmission Pole and Its Concrete Footing
Load Testing of Prestressed Concrete Transmission Pole and Its Concrete Footing
Load testing of prestressed concrete transmission pole and its concrete footing
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by University of Sheffield - Sub Librarian on 11/15/14
Full-scale load tests on a centrihrgally spun, prestressed concrete pole installed in a reinforced
concrete footing indicate that this s t r u c t ~ ~can
r e be ~lseclfor transmission lines if some dimensional
changes are made to increase the torsional capacity of the pole to withstand broken-conductor
loading conditions. The results also show that the strength and behaviour of the pole can be
predicted analytically if the actual dimensions and propertiesof the materials are known. Strains
in the reinforced concrete footing are very low and, in this case, indicate no neetl for reinforcing
steel to resist stresses due to exterior loading. Where reinforcement is r e q ~ ~ i r efor d the control of
clxcksdue to temperature and shrinkage. it need be included only in the upper part of the footing.
de calculer I21 resistance et le comportement du pyl6ne si les dimensions exactes et les proprietks
du matkriau constitutif de ce dernier sont connues. Les deformations se sont rCveIees tres fuibles
dans le massif d e fondation en beton arme; on peut donc dans ce cas conclure qu'il n'est pas
necessaire d e prevoir des armatures P O L I ~resister aux contraintes engendrees par les charges
exterieures. Lorsque lecontr6ledes fissuresduesaux effets d e la tempe~xtureetau retrait imposc
I'emploi d'armatures, celles-ci peuvent Ptre circonscrites i la partie s ~ ~ p e r i e ude
r e la fondation.
Can. J. Civ. Eng.. 5,274-281 (1978)
[Traduit par la revue]
2 - m GROUND-CABLE ARM
7 formed bars encircled by 13-mm-diameter spiralled
STRAIN DYNAMOMETER
bars at a pitch of 15 cm, was lowered into the excava-
3 - m CONDUCTOR ARM tion. Before the placing of the concrete, the rein-
forcing cage was instrumented with strain gauges.
Soil-pressure cells were also installed at various loca-
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by University of Sheffield - Sub Librarian on 11/15/14
Strength Analysis
The pole was analysed for ultimate strength in
accordance with the basic assuniption and require-
PULL L I N E T O WINCH ment given in the American Concrete Institute (1971)
LOCATED 93m DUE
EAST OF POLE Standard 3 18-7 1 , Builclilirlg code requirements ,for
reinforced concrete. The analysis for torsional
moment capacity was based on the tensile strength
of the concrete only. For the bending moment capa-
TRANSIT
DUE SOUTH city the pole was analysed a s a tapered member with
combined axial load and bending moment. The anal-
For personal use only.
SURVE';.
RODS
SCALES 1 DIRECTION
-
For personal use only.
OF PULL
GROUND
LINE
STRAIN
GAUGES
PRESSURE 4
FIG.2. Instrumentation for load tests on concrete pole and footing.
the south 2-m ground-cable arm at the 28-rn level. Stage B comprised a combined bending and ver-
Masses of 340 kg from each ground-cable arm and tical loading sequence applied directly t o the pole a t
910 kg from each conductor arm were suspended the 20-m level. Stage B tests were performed with
in order to simulate the mass of the overhead ground masses of 910-kg suspended from the lowest con-
cables and phase conductors, respectively. The loads ductor arms. The load was applied t o the pole in
on the ground-cable arm were applied in 2.2-kN 4.5-kN increments to failure, with the load cycled
increments until failure. back to zero at the 27-, 36-, 41-, and 50-kN levels.
NOTE 277
--- THEORETICAL
For personal use only.
T E N S I L E STRAIN
TABLE
2. Coniparison of calculated and actual ultimate
moments
- -
Calculatcd Actual
Property (kN.ni) (kNm)
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by University of Sheffield - Sub Librarian on 11/15/14
LOAD
I]
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by University of Sheffield - Sub Librarian on 11/15/14
I TENSION 1 TENSION
[ I
I I
COMPRESSION ' I 1 TENSION
I I
I I
I \ - F A C E "A"
I I
I I
'/I j
1 I
I I
\ \ \\I
t TENSION
- COMPRESSION
For personal use only.
this is the load at which the curves deviate from the using the principles and practices of crack-controlled
straight-line relationship. mass concrete.
Behaviour of Footing
In deriving the theoretical strains in the footing, Design Improvement
the resistance offered by the overburden soil was The tests demonstrated that although this par-
ignored. However, the soil resistance seems t o have ticular transmission pole withstood the maximum-
reduced the strains quite significantly. From the re- shear-force design requirement given in Table I for
sults of strain measurements in the footing, rein- compact 230-kV two-circuit transmission lines, it
forcing steel for structural purposes is unnecessary withstood only 75'%,of the required bending-moment
under these particular conditions. However, some capacity and only 10% of the required torsional-
nominal reinforcement may be required, but only in moment capacity. It would appear that the torsional
the upper part of the footing, t o control cracking of moment requirement of 107 kN.m would be the most
the concrete by thermal o r drying shrinkage. The difficult to meet with a concrete pole. However, if the
percentage of such 'temperature' reinforcement, steel spiral reinforcing is installed a t a reduced pitch
which is usually lx of the concrete area, should be in both directions, the torsional capacity would be
calculated only on the outer periphery of the footing greatly improved.
as this is the only area in tension when the concrete Preliminary calculations indicated that a pole
cools initially. Although eventual contraction of the having a t o p diameter of 51 cm, a butt diameter of
interior mass might tend t o propagate the surface 81 cm and a minimum wall thickness of 6 crn would
cracks, the steel will limit their width and therefore satisfy all the design requirements. However, the
not jeopardize the structural behaviour of the foot- adequacy of any new design would need t o be con-
ing. No temperature and shrinkage reinforcement firmed by further tests, especially for torsional capa-
would be required where the footings are constructed cities.
NOTE 28 I