PCS-9700 Plant Station Monitoring System: R1 Version Modification Record
PCS-9700 Plant Station Monitoring System: R1 Version Modification Record
Archive for the first time, publishWindows with Solaris-x86 Installation packages for the two operating systems.
Version Information
rcsgraph_platform_v1.2.7_pack3
1
version number:R1.01 (2011.01)
Version Information
Application modification
Application name Whether to modify Application name Whether to modify Application name Whether to modify
Front configuration
new function
3, In pcsoptabconfig Added "User Login Effective Time" setting option,pcsoptab The operation ticket system enters within the valid time of login
You do not need to re-enter the password for permission verification, and you need to log in again after the login timeout;
5, Configmain Configuration Tool scada Set up Protection management settings, adding "soft pressure plate check" configuration option;
6, Configmain Configuration Tool scada Set up General settings, add "remote measurement dead number judging time", "Remote Letter Dead Number Judgment Time",
Function improvement
1, 61850 Front
1-1) Increase the support for general remote control;
1-2) Solve the "import 9794 icd File, loading model is slow" problem;
1-3) Support for INT64 Data type processing to solve the problem of not refreshing the electrical measurement;
2, Modify SCADA Processing flow to avoid "If there is full telesignal or full telemetry upload during remote control, it may cause slower remote control response"
The phenomenon;
3-1) When the measuring point is selected, the measuring point list will display the measuring points under this device by default;
3-2) The library filling procedure is improved, the interval and interval will be filled in the library after the device is renamed next time, and the device will no longer be reported as empty;
3-3) The data configuration tool defaults to display the common attributes of remote signaling, remote measurement, remote control, gear, remote pulse, fixed value, and five-prevention remote signaling;
2
3-4) Modify the library filling program, rename the screen interval, and update all equipment-related measuring point information in the interval. If the measuring point
description name is not in the format of "[ ]", no modification will be made; only those with "[ ]" Format, replace the content in "[ ]".
3-5) The induction type is "system information" 103 When configuring the text, it is no longer judged whether the group number of the measuring point group is 0, Other types of devices
3-6) By default, the sub-type of remote signaling "total accidents" is associated with the "total accidents" alarm group;
3-7) When setting the device model, according to whether it is 61850 The device automatically sets or cancels the communication plan;
6, The user requires the "error checking" of the remote control window, which can unlock the back-end separation and integration logic and the five prevention rules;
7, The data type of the protection management support action component is 18 Message processing;
9-1)pcsoptab Refresh part of the dynamic attributes of the five types of data: plant station, interval, switch switch, remote signal, and remote measurement in the state of invoicing preview;
9-2) Fill in "Factory Station", "Voltage level",Information such as "interval" will be automatically set according to the previously entered information when saving the ticket.
Set "factory station", "voltage level", "interval" and other information, you can also reset;
9-3) Improve operation ticket management and interval filtering options in the historical event query window;
9-4) Synchronize the functions of Lanxi's intelligent transformation toPCSIn the system
10,Online Right-click the "five-prevention input/exit" operation, use "remote control unlock" for permission verification;
12,HISImprove
12-1)modify his_lib_api middlemysql Character set setting method to avoid "mysql When the database is storing historical events, Chinese characters
12-2) Increase telemetry over-limit weekly statistics and annual statistics, electricity hour statistics and weekly statistics;
12-4) Strengthen the connectionmysql Character set, if the encoding is not checked utf8, All set to gb2312;
14, Modify the alarm sound configuration file,windows with unix The settings of the alarm sound files of the same level under the platform are consistent;
Bug repair
1, Solve the problem of "the measuring point set as the double-bit remote signal, if there is a double-bit abnormal phenomenon, the double-bit abnormal alarm will be reported again at regular intervals"
question;
2, Resolve "transponder The problem that the program will fail when the database is released;
3、 Solve the problem of "protection management will exit abnormally when importing and exporting fixed value";
4, Resolve "online When the foreground and background colors are enabled in the print settings, the print preview will exit abnormally";
5, Solve the problem of "the curve cannot display the original data, and the program is easy to exit abnormally when using the pen";
6、 Solve the problem of "the calculation formula is lost when the configuration tool is reloading data";
1, 61850 Front
1-1) The method of identifying the name of the fixed value data set includes "dsSetting";
1-2) Increase the judgment of whether the directory name of the wave file contains "/";
3
2-1) Solve the problem of slow setting speed of calling slave stations from the master station.
2-2) Added the function of the master station directly calling the protection device through the slave station
2-3) Solved the problem of expanding the band _ in the wave file name.s with_f The problem.
1、 In order to solve the problem of too large deployment package, changeMySQLThe database installation is separated from the installation package, and the deployment tool is no longer automatically installedMySQL
database;
Need to install manuallyMySQL Database, please refer to the installation guide documents of each platform for installation instructions;
1, scada_model Library mode version / internal version from 56 upgrade to 57;(Synchronous upgrade of physical libraries, logical libraries, and enumerations). Specific modification
2, wufangmdll Library mode version / internal version from 9 upgrade to 13; (Synchronous upgrade of physical libraries, logical libraries, and enumerations). Within the specific modification
1, ModifyHISAppliedhismodel Library content (including logical library and physical library),eventlogTable and syseventlogTable added "reserve"
Field.
2, ModifyMMI Appliedmmidb Library content, add "under "Application Environment Configuration"scontrolsim0/scada"recording;
3, Modify SYSMAN Applied sysinfo Library,fsvr The application is only configured in scada1 with scada2 On the node,his The application is only configured in
4, Modify sys_cfg Library,configmain System configuration "scada "Settings" added "Remote measurement dead number determination time", "Remote signal dead number determination
"Time", "Remote Pulse Dead Number Judgment Time" and "Soft Pressure Plate Check" configuration items;
5, ModifyALARMapplication alarmdef Add the "handcart displacement" alarm group to the library content,"Switch position"Accident points increase "automatically push the picture"
Settings; (available in pcsdbdef Configure in the "Alarm Settings" interface of the configuration tool)
4
version number:R1.02 (2011.03)
Version Information
baseline: rcsgraph_platform_2011-3-23
Application modification
Application name Whether to modify Application name Whether to modify Application name Whether to modify
Front configuration
new function
2-2) Add the function of "Check whether there is a corresponding report control block in the data set";
3-3) The measuring point information of the device can be in accordance with 9698G/HConfiguration text format export;
Function improvement
2, Accident alarm push screen: interval accident jump, push interval picture; factory station accident jump, push factory station picture;
3-1) Analysis 61850 When configuring the file, prompt for the non-conforming items in the configuration file;
3-4) Modified the library filling procedure to solve the problem that the library could not be filled when the equipment name was exchanged;
3-5) When modifying the operation term group, add the judgment of the same name of the operation term group;
3-6) The full scale value of the remote pulse is expanded to 2147483647;
3-7) Import 103 When configuring the text withGINAs the only criterion for finding the measuring point, it is no longer to judge whether the original name is consistent;
4, According to pt Position, modify the strategy for judging the successful line selection: After all the grounding alarms of the lines participating in the line selection have disappeared, the line selection is judged to be successful.
5, Add the configuration item of "No remote control" or "No listing" in the properties of the picture;
5
8, Permission configuration improvements:
8-2)MMI Add "modification limit" to the field , "Grounding line selection" and "Accident Recall Inversion";
8-4) The authority management library adds default roles and users according to the template provided by the project;
9, 103 When the remote signaling sub-type of the device is "action element", it can also alarm;
10-1) The version parameter is added to the interface method of opening the real-time library in the history and report applications;
10-2) Increase the statistical function that can be configured for the sampling point time period, and you can specify the time More than two months), the program statistics indicate
period (the large, small, average value and time of the specified time period in the time period;
10-3) When the power is negative, it will be counted according to the absolute value;
10-4) Add real-time daily statistical hourly sampling model and real-time statistical model;
11,VQCwithCVT Change the measuring point selection box to single point selection mode;
13, Rule file use fileserver Synchronize and update files in a way;
14, Under the category of "Numerical Values", a new graphic element of "Button Light Plate" is added, which is used for the prospective use of sequential control related "equipment state" and "operation ticket".
15, Permission management to remove the password 6 Restrictions on locking users after input errors;
Bug repair
1, Solve "After the database is released,9794 And the connected devices under it continue to report the problem of “on and off”;
3, Solve the problem of "The primitive tool exits abnormally in extreme cases after the primitive library is emptied";
4, Resolve "report The problem that users other than the super user cannot log in in the login dialog box;
3, Automatically start the five-proof check when the switch is opened and closed remotely;
Sequencing improvement
2、 Solve the problem that the sequence ticket will be lost after the interval name is modified;
PDRImprove
2, Solve the "alarm triggerPDR"The time stamp of the event message is incorrect";
1, R1.02 The standard database capacity released by default is remote messaging 2 Ten thousand points, telemetry 1 Ten thousand points
2, increaseRDBConfiguration interface;
6
3、 Add the "Expansion and Upgrade" function;
1, scada_model Library mode version / internal version from 57 upgrade to 58;(Synchronous upgrade of physical libraries, logical libraries, and enumerations). Specific modification
1, ModifySYSMANApplied sysinfo Library content in report Increase under application report_manager process;
2, ModifySYSMANApplied sysinfo Library content,relay_server Modify the "Run on Standby" attribute to "Yes";
7
version number:R1.03 (2011.06)
Version Information
rcsgraph_platform_v1.2.10_pack
Application modification
Application name Whether to modify Application name Whether to modify Application name Whether to modify
new function
3, WEB;
4, Programmable platform;
5, License verification;
Function improvement
2, 103 Front
2-1) Increase stability control network 103 Protocol plug-in protocol_103_wk_m;
2-2) Two types of "floating point" and "code value" are added to the remote adjustment command;
2-3) Modify the plug-in of the U-spec five-defense protocol to support one-piece five-defense to forward the information collected by the key to theSCADA(Golden Capital Change);
2-4)modify 103 Plug-in to receive telecontrolAGCCurve information and forwarded to the background;
2-5) If the system is configured with the external five defenses, the verification request will not be sent to the external five defenses during the sequence control rehearsal;
3, SCADA
3-1) Realize the mutual locking function between sequence control and remote control;
3-3) Modification of the remote control interface, when the application calls the remote control interface, there is no need to care about the active/standby mode;
3-5) Modify the remote control pre-check and remote control operation interface to unlock the operation ticket verification;
8
5, Grounding line selection, add 61850 Are there many distinctions when installing LD;
6、 In the operation ticket browsing window, you can query the detailed description information of the equipment separation (combination) rules; (Guangdong interface specification requirements)
7-1) When the database capacity exceeds the limit, there will be a corresponding prompt message;
7-2) When updating protection related measuring points, ifFCDAindaAttribute is empty, according toFCDADoes the data type description of the object contain (mag)
9-2)SCADA:U-spec five-proof verification, U-spec five-proof server factory address, U-spec five-proof server device address
9-3)alarm: Maintenance events will not be stored in the real-time database, maintenance events will not be stored in the history database, and maintenance events will not be processed with alarms
10, Report
10-2) Realizing report editing has nothing to do with browsing operating language environment;
11, Protection management responds to platform loading start, switch, and end messages;
12, When the dispatch number is empty, the sequence control can be remotely controlled correctly;
1, Add the configuration items of "Prohibition of listing" and "Prohibition of remote control" in the screen properties;
2, When the bypass generation occurs, the generation switch on the wiring diagram is displayed in white;
4、 When manually setting the number of remote signals participating in the back-end interlocking logic, the setting authority shall be independently verified;
5、 When the switch hangs the "Do not count switch position" card, the number of opening and closing is not counted;
6、 Added the “Manual Set Data by Locking Logic” permission in the permission management;
7, The remote control point configuration adds "remote adjustment data type" and "control exclusivity" attribute settings;
8, The setting item of "read from database" is added to the call level of communication parameter configuration data attribute;
9, The gear position and remote control have increased the multi-source setting function;
12,SCADAIncrease the dead number processing function of telemetering, telesignaling and telepulse;
13, Add a method for judging accident jump: all trip actions caused by non-remote control operation in remote control mode are judged as accident jump;
14, The signal changes position under the interval, and the photon sign flashes in this interval;
15, The alarm events in the maintenance state can be handled separately;
Hong KongETRmodify
1, InMMI On the right 9698HThe alarm information sent to the dispatcher is locked and unlocked;
3, Add the function of setting the validity period of the user password;
4, IntegrationWEBFeatures;
Jindu change
9
1, The size of the header and footer of the operation ticket printing is adjustable;
2、 When setting the name of the operation task, you can choose the scheduling number;
5, The format of the five-prevention rule verification prompt string is simplified, without plant station name, bay name or device name;
6、 Add the function of "prompt the user whether to continue to issue tickets if the status and rules check fail during rehearsal issuance";
7, The remote operation handle of the measurement and control screen is made into three states (mandatory manual, remote and synchronous hands are closed), which can be simulated during billing simulation;
8, The reclosing operation handle of the protective screen is made into four states (single, triple, comprehensive and deactivated), which can be simulated during the billing simulation;
Bug repair
1, 61850 Front
1-1) Solve the problem that "the joint debugging of the Baojia Substation Plant found that some dual position points of the device could not be reported";
1-3) Solve the problem of "Baojiabian Sifang Protection does not support pressingCO"Read model properties" problem;
1-4) Solve the "Vietnam ProjectSEL Protect data sets across multiple LD, Causing the problem of model loading failure";
1-5) Solve the "Qingdao Beizhuang Change 9794 The agent’s external manufacturer’s device cannot be remotely controlled";
2, 103 Pre-resolve "the length of the measuring point name is greater than 28 Characters, the pre-library only takes 28 Characters";
4, Solve the problem of "listing the remote signaling measurement points in the remote signaling list,online "Abnormal exit" problem;
6, Online The protection management on the Internet solves the problem of "repeat waveform information when summoning the waveform list";
10
version number:R1.04 (2011.11)
Version Information
rcsgraph_platform_V1.2.13_pack1
Application modification
Application name Whether to modify Application name Whether to modify Application name Whether to modify
new function
Function improvement
1, 103 The front bottom communication module is only connected to the backgroundSCADADevices configured in the library;
4, online
4-11) Whether the detailed attributes of objects such as equipment and measuring points can be configured online;
4-2) A new window will be launched regardless of whether the accident screen has been opened or not;
11
4-3) When multiple machines are running, the control operation can choose different machine monitoring nodes;
6, "Status" and "Processing Flag" in the property box of the measuring point realize engineering configuration;
7-1) Solve the problem of "Database configuration editing, the descriptive name of the measuring point name cannot have a'.'" problem;
7-3) Analysis 61850 Text, the enumeration object data type is determined by Long Convert toByte Types of;
7-4) The type of intelligent remote motor is added to the definition of device type;
7-5) The telemetry sampling period only displays the sampling period entries in minutes and hours;
7-6) The original "remote control locking permission" permission label description in the remote control point permission label is modified to "error verification permission";
7-8) The "Real-time Statistics Allowed" flag is added to the allowable flag of telemetry, and the default is false status;
7-9) The "Interlock Release Soft Press Plate" type is added to the remote signal sub-type;
7-10) Increase the configuration function of the action processing scheme for the gear position;
7-11) Add power factor and current fixed value area code to telemetry subtype;
7-12) Batch setting of remote control point correspondence FCDAStructure check Attribute value
8, Protection management
8-1) Automatically generate a report on the action of the stability control device;
8-2) When the stability control takes place, it can actively call the waveform file to the stability control device;
8-3)solve 61850 Device rating exceeds 255 When bar, the protection management interface can only display the front 255 Article valuation issues;
8-4) Solve the problem that when calling the southern factory to protect the fixed value, the same number of fixed values will be copied under the original fixed value and the actual value and refresh time will be displayed. The original fixed
8-5) To set the value, switch the set value area, and add the guardian verification function to the soft pressing plate;
9, 61850 Front
9-1) To solve the problem of too much remote measurement, resulting inSCADADeal with the problem of data delay;
9-2) Solving the Vietnam projectSEL protection 61850 There is no data item display problem in the model data set;
9-3) Resolve Xinjiang Hami 220kVThirteen rooms have changed, calling in the backgroundRCS9784AThe problem of unsuccessful setting of the later protection device; the reason is that the setting value of the
protection device contains a control word, and the control word has no range or dimension. When pre-calling the fixed value, the range and dimension will be called, causing the device to not report the message or
pre-failure. Modify the program, when encounteredBOOL When setting value in type or string type, the range dimension is not called in the front.
9-4) Solve background accessRCS-931BMDevice, the problem that the fault waveform (the waveform format is the Northeast Power Grid format) cannot be sent. increase
9-5) If the wrong grid fault serial number is obtained by analyzing the wave file name, the front can only accept the fault number in the fault report, and read the fault number directly from
the wave file list to ensure that the fault number and the wave file can be one-to-one correspondence;
9-6) In the wave file list sent by the new version of the device program, the file names containing the fault sequence number are not arranged in ascending order of the fault sequence number, resulting inNOF
The numbers are from big to small. Modify the pre-program, and after receiving the wave file list, it is forcibly arranged in ascending order of the fault number.
10, Alarm
10-1) Solve the problem of voice alarm;
10-2) Events can be saved even if the target folder name is available;
11, Solve the problem of independent five-prevention verification when the five-prevention verification is performed, return theOIDIt is empty, which leads to the problem of verification failure;
12, Authority management realizes the configuration of authority automatic verification control;
13-1) When the telemetry invalid is "true", the sampling is still normal;
13-21) Solve the problem of "the more the upper limit and the lower limit time are incorrect";
12
13-2)solve"Report Update history core"The problem;
Hong KongETRmodify
1、 Lock the remote control according to the interval, and the designated remote control can skip the blocking condition;
2, Realize the manual setting function of the remote control in the background (ONLINEwithALARMThe number can be set up operation);
Zuoanmen modification
2, Five defense combination name setting adds a fifth level: including custom name";
3, Simplify the invoicing, rehearsal, and execution processes in the fast sequential control mode;
4, Simplify the interaction process between the five anti-backstage and the computer key;
5、 The number of the grounding wire is displayed next to the grounding wire graphic element;
6, According to the configuration can be shown or hidden pcsoptab Right-click menu items on the interface;
7, Modified the processing method after the virtual remote letter is sent;
8、 When storing operation tickets, if it is judged that the capacity will exceed the limit, the operation tickets from a week ago will be automatically cleaned up;
10、Provide the function of operation backstep in the fast sequence control mode;
11, When the operation ticket system executes remote control steps,online show on Front, and a prompt dialog box pops up;
14,System Configuration configmain Add "online "Prohibit Sequential Control" configuration item;
15,pcsoptab When performing remote control operations,online Prompt dialog box modification;
16、Modify the intelligent alarm program for the action description of the special protective action event of Zuoanmen;
13
version number:R1.05 (2012.05)
Version Information
baseline: rcsgraph_platform_V1.2.17
Application modification
Application name Whether to modify Application name Whether to modify Application name Whether to modify
According to "Guangdong Power Grid Corporation 110kV~220kV Requirements for the standardization scheme of the man-machine interface of the substation automation system, alarms, consoles,
online, Five defenses, database configuration tools, formulas, historical sampling query and other functional modules have been modified;
2, After the system is deployed,windows with linux Add "PCSCommon Tools" folder;
3, x86 The platform provides script implementation cups Automatic installation
4, In the deployment package inittab File content adds content to realize automatic startup arp Bind
5, Automatically generate a list:1) Increase the display of telemetry units;2) Increase the cell spacing color;3) Increase keep setting;
7, Report default configuration:1) Value retention 2 Place a decimal point and align it in the center;2) The report properties default to "Horizontal Center, Vertical Center,
Print automatic adjustment";3) The default report categories are "daily reports", "monthly reports", and "annual reports";
8, windows Realized under the system sophic_stop Put include sophic_start All processes inside are stopped;
Multi-language modification
2, ModifyPCS9700R1.04 Some problems were found during the test of the English version;
14
Wind power forecast modification
2-1)inWEB Add under the application "WEBPower prediction operation" authority. This authority is verified when the power prediction system logs in.
2-2) When the power-on capacity setting is added, deleted, or modified, the password verification box will pop up, verify "WEB Modifications can be made only after passing the power prediction operation
authority.
3, Add wind power forecast homepage, photovoltaic power forecast homepage, add background replacement function on the homepage
4, Hide navigation menu items for which the user does not have relevant permissions;
5, Provide configuration method, you can set the home page to jump after login.
1、 After the system is upgraded, keep the language environment settings of the system before the upgrade;
2、 After the upgrade is completed, the button in the lower right corner of the interface changes from "Cancel" to "Done".
3, Resolve "Web Server-side pcsonlined_server "Exit abnormally after running for a long time";
1, Front
1-1)in FE_CONFIGIncrease-to-manyRTUThe display;
1-2) The measured quantity is not sent according to the original value, it needs to be multiplied by the coefficient 3413;
1-3) The capacity of the front storage can be based on FE_DATA_MODEL Configure environment variables (expandable to 65535*2);
2, Protection management
2-1) Solve the problem of abnormal exit of "fault record" retrieval in protection equipment management;
2-1) The plant station tree list on the stability control management interface can be automatically sorted by plant station keywords;
2-3) The name of the waveform file plus the waveform failure time is convenient for viewing;
3, hisalam -wSupports the retrieval of stability control device action events, first sorted by device classification, and then sorted by time;
750kVBazhou change
1, User requirements: When the remote control verification is successful, it is necessary to distinguish on the interface whether it returns success without the five-proof verification or after the five-proof verification.
1、 When the sequence control operation is changed from single-bracket running mode to double-bracket running mode, a dialog box will pop up to let the user select the interval to be operated;
2, In pcsoptabconfig Add the configuration item "Prompt the user when handling non-conforming items";
3、 When the sequence control process definition is saved, if it is detectedSCDefine If the number of records in the table exceeds the capacity limit, the temporary sequence control process definition is automatically deleted.
1, Before remotely controlling the primary device in the background, send a control command to the video device to make the video camera move to the corresponding primary device. Video equipment and
15
1-1) According to the requirements of the statute: add the following attributes to the device attribute configuration: the line number the device belongs to, the operating status of the device (0,1,2),
CPU Number,CPU1 Serial number,CPU1 description,CPU2 Serial number,CPU2 description,CPU3 Serial number,CPU3 description,CPU4
Serial number,CPU4 Description; add the following attributes in the line attribute configuration: line number, line switch number, positive sequence capacitive reactance, zero sequence capacitive reactance,
CT Transformation ratio, secondary side large load current; remote measurement adds the following attributes: secondary large value, secondary small value.
1-2) Summon the fixed value configuration information from the device, and then publish it to the physical library;
1-3)increase trans The configuration function of the database under the application is used to forward the device information and the measurement point information under the device
2-2)dbsec\pdbsecs\trans Add under the catalog tans App corresponding relaytransmdl Physical library
2-3)dbsectest\pdbsecs\trans Add under the catalog tans App corresponding relaytransmdl Logic library
2-1) Adopted on the communication 104 According to the protocol, a control agent is deployed in the third safe zone, and when a control request from the master station is received, the request is forwarded to
2-2) A control server is set up in the first security zone. After receiving the control command from the third zone, it undergoes legality verification and control, and the control result is
transmitted to the third security zone through the forward isolation device
2, Modify transponder The program forwards the remote control commands sent by Telecontrol to the system in the second area;
Hong KongETRmodify
1, In "pcs9700\deployment\bin\plat"Added under the directory pcsclient(Hong Kong ETR Client tools). Realize retrieval by time
Specific plantSOE, Retrieve waveforms, one-click access to a specific plant web Web page, one-key remote login, user management functions.
Other modifications
1-1) The total number of telecommuting measuring points exceeds 65535 in the case of,scada When starting to initialize the remote signal, if the range of the counter is exceeded, it may
enter a continuous loop, resulting in scada used internal memory 100% 1-2) The electrical measurement of Yaomai and the corresponding statistical fields need to be modified to double
1-3) If the new refresh time of the measuring point is incorrect, it may cause the calculation of the time in the real-time statistics module scada The problem with the fault
1-4) Remote control operation while publishing the database may lead to scada drop out;
2-1) Added the function of different machine monitoring and verification equipment;
2-2) Click Cancel in the monitoring window to notify the remote control node and exit the remote control;
2-3) When the mouse moves to the photosensitive point, when the line color or background color of the photosensitive point is red, the word color on the photosensitive point changes to yellow; otherwise, the
3, Grounding line selection is based on automatic correlation of measuring points, adding manual correlation I0,I50, Trial jump remote control point function.
4, Screen modification
4-1) The dialog boxes of remote control and number setting are added with custom size and position functions, and the default can be restored;
4-2)Correct online The operation interface is modified by plug-in to adapt to different regions (Guangdong, Shanghai, Beijing) and a variety of applications (sequence control, wind
Electricity, etc.);
5, Five-prevention operation ticket
5-2) When the five preventions are activated, not only must all the five preventions be locked, but also all the non-five preventions must be unlocked;
5-3)GridDll Plug-in upgrades, rare characters can be displayed in reports and five-proof operation tickets;
16
5-4) Solve the problem of "five prevention procedures sometimes die when unreviewed votes are saved as reviewed votes";
5-5) When editing an automatically added prompt operation step, you can only modify the description of the single step operation step.
5-6) Solve the problem of "logging out over time during editing and unable to log in again";
6-1) Realize the function of counting the number of actions of switches, switches, gears, and ordinary remote signals; (Vietnam project)
6-2) When the data is invalid, no history storage is performed, and when the size value is counted, only the valid data is counted, and the dead number is ignored)(green .
Haigermu 250MWGrid-connected photovoltaic transformer)
6-3) Add the function association of remote pulse start and stop code at any time; (Taishan Power Plant)
6-4) Add the export report synthesis to excel Functions in the template; (Taishan Power Plant)
6-5) The anti-shake function is added to the sampling program. If the mutation exceeds a certain range, the last sampled value will be saved; (Taishan Power Plant)
7, Configuration tool
7-1) Modify the library filling program, the group name of the measuring point and the description name of the measuring point under the synthetic information when generating the plant station are the same as those when generated by the configuration tool;
7-2) The input format of the lock number in the five defense library configuration: co-creation 26 Version/27 Version is 16 Base 4 Bit; Nari protectionUSBThe version of the computer key is 10
7-4) Analysis 61850 In the process of configuring the text, judge the data set FCDA When it is repeated, add the right LDJudgment
7-5) Specify the corresponding voltage level under the exported transformer coil; the exportedCIMThe model distinguishes series and parallel capacitive reactors. (Jiangxi ultra high pressure);
8, Intelligent alarm configuration tool to modify the program to meet the secondary model update requirements;
9-1)solve"app_server "Part of the output log does not match the actual situation";
9-3) Zhuhai, Guangdong 220kVPiano rhyme change VQCDealing with problems found in the acceptance process
9-4) To increase the capacitor timing switching functionVQCSpecial version, need to add related fixed value node synchronization function;
9-5)perfectVQCForwarding information;
10-1) System configuration library supportCS Open mode; add offline access interface; do not modify the database content in offline mode;
10-2) In the configuration library mmi Increase under the group bShowCtrlMode Configuration item, Boolean type, Chinese name: control sub-remote control type optional, default
think false.
10-3) Solve the problem of "If special characters are included when adding users to the rights management tool, it may cause a crash";
11,61850 Front
11-1) Solve the problem of "Siping Primary Digital Transformation and Transformation Station in Jilin Province continues to receive waveform files, which seriously affects operation monitoring";
11-2) Solve the problem of "Indonesia test some manufacturersSOEuseURCB"Send it, the background can’t call the police" problem;
11-4) According to the device's "recording automatic summoning allowed" mark, judge whether it is necessary to automatically summon the waveform. When manually summoning the waveform, it is not affected by
13,AGC
13-1) QinzhouAGCPlan curve, increaseASDU137 Support, the transmission mode is modified to the inflection point transmission mode;
14, Increase the analog screen communication plug-in with Hangzhou Taoyang Technology tykj;
15-1) "Clear confirmed events" in the right key menu of the alarm window will cause the alarm events sent later to be confirmed and not displayed.
17
15-2) The translation of the "Alarm Action" of the remote signal displacement event on the English version of the "All Types" tab is inconsistent with the translation on the "Remote Signal" tab.
15-3) The Spanish version of the alarm setting window has no English translation;
15-4) During an avalanche test, if a large number of alarm events are generated instantaneously (more than 3000 Article),alarmserver Call the database interface to store
the alarm event, which will exceed sophicnet The large length limit of network packets makes it impossible to store;
15-5)in alarm_mmi On the interface, press the device to retrieve the alarm event, the remote signal type is switch, knife switch displacement event can not be retrieved;
In the installation package scompress Compression/decompression tool decompression pcs9700_package\pcs9700 Compressed package, will install the directory in the package
4.
1. in"deployment\etc\alarm"Added under the directoryAlarmSetting_gd.xml; (If the upgraded system adopts the Guangdong interface standard,
2. in"deployment\etc\his"Added under the directory privconfig.csv;(Hong Kong ETR The client tool is dedicated and needs to be changed manually when upgrading
new)
3. in"deployment\etc\dms"Added under the directory report_manager.sh; (This script is used to pick up the report service program,
Update "deployment\etc\sysman"After the directory, execute deployment\bin\plat Under the directory sysmanupdate Program, upgrade
Update "deployment\etc\dms"After the directory, execute deployment\bin\his Under the directory hisupdate Historical subsystem upgrade tool,
18
version number:R1.05P001 (2012.05)
Bug repair
1, Modify the configuration tool, in the generation IEC61850 Device, when updating the protection telemetry and protection remote signaling information under the device, remove the extra LDname;
2、 Modify the configuration tool to display the device type correctly when importing the device model;
19
version number:R1.05P002 (2012.06)
2-1) Solve the problem of "data loss due to historical connection failure";
2-2) Optimize the dual-machine dual-database connection mechanism, which can actively reconnect when the historical connection is invalid;
2-3) Provide a mechanism to synchronize the two historical databases with each other in a dual-database configuration;
2-4) Set the correct user name and password during initialization. When the application reconnects to the database, as long as the database service is running normally, the correct user name and password can
be used to connect.
2-5) The error code returned by the database is judged and classified. One is the operation that should be discarded immediately (for example, field error, table name error, primary key
conflict), and the other is the operation that needs to be cached and redone (for example, connection interruption) , The primary key does not exist when the primary key is deleted).
3, usermgrapi The module solves the problem of "program exception caused by empty string and null pointer";
4, Solve "Zhejiang Yueqing Sidu Transformation site feedback 9211BAfter the computer key is operated on the spot, the operation ticket will be returned, and the operation ticket system will pop up.
After the "OK" button on the "All Project Operations Completed" dialog box,pcsoptab sometimes core"The problem;
20
version number:R1.05P003 (2012.06)
1, rdb_daemon_newImprove the exception handling method, even if the exception file is read, normal operation can be guaranteed;
2, Software license verification is improved, and the loop test is solved (10000 Times), possible memory leaks;
3, Solve the problem of "the system management accidentally kills the process of timing report status due to time backflow";
4, Solve the "Wenzhou, Zhejiang 500kVSidu change feedback:Online "Slow font display and screen opening" problem;
5, Solve the problem of "The accident recall function cannot be demonstrated normally";
7, Roger thatRCS9200 After the remote control request, you can specify on which machine the "remote control request" operation window will pop up;
8, Solve the "Wenzhou, Zhejiang 500kVFeedback from Sidu Substation: Topological abnormality after inverted bus operation (double bus system)" problem;
9, Solve the problem of "when the interlocking conditions are not met,scada The parsing device returns the failure reason abnormal "hungry problem";
10, To resolve the "adopt ut When the five-proof server performs the five-proof check, after the remote control is successful, it prompts the question of an empty bracket in the string;
12,modify hisupdate The statistical conditions for the statistics of the switch day.
twenty one
version number:R1.06 (2012.10)
Version Information
pcsgraph_platform_lab_v2.0.1_test2
Application modification
Application name Whether to modify Application name Whether to modify Application name Whether to modify
Platform update
1, Graphic platform fromR1 Upgrade toR2,mmidb Library mode version from 20 Rise to twenty four;
Package update
1, MySQL Database installation package update (increase automatic backup configuration,windows Installation package compatible 32/64 Bit Operating System & Multilingual
2, tomcat Installation package update, release tomcat _win7-linux-solaris_r1.06.zip Version (if not needed at the project site web Features,
No need to install);
new function
2, Develop the information retrieval function in accordance with the requirements of the Guangdong interface specification, in bin\alarmAdd under the catalog info_search;
3, Yunnan Chuxiong Transformation Science and Technology Project: Sequence control adds "uploading fixed value" and "checking fixed value" operations;bin\relayAdd under the catalog relay_scontrol;
Function improvement
1、 Due to the upgrade of the graphics platform, the code corresponding to the application layer is updated synchronously;
2, Improve the report control, can export the formula information excel file;
3, SimplifyVQCCapacitive reactor timing switching settings: only need to configure the main transformer, capacitance, and time;
4, Unified Statute Plugin IDAmended to 7000 Below, avoid causes IDNumber is greater than 7000 Cooperating with the communication layer plug-in;
5, Modify 103 The front plug-in identifies the "external failure" group, and treats the "external failure" group as the "operational alarm" group. (Xinjiang stable
control)
twenty two
6, sysinfo Remove from library archive report Under application report_manager;
7, 61850 Front
7-1) For telemetry f with i Parse separately
7-2) Due to the agent LDThe name of may include, so change the comparison agent device from include to compare;
7-4) For shaping the amount of remote pulse, increase the long Type compatibility;
8, Configuration tool
8-1)Add the option of "Add logical node description name" in "Measurement point extraction principle", import 61850 When configuring the file, from du or desc
The extracted description name is preceded by the logical node description name as the measurement point description name, separated by a space.
8-2)in configmain in"SCADAThe configuration item "Prohibit multiple people from maintaining the database at the same time" has been added in "Settings";
9, Protection management
9-1) Different encoding methods can be displayed according to different language environments, but the current encoding method cannot be adaptively obtained;
9-2)System Configuration relay Increase in group settingprecision Configuration items,61850 The fixed value and parameter display the number of decimal places according to the configuration;
10-1) Added the function of user-defined operation ticket name in the definition of sequence control process. User-defined operation ticket name can be displayed during ticket adjustment;
10-2) The "Five-prevention chain" menu is added to the definition of the sequence control process, and users can customize the switch-on and return of the five-prevention function;
2, Resolve "relay_server The communication of the device is abnormal during startup, so the fault information and disturbance data describe the description of "cannot be called" at this time.
problem;
3, relay Increase the fault briefing archive function and record detailed log function;
4, Real-time alarm adds the functions of opening and analyzing waveform files and viewing fault briefings;
5, Historical event retrieval tool (hisalarm) Add the functions of opening wave files and viewing fault briefings;
6-1) After the database is released, it often happens fe_server versus relay_server The problem of inability to exchange data between
6-2) After the database is released, it sometimes appears fe_config Unable to start phenomenon;
BUGrepair
1-1) Solve the problem of "deleting the operation ticket in the operation ticket management core"The problem;
1-2) Solve the problem of "Operation ticket printing, when the operation statement is displayed on the entire line (the last character is incomplete), there will be duplication of the operation
statement";
1-3) Solve the problem of "When editing an operation ticket, move a certain group of operation steps up and down and save it. core"The problem;
2, Solve the "Hong KongETRClient tool pcsclient When setting the factory site history database name to be empty, it will core"The problem;
3, Solve "upgrade toR1.05 After, with 103 Device communication, the original configured telemetry value is displayed abnormally";
In the installation package scompress Compression/decompression tool decompression pcs9700_package\pcs9700 Compressed package, will install the directory in the package
twenty three
Overwrite the corresponding local directories, including:
1. Update "deployment\etc\dms"Catalog, add blankmodel.xls with eif.jar; Update "deployment\etc\sysman"Manually modify the
2. local directory"etc\fe"Under the directory fe_config.xml In the configuration file ytwf Plug-in number. Will "<PLUGIN ID="7517" />
twenty four
version number:R1.06P001 (2012.11)
Version Information
baseline:pcsgraph_platform_lab_v2.0.1_test2
Package update
1, Factory station soe Alarm information and wave file information transferMicrosoft SQLServer database
2-2) Add remote control signal locking and remote control signal unlocking on the two-dimensional meter;
2-3) Modification of the remote operation function of the right-click menu and the remote signaling properties dialog box;
3、 Modify the configuration tool to display the device type correctly when importing the device model;
6, Real-time alarm
6-2) List of unreturned signals, supporting remote signal setting and freezing functions;
7, After the user logs in, if there is no operation for a long time, the background can automatically log out.
4, etc\sysman Catalog update, need to be executed sysmanupdate Command to update authority database and system configuration database;
25
version number:R1.07 (2013.01)
Version Information
pcsgraph_platform_lab_v2.0.2
Application modification
Application name Whether to modify Application name Whether to modify Application name Whether to modify
Focus
1, According to the requirements of State Grid Security Evaluation,R1.07 The encryption algorithm for user passwords has been upgraded. Upgrade toR1.07 version Must be executed
Package update
1, tomcat Installation package update, release tomcat _win7-linux-solaris_r1.07.zip Version (if not needed at the project site web Features,
No need to install);
2, Data identification
3, PMUAccess
4, Smart invoicing
1, Solve the problem of "the screen sometimes becomes garbled when remote control";
2, Solve the problem of "Baojia change accident sound does not call the police";
3-21) When the backup node is not online or fails, the corresponding display information will be given during backup;
3-3) When restoring, the resource file is designated as the backup folder, and there is no need to select the file under the folder;
3-4) Record during backup: operating system, program version number, commercial library version, backup time;
26
3-5) Automatically created by the restore tool data An empty directory, which needs to be created manually when solving the restoration data The problem of the empty directory.
1, Solve the problem of "after setting the'manual call fixed value',relay "Exporting the fixed value abnormal" problem;
3, Sequence control rehearsal adds the function of manually setting the equipment state;
6-1) After the rehearsal is successful, a prompt dialog box will pop up, and the user will enter the running state after confirming;
6-2) Provide configuration items, sequence control operation can be performed without rehearsal;
8, PMUAccess
9, security audit
9-1)alarm_mmi The "Security Audit" alarm item definition was added to the "System Management" alarm group of the library;
9-2) The encryption method of user password is changed from the original simple encryption method toAESEncryption;
9-4) Audit function enable switch:sm_system_config sysset group security item(bool Types of)
9-5) Increase the verification of password complexity. (The length of the password must be greater than six digits, and it must be composed of uppercase and lowercase letters and numbers)
9-6) If the user permission verification fails, the corresponding alarm event will be generated
9-7)3 The password verification dialog box is automatically closed if the user password fails to be entered for the second time
10-1) Increase the configuration of the pre-application identification to which the device belongs;
10-2) Increase the threshold setting of automatic clearing of telemetered values when telemetering-related telesignaling is abnormal;
11,SCADA
11-1) The time stamp is sent to the device that records the telemetry data;
11-2) Improve the sudden change alarm function of remote measurement: increase the delay judgment when the sudden change alarm occurs.
11-3) Improve the real-time statistics function of telemetry, which can carry out real-time statistics of the telemetry in a specified period;
12-1) Added statistical models: primary equipment remote control statistics, primary equipment split and combined statistics
12-2) Increase the remote measurement statistics data source selection function, the optional sampling value and real-time statistics value are the statistics data source.
1-1) After downloading the computer key, all lock operations are allowed;
1-2) Solve the problem of "multiple pre-shows wrong after ticket issuance";
1-3) When the rehearsal ticket is issued, if the device is in an abnormal state, an inspection state, a shutdown state, or a communication abnormal state, the rule verification fails;
1-4) Solve the problem of "When multiple tickets are operated at the same time, a certain ticket that has not yet been executed will occasionally terminate the operation";
1-5) After the operation ticket is executed, a delayed confirmation dialog box pops up to remind the user that the operation ticket has been executed;
1-6) In order to avoid misoperation by the user, the step loading of the operation ticket is changed from double-click to single-click;
1-7) Simplify the operation process, and execute it directly after selecting "Execute Operation Ticket" in the operation selection dialog box;
1-8) Solve the "in pcsoptab “The layer cannot be switched automatically after switching the screen through the photosensitive point” in the problem;
1-9)solve"pcsoptab The maximum number of running instances is set to 1, But can actually run two instances" problem;
27
1-10) Optimize the operation process of multi-ticket execution;
1-11) The online five-prevention unlock logic considers the situation of getting on and off the vehicle;
2, Sequence control
2-1) During the rehearsal of the sequence control server, the upper and lower carts can be shifted simultaneously;
2-2) Solve the problem of "cannot unlock the handcart when performing remote control steps";
2-3) Refresh the dynamic attributes such as the device communication status in the simulation library when the rehearsal issuance;
3, Edit the screen to delete the connection line arrow style setting;
1, Solve "After the database is released, it often happens fe_server versus relay_server The problem of data exchange cannot be carried out between them;
3, Configuration tool update 103 After configuring the text, synchronize the corresponding measuring point name under the protection measuring point group;
1, The electric railway protection device displays the fault data when tripping, the current (primary value) and voltage (primary value) at the time of the fault in the background alarm box , Hinder
Iran Project
1、 Solve the problem of "In English language environment, the dialog box of report data source selection displays Chinese information";
Yunnan Chuxiong changes the technology project of the automatic area code and checking the value of the isolated island method
1, pcsoptab When the sequence control operation ticket is executed, the sequence control fixed value check result can be displayed
2, pcsoptab After startup, the typical operation ticket can be automatically opened according to the parameters
Other modifications
1, Add configuration items refreshpermit. The protection management interface displays and hides the refresh button according to the configuration;
2, Five defenses
2-1) Optimize the processing process of the computer key return operation steps;
2-2) The baud rate of the serial communication module can be set to 115200;
3, Console
3-1) English version entry archive;
4, The background grounding line selection program adds the line selection result to the dispatching function;
5, Configuration tool
5-1) When the configuration tool performs data verification, check whether the description name of the same type of measuring point under the device is duplicated. If there is duplication,
5-21) The formula module is merged with the formula module used in the wind power monitoring system and wind power centralized control;
5-3) Import 61850 When the configuration file generates the measuring points, it is necessary to traverse the measuring points of the entire device to confirm whether the measuring point with the same reference name already exists.
5-6) When importing the configuration text, import the fault information and disturbance data to explain the measurement point information in the form of fixed value;
5-7) The requirements of the Ladong transformation: the detailed model configuration, software version configuration andCPUVersion configuration function;
28
5-8) Solve the problem of "Incomplete display of measuring points when switching between measuring point groups of different types of devices in the configuration tool";
5-9)increaseEquipmentMax val Configuration items to solve the problem of too many devices at one time when filling the library;
5-10) When filling in the library, no longer ignore the space in the object name string in the picture file, and enter the library according to the actual;
5-11) When adding virtual measuring points under the synthetic information of the configuration tool, if the number is greater than 255 Automatically generate a new group;
5-131) The real-time statistics permission flag is added to the remote signaling permission flag, and the statistical period can be set;
5-15) Analysis 61850 File, get FCDAIn the case of data attributes, if the length is too long, a relationship is established and used to express longer content
alone;
5-16) Add report communication parameter configuration on the report control block configuration page, you can set the enable mode of the report control block and the report control block
Correspondence name
7, 61850 Front
7-1) To increaseCURVETypes of setCharact Processing
9-1) Historical sampling adds to telemetry: current value, invalid value, Big value, Big moments, Small value, Small value moment, average value,
The relevant active power at the moment of high value, the relevant active power at the moment of small value,
Relevant reactive power at the moment of great value, Relative reactive power at small value moments, large value moments
Engrave the relevant current, and the relevant current at the moment of small value. Telesignalling:0,1,2,3 Sampling of the number of status changes and duration attributes, and historical
9-4) Solve the "Report exportExcel When the value is very large double Type data will lose accuracy" problem;
9-5)modify his The way of verifying the database filling improves the efficiency of verifying the database filling;
10,multi-language
10-2) The historical adoption of the solution "The local time zone is-4:30, If the storage period is selected 1 Hour, historical data cannot be stored on the hour" problem;
29
[Files that need to be updated manually during the upgrade process]
In the installation packagemanual update Down etc with dbsec The directory covers the local corresponding directory, including:
3. etc Add under dataident with remotebrows Configuration directory; "etc\dbtools"Added under the
5. Update sophic Under application dbiotemp Physical library; (add switch and grounding line selection search path configuration)
Update "deployment\etc\sysman"After the directory, execute deployment\bin\plat Under the directory sysmanupdate Program, upgrade
Update "deployment\etc\dms"After the directory, execute deployment\bin\his Under the directory hisupdate Historical subsystem upgrade tool,
1. Added "Security Audit", "User Login", and "User Logout" alarm items under the system management alarm group; Newly added "Data
2. Identification Results" alarm group, including "Data rationality detection" and "Bad data detection" alarm items;
30
version number:R1.08 (2013.04)
Version Information
pcsgraph_platform_lab_v2.0.3
Application modification
Application name Whether to modify Application name Whether to modify Application name Whether to modify
Package update
1, tomcat Installation package update, release tomcat _win7-linux-solaris_r1.08.zip Version (if not needed at the project site web Features,
No need to install);
1, Equipment management;
3, bridge;
4, Multi-site configuration;
1, increase fe1 The application realizes the front access function of the integrated application server of the integrated monitoring system;
2-1) Solve the problem of "reporting control block caused by publishing database after batch setting of report control block propertiesEntryIDCleared 0"The problem;
2-2) Solve the problem of "The alarm configuration page is empty after the configuration tool is reloaded";
3, Solve the problem of "After the background network switch restarts, the monitoring system alarm events cannot be confirmed";
4, Record the system time synchronization success/failure information to sysinfo In the library, it can be used for interface display;
1, Linux Operating system supportingA4 The recommended model of black and white laser printer isHP LaserJet P2035;
2, Solve the problem of "abnormal communication between Baofeng Energy's on-site monitoring background and the five-proof analog screen";
31
Other modifications
1, 61850 Front
1-1) Can be handled correctly doName for stVal Telemetry
1-2)in LDOnly under dsParameter When, the front can also generate a fixed value control block model;
1-3)CorrectBRCB The report does not carry out the redundancy check of the submitted time, and passed entryIDEliminate redundant messages;
1-4) Increase the file record list and improve the function of calling general files;
2, Power prediction
2-1) Add the calculation functions of the root mean square error, average absolute error, and correlation coefficient of short-term forecast and ultra-short-term forecast results, andweb
In the statistical query on the page, select the time interval and display it by day or month;
2-3) Modify the calculation method of short-term forecast and ultra-short-term forecast accuracy;
2-4) Solve the problem of “the forecast result file cannot be generated when the time synchronization is abnormal, that is, when the time synchronization is much ahead of the current time”;
3, Programmable platform
3-3) To meet the requirements of Shanghai Shidongkou Second Power PlantVQCSpecial function requirements, added on the programmable platformVQCApplication script
4-1) Customize the format of the scenic spot before the upper/next page and the format of the scenic spot before the upper/lower ticket number;
4-3) Solve the "co-creation 26 The problem that the execution steps of the full remote control operation of the computer key is abnormal"
4-4) Add the function of manually setting the page serial number by the user before printing the operation ticket;
5、 Sequential control solves the problem of "the dispatch number verification error when there is no switch switch under the interval of the sequence control process definition";
6, Database configuration
6-1) Analysis 61850 Priority reading when configuring filesDescription The content is used as a description of the measuring point;
6-2) The remote measurement object adds the integration power allowable mark setting function and the related integration power setting function;
6-3) Adjust the data type of the "delay alarm" attribute of the remote signaling point as short;
7, The formula solves the problem of "the five prevention rules cannot be derived";
8, Protection management solution "Foshan 110kV When Xincheng changed into an avalanche experiment, the action signal SOE It’s more than ten seconds away from the remote signal displacement time"
problem;
9, Recall the accident to solve the problem of "section import error and inversion time jump";
10-2)solve"102 The problem that the protocol plug-in cannot send power prediction data after the channel is interrupted and restored;
11、The report adds to automatically update the measuring points according to the pathOIDFunction
12, Screen
12-1) Solve the problem of "The telemetry foreground color setting is invalid";
12-2)online When performing the alarm confirmation operation in this picture, add the foreground of the current screen oid Judgment whether it is valid or not, the alarm confirmation is
12-3) When different nodes remotely control the same object, the remote control dialog box on the node that initiated the remote control prompts an error, and the remote control is terminated; the remote
control can continue on the node that initiates the remote control first.
12-4)online Execute sequence control operation on the computer, increase the wait for execution timeout judgment, the execution button will be grayed out after the timeout, and the sequence control ends;
13,VQC
13-1) Set the remote control execution life cycle, and clear the remote control that cannot be sent during the life cycle to prevent the remote control channel from being blocked;
32
13-2) According to the requirements of the Beijing Bureau, in the case of parallel operation of main transformers, the main transformer that needs to be adjusted can only switch the compensation equipment under the interval of the main
transformer, but cannot switch the compensation equipment under the interval of the parallel main transformer. The Beijing large and small string anti-matching switching capacitor model is also compatible with the above requirements;
14,CVT Solve the problem of "abnormal alarm confirmation time timer failed to return when the start condition is not met";
15,SCADA
15-1) The remote measurement adds the function of integrating electricity;
15-2) Ruoyaoxin BofSOEThe signal is calculated by the formula to trigger the synthetic remote signalAThe deflection, thenAUse of the time scale for the displacement alarmB of
SOE Time scale; Ruoyao letter B The total remote signal or artificial setting of the number triggers the synthetic remote signal through formula calculation A The deflection, then A 'S conjugation
Use of warning time scaleB The remote signal displacement time scale;
15-3) Solve the problem of "The number cannot be cancelled after the remote pulse is manually set";
15-4) Solve the problem of "defects in the judgment of the number of remote pulse deaths";
15-5)scada The number of front channels in the library is from 16 Expanded to 512;
15-6) Solve the problem of "the storage of accident recall messages is defective";
18, Warning pair scada_model The access method of the library is changed from tight coupling toC/S;
19, The backup and restore tool solves the problem of "Chinese characters are still displayed on the interface in an English environment";
4. increase state App corresponding statemdl Logical library and physical library;
33
version number:R1.09 (2013.08)
Version Information
pcsgraph_platform_lab_v2.0.4
Application modification
Application name Whether to modify Application name Whether to modify Application name Whether to modify
Package update
1, tomcat Installation package update, release tomcat _win7-linux-solaris_r1.09.zip Version (if not needed at the project site web Features,
No need to install);
1, VQCThe action record of the debugging terminal interface adds the information of the target voltage and the upper and lower limits of the target reactive power;
2, The anti-error locking rules of the station control layer and the bay layer can be compared;
3、 When checking the five prevention rules, it can display the specific rules that are satisfied and not satisfied;
4, Solve the "main-standby machine switching test, in the case of system exit and power cut off,SOEcorrect,COSMany" problems;
1, Solve the problem of "when the main and standby machines are switched, the alarm events with a level greater than the general level that occurred before the switchover (SOE,COS) Repeated alarms" problem;
2, Intelligent alarm;
3, Data identification;
Hong KongCLRengineering
1, Prepare automatic input simulation function and low-frequency load shedding function archive;
4, The remote control's opening and closing description can be configured manually, and the screen will be displayed according to the configuration content during remote operation;
34
5, Online The waveform list of the protection device can be popped up on the top, and the waveform analysis tool can be started to view;
6, In the system permissions libraryMMI Domain adds new features gd90;(start upABB gd80 software)
7, Online Call other executable programs and verify the specified permissions;
4, Solve the problem of "The device on-off alarm information cannot be searched in the historical alarm window";
Gear modification
1, "Gear position remote control" adds the "Emergency stop" option on the basis of "Upshift" and "Downshift", which involves screen,SCADA And pre-modification;
1, After the alarm is pushed to the screen, the video control in the screen is switched to the relevant preset position, which involves the modification of the screen and the alarm;
Stability control
1, Increase Guangdong's stability control 103"protocol_gdwk_103_m"And Guangdong Stability Control 104"protocol_wk_104_m"Protocol plug-in,
Connected to Xinjiang stability control device. Involving the modification of the front and the guarantee;
Power prediction
1, According to the requirements of Anhui Province, increase the wind power forecast short-term forecast results and ultra-short-term forecast results xml File generation function;
2, Resolve "web "Curve query" on the page, click the "Add" button and the drop-down menu is empty";
6, Increase the power prediction curve, the revised data display function;
7, After the ultra-short-term data is modified, the ultra-short-term data file sent to the dispatcher can be corrected according to the modified data;
8, After the short-term data is modified, the short-term data file sent to the dispatcher can be corrected according to the modified data;
9, The photovoltaic power forecasting regulates the log type, and adds the function of regularly deleting the log;
10, Open the training sample selection days of the neural network, which can be manually configured;
11, Open the statistics of the start-up capacity in the photovoltaic power forecast, and you can manually set the start-up capacity threshold when selecting samples;
12, Added the simple curve fitting function of photovoltaic power prediction;
13, The calculation of the short-term and ultra-short-term forecast results of photovoltaic forecasting has been revised to prevent the nighttime results from being incorrect 0 Case;
14, The ultra-short-term calculation method has been revised to avoid the impact on the ultra-short-term calculation results when the boot capacity is invalid;
Chongqing Metro
1, The dispatching terminal conducts listing operations on the sub-stations through remote control; involving screens and transpond Modifications;
Other modifications
1, Sequence control
1-1) Solve the "Liaoning Anshan 220kV Wang Tie BiancongR1.02 upgrade toR1.08 Later, when the device state definition tool was opened, the problem of "error reading
1-2) Solve the problem of “judgment current has been added during the definition of sequence control process 1, After deleting, the judgment current will be reported when the sequence control task is executed in this step 1 Object wrong
35
"Error" problem;
1-3) Sequential control supports automatic execution and single-step execution. In the single-step mode, each operation step needs to be manually confirmed by the operator before
1-4) After modifying the defined sequence control task object in the sequence control process definition tool, the execution conditions and confirmation conditions should be automatically updated accordingly;
2, Five defenses
2-1) Realize the online five-defense scheme of Maoming Plaza to adopt direct control mode;
2-2) When the operation ticket skips, the user is prompted whether to setSCADAObject value
2-3) Solve the "Jinan 110kVThe problem of “reminder lock operation feedback from the West Railway Station”;
3, The equipment management tool adds input validity verification. inequip_id When invalid, it’s not allowed to enter the ledger information, add equipment defect information and
Maintenance records.
4, Solve the "in Solaris operating system,oracle In a commercial database environment, use the historical database backup tool (rdb_backup), cannot be
5, For historical events, when retrieving events according to the alarm tab page, the function of filtering alarm events by character matching is added;
6, 61850 Front
6-1) Solve the problem of "Yangzi Petrochemical Siemens low-voltage protection cannot be connected normally";
6-2) Solve the "Phase II Expansion of Jiangsu Wuxi Telecom International Data Center" 10kVThe problem of "The power meter cannot be fully connected";
6-3) According to the State Grid 396 Implementation of standard requirements: the report enabling process is carried out in one network, and the priority is in A Net, if A Network failure, atBRe-enable the network
6-5)linux Add intermediate variables when assigning integers to floating-point types in the operating system;
6-6) Improve the program processing flow when reading the wave file list fails.
6-7)because relay The program adds a new interface, and the pre-program adds corresponding interface parameters synchronously;
6-8) Solve the problem of "The data model cannot be loaded correctly beforehand after the on-site duty machine of Jilin Baojia Substation is switched";
7, Programmable platform
7-1) Improve the connection method of connecting lines and graphic elements: as long as the end of the connecting line is dragged into the graphic element, the program will automatically generate the connection relationship;
7-2)CorrectAGC/AVCThe schedule is divided into 2 One level: real-time instruction + day-ahead planning curve;
7-3) The previous plan curve is generated by the power prediction system of the master station and placed in II Area FTPon
7-4) Passed by the station power prediction system FTPDownload the data and forward it toAGC/AVC
7-6) Newly added advanced application power plantAVCSystem script to realize the automatic control function of power plant voltage and reactive power.
8, The console increases the control of the number of incorrect password input, when the number of incorrect input exceeds the set value (default 4 Times), then exit the login box.
9、 Improve the data identification function of the integrated monitoring system of Wannan UHV substation;
10, Implementation based on JMS Communication realizes the remote browsing function of China Southern Network;
11-2) Solve the problem of "when the remote adjustment command is issued at a faster rate,103s The problem that the protocol plug-in cannot return the results of anti-calibration execution;
11-3) Solve the "Anhui Hefei Screw Gang Substation Monitoring Backstage and U Special Five Prevention Communication Problems";
11-4) Front 103 Can handle remote control with negative remote adjustment value;
11-5)solve"103 The problem that the measurement points on the remote control device cannot be manually set in the background;
13, Aiming at the online five-prevention scheme of Maoming Plaza's direct control mode, the five-prevention configuration tool realizes the automatic association of the control object and the remote control lock control point and remote control.
14, The formula makes a special judgment for the tri-state of the handcart: the state value of the handcart is 2 Hour (test state), equivalent to sub-state (0);
36
15,Trans
15-1) Solve the problem of "protective devices cannot be associated with primary equipment/intervals";
15-2) According to the configuration, the interval configuration information that meets the voltage level requirements is sent;
16, Protection service process improvement: non-duty nodes also receive messages in the front buffer, but do not process them.
3. eventinfo Library mode version / internal version from 17 upgrade to 18; increase nas with nufls App corresponding
37
version number:R1.09P001 (2013.08)
Version Information
baseline:pcsgraph_platform_lab_v2.0.4
Bug repair
1-1) Fix the problem of "The configuration tool is slow to read data";
1-2) Fix the problem of "messages may be lost when quickly forwarding alarms";
2, Protection management
2-1) Increase the processing of the subsequent bits of the pre-uploaded signal;
38
version number:R1.09P002 (2013.10)
Version Information
baseline:pcsgraph_platform_lab_v2.0.4
Function improvement
1, Five defenses
1-1) According to Jiangxi Leping 220kVJiedu substation requires an increase in the lock type at the scene"R": Check the electricity first, then unlock the padlock or the electric lock.
1-2) According to Ningbo, Zhejiang 110kV Zhonghe Substation site requirements: When rehearsing ticketing, the operation type prompt dialog box of the handcart object can be displayed as "handcart from the
test position to the running position" or "handcart from the test position to the position outside the cabinet".
3, Alarm:online_alarmEvent query interface, access scada The library is changed from tightly coupled mode to loosely coupled mode for protection management;
4, Power prediction: According to the requirements of Yunnan Province, increase wind power prediction results of ultra-short-term prediction dat File generation function;
5, 61850 Communication: New in the communication planRCSDual network solution, solveRCS When the device adopts the company's dual network solution, it will send more change reports
Text problem
6, Video: The video server is improved, and it can be connected to the Guangdong Environmental Video Protocol to meet the needs of the Maoming Plaza's cockpit transformation project;
39
version number:R1.09P003 (2013.11)
Version Information
pcsgraph_platform_lab_v2.0.4_p003
Function improvement
1, Database configuration
1-1) The virtual point and interval copy and paste operation under the synthesis device increase the copying of the measuring point formula;
1-2) According to the selected protection information type, online summon entries can be merged into the logic library;
1-3) Import 9798 Compatible with different positions of delimiters when configuring files;
1-4) Verify the logic and formula before publishing the database. If the factor object in the formula does not exist, give an error message and prohibit publishing the
database;
2, Formula
2-2) Solve the problem that "when the five-prevention interval is copied, after the split-and-close rule is successfully copied, the object name displayed in the rule is not the current five-prevention remote signaling point, but the source five-
2-3)solve"online During the rehearsal of sequence control, after the first sequence control task was successfully executed, the problem of “conditions not met after execution” was falsely reported;
3, Sequence control
3-1) When the device state is defined in the device state definition tool, the formula primitives can be edited normally;
3-2) Modify the sequence control process definition file parsing module to solve the problem of cross-platform sequence control file reading exception;
4, Five defenses
4-1)versusPCS-9212 The charging communication management machine adds the Ethernet communication mode (synchronous modification of the configuration tool);
4-2) Perform user permission verification before the five-prevention equipment alignment operation;
5-1)call 61850 Distinguish the upper and lower case of the extension name when storing waveform files and libraries;
5-2)61850 When the device is printing protection status, a data set selection dialog box is added, and only the soft platen data set can be printed;
5-3) The stability control management interface adds the functions of categorizing by region and searching for plants by plant name;
5-4) Solve the problem of "The content of the call setting value and the protection measurement in the stability control screen of Xinjiang is duplicated or the data is not in the plant";
6, Warning
6-1)online After querying the alarm event, the waveform file can be opened according to the alarm event, and the fault brief report can be displayed;
6-2) Electric Railway: Add the function of exporting and printing fault briefing information;
7, Plug-in
7-1)repair"gccdt Unable to deal with the problem of “message sent by the other party” in time;
7-2)solve"kaiy Analog screen telemetry sends a negative number that is too large and too small to display abnormally"
8, AGC
8-1) Simplify the blocking judgment conditions, no longer judge the communication of the inverter, the number of operations, and the switch refuses to move;
8-2) For photovoltaic AGC/AVCThe operating characteristics of the system, remove all unnecessary locks, and ensureAGC/AVCReliable adjustment;
9, Multilingual translation: increaseDateFormat Configuration item, the system supports the British format display of the date, that is, day-month-year; it involves the console, report
40
11,solve"net_daemon After the failure,maintainserver Can't get it normally ldb_server The process of ID, Resulting in repeated launches of multiple
ldb_server"The problem;
12-1) According to the requirements of Qinghai Province, the photovoltaic power forecasting system downloads the plan data and forwards it toAGCsystem
12-1) Add a programmable platform plug-in to determine whether the photovoltaic power station is under active power control
13-1) The configuration tool is very slow to read the measuring point data
13-2) Alarm direct transmission may cause packet loss when fast forwarding alarms
14-1) The user level is 5 After logging in, users can modify the factory site, modify user permissions, add and delete users, and other users can only
14-3) When synchronizing and modifying information to the slave station, it can report the status of synchronization success or failure;
15,61850 Front
15-1) There is only one instance of the report control block compatible with foreign manufacturers' devices, and multiple report control blocks are provided for the client's use;
15-2) The wave file of the recorder adopts sliding window method to synchronize with the data in the library;
15-3) Add a unified protection device for the new sixmid Files and des Document support;
15-4) Add the configuration of the logical node, file name, and storage path of the calling file in the communication plan;
41