DAILY REPORT

Project: 115kv underground transmission line in Sihanoukville Date: 25/11/2020


Weather
Location: Sihanouk Ville Sunny
Condition:
Owner: Contractor: E.M Construction Import Export
Site Engineer Phon Den Team Leader 5 Person
Site Manager Nget Chhay Worker 27 Person

Description Completion

No. Work Route Line Approval (6336m)


Contract Previous This Total Progress
Install Install Install %
Today Tomorrow

Trench excavation: Trench excavation:


1 Civil Work 6000 4611 24 4635 77.25%
-B-SMH-06 to B-SMH-07=24m -B-SMH-06 to B-SMH-07

Installed Pipe: Continue Installing Pipe:


2 HDPE Installation - B-SMH-06 to B-SMH-07 =24m -B-SMH-06 to B-SMH-07 6300 4841.55 25.20 4866.75 77.25%

3 Joint Pit 10 7 0 7 70.00%

4 Manhole 51 37 0 37 72.55%

5 Cable Laying Work

6 Cable Joint Work

Prepared by: .....Phon Den...................

Page | 1
DAILY PHOTO REPORT
Date: …25/11/2020….

A1. Pipe installation from B-SMH-06 to B-SMH-07 A2. Sand bedding and watering for pipe installation
(24m) from B-SMH-06 to B-SMH-07 (24m)

A3. Concrete slab installation for Pipe installation from A4. Concrete cuter from B-SMH-06 to B-SMH-07
B-SMH06 to B-SMH07

Page | 2
Comment: ………………………

Page | 3
DAILY PLAN WORK FOR TOMORROW
Project: 115kv underground transmission line in Sihanoukville
Date: 26/11/2020

Working Location: From B-TMH-05 to B-SMH-06


Work Description:
1. Continue to do trench excavation and pipe installation B-SMH-06 to B-SMH-07

B-SMH-06

B-SMH-07